Electrical Solutions Reference
Instrumentation, Controls & Electrical
SPPA-E3000 Excitation Systems & Startup
Frequency Converters
is the modernization solution for Pasir Gudang,
supporting a high availability of the plant.
The Result
■ Reduced obsolescence risk
thanks to replacement of
aging Excitation System
and SFC
■ Utmost availability thanks
to long-term support by
spare parts, repair and
services
■ Minimized outage time
thanks to optimized project
implementation
The Plant
Pasir Gudang Power Station is a gas-fired CCPP
in Malaysia, which is operated by YTL Power
Services. It consists of two gas turbines, two
heat recovery steam generators and one steam
turbine with a total power of 404 MW. The first
unit was commissioned in 1994 and the last in
1995. The plant supplies power to the national
utility company Tenaga Nasional Berhad.
The Task
Due to the aging excitation system and startup
frequency converter of unit 11 in Pasir Gudang,
the spare parts, repairs and services became
obsolete. In case of a failure YTL Power would
not be able to operate the gas turbine, which
would affect the availability of the whole plant.
To reduce this risk and ensure the availability
of the plant, the aging technology needed
to be upgraded.
Our Solution
With SPPA-E3000 Excitation Systems and
Startup Frequency Converters we offered
a technical solution that meets the footprint
and customer requirements in Pasir Gudang.
The aging components were replaced by the
newer version D03 of SPPA-E3000 SES Type
SEMIPOL, which was designed and configured
to the power plant environment. Not only that
the latest digital technology is incorporated in
the system, it is also supported for 15 years in
spare parts. Through a additionally guarantee
of repair until 2030 and services up to the year
2034 the obsolescence risk was reduced,
whereas availability was considerably increased.
Thanks to our optimized project implementation
we delivered, installed and commissioned the
solution according to customer‘s planned
outage.
“The local competency to
execute the project convinced
us to conclude the contract with
Siemens. Now we are pleased
with the result: A solution with
the latest technology, that
meets the footprint and ensures
long-term support – realized
within a short amount of time.”
Ir. Mohd Azmi Jusoh, Station Manager
YTL Power Services
Answers for energy.
Published by and copyright © 2012:
Siemens AG, Energy Sector
Freyeslebenstrasse 1
91058 Erlangen, Germany
For more information contact
sppa-e3000.energy@siemens.com
www.siemens.com/energy/sppa-e3000
Siemens AG
Fossil Power Generation
Instrumentation, Controls & Electrical
Siemensallee 84
76187 Karlsruhe, Germany
E307_FR_Pasir_Gudang-Excit-SFC_e_V1-0
Order no. E50001-G230-A312-X-4A00
Printed in Germany
Dispo 05401, c4bs-Nr. 7465
Printed on elementary chlorine-free
bleached paper.
All rights reserved.
Trademarks mentioned in this document are
the property of Siemens AG, its affiliates, or
their respective owners.
Subject to change without prior notice.
The information in this document contains
general descriptions of the technical options available,
which may not apply in all cases.
The required technical options should therefore
be specified in the contract.