*please print on company letterhead [Date] Ms. Deborah A. Le Vine California ISO Director, Implementation Contracts and Management 250 Outcropping Way Folsom, CA 95630 QueueManagement@caiso.com Subject: [Project Name] (ISO Queue Number __ ) Quarterly Status Report [Interconnection Customer Name] provides the following status updates on the progress of [Project Name]: 1. Environmental or land use permit status What permits are required for the project (examples: CUP, CEQUA, SF299, Cost Recovery Account, EIR, EIS)? Which permits are approved? Which are still outstanding? What is the estimated approval date for the outstanding permits? Click here to enter text. 2. Financing status Please provide a summary of the recent financing activities for the project and proof that financial security has been posted per the terms of the Interconnection Agreement. Click here to enter text. 3. Land acquisition Please provide land acquisition status or proof that site exclusivity is current. Click here to enter text. 4. Written notice to proceed Have you provided the notification to the Participating Transmission Owner (PTO) to design, procure, and construct transmission upgrades? Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015 *please print on company letterhead ☐ Yes ☐ No If not, when is it due? Click here to enter text. 5. Equipment Ordered Have you ordered equipment to construct your project? ☐ Yes ☐ No Click here to enter text. 6. Project Modification Have any of the project facts changed since the facilities study or phase 2 results were published? ☐ Yes ☐ No If yes, have these changes been reviewed through the material modification review process? Click here to enter text. 7. Affected System Are there any Identified Affected Systems for this project? ☐ Yes ☐ No If yes, list Identified Affected Systems: Click here to enter text. Which Affected Systems have you contacted and what were the responses? Click here to enter text. 8. Metering and telemetry Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015 *please print on company letterhead Have you completed the design for your metering and telemetry? ☐ Yes ☐ No If yes, have you contacted NewResourceImplementation@caiso.com? Click here to enter text. If not, what is the estimated completion date for metering and telemetry design? Click here to enter text. 9. Station Power Please describe the project’s plan for receiving station power. Has the project made arrangements for station power with the local retail service provider? Click here to enter text. 10. In-service date What is the in-service Date specified in the Interconnection Agreement? Click here to enter text. Is the project still on track to meet this in-service date? ☐ Yes ☐ No If not, please provide the projected in-service date and an explanation here, and submit a request for a material modification assessment to queuemanagement@caiso.com with an explanation of the cause of the delay. Click here to enter text. Is the project within 9 months of its in service date? ☐ Yes ☐ No If yes, have you contacted NewResourceImplementation@caiso.com to begin the implementation process? Are you in an upcoming Full Network Model data base build? Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015 *please print on company letterhead ☐ Yes, which model build: Click here to enter text. ☐ No Click here to enter text. 11. Initial Synchronization What is the initial synchronization date specified in the Interconnection Agreement? Click here to enter text. Is the project still on track to meet this initial synchronization date? ☐ Yes ☐ No If not, please provide the projected initial synchronization date and an explanation here with the cause of the delay. Click here to enter text. 12. ISO Program Participation Is the project involved in any of the following ISO programs? Are you on track to meet the program’s requirements? Multi-stage generator ☐ Yes ☐ No PIRP – participating intermittent resource ☐ Yes ☐ No QF – qualifying facility ☐ Yes ☐ No RA – resource adequacy ☐ Yes ☐ No ISO Station Power Program ☐ Yes ☐ No Use-limited resource Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015 *please print on company letterhead ☐ Yes ☐ No If yes, are you on track to meet the program’s requirements? Click here to enter text. 13. BAA Is the current date within three months of the Initial Synchronization Date outlined in the contract or the actual Initial Synchronization Date? ☐ Yes ☐ No If yes, has the IC provided the ISO and PTO with Balancing Authority Area notice? ☐ Yes ☐ No Click here to enter text. 14. Construction status for the project and interconnection facilities Has the project broken ground? ☐ Yes ☐ No Is the construction schedule for the project and interconnection facilities on time? Please provide photos if practical. Click here to enter text. 15. Testing status Has your project started putting test energy on the grid? ☐ Yes ☐ No Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015 *please print on company letterhead If yes, what percent complete is the testing? Have any major issues come up? Is there any risk to the contract milestone dates? Click here to enter text. 16. Commercial Operation for Markets Is the project planning to declare Commercial Operation for Markets in advance of declaring Commercial Operation as specified in the Interconnection Agreement? ☐ Yes ☐ No If yes, please describe the current plan for the block implementation schedule. Has the project executed an Implementation Plan with the ISO? Click here to enter text. 17. Commercial Operation Date Is the project still on track to meet the Commercial Operation Date (COD) specified in the Interconnection Agreement? ☐ Yes ☐ No If not, please provide an explanation here and submit a request for material modification review to queuemanagement@caiso.com with an achievable date and an explanation of the cause of the delay. Click here to enter text. 18. Point Of Contact/ Ownership Has the primary point of contact, Interconnection Customer of Record, or upstream ownership changed for the project? Who should ISO Queue Management reach out to with questions? Click here to enter text. Quarterly Status Report Template for Generators with Executed Interconnection Agreements http://www.caiso.com/documents/QuarterlyStatusReportTemplate_Version3.doc Updated: September 23, 2015