Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 www.caiso.com │ 250 Outcropping Way, Folsom, CA 95630 Author: MI&D/ IC&M/ R. Quadro │ 916.351.4400 Copyright © 2015 California Independent System Operator. All rights reserved. Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 Revision History Date 4/20/2015 Version 1 Description Published initial version Author R. Quadro Note: This technical guidance is provided for the convenience of the interconnection customer for the purpose of communicating complex and technical information. The guidance is intended to be consistent with the ISO tariff, however, the ISO is bound to operate in accordance with the tariff in all cases. In the event there is any conflict between guidance and the ISO tariff, the ISO tariff will control. Table of Contents BACKGROUND .................................................................................................................................................. 3 GENERAL ITEMS ............................................................................................................................................... 3 SPECIFIC ITEMS ................................................................................................................................................ 4 www.caiso.com Author: MI&D/ IC&M/ R. Quadro Copyright © 2015 California Independent System Operator. All rights reserved. Page 2 of 6 Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 Background This document outlines the specific items that are the most common cause of deficiencies when an Interconnection Customer (IC) submit an Interconnection Request (IR), one-line diagrams, and technical data (PSLF files) to the CAISO. Incomplete, inaccurate, or otherwise unacceptable data leads to delays and the risk of IRs being deemed invalid and not studied for customers submitting new IRs in the annual Interconnection Request Window, the Fast Track process, or the Independent Study Process. These deficiencies are also the most common factor that cause Material Modification Assessment requests (MMAs), Repowering requests, and other modification requests to go beyond the respective tariff and Business Process Manual (BPM) defined timeframes that the CAISO and the Participating TO have to review and respond to the request. The CAISO and the Participating TO will work with the IC to resolve deficiencies and questions about technical data and diagrams as soon as possible after receipt. It is adventageous for the IC to provide its IR prior to the cluster window closing so that it has more time to address any deficiancies in its IR submittal. The ISO Generator Interconnection and Deliverability Allocation Procedures (GIDAP) Tariff, Appendix DD, states – “If an Interconnection Request has not been deemed valid, the Interconnection Customer must submit all information necessary to meet the requirements of Section 3.5.1 no later than twenty (20) Business Days after the close of the applicable Cluster Application Window.” Prior to submitting the technical data and associated diagrams, the IC may want to review the IR and associated technical data with the following considerations in mind. This is a list of the most frequent items that require correction: General Items CAISO Tariff Appendix DD, Attachment A to Appendix 1 received from the IC is not the latest IR template. The latest IR template is on the CAISO website at: http://www.caiso.com/Documents/GIDAPAppendix1-AttachmentA-Appendix1InterconnectionRequest-GeneratingFacilityData.doc All sections of Appendix 1 and Attachment A must becompleted. If a section is not applicable, please mark it as N/A. www.caiso.com Author: MI&D/ IC&M/ R. Quadro Copyright © 2015 California Independent System Operator. All rights reserved. Page 3 of 6 Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 Even if the Modification request is limited in scope, the IR (including one-line diagram and PSLF files) should represent the whole project. Review the sample completed IRs on the ISO website for instructive examples of correctly completed IRs using the link below: Interconnection Request Resources Specific Items Dynamic data does not use the GE PSLF v18.1 WECC approved dynamic models. Because of a limitation on the number of user-defined models that can be used by the CAISO and Participating TOs, user defined models may only be submitted in the case that GE PSLF library does not contain the model for the technology of the Generating Facility. o If you require assistance in developing the models, we suggest you contact General Electric directly. Accurate models are important to obtain accurate results. Costs associated with any changes in facility requirements that are due to differences between model data provided by the generation developer and the actual generator test data, may be the responsibility of the generation developer. Inconsistent values between Attachment A Sections 10/10a and epc file power flow data o Attachment A Sections 10 and 10a request Line Charging (B/2) in per unit. The epc power flow data file format is total line charging B in per unit. The value in the epc file must be 2 times the value in the IR. A project that is required to meet 0.95 lead/lag at the POI as per its Phase I or Phase II study results must demonstrate through the data in the IR package, how this will be accomplished. There are inconsistent values between attachment A and the load flow and dynamic models: Inconsistent values between Attachment A Section 4c vs dynamic data Failure to model aux load in EPC files. Auxiliary load is not intended to represent losses in the project transformers/collector circuits/gen tie lines/etc. Auxiliary load is intended to represent other loads at the Generating Facility (motors/pumps/etc…) that are served from the grid if the generator is not operating. www.caiso.com Author: MI&D/ IC&M/ R. Quadro Copyright © 2015 California Independent System Operator. All rights reserved. Page 4 of 6 Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 Project has two different kinds of inverters, but the model of the project includes only one aggregated unit and aggregated inverters. Aggregated modeling is acceptable provided that the dynamic models, short circuit duty contribution, terminal voltages, and same MVA base are the same for all inverters. If they are different, then there must be two separate models. Updated single-line diagram was not provided, or did not contain enough detail. o Single-line diagram showing applicable equipment such as generating units, step-up transformers, auxiliary transformers, switches/disconnects of the proposed project, including the required protection devices and circuit breakers. For wind and photovoltaic Generator Facilities, the one line diagram should include the distribution lines connecting the various groups of generating units, the generator capacitor banks, the step up transformers, the distribution lines, and the substation transformers and capacitor banks at the Point of Interconnection with the CAISO Controlled Grid. o Parameters shown on the one-line diagram do not match data in other sections of Attachment A to Appendix 1, e.g. different transformer impedances and MVA bases. Please provide supporting manufacturer’s documentation and Max Short Circuit Duty Capability information for Short Circuit Duty Analysis for change in Inverter. o Provide information on “Stand-Alone Operation” capability of Inverter. o The provided short circuit fault contribution for asynchronous generators in the IR should include Low Voltage Ride Through (LVRT) capabilities. For MMA requests, include proposed In Service Date (ISD) in addition to the proposed Commercial Operation Date (COD) in Appendix 1 and also in other documents requesting changes in milestone dates. The IR states that Appendix 1, item 4b should be equal to Appendix 1 Attachment A, item 2C. Also, item 2C must equal the data in item 2A lessitem 2B. But item 2 C does not take into account losses within the project. The IR should be completed as follows: o Item 2A, Total Generating Facility rated output (MW): the gross output number at the generator terminals. Typically the inverter MW capacity provided by the manufacture is under the unity power factor. The MW capacity under a different power factor is lower than that under the unity power factor. If the IC uses the inverters to meet the reactive power www.caiso.com Author: MI&D/ IC&M/ R. Quadro Copyright © 2015 California Independent System Operator. All rights reserved. Page 5 of 6 Guidance for Interconnection Customers Submitting Technical Data June 17, 2015 capability requirement, please clearly indictate the MW capacity and the associated power factor. o Item 2B, Generating Facility auxiliary load (MW) : auxiliary load that does not include any losses, instead it is actual loads that are modeled explicitly. o Item 2C, Project net capacity (MW, 2A-2B): the IR states that this should be equal to Appendix 1 item 4b which is the desired maximum output for the project. This is a net value and doesn’t account for losses. The net output to the grid is really Gross output at generator terminals – Generator Auxiliary load – Losses on the IC side of the POI. The IR does not specify the Losses component. Instead the transmission loss is calculated using the power flow model submitted by the IC. o All energy storage projects must submit the technical data in accordance with the “Supplemental Information for Energy Storage Projects” document provided at the following link: http://www.caiso.com/Documents/EnergyStorageProjectsSupplementalInformation.pdf The IR should include current data to capture the following characteristics of Wind Turbines and PV inverters in order to determine their fault contribution : Isc max current during fault detection. Duration of Isc max Isc max after fault detection Ilv max current for low voltage ride through (LVRT). Duration of Ilv max www.caiso.com Author: MI&D/ IC&M/ R. Quadro Copyright © 2015 California Independent System Operator. All rights reserved. Page 6 of 6