Chapter 10 Making Capital Investment Decisions Chapter 9 REVIEW I. Discounted cash flow criteria A. Net present value (NPV). The NPV of an investment is the difference between its market value and its cost. The NPV rule is to take a project if its NPV is positive. NPV has no serious flaws; it is the preferred decision criterion. B. Internal rate of return (IRR). The IRR is the discount rate that makes the estimated NPV of an investment equal to zero. The IRR rule is to take a project when its IRR exceeds the required return. When project cash flows are not conventional, there may be no IRR or there may be more than one. C. Profitability index (PI). The PI, also called the benefit-cost ratio, is the ratio of present value to cost. The profitability index rule is to take an investment if the index exceeds 1.0. The PI measures the present value per dollar invested. II. Payback criteria A. Payback period. The payback period is the length of time until the sum of an investment’s cash flows equals its cost. The payback period rule is to take a project if its payback period is less than some pre-specified cutoff. B. Discounted payback period. The discounted payback period is the length of time until the sum of an investment’s discounted cash flows equals its cost. The discounted payback period rule is to take an investment if the discounted payback is less than some pre-specified cutoff. III. Accounting criterion A. Average accounting return (AAR). The AAR is a measure of accounting profit relative to book value. The AAR rule is to take an investment if its AAR exceeds a benchmark. Chapter 10 Making Capital Investment Decisions Chapter Organization •Incremental Cash Flows •Terminology •Cash Flows vs. Accounting Income •Pro Forma Financial Statements and Project Cash Flows •More on Project Cash Flows •Alternative Definitions of Operating Cash Flow •Some Special Cases of Discounted Cash Flow Analysis •Summary and Conclusions Fundamental Principles of Project Evaluation: Project evaluation - the application of one or more capital budgeting decision rules to estimated relevant project cash flows in order to make the investment decision. Relevant cash flows - the incremental cash flows associated with the decision to invest in a project. The incremental cash flows for project evaluation consist of any and all changes in the firm’s future cash flows that are a direct consequence of taking the project. Stand-alone principle- evaluation of a project based on the project’s incremental cash flows. Incremental Cash Flows Incremental Cash Flow = cash flow with project - cash flow without project IMPORTANT Ask yourself this question Would the cash flow still exist if the project does not exist? •If yes, do not include it in your analysis. •If no, include it. Terminology A. Sunk costs B. Opportunity costs C. Side effects D. Net working capital E. Financing costs F. Other issues A. Sunk costs Suppose $100,000 had been spent last year to improve the production line site. Should this cost be included in the analysis? • NO. This is a sunk cost, already spent and irretrievable, so “forget it”, “water under the bridge”, SUNK. Focus on incremental investment and operating cash flows. B. Opportunity costs Suppose the plant space could be leased out for $25,000 a year. Would this affect the analysis? • Yes. Accepting the project means we will not receive the $25,000. This is an opportunity cost and it should be charged to the project. C. Side effects If the new product line would decrease sales of the firm’s other products by $50,000 per year, would this affect the analysis? • Yes. The effects on the other projects’ CFs are “externalities” or “spillover effects”. • Net CF loss per year on other lines would be a cost to this project. • Externalities will be positive if new projects are complements to existing assets, negative if substitutes. D. Net working capital NWC = CA - CL In estimating cash flows we must account for the fact that some of the incremental sales associated with a project will be on credit, and that some costs won’t be paid at the time of investment. How? Answer: Estimate changes in NWC. Assume: 1. 2. Fixed asset spending is zero. The change in net working capital spending is $200: 0 A/R 1 Change $100 $100 0 INV 100 350 +250 - A/P 50 100 -50 NWC $150 $350 Change in NWC = $200 E. Financing costs Should CFs include interest expense? Dividends? • NO. The costs of capital are already incorporated in the analysis since we use them in discounting. • If we included them as cash flows, we would be double counting them. F. Other issues Depreciation Basics Depreciable Basis = Cost + Shipping + Installation T10.7 Modified ACRS Property Classes (Table 10.6) Class Examples 3-year Equipment used in research 5-year Autos, computers 7-year Most industrial equipment T10.8 Modified ACRS Depreciation Allowances (Table 10.7) Property Class 5-Year 7-Year Year 3-Year 1 33.33% 20.00% 14.29% 2 44.44 32.00 24.49 3 14.82 19.20 17.49 4 7.41 11.52 12.49 5 11.52 8.93 6 5.76 8.93 7 8.93 8 4.45 Cash flow estimation bias • CFs are estimated for many future periods. • If company has many projects and errors are random and unbiased, errors will cancel out (aggregate NPV estimate will be OK). • Studies show that forecasts often are biased upward (overly optimistic revenues, underestimated costs). Agency Problems? What steps can management take to eliminate the incentives for cash flow estimation bias? • Routinely compare CF estimates with those actually realized and reward managers who are forecasting well, penalize those who are not. • When evidence of bias exists, the project’s CF estimates should be lowered or the cost of capital raised to offset the bias. Option value • Investment in a project may lead to other valuable opportunities. • Investment now may extinguish opportunity to undertake same project in the future. • True project NPV = NPV + Value of options. Cash Flow -VS- Accounting Income •Discount actual cash flows •Using accounting income, rather than cash flow, could lead to erroneous decisions. Cash Flow -VS- Accounting Income Example A project costs $2,000 and is expected to last 2 years, producing cash income of $1,500 and $500 respectively. The cost of the project can be depreciated at $1,000 per year. Given a 10% required return, compare the NPV using cash flow to the NPV using accounting income. Cash Flow -VS- Accounting Income Year 1 Year 2 Cash Income $1500 $ 500 Depreciation - $1000 - $1000 Accounting Income + 500 - 500 Cash Flow -VS- Accounting Income Year 1 Year 2 Cash Income $1500 $ 500 Depreciation - $1000 - $1000 Accounting Income + 500 - 500 500 500 Accounting NPV = $41.32 2 1.10 (110 . ) Cash Flow -VS- Accounting Income Today Cash Income Project Cost Free Cash Flow - 2000 - 2000 Year 1 Year 2 $1500 $ 500 +1500 + 500 Cash Flow -VS- Accounting Income Today Cash Income Project Cost Free Cash Flow - 2000 - 2000 Year 1 Year 2 $1500 $ 500 +1500 + 500 1500 500 Cash NPV = - 2000 $223.14 1 2 (1.10) (1.10) Pro Forma Financial Statements and Project Cash Flows Suppose we want to prepare a set of pro forma financial statements for a project for Norma Desmond Enterprises. In order to do so, we must have some background information. In this case, assume: 1. Sales of 10,000 units/year @ $5/unit. 2. Variable cost per unit is $3. Fixed costs are $5,000 per year. The project has no salvage value. Project life is 3 years. 3. Project cost is $21,000. Depreciation is $7,000/year. 4. Additional net working capital is $10,000. 5. The firm’s required return is 20%. The tax rate is 34%. Pro Forma Financial Statements Projected Income Statements Sales $______ Var. costs ______ $20,000 Fixed costs 5,000 Depreciation 7,000 EBIT Taxes (34%) Net income $______ 2,720 $______ Pro Forma Financial Statements Projected Income Statements Sales Var. costs $50,000 30,000 $20,000 Fixed costs 5,000 Depreciation 7,000 EBIT Taxes (34%) Net income $ 8,000 2,720 $ 5,280 Projected Balance Sheets 0 1 2 3 NWC $______ $10,000 $10,000 $10,000 NFA 21,000 ______ ______ 0 Total Invest $31,000 $24,000 $17,000 $10,000 Projected Balance Sheets 0 1 2 3 NWC $10,000 $10,000 $10,000 $10,000 NFA 21,000 14,000 7,000 0 Total $31,000 $24,000 $17,000 $10,000 Now let’s use the information from the previous example to do a capital budgeting analysis. Project operating cash flow (OCF): EBIT Depreciation Taxes OCF $8,000 +7,000 -2,720 $12,280 Project Cash Flows 0 OCF 1 $12,280 Chg. NWC ______ Cap. Sp. -21,000 Total ______ 2 3 $12,280 $12,280 ______ $12,280 $12,280 $______ Project Cash Flows 0 OCF Chg. NWC -10,000 Cap. Sp. -21,000 Total -31,000 1 2 $12,280 $12,280 3 $12,280 10,000 $12,280 $12,280 $22,280 Capital Budgeting Evaluation: NPV = -$31,000 + $12,280/1.201 + $12,280/1.20 2 + $22,280/1.20 3 = $655 IRR = 21% PBP = 2.3 years AAR = $5280/{(31,000 + 24,000 + 17,000 + 10,000)/4} = 25.76% Should the firm invest in this project? Why or why not? Yes -- the NPV > 0, and the IRR > required return Proposed Project • Cost: $200,000 + $10,000 shipping +$30,000 installation. • Depreciable cost $240,000. • Inventories will rise by $25,000 and payables will rise by $5,000. • Economic life = 4 years. • Salvage value = $25,000. • MACRS 3-year class. Incremental gross sales = $250,000. Incremental cash operating costs = $125,000. Tax rate = 40%. Cost of capital = WACC = 10% Set up without numbers a time line for the project CFs. 0 1 Initial Outlay OCF1 NCF0 NCF1 2 3 OCF2 OCF3 NCF2 NCF3 4 OCF4 + Terminal CF NCF4 What is the annual depreciation? Year 1 2 3 4 Rate x 0.33 0.45 0.15 0.07 1.00 Basis $240 240 240 240 Depreciation $ 79 108 36 17 $240 Due to half-year convention, a 3-year asset is depreciated over 4 years. Operating cash flows ($000): 1 2 Sales $250 $250 Cash costs 125 125 Depreciation 79 108 EBIT $ 46 $ 17 Taxes (40%) 18 7 Net Income 28 10 Add: Depreciation 79 108 Operating Cash flow $107 $118 3 $250 125 36 $ 89 36 53 36 $ 89 4 $250 125 17 $108 43 65 17 $ 82 Net Investment Outlay At t=0 Equipment ($200,000) Ship + Install (40,000) Change in NWC (20,000) Net CF0 ($260,000) NWC = $25,000 - $5,000 Net Terminal Cash Flow At t = 4 Salvage value $25,000 Tax on SV (10,000) Recovery on NWC 20,000 Net Termination CF $35,000 Project net CFs on a time line: 0 (260) 1 2 3 107 118 89 4 117 Enter CFs in CFLO register and I = 10. NPV = $81,573 IRR = 23.8% What is the project’s MIRR? 0 (260) 1 2 3 107 118 89 4 117 97.9 (260) MIRR = ? 142.8 142.4 500.1 What is the project’s payback? 0 (260) 1 2 3 107 118 89 Cumulative: (260) (153) (35) 54 Payback = 2 + 35/89 = 2.4 years 4 117 171 If this were a replacement rather than a new project, would the analysis change? Yes. The old equipment would be sold and the incremental CFs would be the changes from the old to the new situation. • The relevant depreciation would be the change with the new equipment. • Also, if the firm sold the old machine now, it would not receive the salvage value at the end of the machine’s life. T10.15 Alternative Definitions • The Tax-Shield Approach of OCF (concluded) OCF = (S - C - D) + D - (S - C - D) T = (S - C) (1 - T) + (D T) = (S - C) (1 - T) + Depreciation x T • The Bottom-Up Approach OCF = (S - C - D) + D - (S - C - D) T = (S - C - D) (1 - T) + D = Net income + Depreciation • The Top-Down Approach OCF = (S - C - D) + D - (S - C - D) T T10.16 Chapter 10 Quick Quiz • Now let’s put our new-found knowledge to work. Part 1 of 3 Assume we have the following background information for a project being considered by Gillis, Inc. • See if we can calculate the project’s NPV and payback period. Assume: Required NWC investment = $40; project cost = $60; 3 year life Annual sales = $100; annual costs = $50; straight line depreciation to $0 T10.16 Chapter 10 Quick Quiz - Part of 3are(concluded) • Project cash 1 flows thus: 0 1 2 3 OCF $39.8 $39.8 $39.8 Chg. in NWC-40 40 Cap. Sp. -60 -$100 $39.8 $39.8 $79.8 Payback period = ___________ T10.17 Example: A Cost-Cutting Proposal Consider a $10,000 machine that will reduce pretax operating costs by $3,000 per year over a 5-year period. Assume no changes in net working capital and a scrap (i.e., market) value of $1,000 after five years. For simplicity, assume straight-line depreciation. The marginal tax rate is 34% and the appropriate discount rate is 10%. Using the tax-shield approach to find OCF: OCF = (S - C)(1 - T) + (Dep T) The after-tax salvage value is: = [$0 - (-3,000)](.66) + (2,000 .34) market value - (increased tax liability) = market value - (market value - book) T = $1,980 + $680 = $2,660 = $1,000 - ($1,000 - 0)(.34) = $660 T10.17 Example: A Cost-Cutting Proposal (concluded) The cash flows are Year OCF 0 $ 0 1 2,660 2 2,660 3 2,660 Capital spendingTotal -$10,000 -$10,000 0 2,660 0 2,660 0 2,660 T10.18 Chapter 10 Quick Quiz Evaluating Cost Cutting Proposals 2 of 3 Cost = Part $900,000 Depreciation= $180,000 per year Life = Salvage = Cost savings = Tax rate = Add. to NWC sign) 5 years $330,000 $500,000 per year, before taxes 34 percent = –$220,000 (note the minus 1. After-tax cost saving: $500K (______) = $______ per year. 2. Depreciation tax shield: $180K ______ = $______ per year. 3. After-tax salvage value: $330K - ($330K - 0)(.34) = $______ T10.18 Chapter 10 Quick Quiz - Part 0 2 of 1 3 (concluded) 2 3 4 5 AT saving $330.0K$330.0K$330.0K$330.0K $330.0K Tax shield 61.2K 61.2K 61.2K 61.2K 61.2K OCF _____ _____$391.2K$391.2K $391.2K Chg. in NWC____ _____ Cap. Sp.-900K 217.8K T10.19 Example: Setting the Bid Price The Army is seeking bids on Multiple Use Digitizing Devices (MUDDs). The contract calls for 4 units per year for 3 years. Labor and material costs are estimated at $10,000 per MUDD. Production space can be leased for $12,000 per year. The project will require $50,000 in new equipment which is expected to have a salvage value of $10,000 after 3 years. Making MUDDs will require a $10,000 increase in net working capital. Assume a 34% tax rate and a required return of 15%. Use straight-line depreciation to zero. Operating Year cash flow 0 1 2 3 $ 0 OCF OCF OCF Increases in NWC – $10,000 0 0 10,000 Capital spending Total = cash flow – $50,000 – $60,000 0 OCF 0 OCF + 6,600 OCF + 16,600 T10.19 Example: Setting the Bid Price (continued) • Taking the present value of $16,600 in year 3 ( = $10,915 at 15%) and netting against the initial outlay of – $60,000 gives Total Year cash flow 0 1 – $49,085 OCF T10.19 Example: Setting the Bid • The PV annuity factor for 3 years at 15% is 2.283. Setting NPV = $0, (continued) Price NPV = $0 = – $49,085 + (OCF 2.283), thus OCF =OCF $49,085/2.283 = $21,500 = Net income + Depreciation Using the bottom-up approach to calculate OCF, $21,500 = Net income + $50,000/3 = Net income + $16,667 Net income = $4,833 Next, since annual costs are $40,000 + $12,000 = $52,000 Net income = (S - C - D) (1 - T) $4,833 = (S .66) - (52,000 .66) - (16,667 .66) S = $50,153/.66 = $75,989.73 Hence, sales need to be at least $76,000 per year (or $19,000 per MUDD)! T10.19 Example: Setting the Bid Background: Suppose we also have the following Price (continued) information. • 1. The bid calls for 20 MUDDs per year for 3 years. • 2. Our costs are $35,000 per unit. • 3. Capital spending required is $250,000; and depreciation = $250,000/5 = $50,000 per year • 4. We can sell the equipment in 3 years for half its original cost: $125,000. • 5. The after-tax salvage value equals the cash in from the sale of the equipment, less the cash out due to the increase in our tax liability associated with the sale of the equipment for more T10.19 Example: Setting the Bid • The cash flows ($000) are: Price0 (continued) 1 2 3 OCF $OCF $OCF $OCF Chg. in NWC - $ 60 + 60 Capital Spending - 250 ______ +115.25 Find the______ OCF such that the NPV is zero at 16%: +$310,000 - 175,250/1.163 $197,724.74 OCF = OCF (1 - 1/1.163)/.16 - $310 $OCF $OCF $OCF + = OCF 2.2459 = $88,038.50/year 175.25 T10.19 Example: Setting the Bid Price (concluded) If the required OCF is $88,038.50, what price must we bid? Sales $_________ Costs Depreciation EBIT Tax Net income 700,000.00 50,000.00 $_________ 24,319.70 $ 38,038.50 Sales = $62,358.20 + 50,000 + 700,000 = $812,358.20 per year, and T10.20 Example: Equivalent Annual Cost Analysis • Two types of batteries are being considered for use in electric golf carts at City Country Club. Burnout brand batteries cost $36, have a useful life of 3 years, will cost $100 per year to keep charged, and have a salvage value of $5. Longlasting brand batteries cost $60 T10.20 Example: Equivalent Annual Cost Analysis (continued) • Using the tax shield approach, cash flows for Burnout are: OCF = (Sales - Costs)(1 - T) + Depreciation(T) = (0 - 100)(.66) + 12(.34) = -$66 + 4 = -$62 Operating Capital Total Yearcash flow- spending= cash flow T10.20 Example: Equivalent • Again using the tax shield approach, OCFs Annual Cost Analysis (continued) for Longlasting are: OCF = (Sales - Costs)(1 - T) + Depreciation(T) = (0 - 88)(.66) + 12(.34) = -$58 + 4 = $54 Operating Total Year flow OCF Capital - spending = cash T10.20 Example: Equivalent Annual Cost Analysis (continued) • Using a 15% required return, calculate the cost per year for the two batteries. Calculate the PV of the cash flows: The present value of total cash flows for Burnout is -$175.40 T10.20 Example: Equivalent Annual Cost Analysis (concluded) What 3 year annuity has the same PV as Burnout? The PV annuity factor for 3 years at 15% is 2.283: -$175.40 = EAC 2.283 EAC = -$175.40/2.283 = -$76.83 T10.21 Chapter 10 Quick Quiz Part 3 of 3 • Here’s one more problem to test your skills. Von Stroheim Manufacturing is considering investing in a lathe that is expected to reduce costs by $70,000 annually. The equipment costs $200,000, has a four-year life (but will be depreciated as a 3-year MACRS asset), requires no additional investment in net working capital, and has a salvage value of $50,000. The firm’s tax rate is 39% T10.21 Chapter 10 Quick Quiz - Part 3 of 3 (continued) Depreciation: YearDep (%) Dep ($) 1 2 3 4 33.33%$_______ 44.44% 88,880 14.82% 29,640 7.41% 14,820 100% $200,000 T10.21 Chapter 10 Quick Quiz Partare3thus: of 3 (concluded) The cash -flows 0 1 2 3 4 AT saving $42,700.0$42,700.0$42,700.0 $42,700.0 Tax shield 25,997.434,663.2 11,559.6 5,779.8 OCF $68,697.4$77,363.2$54,259.6 $48,479.8 Cap. Sp.-200,000 _______