Group Name:
LifeSub Engineering
Group Number:
M14
Group Members:
Ajanthan Asokan
William Barkhouse
Matthew Browne
Stephen Handrigan
Client: Dr. Michael Hinchey
April 1, 2014
Agenda
Problem Statement
Project Overview
Deployment Strategies
Prototype Design
Manufacturing
Commissioning
Conclusion
Future Work &
Recommendations
Questions
April 1, 2014
2
Problem Statement
Develop a prototype and deployment strategies to prove an
autonomous submersible could be used as an evacuation
method for offshore structures.
February 4, 2014
3
Project Overview
Current Problem
Lifeboats – Exposed to Hazards
Freefall – Uncontrolled
Proposed Solution
Deployable Submarine
Project Goals
Develop and Test Automated
Submarine Prototype
Develop and Test Deployment
Options
Identify Design Requirements
April 1, 2014
4
Control Sequence
+Φ
-Φ
+θ
-θ
Z1
Z2
April 1, 2014
+Z
5
Deployment Strategies
1. Vertical Deployment
1.
2.
2. Horizontal Launch
3.
April 1, 2014
Propeller-down launch
Underwater
Avoid GBS interference
Release bay filled with water
Exit from enclosed piping
3. Horizontal Docking
Connect with GBS
6
Prototype Design Evolution
Phase 1
Phase 3
Propeller Shroud with
Phase 2
Streamline Hub
Piston Ballast Pumps
Internal Support
Mounts
Stepper Motor Sleds
Phase 3
April 1, 2014
7
Prototype Design
Ring guide and shroud
Protect hull
Allow air and water passage
around sub during
deployment
Shroud
Protects thruster from being
damaged
Streamlined hub reduces
eddy currents
Lifting Hook allows for the
lifting of prototype
Center-axis mounted thruster
with F/R control
Piston Pumps
April 1, 2014
8
Prototype Design: Internal Mounting
Prototype
2 Ballast Pump
SolidWorks Model
¼ "-20 Hex Nuts
April 1, 2014
¼" -20 Threaded Rod
Mounts
2 Ballast Pumps
2 Support Rings
3 Batteries
1 Circuit Board
2 Stepper Motors
4 ¼”-20 Threaded
Rod
9
Prototype Manufacturing
Ballast Chamber
25mm diameter piston
pump
40mm vertical piston
travel
Driven by stepper motor
via rack in pinion
10
Prototype Design: Ballast System
Internal Piston Setup
Rod Support Mounts
Piston Ballast Pump
Rack &
Pinion (32 - 3/16”)
April 1, 2014
Stepper Motor &
Sled
11
Pseudo-wiring Diagram
Circuit
* GND
RS-232 DE-9
Female Pinout
MOSFETS
PIC
*
Pressure Sensor,
Accelerometer, etc.
** +5 V
**
GND
Signals 1-6
Signals 1-6
VIN
Stepper Motor
Stepper Motor
Piston
Batteries
Clamp
April 1, 2014
Thruster
12
Prototype Manufacturing
Hull
Extruded ABS
Pipe provided by
EMCO
Completed by
Tech Services
Ring
Piston Pumps
Guide/Shroud
Fabricated from
RP ABS Plastic
recycled piston
shocks
Completed by
Tech Services
Completed by
MTC
13
Commissioning
Water Control Tests
Water Tight Hull
Pre-ballast and leveling
Dry Control Tests
Stepper Motor Test
Thruster Test
Sensor Test
Dynamic Balancing
April 1, 2014
14
Conclusion
Developed an automated submersible prototype with active Pitch,
Depth, and Thrust control
Developed commissioning procedures to verify operability of prototype
Developed test procedures to simulate emergency evacuation of
offshore structures
Developed the codes required to perform testing with the prototype
April 1, 2014
15
Recommendations and Future Work
Complete commissioning of active
systems
Depth
Pitch
Thrust
Complete deployment tests
Analyze motion
Make recommendations for viability
of full-scale implementation
April 1, 2014
16
Questions?
Thank-you
www.lifesubengineering.weebly.com
April 1, 2014
17