Revision Effective Date Contract Review 2 12/1/04 PR-06 Page 1 of 2 1. Purpose: Contract and Specification Review 2. Approval Responsibilities 2.1. The Management Team is responsible for reviewing and approving this procedure. 3. Procedure 3.1. Once the contract has been awarded, the Estimating Department generates a “Contract and Specification Review” sign-off form (Form F-06) identifies and attaches to it the following: The contract Specifications Specific customer supplied documents and requirements related to production General notes, Project specific work instructions Quality plans with unique hold points Requirements from the contract or specification that vary from ABC’s methods will be highlighted, and copies will be distributed to the appropriate processing departments. Once the designated departments have reviewed the documents, they will sign in the appropriate space, commenting if desired, and return to the Estimating department’s Inbox. A completed “Contract and Specification Review” sign-off form (F-06) will demonstrate a complete review. 3.2. Throughout the project, revisions to contract documents will be reviewed with the original Estimator and the Project Coordinator to ensure compliance with the contract documents. Questions back to the job owner or Engineer will be documented via RFI (Request For Information) form, and an entry made to the RFI Log. The potential cost and/or schedule impacts to the project will be determined 3.3. These subsequent reviews are documented by memo or other suitable means and are routed with a new F-06 form to any function that is affected by the change to inform and solicit input. The final result is filed in the job folder. 3.4. The Estimator will attach the completed F-06 to the Estimator’s budget sheet(s) and place them in the job folder. The job folder is then furnished to the Project Coordinator for project assignment. 3.5. The Project Coordinator will assign a Job Number to the project and make four copies of the form (F-06) and re-distribute to all functions. Revision Effective Date Contract Review 2 12/1/04 PR-06 Page 2 of 2 4. Quality Records Contract Review form (F-06) RFI (Request for Information) RFI Log Contract Review Procedure Revision History Changed paragraphs are marked with a bar in the left margin. General descriptions of changes are noted below. No. 1 2 Date 11/15/04 12/1/04 Description Adjusted ¶4.1.3 to include RFI generation Added ¶4.5 to include documenting reviews after the intial review This is a sample procedure to assist a firm as a reference in preparing their own procedures. It represents only one approach to satisfying the requirements of this element. At a minimum, the firm must replace or insert titles and describe responsibilities that reflect how the work is done at their facility. This editing is mandatory to comply with the requirements of the AISC Certification Standard for Steel Building Structures.