Public Disclosure Authorized I~~~~~~~~~Vt s 4"l RESTRICTED LSK ,_ l ReportNo. PI-8 Public Disclosure Authorized This report was prepared for use within the Bank and its affiliated organizations. They do not accept responsibilityfor its accuracy or completeness,The report may not be published nor may it be quoted as representing their views. INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Public Disclosure Authorized INTERNATIONAL DEVELOPMENT ASSOCIATION APPRAISAL OF THE COCHIN II FERTILIZER THE FERTILISERS AND CHEMICALS, Public Disclosure Authorized INDIA May 14, 1971 Industrial Projects Department PROJECT TRAVANCORE LIMITED Currency Equivalents $0.133 Rs 7.5 1 Rupee (Rs) 1 U.S. Dollar ($) Rs 1,000,000 ' $133,000 Weights and Measures All weights and measures are 1 metric ton 1 metric ton 1 kilometer (km) Principal GOI, Government FACT FEDO UDL PCI UWNDP TPY TPD CIF expressed = - Abbreviations in metric units: 1,000 kilograms 2,205 pounds 0.62 miles (kg) and Acronyms Used The Central Government of India The Fertilisersand Chemicals,TravancoreLtd. FACT Engineering and Design Organisation Udyogamandal Division of FACT Fertilizer Corporation of India United Nations DevelopmentProgramme Metric Tons Per Year Metric Tons Per Day Cost, Insurance and Freight N, P, and K are used throughout nutrients: the report to refer N = Nitrogen Content P = P2 05 or PhosphateContent K = K2 0 or PotashContent Fiscal Year April 1 - March 31 to the fertilizer TABLE OF CONTENTS Page No. SUMMARY AND CONCLUSIONS ............................. .............................. I. INTRODUCTION .......... II. FACT'S EXISTING OPERATIONS .......................... A. B. C. III. PROPOSED COCHIN II PROJECT .......................... A. B. IV. V. 2 2 2 3 5 ........................... 5 Project Scope ....... ............ 5 Project Description and Ecology .... 6 A. B. C. 6 7 7 Capital Costs ..................... Working Capital ................................ Financial Plan ................................. PROJECT EXECUTION ............................. Project Management ............................. Project Schedule and Procurement ............... Allocation of IDA Credit ....................... MARKET AND MARKETING ....... A. B. C. D. E. F. G. VII. 1 PROJECT COSTS AND FINANCIAL PLAN ............... A. B. C. VI. History and Organization ................. ......................... FACT Management ....... ...... Financial Analysis of Existing Operations i 8 9 10 ......................... 11 ................ 11 Present Situation in India ..... 12 ................. Market Forecast for India ..... ........... 13 Fertilizer Market in South India .... 15 .... .... FACT Marketing Area and Handling System 16 ............................ NPK Seeding Program 16 ................... Sales Prices and Competition 17 Agricultural Credit ............................ OPERATING COSTS A. B. 8 ..................................... Raw Material Costs ............................. Production Costs ............................... This report has been prepared by Messrs. Donald E. Browni and Anthony R. Perram of the Industrial Projects Department based on missions to India in December 1970 and February/March 1971. 18 18 19 Table of Contents VIII. (Continued) FINANCIAL AND ECONOMIC ANALYSIS OF THE PROJECT 20 A. B. C. 20 Financial Analysis and Sensitivity Tests Economic Analysis .21 Imported Vs. Manufactured Phosphoric Acid IX. FUTURE PROFITABILITY AND FINANCIAL POSITION ON FACT . X. RECOMMENDATIONS .24 ANNEXES 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. MAP - Page No. Description of FACT's Existing Operations FACT Historical Income Statements FACT Historical Balance Sheets Product Schedule and Sales Price - Cochin II Project Technical Description - Cochin II Project Summary of Capital Costs - Cochin II Project Working Capital Requirements - Cochin II Project Forecast of Nitrogen Production - India Forecast of P2 0 5 Production - India Fertilizer Market - Demand Forecast for South India Fertilizer Market - Supply Forecast for South India Annual Cost of Production - Cochin II Project Forecasted Income Statement - Cochin II Project Sensitivity Analysis and Major Assumptions Project Breakeven Analysis Annual Foreign Exchange Savings FACT Income Statement Forecasts FACT Source and Application of Funds Forecast FACT Long-Term Debt Service Coverage Forecasts FACT Balance Sheet Forecasts Present and Proposed Major Fertilizer Plants in South India. 22 22 SUW4ARYAND CONCLUSIONS This report appraises a proposed major expansion of the producI. tion facilities of The Fertilisers and Chemicals, Travancore Ltd., (FACT), a public sector company in the State of Kerala, India. The Government of India (GOI) owns 81% of the company. Fertilizer production is a major part of India's efforts to improve agricultural output. This project, which will have a design capacity of 485,000 tons per year of granulated nitrogenous, phosphatic and potash (14PK)fertilizers, would make a significant contribution towards rmeeting India's increasing fertilizer requirements. A small by-product plant for 7,500 tons per year of cryolite which is used in aluminum manufacture is also included. Total financing required for the project is estimated at $50.7 ii. million (Rs 380 million), of which $19.6 million is in foreign exchange. GOT will provide the financing with at least half in equity and with the balance in loan. The proposed IDA credit of $20 million (Rs 150 million) will be relent by the Government as part of its loan. The loan to FACT will be at 3.5% interest per annum with a maturity schedule that includes three years of grace and ten equal annual repayments for each wiclhdrawal from GOI by FACT. Based on expected withdrawals the maximum life of the loan will be 16 years. FACT's existing plants are small, in part obsolete and have iii. encountered operating difficulties which have adversely affected the company's financial position. Followin,grecommendations of a 1969 IDA mission the company prepared a rationalization program which is now being implemented. The December 1970 appraisal mission reviewed this program and the Association is satisfied that FACT, with the help of some experienced consultants, is capable of improving existing operations, completing and operating a new urea plant (Cochin I) now under construction and of executing the proposed NPK project. To carry out such ambitious investments and to adjust its debt service to realistic expectations of cash generation, the company's financial position will be improved by increasing equity and rescheduling existing debt. The managing contractor for the project will be FACT E.ngineering iv. and D)esignf)rganisation (FEDO), a division of FACT, withimajor portions subcontracted to other engineering firms and local contractors. The project is based on conventional technology within the experience and capability of FEDO which has designed and constructed similar plants although not of the same magnitude. To assist with the project, the company has selected several international engineering firms as process subcontractors who will supply the necessary technical support. CGovernment-owned fertilizer plants in India have experienced v. substantial delays in construction and start-up difficulties and on the utilizaof capacity whlole have not yet been able to reach normal levels - tion. Various factors control of the plants if - have been responsible for tlhis, niot all within concerned. 1lowever, GOI has become increasingly the aware of the high cost of construction delays and undertutilizedplant. It has agreed that for the planned project the construction scheduile should not be more than 33 months. It is therefore expecte(dthat tlle project will be completed by March 1974. vi. Procedures for the procurement of foreign and domestic equipment have been agreed with FACT and GOI. The Government has indicated that it will reserve about 12% of the value of equipment and materials for Indian suppliers. These items are expected to be procured within the requirements of time and quality imposed by the project. All other equipment will be bid competitively by international tender with assurances given by GOI that all import licenses required will be promptly issued. Any reserved Indian equipment which is delayed and might endanger timely completion of the project will be promptly secured from other sources. The proceeds of the proposed IDA credit would be used for internationally bid equipment, imported materials for equipment on the "reserved list", costs of foreign process licenses, plant designs and consultant services as well as a portion of the local costs of FEDO's engineering and equipment erection costs. vii. Projections of Indian fertilizer demand and supply indicate that, even on optimistic estimates of local production, India will have an annual production shortfall through this decade of around 900,000 tons of nitrogen and 800,000 tons of phosphates. The foreign exchange required to import the tonnages required is substantial and emphasizes the hiigh priority of the proposed project, which will save India approximately $16 million per year in foreign exchange. viii. In FACT's marketing region in South India, projections of fertilizer demand and supply show nitrogen in balance in the latter half of the decade and a continuing shortfall in phosphatic fertilizer supply of around 150,000 tons per year (in terms of nutrients). Since the project's output will be NPK fertilizers with a high nutrient content and ease of application, no sales difficulties are expected. FACT's marketing organization will be strengthened by adding more distribution points and, on the basis of the company's successful marketing experience in the past, it should be able to handle the increased volume satisfactorily. Moreover, FACT will carry out a large seeding program for NPK to assure the successful introduction of its new products. The effectiveness of the company's marketing efforts will depend heavily on the availability of agricultural credit. The Government has assured IDA that FACT will have a suitable level of working capital to cover normal company operations and to finance required credit to the extent not available from the banking system. - iii - ix. The project provides a suitableeconomicreturn of 13.5%, which indicates that productioncosts of the project are competitiveinternationally. Profitabilityof the project is satisfactory,with an indicated financial return of 19.5%. The project is highly sensitive to relative changes in selling and raw materialprices and to any delay in completion of the project. x. There have been no previous IDA credits or Bank loans to the Government-ownedfertilizerindustryof India. IFC has participated in two private sector fertilizerprojects, (IndianExplosives,Ltd., in Uttar Pradesh and Zuari Agro Chemicals,Ltd., in Goa) and is considering a third. Indian Explosivesis successfullyin operationand Zuari Agro is anticipatedto start productionin mid-1972. IDA is also considering several other fertilizerprojectswith the GOI-ownedFertilizerCorporation of India (FCI), the largest fertilizercompany in India with five existingplants and three presently under construction. In addition, the Bank is ExecutingAgency for a UNDP-financedphosphatemining project study in Rajasthan. xi. Based on the assurancesreceived during negotiations,the project is suitable for an IDA credit of $20 million. I. INTRODUCTION The Governmentof India (GOI) has requested financing from the 1.01 InternationalDevelopmentAssociation (IDA) for a major expansion of fertilizerproduction facilitiesof The Fertilisersand Chemicals,Travancore Limited (FACT),which are located near Cochin port in Southiwest India. This expansion,designatedas the Cochin II Project, would add about 115,000metric tons per year (TPY) phosphates (as P2 05); 54,000 TPY potash (as K20); and 47,000 TPY nitrogen (as N) capacity to FACT's present capability. The increased productionwill be high nutrient content, granulated NPK 1/ fertilizersto meet the increasingdemand in South India and will permit FACT to market more balanced and competitivegrades of fertilizersthan their present products. The plant will produce six different grades with an average NPK analysis of 19-23-11. FACT has been producing fertilizersin Kerala State since 1948 1.02 and markets its own production,as well as fertilizerfrom the Government FertilizerPool, in the states of Kerala, Tamil Nadu, Mysore, Andhra Pradesh and the Union Territoriesof Goa and Pondicherry. FACT's existing factories are in Udyogamandalnear Cochin port (see Map). A major ammoniaurea factory (Cochin I) located about 20 km from Udyogamandalis expected to begin operations in mid-1971 and the proposed expansion would be adjacent to it. Both factoriesare served by major highway routes and are located adjacent to commercialwaterways. Cochin has railroad facilities at its factory and Udyogamandalhas railroad stationsnearby. The proposednew project was originallyconceivedby FACT as an 1.03 elementalphosphorusproject. An IDA mission studied this proposal in mid1969 and recommendedthat FACT should consider a more economic route for obtaining phosphoricacid, either by import or manufacturefrom sulfur and phosphate rock. IDA also recommendedthat FACT review its existing facilitiesand devise a scheme for increasingperformance. FACT has responded to both recommendationsand submitted a project feasibilityreport to IDA in October, 1970. An appraisal mission visited FACT in December 1970 to assess the proposed project and a program to rationalize existing operations. The Cochin II Project will produce sulfuric acid, phosphoric 1.04 acid, granularNPK fertilizers,as well as cryolitewhich is used in the productionof aluminum. The design is based on imported sulfur, ammonia, phosphate rock and potash; plus urea from the Cochin I plant. The! project includesnecessary port facilities to handle the large quantities of raw materials and all requiredoffaites. 1/ The nomenclatureused to describe multi-nutrientfertilizersis N-P-K, referring respectivelyto the % Nitrogen (N), % P2 05 (P), and % K20 (K). Thus 28-28-0 contains 28% nitrogen, 28% P2 05 and no potash; 17-17-17contains 17% of each nutrient. The term phosphate is used in all cases to refer to the P2 05 content. -2- FACT is presently in financial difficulty due to poor operating 1.05 performance at Udyogamandal and a 1-1/2 year delay in completing the Cochin I ammonia-urea project. Due to losses in recent years, FACT has not been able to meet portions of its maturing debts to GOT and negotiations are now being completed between GOT and FACT to restructure the company's debt. The appraisal report was prepared by Messrs. Donald E. Brown 1.06 and Anthony R. Perram of the Industrial Projects Department, based on missions to India in December 1970 and February/March 1971. II. A. FACT's EXISTING OPERATIONS History and Organization 2.01 FACT was incorporated iln 1943 as a private company with the Government of the State of Travancore (now part of Kerala) having a substantial holding. The company's management was taken over in 1960 by the Government of Kerala, by then the major shareholder. GOI, which subsequently acquired the majority shares, has managed the company since 1963. GOI presently owns about 81% of FACT with the State Governments of Kerala, Tamil Nadu, PHysoreand Andhra Pradesh holding about 15% of the shares and the remaining 4% is held by about 5,500 private shareholders. FACT began operations as a small producer of single super phos2.02 phate and since then has completed several expansion projects. FACT presently produces and markets ammonium phosphate, ammonium sulfate, mixed NPK products, and in 1971, will add urea production. The company's present capacity is about 7% of the total fertilizer capacity in India. With the Cochin Division the proportion will increase to about 12%. 2.03 FACT has five operating divisions which report to the Managing Director: (1) Udyogamandal (UDL), which operates the existing plants; (2) Cochin, which will operate the ammonia/urea plant now under construction and the Cochin II plant when it is completed; (3) FACT Engineering and Design Organisation (FEDO), the planning and engineering arm of FACT; (4) FACT Engineering Works (FEW), a small equipment ranufacturer; and (5) Marketing, which handles all ferti:Lizersales. These divisions are further described in Chapter VI and in Annex 1. B. FACT Management FACT has a 12-member Board of Directors of which eight are chosen 2.04 by GOI, two by Kerala, and two by private shareholders. The Board meets about seven times a year to review operations and decide on major investments, budget and policy issues. The Board has delegated considerable authority to the Managing Director, who is a Board member chosen by GOI. He acts as principal liaison with the shareholders and directs day to day operations assisted by the Finance Manager, who functions as his deputy. -32.05 FACT's overall managementcapabilitywas assessedby IDA in July and August 1969, includinga report by P. A. ManagementConsultants,Limited, of London. The major problems found then were: (1) managementinformation, such as production,marketing,and financial reportswere not complete nor prepared on time; (2) the UDL division had excessivestaff, with poorly defined lob specifications;and (3) maintenancewas not properly scheduled. Some improvementhas occurredbut the basic problems still exist. 2.06 The Managing Directorhas recentlybeen transferredand a new Managing Directorhas been appointedwho appears to be capable and is satisfactory to the Association. The Cochin II Project Manager has had production and engineering experience and appears to be capable. The appointment of highly competent people to the senior managementpositions (three key personnel have been lost recentlyby death or transfer)and continuityof management are particularlyimportant to the company and the execution of the project since the company is not deep in managementpersonnel. 2.07 The company recognizesthat cost accountingand reportingneed improvement. Reasons given for the unsatisfactoryreportingwere union problems within the accountingdepartment,installationof a new computer system, and concentrationon improving productionrates. However, the speed with which informationrequestedwas produced,was impressiveas was the amount of detail provided. The company intends to introducemonthly production cost data for each individualproductionunit, improve quarterly fi-. nancial statementsand budget goals for future operations,using realistic production targets to stimulate improvementsin operations. FACT has given assurances to IDA that its cost accountingand managementinformationsystem will be satisfactoryby January 1972. C. Financial Analysis of Existing Operations 2.08 Historicalincome statementsfor the fiscal years (FY) 1966 through 1971 are contained in Annex 2 and are summarizedbelow. Summary Income Statements (millionof Rs) Total 1966- Fiscal Years FY66 FY67 Net Sales (from operations) Operating Costs 25 31 Operating Profit (Loss) Non-OperatingIncome Gross Profit (Loss) Interest Taxes FY68 FY69 57 51 77 73 119 116 (6) 2 6 5 4 2 3 7 (16) 3 (3) (12) 2 21 (4) 3 11 7 6 6 10 7 (13) 6 (1) 9 _ Net Income (Loss) *Preliminaryfigures __ (7) 4 FY70 118 134 ___ -__ 3 FY71* 1971 133 136 529 541 9 38 -__ (19) (10 (9) -4FACT's earnings record has been unsatisfactory over the past years. Increasing sales and stable selling prices since 1968 have been offset by low operating performance and higher operating costs, particularly labor. These problems were quite evident in 1970. Net losses over the six-yea?r period total Rs 29 million or about 5.5% of net sales from operations. The corn-pany expects that fiscal 1971 will show a loss although the exact result will depend upon decisions to *bemade regarding deferred expenses for rmarket development. Historical 2.09 below. balance sheets are shown in Annex 3 and are summarIzed Summary Balance Sheets (millionof Rs) Fiscal Years Assets Current Assets Net Fixed Assets Other Assets Total Assets Liabilities and Capital Current Liabilities Long-Term Debt Equity: Share Capital Reserves & Surplus Total Total Equity Liabilities Current Assets/Current Long Term Debt/Equity *Preliminary & Capital Liabilities FY66 FY67 FY68 FY69 FY70 54 172 4 98 207 4 177 257 4 232 499 10 216 598 12 189 684 16 230 309 438 741 826 889 59 100 75 (4) 109 124 75 1 166 197 75 - 205 392 141 3 277 391 174 (16) 318 371 226 (26) 71 76 75 144 158 200 230 309 438 741 826 889 .9:1 58/42 .9:1 62/38 1.1:1 72/28 1.1:1 73/27 .8:1 71/29 .6:1 65/35 FY71* figures 2.10 Recent losses and delays in the completion of the Cochin I Project have prevented FACT from paying its maturing debt to GOI. By March 31, 1971 this unpaid debt had accrued to Rs 81 million including Rs 21 million interest which is now being renegotiated. Payments on outstanding loans to the Industrial Finance Corporation of India and on the Italian credits for Cochin I have been paid on schedule. GOI has been supplying funds to FACT, particularly for the Cochin I project, in the form of two-thirds debt and one-third equity. The combination of high debt and losses has made the company financially weak and has required increased short-term borrowings which have been difficult to obtain. The company now has a negative working capital position and high debt service requirements which will be eased by the rescheduling of the GOI loans and the provision of additional funds by GOI if required (para. 4.08). III. A. PROPOSED COCHIN II PROJECT Project Scope 3.01 The proposed expansion (Cochin II) has a design capacity of 435,000 TPY of granulated, high analysis NPK fertilizers and 7,500 TPY cryolite. The grades, production schedule and ex-factory sales prices for the NPK products and cryolite are shown in Annex 4. NPK production is based on imported phosphate rock, potash, sulfur and ammonia and includes manufacture of sulfuric and phosphoric acid as intermediate products. Urea will be obtained from Cochin I. The major plants will be based on licensed designs from contractors that have been selected by FACT. The project also includes the necessary facilities at Cochin port, about 15 km away. B. Project Description and Ecology 3.02 The phosphoric acid plant will have a design capacity of 115,000 TPY P205. FACT has a licensing agreement with The Engineering and Industrial Corporation of Luxembourg (Prayon) for phosphoric acid design knowhow. The process represents conventional and commercial technology, and Prayon and FACT both have considerable experience in design and operation of these plants. 3.03 The sulfuric acid (H2SO4 ) plant is a 330,000 TPY unit based on elemental sulfur. The process and size represent commercial and conventional technology and FACT's licensor, Chemiebau, Dr. A. Zieren GmbH & Company KG (Chemiebau), of Germany has adequate experience, including designs of up to 264,000 TPY sulfuric acid. 3.04 The NPK plant will have a design capacity of 485,000 TPY NPK based on technology from Wellman-Power Gas Inc., of the U.S. Their granulation experience includes about 20 commercial plants including Coromandel in India. 3.05 The cryolite plant will produce 7,500 TPY and is based on a similar plant that FACT now has under construction. 3.06 Port facilities and other offsites represent a major portion of the project. The Cochin Port Trust has agreed to provide a wharf and a mooring berth exclusively for FACT. GOI and FACT have agreed to provide the necessary assurances from the Cochin Port Trust as a condition of effectiveness of the IDA credit. FEDO's design of the port, transportation and site facilities was reviewed with FEDO's engineering staff and is considered adequate. 3.07 A phosphate fertilizer complex such as the Cochin II project discharges several streams that are potential pollution hazards. The effluents are fluorine and sulfur compounds that may be discharged to - 6the atmosphere, fluorine compounds that may be discharged in liquid wastes, and a solid material (gypsum) that is stored. FEDO has designed the project to control these effluents within normal practice in the industry. The cryolite plant offers the advantage of recovering fluorine from phosphoric acid manufacture and decreases a potential pollution problem. A more complete technical description of the project, including 3.08 pollution control is given in Annex 5. IV. A. Capital PROJECT COSTS AND FINANCIAL PLAN Costs is Rs 380 for the project required financing estimated The total 4.01 during construction. which includes interest million (US$50.7 million) These costs are summarized below and further details are given in Annex 6. Summary of Project Costs (in millions) Indian Rupees Total Lcocal Foreign Local U.S. Dollars Foreign Total 510.3 20.2 39.4 68.3 8.8 - 79.7 9.9 0.5 3.9 130.0 20.2 49.3 68.3 9.3 3.9 6.7 2.7 5.3 9.1 1.2 - 10.6 1.3 0.1 0.5 17.3 2.7 6.6 9.1 1.3 0.5 Sub-Total Working Capital Contingency 187.0 12.0 13.0 94.0 38.0 15.0 281.0 50.0 28.0 25.0 1.6 1.7 12.5 5.1 2.0 37.5 6.7 3.7 Total Project Costs Interest during Construction 212.0 21.0 147.0 - 359.0 21.0 28.3 2.8 19.6 - 47.9 2.8 Total Financing Required 233.0 147.0 380.0 31.1 19.6 50.7 Freight Equipment, Materials, Duty, Sales Tax Design, Erection Civil Works, Land, Offices Pre-Operating Expenses Technical Assistance The foreign exchange portion of capital costs, including working 4.02 capital, is estimated at $19.6 million. The foreign exchange costs are based on 12% of total equipment beLng reserved for Indian procurement and the expectation that approximately 40% of the internationally bid equipmnent will be won by Indian suppliers. 4.03 The above costs represent:preliminary estimates based on the escalation. project beginning in mid-1971 and iincludeadequate price Costs have been conservativelystated and the contingency,representing 10% of the direct project costs, should be sufficient. B. Working Capital 4.04 Total working capital requirementsfor the project at an annual productionrate of 436,500 tons (90% of capacity)are estimatedat Rs 209 million ($28 million) as shown in Annex 7. The above figure is based on four months accounts receivable,three months raw material storage (except urea and ammonia) and two months product storage. The initialworking capital is assumed at Rs 50 million ($6.7 million) of which the foreign exchange componentis $5.1 million. C. Financial Plan 4.05 The Rs 380 million financingneeded for the project will be providedby the Government,with at least half (Rs 190 million) in the form of equity and the balance as loan. The proceedsof the proposed IDA credit of Rs 150 million ($20 million)would be relent by the Governmentas part of its loan under a subsidiaryloan agreement. 4.06 The interestrate for the subsidiaryloan agreed to in negotiations is 8.5% per annum. GOI's normal policy is to approve the funds for the entire project and then disbursethem to the recipient in quarterly installments,each of which constitutesa separate loan. Each disbursement has a three-yeargrace and a ten-yearrepaymentperiod. Since the final disbursementis expected to be made in the fourth year after start of constructionthe last maturitywould be in the sixteenth year of the project. The financialforecasts in the annexes correspondto this maturity schedule. Since the loan from GOI to FACT is wholly a rupee loan, the exchangerisk remains with the Government. 4.07 The followingtable gives a summary of the total estimated sources and applicationof funds for FACT as a whole during implementation of the project (Refer to Chapter IX). Summary of Source and Applicationof Funds during Project Implementation1971/1974 (millionsof rupees) Sources Long-TermDebt Equity Cash Generation- UDL/CochinI Short-TermFunds Total Application 190 213* 380 60 843 *IncludingRs 23 million for Cochin I. Cochin II Project UDL and Cochin I Debt Service Total 380 199 264 843 - 8 - 4.08 The forecastedcash generationis based on UDL operating at improved levels and Cochin I achieving its expected production. GOI and FACT are currently renegotiatingthe company's debt. It is expected that the actual amount of reschedulingwill be Rs 85 million with repayment beginning in FY 1972 and ending five years thereafter. Completionof the arrangementsfor the debt reschedulingwill be a conditionof effectiveness of the proposed credit. Although IDA anticipates that further rescheduling may be necessary for some arnounts; due towards the end of FY 1972, the Association has agreed to this scheme because (a) negotiationsfor the rescheduling are virtually completedand (b) the Governmenthas agreed to keep the company in a liquid position during constructionwith a current ratio of at least 1.5:1 being obtained at the start of commercialproduction. 4.09 To protect against an overrun in project costs (includingCochin I) or shortfall in cash generation,GOI has agreed to provide funds necessary to complete the project and put FACT in a sound financial position including adequateworking capital. To this end the Governmentwill put a minimum of 50% of the funds representingCochin I and Cochin II investments in the form of equity by completionof Cochin II. GOI also agreed to set a goal of a long-term debt/equityratio of not greater than 55/45 for the company after Cochin II begins commercialoperation. The Association's projectionsshow that at the time Cochin II starts up, FACT should be in a sound financialposition (a long-term debt/equityratio of about 50/50 and a current ratio of about 1.5:1). V. A. PROJECT EXECUTION Project Management 5.01 FEDO will act as managing contractorfor the Cochin II project. IDA's evaluationof FEDO as an engineeringcompany, is given in Annex 1. In view of the overall size and complexityof Cochin II, FACT has agreed to employ an experiencedAssistant Project Manager plus one experienced Engineer to assist FEDO in budget and schedule control and in general engineering,procurement,and constructionduties. The Assistant Project Manager will remain until completionof the project and the Engineer is expected to stay 2-3 years. 5.02 Tn addition, FACT will use selectedprocess licensors in design, equipment selection,constructionand start-up. The extent of such assistance by the licensors (beyond their initial process package) is expected to be as follows: -9- Man Months Sulfuric Acid (Chemiebau) PhosphoricAcid (Prayon) NPK (Wellman-Power Gas) 8-12 12-18 60-80 The assistanceis primarily aimed at adding depth and experienceto the FEDO organizationto ensure the success of Cochin II. FEDO has already establishedcontinuingassociationswith Chemiebau and Prayon for sulfuric and phosphoricacid designs, respectively,and has recently concluded a contractwith Wellman-PowerGas for the NPK plant. FACT is now completing final agreementswith Chemiebau and Prayon and arranging for the engineering personnel described above. IDA has reviewed these agreementsin draft form and found them acceptable. Their satisfactoryconclusionis a condition of effectivenessof the proposed credit. To avoid FEDO's overextendingits management and engineering 5.03 staff capacity during project execution,FEDO will not accept any engineering contractsin excess of Rs 1,500,000 ($200,000)each without first consultingwith IDA until engineering for Cochin II is substantially completed. FACT has agreed not to undertake any other major capital investment program in excess of Rs 7,500,000 ($1,000,000)per year without IDA's consent. B. Project Schedule and Procurement on for the project path schedule FEDO has updated its critical 5.04 the basis of a completiontime of 33 months. For appraisal purposes, project constructionhas been assumed as 36 months, but a concerted effort will be made to realize the 33-monthschedule. The shorter schedule is largely dependent on efficient implementationof procurement. GOI has expressed a strong desire to minimize project execution time and has agreed to the 33-monthschedule as the governing criterion to which all its and the company's actions will be geared and has modified its procurementpolicy with this objective in mind. The Governmentagreed that the equipment and materials reserved 5.05 for procurement from Indian supplierswill be limited to about 12% of the total estimated equipment value. IDA is satisfied that the "reserved list" includes only those items that do not have critical delivery time and can be supplied from Indian firms in adequate quality. If it should become evident affect that delivery of any equipment on the reserved list would adversely the project's criticalpath schedule, then the Governmentwill permit such items to be shifted promptly to internationalor other procurementsources. - 10 - All other equipmentwill be bid by internationalcompetitive 5.06 tender, including India. Indian suppliers will be given a 15% cost preference in bid evaluationscompared against the CIF India price of competitive equipmentbids. GOI has given assurance that after FEDO has completed its bid analysis and decided the procurementsource, any required import licenseswill be issued promptly. In collaborationwith the process licensors,FEDO will prepare 5.07 suitablebid packageswhich will permit qualified Indian suppliers to compete on the smaller of the packages but still maintain project schedule and equipmentstandardizationrequirements. The proposed IDA credit will include an estimated $0.5 million 5.08 of foreign exchangecosts for the import of materials and componentsto be used by Indian suppliers for items on the "reserved list". While to the extent practical these imports will be subjected to international shopping, their speed of procurementwill be the governing factors. FEDO will coordinatethe import of such materials and components. C. Allocationof IDA Credit The proceeds 5.09 (see Annex 6): of the proposed IDA credit would be used as follows Use of IDA Credit $ Million 1. 2. 3. 4. 5. Equipment Equipment (for foreign components of "reserved list") and Equipment Erection Engineering Licensors (a) (b) FEDO TechnicalAssistance Unallocated Total 15.2 0.5 1.3 0.5 0.5 2.0 20.0 The allocationof IDA funds to the above categoriesis approximateat this time and may have to be revised somewhatwhen FEDO has completedits detailed engineeringwork. The credit will cover the CIF cost of imported equipment and the ex-factoryprice (excludingtaxes) of locally procuredequipment that is internationallybid. As mentioned before, the credit will also include the CIF cost of imported foreign componentsof locally procured equipmenton the "reservedlist", and the foreign exchange costs of process licensesand consultants'services. A portion of FEDO's local costs for engineeringand equipment erectionis also included. The estimated foreign - 11 - exchange content of the proposed credit is about $15 million, which assumes that 30% of the internationally bid equipment is won by Indian suppliers (para. 4.02). The projected disbursement schedule for the IDA credit is contained in Annex 6. VI. A. MARKET AND MARKETING Present Situation in India 6.01 A major goal of Indian economic development is self-sufficiency in agriculture, including fertilizer production. However, India currently imports about half of the required fertilizer nutrients as finished products and as intermediate raw materials. Nitrogen, the major fertilizer nutrient, is produced in India primarily as ammonia and urea with most manufacture based on naphtha from imported petroleum feedstocks. Current plans propose increasing reliance on fuel oil and indigenous coal as raw materials to produce nitrogen fertilizer. India permits some ammonia imports, but imposes a 60 percent duty on the CIF price. Use of imported ammonia may increase as a result of recent trade agreements between India and Iran. 6.02 Virtually no phosphate material is produced in India. While feasibility studies are about to start (financed by UNDP with the Bank as Executing Agency) to develop promising phosphate rock deposits in Rajasthan these deposits are not likely in the near future to produce enough rock to make India self-sufficient. India imports large amounts of phosphate rock and, in recent years, the Government has granted permission for three companies 1/ to also import phosphoric acid. Potash, or potassium chloride, is not produced locally; so all requirements are imported, either as potash or in a finished NPK product. Fertilizer consumption and production for the period 1964-1970 6.03 are shown below based on data from the Fertilizer Association of India, the Ministry of Food and Agriculture and IDA. 1/ Madras, Zuari Agro, and Indian Farmers Fertilizer Cooperative (IFFCO). - 12 - FertilizerConsumptionand Productionin India (thousandsof tons) Nitrogen (N) Phosphate (P205) Apparent Apparent ConsumptionProductionImports ConsumptionProduction Imports FY FY FY FY FY FY 65 66 67 68 69 70 580 530 660 920 1,200 1,450 240 240 310 400 560 720 340 290 350 520 640 730 160 160 200 290 410 560 130 120 150 210 210 220 30 40 50 80 200 340 6.04 Consumptionof nitrogen increasedduring the six-year period at an average annual rate of about 20%. Local productionrose even more quickly (about 28% per year) but was not able to catch up with demand. Phosphate consumption increased at about 28% annually and here too production was unable to meet demand. Low production levels (about 60% of capacity) in existing plants have contributedto these deficits. Furthermore, while a more normal ratio between nitrogen and phosphate should be approximately2:1, the actual ratio in India in 1969/70was about 3.3:1. Consumptionof phosphate fertilizerthereforehas lagged substantially behind that of nitrogenous fertilizer.Foreign exchange expendituresfor imports of nitrogen and phosphate have averaged in excess of $150 million annually during recent years. 6.05 Annexes 8 and 9 give lists of the fertilizerplants now in operation, under construction,or planned in India; recent production;and major sources of finance. B. Market Forecast for India 6.06 Estimates for supply and demand of nitrogen and phosphate fertilizer nutrients for all of India for the current Fourth Five-Year Plan (ending March 31, 1974) and the Fifth Five-YearPlan (endingMarch 31, 1979) are shown below. These projectionsare based on a previous Bank study (September30, 1970) and a projectionrecently preparedby the GOI (Ministry of Petroleum and Chemicals). The demand projectionsthrough 1973/74 are taken from the Bank study mentionecd above and are based on a projection model that included historical data plus growth rates in area irrigated and in fertilizer consuming crops. The figures for the Fifth Five-Year Plan (1974/79) are based on IDA's extrapolation of these data and its estimate of completiondates for individualplants (Annexes 8 and 9). - 13 Market in India Fertilizer of tons) (thousands Demand FY FY FY FY FY FY FY FY FY 1,760 2,110 2,500 2,910 3,300 3,700 4,100 4,600 5,200 71 72 73 74 75 76 77 78 79 Nitrogen Supply 850 1,470 1,830 2,050 2,260 2,590 3,390 3,860 4,230 (N) Deficit 910 640 670 860 1,040 1,110 710 740 970 Demand 750 970 1,220 1,510 1,700 1,900 2,100 2,300 2,600 Phosphate Supply (P 2 05 ) Deficit 230 380 430 530 750 940 1,310 1,540 1,730 520 590 790 980 950 960 790 760 870 The table indicates a substantialnitrogen deficit through the 6.07 period. The deficit decreases slightly in the early years as new Fertilizer Corporationof India (FCI) and FACT urea units come on stream but widens again thereafter. The phosphatedeficit grows from about 500,000 tons per year to 800-900,000. The supply forecastsare based on a realizablebut optimisticschedule for new projects and on all plants achieving a 90% capacityutilization. The assumptionsused in the forecasts are explained in Annex 8. Therefore, the supply figures representIDA's best estimate of the maximum fertilizerproduction India can reasonablybe expected to achieve. If the assumptionson capacityutilizationand schedule of projects are not fulfilled,then the estimated supply could be 10-20% below the above forecasts. C. FertilizerMarket in South India Estimated consumptionof nitrogen and phosphate from 1969/70 6.08 (actual) to 1978/79 for the four southern states (FACT's marketing area) is given in Annex 10. Average annual growth rates anticipatedby FACT through 1973/74 are about 10% for nitrogen and 20% for phosphate and thereafterare assumed for both nutrients at about 13%. It has been assumed that phosphate consumptionwould increase at a faster rate than nitrogen until the ratio reaches 2:1. FACT assumed fertilizergrowth rates below those for the rest of India because of the already higher fertilizerapplicationin South India. The FACT estimates are the most conservativeand are used in this evaluation. They are based on extensive market surveys and the requirementsof N, P and K for the area's main crops (rice, wheat, tea, fruits, nuts, spices, sugar, cotton, vegetables, and tobacco). The projected supply and demand of fertilizerfor South India 6.09 are shown below. The supply data are taken from Annex 11. - 14 - FertilizerMarket in South India (thousandsof tons) Demand FY FY FY FY FY FY FY FY FY 71 72 73 74 75 76 77 78 79 6.10 600 670 730 810 910 1,030 1,180 1,330 1,500 Nitrogen (N) Deficit Supply 140 340 550 670 720 810 1,180 1,330 1,530 460 330 180 140 190 220 0 0 -30 Demand Phosphates(P2 05) Supply Deficit 230 280 330 400 470 550 620 700 790 The locations of the fertilizer producers 110 180 230 260 330 380 490 530 630 in 120 100 100 140 140 170 130 170 160 South India are shown in the map along with major broad gauge rail lines to illustratethe market area served by FACT. The principal competitorsto FACT will be Zuari Agro (Goa), Madras (Tamil Nadu), and Coromandel(Andhra Pradesh). IDA's assessmentof supply assumes that the above three producerswill operate at 90% capacity from 1974/75onward. Superphosphateproductionis projected at 40,000 TPY P2 05 based on FACT's estimate. Other proposed projectsin South India are CoromandelExpansion (II and III), Mangalore,Tuticorin (SouthernPetrochemicalIndustriesCorporation),Ramagundam,and Occidental at Vizag. These are assumed to come into productionover the period 19751979; however, the probabilityof all five of these projectsmaintaining the schedule given is consideredunlikely. These productionforecastsare more optimisticthan the all-India forecast in Annexes 8 and 9 to show the maximum competitionthat FACT would have to contendwithin its marketing area. 6.11 In spite of the optimisticsupply forecast, a phosphateproduction deficitwill still exist in South India and FACT should have no sales difficultyas far as total market demand is concerned. The phosphatedeficit ranges from 130-170,000TPY over 1974-1979and would be met by a net inflow from North Indian plants (such as FCI Trombay) or imports. The supply deficitwill remain high unless a number of the other projectsproceed at a considerablyfaster rate than now appears likely. 6.12 The nitrogensupply could be essentiallyin balance in South India by 1976/77based on FACT's conservativeestimateof consumptionand the optimistic forecastof supply. Nevertheless,even if such balance could be achieved the nitrogen from Cochin II will be sold as NPK fertilizerand, with the large deficit of P2 05 expected, the company'sNPK fertilizersshould be marketed with no difficultyeven if competitiondevelopsin straight nitrogen. The company's competitiveposition is further discussedin paras. 6.21 to 6.23 below. - 15 - D. FACT Marketing Area and Handling System 6.13 The marketing area of FACT in South India includes the four states of Kerala, Tamil Nadu, Andhra Pradesh, and Mysore. Within this area, FACT has establishedan extensive distributionnetwork of godowns,wholesale and retail dealers, and a marketing staff to service the more than 6,000 final distributionpoints. At present the company markets about 460,000 TPY fertilizers of which 250,000 TPY are purchased. Tonnagesmay increase to about 700,000 TPY with Cochin I and about 1,000,000TPY with Cochin II, excluding amounts for seeding programs or other outside purchases. To handle this expanded tonnage, FACT expects to utilize its existing distribution network more efficientlyand also to establish additionaldistribution points. 6.14 The market share that the company expects to obtain in each of the four southern states is shown below: FACT Market Share by Area Market Kerala Tamil Nadu SouthernMysore Northern Mysore Andhra Pradesh % of Market N P205 K20 70 25 25 12 12 70 25 25 7 7 70 25 25 7 7 Rail Freight Avg. Cost Rs/ton 12 35 35 45 45 Sales Headquarters Trivandrum Madras Bangalore Bangalore Hyderabad Selling Points Dec. 1970 3,000 2,100 210 (inc. above) 500 6.15 Kerala forms the principalmarketing area. At present FACT markets about 70% of the total supply to the state and its forecasts are based on maintaining this percentage. No other producer can effectively compete with FACT in Kerala due to the company's location advantage and its wellestablishedname. FACT has a large sales network in Tamil Nadu and Southern Mysore and estimates that it will supply 25% of the total market demand. The lower share is due to the longer freight distanceinvolved and the competition from Madras Fertilizerand Zuari Agro, both of which will be marketing similar products. 6.16 The other marketing areas contain northern Mysore and Andhra Pradesh. These are much farther from FACT and substantial competitionmay be expected from Zuari Agro and from Coromandel. Therefore,FACT has estimated that it will obtain only 12% of the nitrogen market and 7% of the phosphate and potash market. The market penetration projectedseems reasonable for all areas. FACT reports an average Rs 138/ton ($18.40/ton)distributioncost, 6.17 which includescharges for freight,storage, marketing overhead, credit and dealer comnission. These costs compare favorablywith marketing costs in - 16 other countries. Distributioncosts, plus sales and excise taxes, are passed on to the farmer. About 70% of the fertilizeris sold under some credit arrangement. Fertilizercredit is discussed further in paras. 6.24 and 6.25. E. 6.18 NPK Seeding Program Presently FACT sells the followingtonnagesof fertilizerannually: 110,000 20,000 60,000 100,000 170,000 NPK Mixtures Superphosphate Ammonium Phosphate Ammonium Sulfate Urea 460,000 Total While sales of the above provide FACT witlhvaluablemarketing experience, they provide little help in developingmarkets for the NPK's to be produced in Cochin II. The analysisof the above NP and NPK mixtures varies but they are generallymuch lower in nutrient content than those expected from the project. 6.19 It will be necessary for FACT to develop a comprehensiveseeding program for Cochin II based on the import of grades conformingas closely as possible to those to be produced. This is particularlyimportantsince most grades are not now available to the farmers. The specific grades are listed in Annex 4 along with detailed commentson the fertilizerrequirementsof the area and the basis for the selectionof the grades to be producedby the project. To be successfulthis program should provideNPK fertilizersin suitablegrades in at least the followingamounts (in tons per year): FY 72 FY 73 FY 74 25,000 - 50,000 NPK 100,000 - 150,000 NPK 200,000 - 250,000 NPK FY 75 As necessary to supplementproduction During negotiationsit was agreed that FACT will implementa suitable seeding program and that the Governmentwill import fertilizersfor that purpose as necessary. F. 6.20 Sales Prices and Competition Typical current retail fertilizerprices in India are: Source GovernmentPool GovernmentPool Coromandel Grade 14-14-14 15-15-15 28-28-0 Ex-plant prices Rs/ton US$/ton 757 832 1,270 101 111 170 - 17 - Witlhthe exceptionof 28-28-0,the grades proposedby FACT (Annex 4) are not now marketed in India. Therefore,FACT calculatedthe current prices for its NPK productsbased on the above prices of the Governmentpool and Coromandel (Annex 4). The average grade of 19-23-11would thus have an ex-factorysales price of Rs 928/ton ($124/ton). 6.21 Fertilizersales prices have been constant for about two years during which time raw material prices on the whole have increased slightly. Currently, only Coromandel is producing and marketing high analysis, ureabased NPK fertilizers in India. When Madras and Zuari Agro come on strces in 1971 and 1972 respectively with new NPK capacity, the price could rea- sonably be expected to drop due to increasedcompetitionbut this tendency will probably be offset by the continuingshortfall in supply. IDA concludes, therefore, that prices are likely to remain at about existing levels and represent a reasonable basis for evaluating the project. 6.22 FACT will face major competition in its market area from Coromandel and Madras but other producers will be less competitive. Zuari Agro will market a bulk blend based on urea and ammonium phosphate. Although the grades can be the same, bulk blends are not generally as acceptable as the granular product that FACT will manufacture. Also, Goa and the nearby area of Mysore are serviced only by narrow gauge rails so transportation becomes a major problem for Zuari Agro. 6.23 Manufacturers in north India will not be able to compete very well in South India due to higher freight costs and product disadvantages. Thus, competition from Northern producers should have limited impact and FACT should be able to sell its output within its marketing area at projected prices. G. Agricultural Credit 6.24 The importance of credit to fertilizer consumption is well recognized in India. At present credit is provided by the commercial banking system and by the GOI to cover purchases from the Government Pool. The Fertilizer Association of India (FAI) has estimated total fertilizer credit for India of Its2,970 million ($400 million) in 1970/71. Based on consumption forecasts, the requirements in 1974/75 will be approximateLy Rs 5,000 million ($670 million). While availability of credit has thus far not seriously restricted growth in fertilizer demand, continuing efforts will be necessary if future consumptionforecastsare to be met. To fulfill this need FAI recommended comprehensive changes in the agricultural credit policy of India including establishment of a Fertilizer Credit Guarantee Corporation by the GOI. This corporation has not yet been established. Other programs to improve fertilizer credit are being studied by GOI, the State Governments, and the Reserve Bank of India. 6.25 FACT estimates its total fertilizer credit needs in the latter 1970's at about Rs 800 million annually, of which it expects to provide - 118 - about Rs 120 million from its own resources. The company's financialprojections indicate that FACT can readily provide this amount. Total credit will be supplied as follows (in Rs million): Dealers CommercialBanks Cooperatives FACT 200 400 80 120 Total 800 The above distributionof credit sources has been proposed by FACT to reduce the amount of credit to be suppliedby FACT and its dealers through increased relianceon commercialbanks. The company has been successful in involving local banks in selected areas in extending fertilizercredit but this system is not in wide use at present. FACI's marketing efforts depend on the availability of such credit, and the Governmenthas agreed to provide adequate working capital if funds are not available from commercialbanking sources. VII. OPERATING COSTS A. Raw Material Costs 7.01 Raw material costs representabout 70% of total production costs and their impact on the company's profitabilitytherefore is significant. As noted before, the project is based on urea from Cochin I plus imported phosphate rock, sulfur, potash and ammonia. At full production,annually recurring foreign exchange expendituresfor the importedraw materials alone are approximately$21 million at present prices. Prices of raw materials have fluctuatedwidely over the past two to three years which makes accurate forecasts of raw material costs difficult. The following table shows the present prices (actually paid by FACT and used in the financial forecasts) for these materials and the price trend (used in the economic return calculations) expectedby IDA. Comparisonof Present and Future CIF Prices Present Prices Delivered CIF Plant Site $/ton Phosphate Rock Sulfur Potash Ammonia (plus 60% duty) Urea (from Cochin I) Rs/ton Assumed Future Prices Rs/ton $/ton 30 36 53 227 270 400 245 290 423 24 30 40 37 278 318 37 620 ($82.70) 60 - - There are no import duties on phosphate rock, sulfur and potash. Other raw materials,such as filler and coating agent, are available in India. - 7.02 All imports now channeled of sulfur, through 19 - phosphate the Minerals rock and potash and Metals Trading into India Corporation are (MMTC), a government-ownedcorporationwhich contracts for supplies from international sources,usually under bilateral trade agreements. MMTC suplies the materials to the users such as FACT at its import price plus a fee. Present raw material prices are generallyhigher than current international prices due to such bilateral arrangements. Ammonia will be supplied for Cochin II through a long-term contractrecently concludedbetween Iran and GOI. GOI has bagging agreed supplies to permit to the extent import of all not available raw materials needed including in India. 7.03 Present raw material prices are higher than those expected by IDA in the longer run. IDA's assumptionsare based on internationalprices and assume that freight rates, which have greatly escalatedover the past two years, will decline to more normal levels. Present prices have been used in financialprojectionsto allow an accurate comparisonwith present NPK prices. The effect of raw material and fertilizerprice changes on the company'sprofitabilityis discussedin Chapter VIII. 7.04 The project analysis does not include the possibilityof supply of phosphate rock from the mining project now being consideredin Rajasthan (para. 6.02). It is too early to predict the quantity and price of any indigenousrock supply, and it is not anticipatedthat Rajasthan phosphate rock will be supplied to FACT in the near future. Cochin II will, however, be designed to permit use of Rajasthan rock when it does become available. B. ProductionCosts 7.05 Productioncosts were calculated for the average NPK grade to be produced (19-23-11)and include costs for sulfuric acid and phosphoricacid. Details of these costs are given in Annex 12 for various levels of plant utilizationand are summarizedbelow for the normal operating level assumed at 90% of design capacity. Annual ProductionCosts- at 90% of Design Capacity (Rs million) NPK Variable Costs Fixed Costs Total ProductionCosts /1 Cryol:Lte 258.2 46.9 8.3 1.1 305.1 9.4 Includes depreciation,but no intereston long-term debt. 7.06 The high proportionof variablecosts reflects the large raw material component. Since the raw material costs used in the projectionsare higher than the estimated trend, they should not increase further unless - 20 - affectedby bilateral arrangements. Overall productioncosts are therefore consideredconservative. A direct comparisonof Cochin II's projected operating costs with FACT's existing cost of productionis not possible since the grades produced differ markedly in nutrient content and composition. However, a comparisonon a cost per ton nutrient basis indicatesmuch lower productioncosts at Cochin II than FACT can obtain at UDL Division. While cryolite representsonly about 3% of the project's output and will hardly influence the company'sprofitability,it is neverthelessan importantproduct in that it is crucial in the productionof aluminum and would help to replace current imports. 7.06 The project will provide direct employment for about 500 skilled and semi-skilledpersonnel. The lprojectis capital intensive and labor costs representonly a small fractionof operating costs. No attempt was made to project employment created as an Lndirectresult of the project in ancillary industries. VIII. FINANCIALAND ECONOMICANALYSIS OF THE PROJECT A. FinancialAnalysis and SensitivityTests 8.01 Detailed income statements for the project are containedin Annex 13. Summary statementsof these forecastsare shown below: Summary Income Statements- Cochin II (in millions of rupees) FY75 FY76 FY77 FY78 FY79 FY80 FY81 FY82 FY83 FY84 FY85 FY86 FY87 CapacityUtilization (%) 50 80 90 90 90 90 90 90 90 90 90 90 90 Sales 195 353 413 422 422 422 422 422 422 422 422 422 422 Operating Costs 162 269 308 315 315 315 315 315 315 315 315 315 289 Gross Profit Interest Profit before Taxes Taxes Net Profit 33 14 84 15 105 107 107 107 107 14 13 11 10 8 19 69 91 94 96 97 99 101 - - - - - 53 54 56 56 57 58 19 69 91 94 96 44 45 45 46 47 47 107 6 107 5 107 3 107 2 107 1 133 - 102 104 105 106 133 58 73 48 60 8.02 The project shows a small profit in the first year of production in the next two years as are expected to rise rapidly (FY 1975). Profits production increases to 90%, and remain at a level above Rs 90 million - 21 - per year until FY 1980, when - after a tax holiday of five years - the impact of taxes (about 55%) forces net profit down to approximatelyRs 45 million per year. 8.03 Due to the relativelyhigh selling prices of fertilizer:LnIndia, the project is very profitable and, after taxes become applicable,net profit equals 11% of sales and 24% of share capital. If Cochin II were carried out in a separate corporation,it would have a quite satisfactorydebt service coverage of around 4.0 times in the early years when no taxes are paid, and about 2.9 times thereafter. 8.04 The internal financial return (IFR) for the project has been calculated at 19.5%. The assumptionsused in this analysis,as well as for the sensitivity tests, are shown in Annex 14. 8.05 The project has been tested for various factors and is very sensitive to changes in raw material and product selling prices. If raw material prices are reduced to the level of the expected long-rangetrend, selling prices could be decreased 7% without reducing the financial return. With current raw material prices and a 10% reduction in selling price, the IFR decreases to 9.3%. The project is not appreciablyaffectedby changes in production 8.06 levels. The IFR for a maximum of 80% productionbeginning in the second year and 100% beginning in the fourth year are 16% and 21% respectively. A project delay, however, is critical. A one-year delay with a resulting 15% cost overrun would decrease the IFR to 9.2%. If this delay were followed by other adverse circumstances,such as a 10% decline in selling prices, the project would show a negative return. 8.07 As shown in Annex 15, the profit break-even point for the project at the assumed selling prices is 37% of capacity. At normal production the project would break-even profitwiseif NPK prices were reduced as much as 22%. The cash break-evenpoint on the same basis including the service of long-termdebt would require sales at 32% capacityor an NPK selling price of Rs 710/ton (22% reduction). B. EconomicAnalysis The internal economic return (IER) for the project is 13.5% as 8.08 shown in detail in Annex 14 and is based on the followingmajor assumptions: (1) Raw material costs are the long range trend prices shown in para. 7.01. (2) The average selling price is equivalentto expected CIF import prices of N (as urea); P2 05 (as phosphoricacid), and K20 (as potash) in the proportions required for the -- 22 - project's average NPK formulation£A2 notional manufacturing costs and profits if produced in a modern and efficient plant in one of the industrializedcountries. 8.09 Although the above analysis has its shortcomings,it still offers the best comparisonwith importedNPK products, since the grades to be manufactured at Cochin II are not avaLilable internationally. This evaluation indicates that when using internaLtional input prices, the project would be competitivewith imported NPK fertilizerswhile earning at the same time an acceptableeconomic return. 8.10 Sensitivityanalyses of the economic return show the same trends as the financialreturn with the project being very sensitive to relative changes in raw material costs and selling prices. Again, a delay in project completion reduces the return substantiallyto 6.0% and a delay coupled with a relative selling price reductionof 10% results in a negative return. Details of the sensitivity tests are contained in Annex 14. 8.11 As shown in Annex 16 the project would realize net annual foreign exchange savings of $15.6 million at normal 90% production. The local currency expenditurerequired to achieve this savings is Rs 92 million ($12.2 million) per year. C. ImportedVs. ManufacturedPhosphoricAcid 8.12 In consideringCochin II, an analysishas been made to see if a more optimum solutionwould be to use imported phosphoricacid rather than to produce acid from imported raw materials (phosphaterock and sulfur). Essentially the decision to import phosphoricacid would save about $18 million in capital costs, of which $4-6 million would be foreign exchange. However, local productionof acid would save annually about $3.7 million in foreign exchange operating costs, albeit at an increasein local costs of about $3 million equivalentper year. Details of this evaluation are contained in Annex 16. 8.13 As shown more fully in Annex 14, an economic return has been calculated on a separate project to produce phosphoricacid. The return has been based on two alternativeassumptionsof delivered cost of imported P205 - $160 per ton and $150. The return at the higher cost is 13.7% and at the lower 9.0%. The foreign exchange savings (para. 8.12), plus the possible use of phosphate rock from Rajasthan support the decision to produce rather than import phosphoricacid. IX. FUTIUREPROFITABILITYAND FINANCIAL POSITION ON FACT 9.01 Forecastedincome and cash flow statements for the company as a whole through FY87 are containedin Annexes 17 and 18. Consolidatedincomes statement forecasts through FY79 are summarizedbelow: - 23 - Summary Income Statements-- FACT (millionof rupees) FY72 FY73 FY74 FY75 FY76 FY77 FY78 FY79 Net Sales 251 379 14 31 72 29 Profit before Taxes Tax Provision (17) - Net Profit Operating Profit Interest Debt Service Coverage 421 586 721 774 783 783 86 24 115 34 173 30 193 26 195 21 195 17 43 - 62 - 81 - 143 - 167 - 174 50 178 85 (17) 43 62 81 143 167 124 93 .9 1.6 1.8 2.1 2.5 3.5 :3.0 2.8 9.02 FACT is expected to show an operatingprofit in FY72, Cochin I's first year of operation;however, this will be more than offset by interest expense and a net loss for the year of Rs 17 million results. A net profit of Rs 43 million is expected in FY73 which will increase in succeedingyears as Cochin I output increases and Cochin II comes on stream. Profit reaches a peak in FY77 at a level of Rs 167 million when Cochin II reaches 90% capacity. Net profit is reduced in FY78 when income taxes are first applicable and again the next year when the full tax impact is felt. In that year net profit reaches a plateau of about Rs 90 million, or 11% of net sales. This profit level is consideredsatisfactory. 9.03 The likelihoodof FACT profitabilitybeing in line with estimates rests primarily on its ability to completeCochin II within the time and cost now forecast,and to reach expected productionlevels at Cochin I and II. UDL's contributionto profits is marginal and, after completionof Cochin II, will amount to only about 7% of profit before interest and taxes, while those from Cochin I and II are 38% and 55% respectively. 9.04 As the company'searnings improve,its cash buildup should enable FACT to begin paying dividendson share capital. It has been assumed that Rs 44 million, or 10% on share capital,will be paid each year beginning in FY76. This will representonly about one-half of net profit after full taxes are reached in FY79 and furtherpaymentsmay be possible. 9.05 After FY72 when some debt may have to be postponed (para. 4.08), debt service coverage,Annex 19, is adequateat 1.6 to 1.8 times in FY73 and FY74 and above 2 times in each year thereafter. Since GOI has assured IDA that FACT will have adequate liquidityduring project execution,protection against the lower coveragein the first three years is provided. 9.06 Forecastedbalance sheets for 1972-1987are containedin Annex 20. Pertinent data from these for FY72 through FY79 are as follows: - 24 Selected Balance Sheet Items - FACT (in millions of rupees) FY72 FY73 FY74 FY75 FY76 FY77 FY78 FY79 Current assets Current liabilities 229 309 Net working capital (80) (32) 280 312 388 302 557 364 698 368 858 1,024 1,145 370 420 452 86 193 330 488 604 693 Current ratio .7:1 .9:1 1.3:1 1.5:1 1.9:1 2.3:1 2.4:1 2.5:1 Long-Term Debt/ Equity Ratio 63/37 54/46 47/53 38/62 30/70 23/77 17/83 12/88 9.07 The long-term debt equity ratio improves from the present 65/35 to better than 50/50 by March 1974 and the current ratio improves to 1.5:1 by March 1975. These ratios assume defermentof Rs 85 million debt (see para. 4.08) and no further increase in long-term funds above the the financing for Cochin I and Cochin II. After 1974 the company's financial position improves steadily and its long-termdebt/equity ratio is forecasted to reach 12/88 by FY79. Net working capitalbecomes positiveby FY74 and increases each year. Dividends and debt prepaymentswill not be permitted if they would reduce the current ratio below 1.5 to 1. X. RECOMMENDATIONS 10.01 During credit negotiations,agreementwas reached between the Government,FACT and IDA on the followingprincipal points: (i) GOI will furnish at least Rs 190 million in equity and the balance (not less than Rs 150 million) in loan for the project (para. 4.05); (ii) GOI will provide additionalfunds as necessary to complete the project and Cochin I; assure a sound financial position for FACT at the time Cochin II is completed;and maintain an adequate liquidityposition of FACT during project execution (para. 4.09); (iii) GOI will promptly issue import licenses as requiredincluding such items on the "reservedlist" which cannot be procured in India without adversely affecting the project (paras. 5.05, 5.06); (iv) GOI will provide credit facilitiesfor marketing of FACT's fertilizersto the extent required (para. 6.25); - 25 - (v) FACT will implementsatisfactoryaccountingand management informationsystems by January 1972 (para. 2.07); (vi) FACT will implement an appropriateseeding program including necessary imports of NPK fertilizers(para. 6.19); (vii) FACT will carry out the project according to its critical path schedule (para. 5.04). Completionof the followingarrangementswill be additionalcon10.02 ditions of effectivenessof the credit: (a) FACT will have completed arrangementswith the Cochin Port Trust that terminal facilitieswill be permanentlyavailable at the time required (para. 3.06); (b) FACT and GOI will have completedarrangementsregardingreszheduling FACT's debt that is in arrears as of March 31, 1971 (paras. 4.08 and 9.07); (c) FACT will have completed arrangementsfor obtaining process licenses,plant designs and technical assistanceas required and on terms that are satisfactoryto IDA (paras. 5.01 and 5.02). The project has a high priority in the Government'sefforts 10.03 to increase fertilizerproduction. The project's attractivenessdepends largely on FACT's ability to complete constructionon schedule and FACT and the Governmenthave agreed to take all necessary steps to complete the project within the agreed time. With such assurancesand those indicated above, the project constitutesa suitable basis for an IDA credit of $20 million for relending under the terms describedherein. IndustrialProjects Department May 14, 1971 ANNEX 1 DESCRIPTIONOF FACT's EXISTING OPERATIONS The five operatingdivisons of FACT are described below: A. UdyogamandalDivision (UDL) UDL started commercialproduction in 1948 and since then has implemented four expansion stages with some of the earlier plants no longer in production. Over the past five years, FACT has invested Rs 200 million in the UDL Division, tripling the gross fixed assets to Rs 300 million. The UDL Division contains a number of small process units with an aggregate capacityof 90,000 TPY N and 40,000 TPY P205. The major products are ammonium phosphate (16-20-0and 20-20-0), ammonium sulphate and single super phosphate. The major productionlevels for FY 72 are expectetdto average about 60-80% of design capacity, and in FY 73 and subsequentyears are forecastedat an average of 90% of the annual design capacity. These improved efficienciesare obtainablewith the RationalizationProgram,see Annex 1 Section F below. Earnings projections for UDL are based onithese production assumptions. Ammonia is produced in four separateunits of which the oldest is a 15 TPD NH3 electrolysisprocess which consumes large amounts of power. Since FACT does not at present show each unit as a separate cost center, the economics of this unit cannot be determinedbut it is difficult to conceive that productionfrom this plant is economical. Two ammonia units (80 and 140 TPD NH3 ) are based on partial oxidationof naphtha. This lprocess is relativelyexpensivein part because it requires oxygen which has to be generatedin air separationplants; furthermorethe units are small by comparison to plant sizes now available. The fourth unit (120 TPD NH3) is due on stream during April 1971 at which time the oldest unit will probably be phased out. The process employs naphtha reformingwhich is the most ecosmall. Overall production cost nomical design but the unit size is still of ammonia from UDL will continue to be high even if all units were to operate at design capacity. However, at 80-90% capacityUDL should be able to produce NH3 at about $65-80/ton (Rs. 500-600/ton)and thus generate a reasonableprofit with the existing fertilizerprices in India. Sulfuric acid is produced in four separate units, which together have a capacity of 750 TPD H2 SO4 and which all use the same basic process. In addition,FACT purchases about 100 TPD H2 SO4 from a nearby aluminum smelter. The first two plants (68 TPD each) were part of the original facilities. The last two plants (160 and 450 TPD) represent reasonable modern design and size and can produce sulfuric acid economicallyor at near design capacity. However, for the reasons stated before, it is impossible to accurately assess their profitability. ANNEX 1 Page2 UDYOGAMANDAL DIVISION DESIGN CAPACITY AND OPERATING PERFORIMANCE OF PROCESS UNITS ON STRFAM DATE PROCF,SS UNITS ANNUALDFSIGN CAPACITY Thousand TPY 1967-71 1971-73 1967/68 TPY % OPERATING CAPACITY Thousand TPY 1968/69 1969/70 1970/71 TPY % TPY % TPY % 1971/72 1972/73 TPY % TPY % 54.9 71 6U 55.0 71 8L.o 70 90.0 80 13.8 26.2 61h 33.0 80 ~mmonia 1) 2) I5 80 3, lihO 20 L20 TPD TPD TPD TPD 1948 1962 1966 1971 335TMU Phosphoric Acid(P 77.6 112.0 33.0 41.3 44.2 57 49.5 2 0s) 1) 25 TPD 2) 100 TPD 125T-PF- 1962 1966 (1) (1) 11. 33 13. 120. 49 135.0 4o 10.6 32 42 Sulfuric Acid 68 2) 68 3) 160 4) 450 i) TPP TPD TPD TPD 750 TPID 1947 1949 1962 1966 59 166.0 59 198.0 80 247.0 247.0 198.0 198.0 78.0 4o 132.0 181.5 54 41 65.0 49 53.0 40 69.0 52 112.0 62 165.0 91 49.5 49.5 42.2 85 28.3 57 29.7 61 30.0 61 9.8 75 TPD 24.8 2h.8 5.6 23 6.5 26 9.0 36 9.0 36 12.0 20 'D 6.6 6.6 2.5 38 2.4 36 2.2 33 88.3 .3 2.6 31 3.0 36 2.2 27 1.5 18 126.0 166.0 AmmnoniumSulfate 1) 225 TPD 2) 330 TPD 3) 45 TPD 600 TPD 1966 112.0 57 101.0 51 116.0 59 155.0 78 172.0 87 Ammonium Phosphate 1) 100 TPD 2) 300 TPD 3) 150 TPT) 550 TrPM 1962 1966 1971 '2uperphosphate L) 150 TPD 1950 20 45.0 90 Antjioniium Chloride 1) Oleun 1) .ulfur 1) Di oxide 25 'PPD Fstimated E.j 48 12.8 50 ANNEX 1 Page 3 Phosphoricacid is produced in two plants, 25 TPD and 100 TPD P205, both of which are very small by current design standards,but use conventionaland competitivetechnology. The operating level of these plants has been low due to corrosion,mechanicalproblems, lack of - partly imported- raw materials,and low operating levels of other plants. Ammonium phosphate is produced in three granulationplants, all considerablysmaller than modern economic units. Their low operatingperformancehas been attributableto mechanicalproblems and non-availability of intermediatefeed materials from other units. When other units operate satisfactorily,the ammonium phosphate plants should also operate at reasonably high capacity. Ammonium sulfate is produced in two different processes. One unit uses ammonia and sulfuric acid and produces product by direct neutralization. This plant consumes sulfur which is imported. The other plant utilizes as its source of sulfur by-product gypsum, or calcium sulfate, from the phosphoric acid plant. It was designed by FACT, has a much higher capital investment than normal but produces ammonium sulfate at a lower cost since raw material costs are lower. The process is basically sound, although it has operated at low efficiency and equipmentsize is small. Single-superphosphatehas been produced by FACT since initial operationof the company in a conventionalprocess of reacting phosphate rock with sulfuric acid. The unit is typical of super phosphate factories throughoutthe fertilizerindustry. FACT operates the plant when raw materials are available. The projected productionof 20% in 1971/72 is due to shortage of phosphate rock grinding capacitywhich will be corrected in 1972/73. FACT also produces minor quantities of other chemicals at UDL including ammonium chloride,oleum (concentratedsulfuric acid), and sulfur dioxide. B. FACT Engine and Design Organisation(FEDO) in Division of FACTwhich was established FEDO, the Engineering induschemical the in work construction and out engineering 1965, carries try based on licensedprocesses and their own know-how. The FEDO personnel are competent but the organization'sdepth in engineeringstaff is lacking. FEDO, with a total technicalstaff of about 240, handles all of the expansion of FACT as well as outside work. They are currentlybuilding a 100,000 TPY sulfuric acid plant in Trivandrum,a 115,000 TPY phosphoric acid plant for FCI at Sindri, and the Cochin I project. In addition to Cochin II FEDO has bid on other projects. It is FEDO could overextend its staff capabilitiesif too much that possible additionalwork is accepted. FACT is aware of this potential problem and has agreed to consult with IDA before further major contracts are accepted during engineeringof Cochin II. ANNEX 1 Page 4 On previous jobs, particularlyCochin I, FEDO has not handled procurementand project delays very,well. It is difficult to assess fully the 1-1/2-yeardelay at Cochin I but FEDO could have improved the schedule by making a concerted effort to minimize delays by replacing orders, changing specificationsor expeditingshipments. Part of these delays were caused by import licensingor other procurement limitationsoutside FEDO's control; nevertheless,to a major extent the delays are indicativeof poor management control. FEDO should concentratecn project schedule and effective use of the project's critical path schedule. The Project Manager should be delegated sufficient authority to identifypotential delays early and undertake correctiveaction. FEDO has experiencewith each of the process units being considered for Cochin II, although the only other large project they have managed has been Cochin I. IDA considers FFDO capable,but consideringthe project's size and their lack of depth in technical staff, several experiencedpersonnel will be added to FEDO's organizationto assist in the execution of the project. C. FACT EngineeringWorks (FEW) FEW is a small equipment fabricationdivision that manufacturesfor FACT and other firms. FEW will not bid on any major equipment for Cochin II. D. Cochin Division The Cochin complex is located about 20 km from Udyogamandal. Cochin I is a 200,000 TPY ammonia and 330,000 TPY urea project estimated to cost about Rs 538 million ($72 million) including initial working capital, interest during constructionand market developmentexpenses. This project is being financed by Rs 126 million ($16.7 million) in Italian supplier credits and Rs 175 million ($23.3 million) in equity from GOI and Rs 237 million ($31.7 million) in loan from GOI. GOI has agreed to increase the equity portion of the Cochin I project cost to 50% to improve FACT's financialposition. This adjustment in equity will be accomplishedby the completionof the Cochin II project. IDA's financialprojections for the company (Annexes 18 and 20) assume this equity ratio will be achievedby profits from UDL and Cochin I. However, if insufficientprofits are earned then the equity will be adjusted by the form of new funds coming into the company or by restructuringthe company's debt. The plant is based on naphtha from the adjacent refinery at a price of Rs 110/ton ($15 per ton). The refinery is expanding its crude oil capacity from 2.5 to 3.3 million TPY. FEDO is the managing contractorand also engineered the ammonia synthesis gas preparationunit based on ICI-PowerGas design. The ammonia synthesis plant and the urea plant are being supplied by FCI and Montecatini. The plant is expected to be completed in May 1971 and begin production in ,idid-1971. ANNEX 1 Page 5 'rheMontecatini ammonia design has not been proven in this size plant and the ammonia/ureaplant may have difficultyin coming on stream even though a substantialnumber of expatriatepersonnelare being used for construction and start-up. The operating factors assumed in preparing the financial forecastfor Cochin I are: 50% of design capacity in 1971-72 (9 months); 75% in 1972/73and 90% in 1973/74and thereafter. On completion,Cochin II will be transferredto this division. E. Marketing Division FACT's Marketing Division is responsiblefor al,lfertilizersales from UJdyogamandal,outside purchases including seeding materials, and the future sales of Cochin. Fertilizerresearchand market promotionare also handled by this division. FACT markets only in South India. F. Udyo .mandal Rationalization Program The operating and profit performanceof UDL Divisionhas been very poor for the past few years. The IDA mission that assessed the company's performancein 1969 found major problems in the followingareas: 1) 2) 3) 4) 5) 6) Power supply Phosphate operations Ammonia operations Maintenance Small process units Management As a result of the mission, FFDO and FACT prepared a comprehensive-program for rationalizingor debottleneckingthe UDL operation. A list of the major projects to be undertakentogetherwith their completionschedule is given on the followingpage. Total expendituresof the program are about Rs 7.7 million ($1.0 million) includingabout Rs 1.0 million ($130,000)in foreign exchange. These costs do not include most of the local constructioncosts which are being absorbed in UDL's maintenancebudget. ANNEX 1 Page 6 UDL DIV1SION MAJOR PROJECTS FOR RATIONALIZATION PROGRAM Atem Total Cost Rs 1,000 1) Power Supply 2) Plant Maintenance & Instrumentation Foreign Cost Rs 1,000 - - - - Estimated Completion Date 4/71 3) NH3 Plant a) PumP Turbinie b) b) Absorption& Drying System (Chemiebau plant) - 6/71 maintenancebudget 12/70 70 2/72 120 4/72 - 6/7:1 Phosphoric Elevator b) Grinding c) Reactor 150 141ll Tank Ammonium Sulfate Cloth 12/71 2,000 1,ltOO 6/72 130 12/71 Plant a) Gypsum Thickener Filter 2,350 Acid Plant a) b) 80 250 c) Acid Storage it) 4/72 SulfuricAcid Plant a) Air Blower (Chemiebauplant) 3) 500 - Carbon Recycle System c) Oxygen Pump 4) 500 (Imported) - 750 6/171 maintenance budget - maintenance budget 7/71 5) Ammonium Phosphate a) 6) Reconditioning lAmmoniumChloride a) Centrifuge b) Vacuurmfluiq. 'T("PAL, 220 200 purchased 1,700 6/72 1/71 1,020 ANNEX 1 Page 7 The Government has given its approval for the program and portions have already been implemented. Items requiring foreign equipment and material are being discussed with GOI and some import licenses have been issued. The rationalization program represents a major step towards profitable operation of UDL and it is expected to be substantially completed by the end of Fiscal Year 1971/72. Power is supplied from the Kalamassery power station of the Kerala State Electricity Board (KSEB). Power distribution in Kerala has been experiencing many interruptions and voltage dips. The principal causes are inadequate protection from lightning. The UDL division, and specifically the armonia and oxygen plants, is sensitive to power variations. The plant has a small auxiliary power generation unit, but it would be prohibitively costly for UDL to generate all its power requirements. The recent history of power interruption as UDL is shown below: Power Interr2uions Voltage Plant Shutdo,wns Failures Dips Total 1969/70 (12 months) 11 100 111 37 17 1970/71 (8 months) /1 12- 63 75 29 20 Ammonia Oxygen 1969 Sept. to Nov. (3 months) - - 53 - - 197() Sept. to Nov. (3 months) - - 33 - - /1 6 are attributed to labor strike at KSEB. Some slight improvement is indicated due to changes already implemented by FACT and KSEB. However, it will be late 1971 before any substantial improvement in power supply can be expected. The problem of power supply in Kerala was evaluated in 1969 by an Indian study commission and specific recommendations were made for both KSEB and the FACT/UDL electrical systems. The recommendpd changes in the FACT power system were: 1. 2. 3. 4. 5. Independent power supply to control circuits. Independent power supply to excitation motor-generator sets. Automatic voltage regulators for synchronous motors. Time lag relays for synchronous motors. Time lag under-voltage relays for induction motors. ANNEX 1 Page 8 The recommended changes in the KSEl3power system were: 1. 2. 3. 4. Operation of 110 KV bus at Kalamassery as an integrate(dbus. Carrier inter-trip facility on all inter-connecting feeders. Single pole opening and reclosing facilities for all feeder circuit breakers. Automatic recording of power interruptions and voltage dips. KSEB has completed some of the changes listed, and is now waiting for imported components to complete the other improvements. FACT has installed time delay relays as recommended on some motors but apparently not all. These relays can correct for most short power dips, but FACT states that further improvements to their internal electrical system cannot be done until after KSEB has completed its changes. It is difficult to assess whether the recommended changes will completely solve the power distribution problems or if more fundamental and costly improvements are needed. The ammonia plants at UDL are heavily dependent on continuous power supply for efficient operation and power dips and interruptions have previously shut them down for 12-24 hours at a time. In addition to the electrical changes, FACT is presently modifying their oxygen supply system so that most power fluctuations will not bring down the ammonia plant completely. Other equipment modifications should permit the ammonia plants to attain steady production by mid-1971. From about 1967 to 1970, the phosphoric acid plant operated primarily on rock which had a high chloride content and is very corrosive in phosphoric acid plants. The corrosive nature of this rock is well-known throughout the world phosphate industry. The phosphoric acid plant has been severely corroded and, as a result, experienced long down times. If the phosphoric acid plant is not working then the downstream ammonium phosphate and ammonium sulfate plants cannot operate. In addition, the ammonium sulfate plant is affected by the quality of gypsum it receives when the phosphoric acid plant does operate. The percentage down time due to the inferior rock supply is not known, but it obviously was high. Nor was it possible to determine who initially ordered the rock, how quickly the cause of corrosion was discovered, nor how effectively FACT tried to circumvent its use. The mechanical changes in the phosphate plant such as rock grinding mill, new reactor, and the ground rock elevator should permit the phosphate plants to operate at close to design capacity. The poor maintenance and operating control was noted in the earlier Bank mission. FACT has set up a system for improving maintenance, and are consulting with an instrument firm on instrumentation. Also, FACT and G0I have agreed to employ three experienced fertilizer plant operators for 6-12 months to assist in the UD)Ldivisicinoperations. Negotiations are now und(erarvwith Wellman Power Gas to supply these engineers. The function of these engineers would be to work with FA(T on maintenance, instrumentation, operation [ln(icost control. ANNEX 1 Page 9 The multiplicity of small units at UDL is inherent in the age and growth pattern of FACT. These small plants are less efficient than modern, single-train plants. T{owever,with good management control and completion of the rationalization program, the plants can operate at a high rate and reduce production Industrial Projects April 1971 costs substantially Department below their existing levels. FACT Historical Income Statements For Fiscal Years Ending March 31 (Thousands Sales Volume From Own Production of Metric Tons) 1967 1968 1969 1970 32.6 13.9 64.7 32.2 55.9 4.2 48.7 4.8 82.3 56.9 6.6 76.8 66.7 8.3 106 60 9 20.2 29.5 17.0 10.3 20.2 6.3 18 10 159.1 173.1 178.3 203 74.8 108.8 7.9 113.5 30.2 97.2 87.6 108 170 (EstiMa (ex NPK Mixtures) AmmoniumSulfate AmmoniumPhosphate 1971 1966 Ammonium Chloride Super Phosphate Others 34.7 10.7 3.2 34.o 14.7 Total 96.1 148.8 Mixed Fertilizers& Urea Seeding 58.7 NPK Mixtures* Urea _ Total 58.7 74.8 116.7 143.7 184.8 278 154.8 223.6 275.8 316.8 363.1 481 132 192 3 261 315 100 12 112 16 6 111 3 7 ) ) 10 (7) 1) 7) 3 19) GrandTotal (Millions of Rupees) Income 514 TotalSales Sales From Own Production Cost of Sales** 1 23 6 Expense & Administration Selling Costs Operating (Loss) Profit Operating Income Non-Operating Gross Profit on Long Term Loans Interest 2 Taxes Net Profit Before Taxes (Loss) 82 m m Depreciation Net Profit * ** e) :;3 10 12 3 223 7136 31 ) T 2 :? 5 2 211 6 7 3) ) _ (7) (6) 4 _ 4 _ (6) Note: The company has reorganized the historical income statements to be consistent with the forecasted statements,which show net sales (from operations) at ex-factory prices. Net sales exclude fertilizer and selling bought and sold (with the trading profit shown in other income), as well as distribution costs passed on to the purchaser. These other fertilizer sales, urea and fertilizer mixes, have increased steadily from about Rs 29 million in FY 1966 to an estimated Rs 227 million in FY 1971. are small and do not appreciably affect the company's operations from these trading However, profits financial results. April 1971 T1-0) - (1)9 from own production ingredients Including Excluding cost of purchased fertilizers Industrial Projects Department 9 2 _ 3 16 (10) Annex 3 FACT Historical Fiscal Years (Millions ASSETS 1966 Current Balance Sheets 1nded March 31 of Rupees) 1967 1968 1969 1970 1971 stimate Assets 3 4 7 50 31 Accounts Receivable 34 12 27 54 59 73 60 Inventories Raw Materials Goods in Prmcess Finished Products Supplies and Spares 10 1 5 23 18 3 23 23 50 3 33 30 4444 4 Total Inventories 39 67 Total Current Assets 54 Cash 40 5 41 34 9 29 30 116 123 112 95 9B 177 232 216 189 108 231 246 264 283 310 Less Depreciation Net Fixed Assets 46 62 56 175 69 177 82 182 100 183 116 194 Expansion Projects 110 32 80 317 415 490 Investments 4 4 4 4 4 4 Deferred _xperses - - - 4 8 12 2 - Fixed Assets Other Assets Total Assets 20 30 230 309 438 741 826 889 24 31 2 2 49 80 68 12 3 80 77 25 19 131 51 70 113 50 4 3 4 3 4 59 109 166 205 277 318 22 80 _ 20 109 17 195 - 15 289 126 13 327 126 11 357 113 212 430 466 481 (15) (38) (75) (110) 124 197 392 391 371 75 75 141 174 226 2 2 LIABILITIES AND CAPITAL Current Liabilities Accounts Payable and Accrued Expenses Short Term Debt Current Maturities of Long Term Debt Past Du Debt* Other Current Liabilities Total 5 - 48 39 56 81 Long Term Debt IFCI GOI Italian Suppliers Total Less Current and Past Due Maturities Net 102 (2) 100 - 129 (5) daquity Share Capital Reserves Surplus (Deficit) Total 75 8761 (12) (6) 6 (1) 71 76 75 144 158 200 Total Liabilities and Capital 230 309 438 741 826 889 Current Ratio .9:1 .9:1 1.1:1 1.1:1 .8:1 .6:1 58/42 62/38 72/28 73/27 71/29 65/35 Net Long Tenn Debt/Equity Ratio * Principal and interest on GOI Loans Industrial Projects Department April 1971 Anrnex 3 Page 2 FACT COCHINII PROJECT POSITION OF LOANSOUT3TANDING AS OF MARCH31, 1971 SOURCE AMOUNT RATE OF INTEREST GUARANTEE PENALINTEREST TERMSOF PAiYMNT (millions of Rupees) 1. Government of India Loans* a) UDL Third Stage 78.8 6% Nil 8k% in case of default of repayment of principal and interest b) UDLFourth Stage 50.0 7% NiL 9½f%in case of default principal and interest repayment of In 10 equal annual installments commencing from the third year after date of drawal. Annual installment Rs 5 million. c) Cochin I Project 215.4 7% Ni-L 94% in case of default principal and interest repayment of In 10 equal annual installments commencing from the third year after date of drawal. Annual installment Rs 21.5 mdllion. d) Ways and Means 12.5 6% Ni: 2k4%in case of default principal and intereat repayment of Due on August 2, 1969, which was extended later. 11.2 4%-6% Guaranteed by Central Gov't. A sum of Rs 2.13 million repayable every year up to FY 72 and Rs 1.83 million up to FY 76 and last installmnt of Rs 1.74 million in FT 77. 11.1 6% Guaranteed by State Iank of India and co-nter guaranteed by Gov't. of Indi.a to State Bank of India Repayment due on 14 March and 14 September from 1970 to 1979. Annual installment Rs 1.30 million. 5.75% Guaranteed by State Bank of India and counter guaranteed by Iov't. of India to State Banbk cf India Repayment due on 15 December 1970 to 1979. Annual installment Rs 11.30 million. 2. Industrial of India 3. Italian Finance Credit: Corporation Cochin I 101.8 480. 8 * Arrears of installments PCL Third Stage UDLFourth Stage Cochin I project Ways and Means of Governmen; Loans 33.1 2.8 11.7 12.5 Interest 21.3 Total Past Due 81.4 n-iustrial Pmoje-to 3ep rtment April 1971 (millions of rupees) In 9 equal annual installments comsencing from 5 years after date of drawal or 2 years after commencing production. Annual installment Rs 10 sillion. ANNEX' PRODUCTION SCHEDULE AND SALES PRICE COCHINII PROJECT PRODUCTION DESIGN PRODUCTION TPY NORMAL PRODUCTIONJ TPY SALES PRICE EX-FACTORY RETAIL Rs/ton Rs/ton 860 1,010 121,250 109,000 28-28-0 72,750 65,500 14-28-14 97,000 87,500 967 1,117 18-36-0 72,750 65,500 1,000 1,150 24-12-12 72,750 65,5oo 829 979 11-22-22 48.,500 43,500 910 1,060 928 1,078 17-17-17 1,036 1,186 AVG. (18.7-23.4-11.1) Cryolite 485,OOO 7,500 436,500 6,750 1/ Normal productioncapacityis assumed at 90% of design. IndustrialProjectsDepartment March 12, 1971 2,250 2,400 ANNEX 4 Page 2 Product Grades The product grades recommended for production in Cochin II contain six different grades of NP and NPK complex fertilizers in the following nutrient ratios, with percentages to total volume of complex fertilizers: N 1 1 1 1 2 1 :P :K 1 : 1 : 1 0 2 : 1 0 : 2 1 1 : 2 2 25% 15% 20% 15% 15% 10% These ratios represent the accepted pattern for different crops in the marketing area of the company and the relative quantities taken into consideration in cropping pattern and areas under major crops. The grades and tonnages can be adjusted to meet changing market preferences. The proposed plant design is flexible, depending on the availability of raw materials, and it is possible to make grades with nutrient ratios other than those indicated above. The existing product mix (including the Cochin I production) indicates an imbalance in the combination of nitrogen, phosphate and potash. The existing product mix offers a poor NPK ratio of 12:2:1. The proposed capacities of Cochin II will improve this position to an NPK ratio of 6:3:1. Such an improved NPK ratio is advisable, both from the requirement of providing balanced fertilizer nutrient to the soil and marketing requirements of providing a balanced product mix for easy market acceptability. The fertilizer consumption trend in FACT's marketing area indicate a definite trend towards urea, ammonium sulphate, NP and NPK complexes. The NPK ratios and grades included in the product mix are in line with the fertilizer recommendations for different crops in the marketing area. The popular ratios of NPK recommended for the various crops in the area are 1:1:1, 1:2:1, 2:1:1 and 1:2:2. For potash rich soils, NP ratios of 1:1:0 and 1:2:0 are generally recommended. Hence all these are included in the product mix. Since many of the important crops in this area require an NPK ratio of 1:1:1 for basal application, a higher production is proposed for this ratio. The ratio of 1:2:1 is taken as next in importance as this is generally recommended for local varieties of paddy. The ratio fo 2:1:1 is preferred for crops in areas without assured irrigation and where all the NPK required by the crops are to be given in one basal application. The ratio 1:2:2 will cater to the requirements of some specific crops like groundnut, vegetables, etc. The NP ratios of 1:1:0 and 1:2:0 are :Lncluded for meeting the requirements of those parts of the marketing area where soil is rich in potash. An analysis of NPK mixture grades recommended for crops and their consumption in the marketing area will show that these NPK ratios are the most popular ones. The product mix also gives the maximum possible concentration of NPK in the various ratios and, therefore, will offer economies in handling, storage and application costs. The product mix offered for production in Cochin II will satisfy marketing requirements and crop requirements of the area. ANNEX 5 TECHIICAL DESCRIPTION COCHIN II A. PROJECT Production Facilities The production facilities consist of four major process plants and their associated services and offsites. The process plants are: 1) 2) 3) 4) Sulfuric acid plant Phosphoric acid plant Complex fertilizer granulation plant Cryolite plant Sulfuric acid will be produced in a 33n,nn TTrYsingle stream plant, based on elemental sulfur. FEDO has an arrangement with Chemiebau Dr. A. Zicren Gmbll of West Germany, for design and engineering of sulfuric acid plants in India. The process know-how will be supplied by Chemiebau and the detailed engineering, procurement and erection will be undertaken by FEDO. Sulfuric acid is produced by melting sulfur and burning it in the presence of controlled quantities of air. The combustion air is first dried in a drying tower by contact with 94% sulfuric acid. The gases, at 900%C, are cooled to about 400°C in a waste heat boiler. The gases, which contain 8% So, are then passed through beds of vanadium pentoxide catalyst, to convert {he sulfur dioxide (SO2) to sulfur trioxide (SO ). The heat evolved is also recovered through heat exchangers. The SO is absorbed in 98% sulfuric acid and product acid is drawn off from the circulating stream and cooled. A part of the 98% sulfuric acid is recycled to the drying tower, taking back portion of the 94% acid in the drying system, and adding water as required. The gases, after absorption of SO3 , are vented to the atmosphere through a stack. Phosphoric acid will be produced in a single stream plant, of 115,000 Tl'YP 0 size. The plant, based on the Central Prayon Process, will give a produc? acid containing about 35% P20 , with a high recovery efficiency. FEDO has an agreement with The EngineerKng and Industrial Corporation (I'rayon)of Luxembourg, for building phosphoric acid plants. Prayon will provide the process know-how and FEDO will do the detailed engineering, and erection. Phosphoric acid is produced by reacting phosphate rock and sulfuric acid. Thicphosphate rock is ground to the required fineness and then reacted with the phospho-sulfuric acid from the hemihydrate section, and the recyclecldihydrate slurry, in the attack tank. A portion of the 98% sulfuric acid is also added and conditions are controlled to precipitate the calcitim sulfate as dihydrate. A portion of the slurry from the attack tank is recycled through an evaporator-cooler, to remove excess heat and water. The ANNEX 5 Page 2 slurry from the attack tank is fed to centrifugesand is further clarified by settlingand taken otlt as product acid containingabout 35% P 0 . The slurry from the centrifuges is sent to the hemihydrate tanks. The5conversion of dihydrate into hemihydrate is the key step, which differentiatesthis process from the dihydrate process and improvesrecovery. The slurry containing dihydrate and phosphoricacidlreacts with the balance of sulfuric acid, at a higher temperature,in the hemihydrate section. The calcium sulfate dehydrate is converted into the hemihydrate form and then filtered, using conventionalfilters. The filtrate, phospho-sulfuricacid, is returned to the attack tank. A portion of the centrifugedphosphoric acid is concentrated in forced circulationevaporatorsto 54% P 0 to meet the needs 2 5 of the NPK granulation plants. Complex Fertilizer (NPK) will be produced in a plant with two identical streams with a total capacityof 485,000 TPY. FEDO has an agreement with Wellman-PowerGas Inc. of the U.S. to supply the basic engineering know-how. FEDO will complete the design and erectionwith substantialassistance from Wellman-PowerGas. Complex fertilizersare produced by reacting acid with ammonia and blending in the required amounts of urea plhosphoric and potash. Phosphoricacid is neutralizedwith ammonia in a 2-stage reactor. Vapors from the reactor corntain free ammonia, which is recovered by scrubbingwith phosphoricacid, and the scrubbedgases are discharged to the atmosphere. A drum type ammoniator-granulator will be used for granulation. The slurry from the neutralizer is further ammoniated in the granulator and mixed with recycled product, urea and potash. Vapors from the granulatorare fed into a fume scrubber,where ammonia is recovered by scrubbing. The product from the grarulatoris then dried, screened,and cooled. A portion is recycled to the granulationstep and a portion is removed as product. The dryer and cooler will be handling dry solid materials which creates dust. The gases from this equipmentare passed through cyclone separators,to remove a large portion of the dust and then are scrubbedwith a circulatingstream of acid to remove the remaining dust. The dust is recycled back to the process, thus, loss of material is minimized. The product, from the bulk storage, is delivered to the bagging plant where it is filled into 50 kg. polyethylenewoven sacks or polyethylene-linedbags through automaticweighing machines, stitchedand dispatched either to the bagged product storage or directly to the platform to be loaded into wagons. Cryolite is produced from the fluorinerecovered from the phosphoric acid plant. A portion of the liquor in the fluorine scrubbing system is pumped to the cryolite plant. This liquor, a 15-20% solution of hydrofluosilicicacid, is filtered and treated with sodium chloride to precipitate sodium fluosilicate. The precipitateis slurriedwith water and then ammoniatedunder controlledconditionsto precipitatesilica, which is filtered off. The resulting solution of ammonium and sodium fluorides is reacted with aluminum sulfate solution (preparedfrom sulfuricacid and hydrated ANNEX 5 Page 3 alumina) precipitatingtrisodiumaluminumhexafluoride(cryolite)and ammonium aluminumhexafluoride. The latter is then converted to cryoliteby reacting it with sodium chloridesolution. Cryolite is then filtered, washed, dried and bagged. The proposed plant will produce 25 TPD of cryolite. B. Offsites and Services Importedraw materials required for the project are: Rock Phosphate Sulfur Potash Ammonia 347,000 TPY 110,000TPY 91,000 TPY 57,000 TPY The above materialswill come by ship to Cochin port, where facilities are planned to unload and transportthem to site as part of the proposed project. Urea requiredfor the project will be available from the adjacentCochin I Project and will be moved from urea silos to the NPK granulationplant by a conveyor. Other materials such as filler, coating agent, hydratedalumina, sodium chloride,soda ash, are available locally and can be moved to the factoryby road using transportcontractors. Cochin port authoritieshave agreed to allot one wharf in the harbor for unloading and handling importedraw materials and have agreed to provide a mooring berth for over-sidedeliveries. Where raw material is unloaded onto the wharf, there is sufficientarea for building storagesand placing of unloading equipment. When the material is unloadedover-side using ship's equipment the raw material will move directlyby barge from the ship to the site. Solid raw materialswill be unloaded at the berth using two mobile grab cranes of 200-ton/hourcapacity. Phosphate rock and sulfur will be unloaded into overhead concretesilos, each of 2,500-toncapacity, the total storage being 10,000 tons. From these silos, materials can be loaded directly into rail wagons or into barges and moved to the site. Potash will be unloaded into a 4000-tonstorage from which it can be loaded on rail wagons. The railways have agreed to place 55-ton box type wagons on a closed circuit for the movement of raw materials to the site. The materials will be moved to storage through covered conveyors and then to consuming plants by conveyors and elevators. Where material is moved by barges, they will be handled by grabs and moved to storage through conveyors. Ammonia will be received in refrigeratedtankersand pumped into an atmosphericpressurerefrigeratedstorage tank of 10,000-toncapacity to be constructednear the unloadingberth. Ammonia will move from port to site in 28-ton rail tank wagons and be stored in a 1,500-tonHortonsphere. The Indian Railwayshave agreed to provide chassis for the wagons on which tanks will be placed by FACT, these being built to specificationsgiven by the railways. ANNEX 5 Page 4 The present proposal is based on rail transport of all major raw materials taking a comparatively less economical alternative. The Government of India has agreed to improvements to a canal connecting the port with the site. The State Government has assured FACT that the improvements can be completed in 24 months, i.e. it will be ready for use for the movement of material from port to site. With the alternatives of overside delivery from ship to barge and the availability of arrangements for loading from berthstorage direct to the barges, it will be more economical to move the material by river. However, as details are still under negotiations, the economics of the project have been worked out on the costlier alternative of transport by rail. Power requirements for Cochin II are 17 MW which will be provided tlhroughtwo 110 KV feeders from the Kalamassery Station of KSEB. Each line can handle the full load of Cochin I and II. (Cochin I requires 25 MW). The electrical drives in Cochin IT will be designed to handle voltage dips that plague industrial facilities in Kerala. Cochin I has a 14 MW generator that has excess emergency capacity and FEDO has included another small diesel generator in Cochin II. These electrical facilities can keep critical units production will of Cochin II operating during a power interruption. Although be stopped by a power interruption, the units can be quickly brought back The Kerala State Electricity Board has indicated that power will on stream. be made available to the project and the power tariffs applicable to nonpower-intensive, bulk consumers will apply to this project. This rate is Rs. 220/KVAY and with existing surcharges is equal to about 4 paise currently per KWH. Steam requirements of the project will be supplied by the waste heat boiler in the sulfuric acid plant and supplemented by a 50-TPH steam generation plant. (Four package boilers of 12.5 TPM capacity). Total steam required for the project will be 2,500 TPD of which 1,300 TPD will be provided by the sulfuric acid plant. Water for the project will be available from the artificial reservoir built for Cochin I. The reservoir, with a capacity of 1,050 million gallons is fed by the two monsoons. In dry months, a State Irrigation Canal of carrying 46 milfeeds water into the reservoir through a channel capable to the been indicated has total water requirement per day. The lion gallons a suitable filling schedule State Public Works Department to determine Kerala during the dry months. This matter is now being considered by the Public Works Department. The total water requirement for the present project will gallons per day and a provision to increase the present capabe 4.3 million city of the reservoir has been included. 150 tons Fuel Oil will be available from the nearby Cochin refinery. a day will be required for the project. About ANNEX 5, Page 5 C. Pollution Control Several effluent streams from the Cochin II factory will be potential pollution problems. The proposedproject design controls these effluent streams within normal industrialpractice. The principal effluentsare fluorine, sulfur oxides and dust. It is understoodfrom FACT that there are no legal requirmentsnow in force in Kerala for the control of these materials. The sulfuricacid plant burns sulfur and then recovers the resulting sulfur oxide by absorption. The efficiencyis a minimum of 98'%recovery with the balance of sulfur oxides being exhausted to the atmosphere;representing about 290 kg/hour of sulfur. This efficiencyis typical of most modern commercialsulfuricacid designs. The efficiencycould be increased by adding more absorptionequipmentbut it is not considerednecessaryby FACT nor the IDA staff. The fluorine effluents are a result of the 3-4% fluorine contained in phosphate rock that is liberatedduring processing. The exhaust gases from the phosphoricacid plant are scrubbedwith water and the gases that are vented to the atmospherecontain about 50 kg/day of fluorine. This level representsa high scrubbingefficiencyand should be acceptable. Most of the recovered fluorineis converted into cryolite. The NPK plant liberates fluorine as it processesphosphoricacid. These gases are also scrubbed and each plant dischargesa maximum of 50 kg/day of fluorine to the atmosphere. The NPK plant dischargessmall amounts of ammonia and dust, but these materials are substantiallycompletelyremoved by scrubbing. Both the phosphoricacid plant and the NPK plant discharge large volumes of water that are contaminatedwith fluorine. FACT has designed a system that neutralizesany overflowfrom the water system to the river. The overflow still containsabout 150 kg/hour fluorine (as calcium fluosilicate). This amount should not be harmful and correspondsto normal commercial practice in plants in the U.S. The system can easily be modified at a later date if more stringentfluorinecontrols are required. The phosphoricacid plant also dischargesabout 1,700 tons/dayof gypsum, a solid waste. The gypsum will be stored in a diked area and converted to land fill as normally practiced in the industry. FACT later proposes to convert a portion to ammonium sulfate and sell the resulting calcium carbonate to cement factories. IndustrialProjects Department April 1971 FACT SUMMARYOF CAPITAL COSTS (in Millions)COCHIN II PROJECT Local Currency Equipment and Materials 48.0 Freight,Handlingand Insurance Duty, Sales Tax Design, Engineeringand Procurement Erectionand Cormissioning Civil Wbrks Land and Development Office Buildings,Furniture Pre-operatingExpense TechnicalAssistance 2.3 20.2 12.4 27.0 60.2 7.2 0.9 8.8 187.0 9hb-Total Indian Rupees Foreign Currency 76.6 3.1 - 7.4 2.5 _ 0.5 3.9 94.0 Total Cost Local Currency 124.6 6.4 5.4 20.2 19.8 29.5 60.2 7.2 0.9 9.3 3.9 0.3 2.7 1.6 3.7 8.0 1.0 0.1 1.2 - 281.0 25.0 U.S. Dollars Foreign Currency 10.2 0.4 - 1.0 0.3 _ 0.1 0.5 12.5 Total Cost 16.6 0.7 2.7 2.6 4.0 8.0 1.0 0.1 1.3 0.5 37.5 12.0 13.0 38.0 15.0 50.0 28.0 1.6 1.7 5.1 2.0 6.7 3.7 Total Project Costs 212.0 147.0 359.0 28.3 19.6 47.9 Interestduring Construction 21.0 21.0 2.8 _ 2.8 Total FinancingRequired 233.0 380.0 31.1 19.6 50.! Working Capital Contingency Projects Industrial March 12, 1971 Department 147.0 ANNEX 6 Page 2 USE OF IDA CREDIT $ Million 1. 2. 3. 4. 5. Equipment Equipment (for foreign components of "reserved list") Engineering and Equipment Erection (a) Licensors (b) FEDO Technical Assistance Unallocated Total Note: 15.2 0.5 1.3 0.5 0.5 2.0 20.0 Category 3(a) above represents the foreign exchange costs of the design packages from the process licensors. The funds for additional consultants services described in Paragraph 5.02 are covered in Category 4 above. Category 3(b) represents local currency financing for a portion of FEDO's engineering and equipment erections costs which total $5.3 million (see Annex 6, page 1). If the proposed IDA credit is not used in other categories or cancelled for any reason then the unallocated or unused funds would be shifted to this category. PROJECTED DISBURSEMENTS OF IDA CREDIT (in US$ millions) 1971 1972 1973 1974 Jan.-Mar. Apr.-June 1.8 3.2 0.7 2.9 3.2 0.7 Industrial Projects April 1971 Department July-Sept. 0.3 0.4 3.2 1.2 Oct.-Dec. Total 0.4 0.4 0.4 1.2 0.7 5.5 10.0 3.R 20.0 ANNEX7 FACT Working Capital Requirements at kmual Production of 436,500 Tons Cochin Phase II Project Amount Rs Milli: o- 1. Accounts Receivable a) 100,000 tons NPK 500 tons Cryolite b) 2. 92.8 1.1 Raw Materials tons @Rs 245/ton 19.1 b) Sulfur, 25,000 tons ORs 290/ton 7.3 c) Potash, 21,000 tons ORs 423/ton 8.9 ORs @Rs 485/ton 620/ton 2.1 5.0 1.4 a) Phosphate Rock, 78,000 d) Ammonia, e) Urea, f) Other Chemicals 3. ORs 928/ton @Rs 2,250/ton Operating 4,300 tons 8,000 tons Supplies a) Bags, 2 mos. suppl;y b) Operating Supplies and Consumables a) Spare Parts 2.9 .6 8.3 4. Goods in Process 3.7 5. Product Storage (2 mos.) a) 72,750 tons NPK b) 1,350 tons Cryolite 50.9 1.9 206.6 3.0 6. Cash Balance 7. Total Working Capital 8. Initial 9. Foreign Exchange Requirement (Total) Working Capital Projects Industrial March 12, 1971 ORs 700/ton ORs 1,400/ton Department 209.0 50.o 38.0 INDIA FORECASTOF NITROGENT PRODUCTION (thousands of metric tons per year) Design Capacity EXISTING FACILITIES Public Secto 1 FACT-UDLTL3) FCI-NAMRUP FCI-SINDRI FCI-NANGAL FCI-TROMPAY FCI-GORAKHPUR FOURFELA NETVELI GSFC, DAROEA OTFER PFRODDUCENS SUB"OTAL (1) FY 70' FT 71 92 45 117 80 go 80 120 70 216 12 922 35 26 79 79 44 73 30 42 111 12 ?MIVATE SECTOR ,ORO1M1ANDEL, VIZAG ICY, YOTA IEL, 12ANPTR OTHER1TWODJCEFS SUB TOTAL 80 130 200 34 68 81 17 30 TOTALEXISTING PLANTS 1366 35 30 60 100 120 30 73 120 185 30 73 120 185 30 00 73 120 185 30 1225 1240 1245 75 75 110 110 1LO 14o 1LO 14o 175 735 160 7 852 80 LO 105 77 80 73 110 60 200 12 4 95 4 75 130 500 140 140 110 110 175 67 - 90 125 - 21 75 X59° 0 TOTALEROBABLE EROJECTS 80 105 77 80 73 110 60 200 12 37 73 120 185 o 1245 7 1644 LONGRANGE PROJECTS (2) TOTAL F'Y 77 FY 78 FY 79 8o 4o 105 77 80 73 110 60 200 12 80 4o 105 77 80 73 110 60 200 12 3 80 4o 105 77 80 73 110 60 200 12 5 37 80 4o 105 77 80 73 110 60 200 12 37 73 120 185 30 7 1; 73 120 185 30 408 73 120 185 73 120 185 1245 1245 1245 140 14O 14o UhO 175 737* 14o 14o 140 14O 175 735 140 140 140 140 175 735 140 140 140 140 175 735 160 160 160 160 °95 R 95 695 45 120 45 115 115 110 110 600 45 120 45 160 160 140 i4o 810 45 120 45 205 205 140 140 150 30 125 80 3 195 30 175 110 710 195 30 220 145 9 lo45 1320 149o 200 boo 6oo 7 1245 895 25 65 25 35 90 35 - - - - - 75 1 215 30 248 160 653 FY 76 lo 537 o FbOBABLE PROJECTS(NEAl?FUTUTE) Public Sector FACTCOCHINII L!7 FCI-TROMBAY EXP. 132 FCI-GORAKHPUR EXP. 50 FCI-TALCHER 229 FCI-RAMAGUNDAM 229 FCI-BIALDIA 152 FCI-TTANGAL EXP. 152 SU' TOTAL 991 Private sector IFFCO, KANDLA COPONLANDEL EXP., II SPIC, TUTICORIN MIANGA LORE SUB TOTAL FY 75 75 LO 70 ho - 35 130 12 5312 PROJECTS UJNDE CONSTRUCTION Public Sector FACT-COCFHIN I 152 -'CI-DURBGAPLT 152 FC1-EARAB UI 152 FCI-XTA1BIRTF 152 IAT 'AS 190 SUIB CCAL 7 Private-Sector ZUtARIAGRO-50A 175 973 FY 74 75 4o 105 77 80 73 110 60 200 12 6 TOTALUNTrERCONSTRUCTION FY 73 60 40 105 77 80 73 110 60 200 12 l 75 727 FY 72 ANNEX 8 75 310 - 110 30 115 450 - _ Aor -=19 goo GRAND TOTAL 6020 727 °52 1470 1830 2045 2255 2590 3385 3860 '4230 GOTESTMATE 6020 716 850 1420 1820 2185 31f40 3970 4420 4700 5200 Fiscal Years ending March 31 Public Sector: Private Sector: Korba, Kamiptee, Rajasthan, Mirzapur, Paradeep Coromandel, Tata, Hindustan Lever, Dharamsi Morarji (3) GOI figures Industrial Projects March 12, 1971 are not consistent Department with FACT's (see Annex 1). ANNEX 8 Page 2 NITROGEN AND PHOSPIIATE PRODUCTION ASSUMPTIONS AND COMMENTS The following comments refer to the forecasts production (Annex 8) and P2 05 production (Annex 9); made on nitrogen 1. Production figures for 1969/70 are actuals and for 1970/71 are provisional estimates supplied by the Government. While overall totals for 1970/71 may be close to the 850,000 tons N and 260,000 tons P2 05 shown, production for individual plants may vary. Production from existing plants after 1971/72 has been estimated at about 90% of design capacity. In recent years production in public sector plants has averaged 60-70% of capacity and these estimates may therefore be high. llowever,any overestimate understates the gap between demand and supply and lends conservatism to the deficit. A 90% production estimate for the private sector is considered realistic based on its operating performance. 2. For projects under construction, production has been assumed at 50% of design in the first year, 70% in the second year, and 90% thereafter. Three plants - Cochin I, Durgapur, and Madras - are substantially completed and start-up by summer of 1971 seems probable. The estimated start-up of Barauni and Namrup is less certain, but it is assumed for spring of 1972. Work at Zuari Agro is on schedule with start-up scheduled for summer of 1972. 3. The 11 projects designated as probable for the near future are in various stages of negotiation and IDA's assessment of the start-up dates varies somewhat from GOI estimates. In each case production is assumed at 50% first year, 70% second year, and 90% thereafter once production begins. The three projects assumed to be in production in 1974/75 must begin construction in 1972. Of these Cochin II should start construction in mid-1971 and negotiations appear well-advanced at the Gorakhpur and Trombay plants of FCI. The project and financing plans for three projects, Nangal Expansion, IFFCO and Haldia, must be completed by early 1972 if the projected 1975/76 start-up schedules are to be met. Plans for Coromandel Expansion, SPIC (Tuticorin) and Mangalore are considered less certain and are projected for 1976/77 start-up. Two plants in the "probable category" are coal-based ammonia plants with a total capacity of 460,000 TPY N. The technology of these plants is not commercially proven and the plants are much larger than any undertaken by FCI thus far. Start-up has been assumed for 1976/77. 4. A number of other projects have been suggested for the longerrange. The tentative nature of the plans for these projects make forecasts highly unreliable so they have been grouped together with arbitrary aggregate production schedules assumed at 10%, 20%, and 30% in 1976/77, 1977/78, and 1978/79 respectively. 5. There is little difference in the aggregate figures between IDA's projection of supply and that of the Government in the early years. Beginning in 1974/75, the difference becomes increasingly greater.,due to ANNEX 8 Page 3 different forecasts of completion dates for various plants. These forecasts (Annex 8 and 9) represent IDA's best estimate of the production that India can reasonably be expected to achieve. If the 90% capacity utilization assumption is reduced to 80%, then the production figures will be approximately 10% less. The project start-up dates assumed could vary either way and give an estimated t10% difference in the forecasts. Progress in fertilizer production in India has been disappointing. 6. This is true both for the public sector, where production has been below expectations and where completion of new projects has been delayed, and the private sector, where only one plant is currently under construction and only one plant, IFFCO, seems likely in the near future. If India is to narrow its supply gap, new projects must be implemented at a much faster pace than projected. Every effort should also be made to improve production levels at existing plants. The deficits forecasted in the Bank estimate indicates the magnitude of the problem India faces in meeting its fertilizer requirements. Pertinent data on the nitrogen capacity of the public and private 7. sectors in India are given below: Public capaNumber city 1000's of Plants TPY Existing Under Construction Probable % Total Capacity Private Capacity Number of 1000's Plants TPY % Total Capacity Total % Capacity Total Number of 1000's Capacity Plants TPY 9 910 69 3 410 31 12 1,320 100 5 798 82 1 175 18 6 973 100 14 1,708 74 4 585 26 18 2,293 100 7 991 60 4 653 40 11 1,644 100 21 2,699 69 8 1,238 31 29 3,937 100 8. The present division of nitrogen plants show about 70% of N capacity in the public sector. This percentage is likely to be increased over the next few years as new plants are completed. 9. The high priority for India's self-sufficiency in fertilizer production suggests that private sector industry should be encouraged as well as public sector projects. Given the limited resources of India, the fertilizer industry should have as broad a base as possible. ANNEX 8 Page 4 10. The public sector projects show increasingreliance on one company, FCI; with 8 plants completed or under constructionand another 6 planned for the near future. The Governmentshould review this situation to determine whether one company is the most appropriatevehicle for expansionof the industry. 11. Also critical to India's fertilizerproduction is its recent decision to build extremelylarge-scalecoal-basedammonia plants. Whether this is appropriatein India, consideringthat the technologyhas not been proven commercially,should be given thoroughstudy before the projects are committed. Foreign exchange financingof fertilizerplants in India in recent 12. years has come from a variety of sources. The principal one recently has been Italian Credits for the four urea plants now under constructionin the public sector - Cochin I, Durgapur, Barauni and Namrup. US AID supplied funds for Trombay plant of FCI but has not participatedin further financing of FCI plants due to problemsrelated to choice of engineeringfirms. US AID also participatedin the Coromandelproject in the private sector and assisted the Madras plant now under construction. It is consideringfinancing for the IFFCO project,which may also have finance from the U.K. Government. Japan has given credits for three Japanese built plants, Gorakhpur, GSFC, Baroda, and Kota. Foreign exchangefor Indian Explosivesat Kanpur and Zuari Agro was supplied by IFC. In several cases foreign equity sponsors also supplied foreign exchange. IndustrialProjectsDepartment April 1971 ANNEX 9 FORECAST OF P2 05 PRODUCTION (Thousands DESIGN CAPACITY EXISTING FACILITIES FY 70(1)FY 4o FACTPLIDL E ' FCI-TROMBAY GSFC, BARODA SUPERPHOSPHATEFACTORIES of metric 11 16 21 14 43 50 45 7 SUB TOTAL PRIVATE SECTOR COROMANDELiVIZAG DMCC, BOMBAY PARRY, ENNORE E.I.D. SUPERPHOSPHATEFACTORIES SUB TOTAL 71 15 16 30 15 73 per year) FY 72 FY 73 FY 74 FY 75 FY 76 FY 77 FY 78 FY 79 26 35 33 33 33 33 33 33 33 35 35 35 35 35 35 45 45 35 30 30 30 30 30 30 30 30 45 45 45 45 45 17N 64 50 66 66 66 66 66 66 66 66 4 5 8 9 120 8 8 9 120 9 120 9 120 9 120 TM 9 90 M 8 9 120 8 7 85 8 9 120 8 10 172 8 9 120 M O 0 w 0 222 230 339 346 346 346 346 346 60 78 78 78 140 78 78 78 140 140 140 ho 40 40 _i 4 TOTAL EXISTING FACTORIES 44 PROJECTS UNDERCONSTRUCTION PUBLIC SECTOR MADRAS FCI.SINDRI SUB TOTAL 156 24i 40 185 PRIVATE SECTOR ZUARI ARGO, GOA 45 TOTAL 86 75 -7J 6 - 22 32 40 82 185 T 110 T ho 228 3 346 w 346 40 258 258 258 258 115 60 80 105 105 105 132 70 65 90 35 120 50 120 63 120 63 100 5° - I7 50 70 70 PRIVATE SECTOR IFFCO, KANDLA SPIC, TUTICORIN COROMANDEL II, VIZAG MANGALORE SUB TOTAL 127 70 7 90 27 - 65 - - - - TOTAL 711 SUB TOTAL 45 11 73 PROBABLEPROJECTS (NEAR FUTURE) P4=UBLCSECTOR FACT-COCHIN II FCI-TROMBAY EXP ECI-HALDIA KHETRI tons 90 90 9 9770 90 90 115 115 50 7 63 165 35 7 177 340 542 613 643 160 320 480 - 175 go 7 76w LONG RANGE PROJECTS 1600 TOTAL GRANDTOTAL GOI ESTIMATE 1/ Fiscal 2/ GOI figures years 3/ Public Private ending are Sector: Sector: not 3041 222 230 379 428 531 749 944 1306 1537 1727 3000 222 230 422 476 671 1200 1663 2025 2250 2500 March 31 consiatent Rajasthan, Dharamsi with FACT's (See Annex 1). Paradeep, and others Morarji, Occidental, and Coromandel III Industrial Projects March 1971 Departmer FERTILIZER MARKET: DEMAND FORECAST SOUTH INDIA! (thousands World BankY/ Kerala Mysore Tamil Nadu Andhra Pradesh GOI (Planning FACT V/ 2/ Kerala, Figures 1971/72 1972/73 1973/74 1974/75 1975/76 1976/77 1977/78 1978/79 N N N N N N N N N N P>Or P,Oe PqOK 32 29 58 40 90 38 68 107 49 49 50 145 69 168 89 326 113 386 515 200 619 260 729 540 186 540 186 - 601 - 231 - 667 Department PnOf P,Oz PoCw 77 59 85 69 95 62 111 144 218 77 86 244 150 141 328 450 844 170 402 515 962 77 134 206 161 89 124 193 577 231 - 281 734 Mysore (including Goa), Tamil Nadu (including Pondicherry) beyond 1973/74 are projected at 12% growth rate. Industrial Projects March 12, 1971 per year) 1970/71 76 123 268 Commission) tons 1969/70 48 Total of metric 333 486 1,077 825 422 - 805 399 912 and Andhra Pradesh. P205 P2 Oc P2(k' 107 181 273 646 87 97 168 258 119 202 306 724 97 108 188 289 134 227 343 810 544 1,207 610 1,351 682 1,514 - - - - 545 1,174 622 1,332 - - 471 1,033 109 121 211 324 PoOC 150 122 254 136 384 236 908 765 1,696 363 857 - 1,800 704 1,502 900 790 ANNEX11 FERTILIZER MARKET- SUPPLY FORECAST SOUTH INfDIA-1 of metric tons (thousands Design 2 Capiacity N 70-/FY FY P205 N 2P 2 71 N 05 72 FY PN P2 0 2 FY per 73 year) FY 75 P2052 05 74 205 FY 05 2 N P FY N 76 77 FY P2 0 P2 05 78 FY 79 FY P2 0 5 N N P205 FACT, UPL-/ 92 40 35 11 35 15 60 26 75 33 80 33 80 33 80 33 80 33 80 33 80 33 COROMANDEL,VIZAG 80 73 68 64 60 50 73 66 73 66 73 66 73 73 66 73 66 73 66 73 66 NEYVFLI 70 _ )42 -- 35 -- 60 -- 60 -- 60 -- 60- -- 60 -- 60 -- E.I.D. 16 10 10 7 -- 80 -- 40 MADRAS 190 85 - - - ZUARI AGRO, GOA 175 45 -- -- -- -- FACT COCHIN I 152 -- FACT COCHIN II 47 115 COROMANDEL EXPANSION_/ 155 55 SPIC, 2)48 MANGALORE PARRY, IMORE SUPERPHOSPHATEFACTORIES - 14 9 14 9 £0-- 14 40 - 40 -- 40 -- 40 175 78 175 78 175 78 175 78 4o 160 4o 160 4O 160 40 160 4O 140 -- 140 -- 1l)0 -- 140 -- 140 -- 25 60 9 14 14 9 40 -- 40 -- 40 -- 40 -- 40 - 95 40 130 60 175 78 175 78 -- -- 90 22 125 32 160 -- 140 -- 110 -- 9 35 80 80 30 4i5105 9 14 9 ])4 9 14 9 75 14 66 45 105 45 105 1]O 4O 140 50 140 50 70 125 35 175 50 220 63 160 90 80 45 1o 63 145 80 RAMAGUNDAM 229 -- 115 -- 160 - 205 -- OCCIDENTAL, VIZAG 140 140 -= -- 1750 800 155 122 1)44 114 337 181 552 230 667 258 727 326 TOTAL DEMAND -- -- 540 186 601 231 667 281 734 333 805 399 912 471 1033 545 1174 622 1332 702 1502 790 DEFICIT -- -- 385 457 117 330 100 182 103 138 141 125 145 TUTICORIN TOTAL SUPPLY Kerala, 2/ Fiscal Mysore Years 3/ GOI Figures 4/ Coromandel Industrial Projects March 1971 (Including ending are II Goa), Tamil Nadu (including 216 169 (3) Andhra Pradesh. 8 and 9 to show possible effect Pondicherry) plus consistent and III are with Data 131 taken than in Annexes on Cochin from Annexes II 70 634 0 168 (25) 156 FACT'S (See Annex 1). shown earlier 7Q 817 376 1177 491 1332 534 1527 March 31 not Department 64 -- Project. 8 and 9. FACT Annual Cochin Cost of Production Phase (millions Design Capacity Tons Unit Cost Rs/ton TonsProduction, 1000 II Project of Rupees) 1974/75 50%Capacity 1975/76 NPK NPK 242.5 Cryolite 3.75 388 80% Capacity Cryolite 6 1976/77 90% Capacity Design NPK Cryolite NPX Cryolite 6.75 485 7.5 436.5 Capacity VARIABLMCOST._ Raw Materials-Fertilizer Sulfur 109,200 290 PhosphateRock Ammonia Duty-Ammonia 346,500 52,700 Urea Potash 245 318 167 106,000 90,600 620 423 4.4 32.8 19.2 32,000 9,700 50 230 0.8 1.1 3,900 318 Fifler CoatingAgent Raw Materials 15.8 42.5 25.3 67.9 8.4 28.5 76.4 13.4 7.0 31.7 84.9 15.1 7.9 52.5 30.7 59 1 34 5 16.8 8.8 1.3 1.8 1.4 2.0 65 7 3 3 1.6 2.2 - Cryolite Ammonia- Cryolite Duty-Ammorna Alumina SodiumChloride SodaAsh 0.6 1.0 900 135 0.3 1.8 1.0 o.6 650 2.8 1.6 0.3 3.2 1.8 0.4 3.5 2.0 0.4 0.5 167 3,900 15,000 750 1.1 1.2 o.6 0.7 Other Utilities OperatingSupplies PackingCosts Laborand Supervision Interest on Short TermLoans 3.8 1.2 9.7 2.5 2.3 TdtAl VariAble coa 0.4 0 0.2 0.1 0.1 6.1 2.0 15.9 3.4 0.6 0 0.2 3.3 0.1 0.1 144.5 4.8 230.6 7,~ 6.4 10.6 25.4 1.5 0.2 0.2 9.0 10.6 0.2 0.2 0.6 0.1 6.9 2.2 0.7 0 0.8 0.3 7.6 2.5 19.4 0 0.3 3.6 0.1 0.1 3.7 3.9 0.1 0.1 258.2 8.3 287.1 9.2 9.4 0.2 0.2 9.7 10.6 25.4 1.5 0.2 0.2 17.1 3.5 FIIEDCOST Selling and Administrative Expense Maintenance, 3.5% of Investment Depreciation, 8.3% of Investment Insurance, 0.5% of Investment TotalFixed Cost Total Cost of Production 43.9 188.4 Cost of Production, Rs/Tons Cost of Production, W/O Depreciation Cost of Production, W/O Depreciation 776.9 163.0 158,6 Industrial Projects Departmmt March 12, 1971 & Duty 0.6 0.1 1.1 5.9 1,573.3 5.3 5.0 25.4 1.5 10.6 25.4 1.5 0.6 0.1 o.6 0.1 46.5 277.1 1.1 46.9 305.1 1.1 47.2 1.1 8.5 9.4 334.3 10.3 714.2 251.7 244.7 1,416.7 7.9 7.3 699.0 279.7 271.8 1,392.6 8.8 8.2 689.3 308.9 300.1 1,373.3 9.7 9.0 FACT COCHINII PROJECT FORCASTEDINCOME STaTEMENT FOR FISCAL YmARS ENDINGMARCH31 1975 1976 1977 1978 242.5 40.5 202.0 388 23 365 436.5 9.5 427.0 436.5 436.5 1979 Thousanis NPK Production Inventory Sales Build-up Cryolite Production Inventory Sales 3.75 .75 3.00 6.oo .25 5.75 5 8 Build-up Acid Sulfuric Sales II 1981 1982 436.5 436.5 436.5 _ 436.5 436.5 _ 436.5 Acid Adjustment of Sales at Net Profit Before 436.5 536.5 436.5 _ 436.5 436.5 _ 436.5 436.5 _ 436.5 436.5 _ 436.5 6.60 6.75 6.75 6.75 6.75 6.75 _ 6.75 6.75 _ 6.75 6.75 _ 6.75 6.75 _ 6.75 6.75 _ 6.75 6.75 _ 6.75 9 9 9 9 9 9 9 9 9 9 9 of Rupees 405 15 2 405 15 2 405 15 2 405 15 2 405 15 2 405 15 2 405 15 2 405 15 2 405 15 2 195 353 413 422 422 422 422 422 422 422 422 422 422 195 32 286 17 315 7 315 - 315 - 315 315 315 315 315 315 315 289 162 269 308 315 315 315 315 315 315 315 315 315 289 107 107 107 107 107 107 107 133 19 Taxes 436.5 _ 436.5 Tons of Metric 405 15 2 14 8.5% 1987 396 15 2 85 2/ Interest 1986 9616 339 12 2 33 Profit Operating 1985 187 7 1 1/ of Production Less Inventory Cost 1984 9416 6.75 6.75 .15 Millions Net Sales NPK Cryolite Sulfuric 1983 _L 6.75 6.75 6.75 Value Cost 1980 ---- I Volume 15 69 107 105 107 14 13 11 10 8 6 5 3 91 94 96 97 99 101 102 104 105 106 133 57 58 58 73 47 48 60 11, 25% ll 25% 14% 32% - - - - - 53 54 56 56 Net Profit 19 69 91 94 96 ss 45 45 46 47 as a Return: Net Profit On Net Sales (Rs 190 million) On Share Capital 10% 10% 19% 35% 22% 47% 22% 49% 23% 50% 10% 23% 11% 24% 11% 24% 11% 24% llg 25% Taxes- detailed operating costs and Annex 14, Page 2, for 1/ See Annex 12 for 2/ Assuming loan 3/ calculations. 5 years for return after Nominal tax of 55% provided againstoverall to Cochin II will be applied attributable tax benefits years actual earlier in is higher for tax purposes As depreciation Industrial April Projects 1971 major assumptions. of Rs 190 million Department 1 2 taxes for Actual comparn profits taxes would range as FACT as a whole may begin earlier by 1977/1978. and thus could be exhausted from 50% to 65%. FACT COCHIN II PROJECT SENSITIVITY ANALYSIS AND MAJORASSUMPTIONS IFR BASE CASES (See Page 2 for Assumptions) A. Financial 19.5 B0 Economic - SENSITIVITIES for Raw Material I. Long Range Trend II, One Tear Delay III. Maximum Production of 80% Reached IV. Maximum Production of 100% Reached V. Selling Prices Reduced VI. Selling Prices Increased VII. Combination of II and III VIII. Combination of II and V C. Economic - Phosphoric l/ * Resulting with Prices* and 7% Decrease Selling in Industrial with Projects A-4I 1 071 in Second in Fourth Year of Production Year of Production 10% 10% 19.5 1/ 13.5- on $160 per on $150 per - 9.2 6.0 17.8 11.4 21.0 14.8 9.1 5.1 27.3 20.0 8.6 Acid as Separate price price 4.0 -1.8 -2.1 _ 13.7 Project ton ton Base Case used in Economic Department Prices Overrun 9.0 exchange ratio at a foreign if evaluated increases The economic return selling of international from the use of the rupee equivalent results than costs. Consistent - on Base A and B Above - Calculated Selling Selling IER Return rlus Duties and Urea This at Rs 7.5/$1.0. greater more which should increase prices CD ( Rs 620 ton. FACT COCHIN II PROJECT TABLE I ASSUMPTIONSFOR BASE CASES PHOSPHORIC ACID FINANCIAL RETURN A DESCRIPTION ECONOMIC RETURN B AS SEPARATEPROJCT C Rs/Ton Rs690 Rs 1930 Rs 230 Rs/Ton $ Rs ($160) Selling Prices Rs/Ton Rs 928 Rs 2250 Rs 230 NPK Cryolite Acid Sulfuric Acid Phosphoric Raw Material Costs Phosphate SulfUr Potash Ammonia Urea Rock Project - DELIVERD 24R % R RB 290 Rs 423 Rs 485* Rs 620 Rs Period of Project Life $ Equiv. 7$ 92) ($257) ($ 31) per ton Cost Construction $ Equiv. (=) ($300) ($ 31) Production Year 4 Year 5 Year 6-15 CIF $(I) ($36) ($53) ($37) ($82.67) 359 million DELIVERED CIF ($30) ($40) Rs Rs Rs Rs 245 321 320 475 Rs 339 million DELIVERED CIF (*R2 s2 % ($30) Rs 245 ($37) ($60) Rs 138 million 36 months Same Same 15 years Same Same 12 years Same Same 50% 80% 90% Same Same 42% 75% 88% 90% Same 50% 80% 90% Same Rs Sales Year Year Year Year h 5 6 7-15 Rs Scrap Value (* Inc. Industrial 60% Duty) Department Projects 1971 April 18 million 7 mill.ion Annex 14 Page 3 COMMENTS ON SENSITIVITY ANALYSIS Case I is a test to see how much the selling prices could be reduced without the IFR decreasing,if imported raw material costs follow the long-range trend used in the IER. Case II indicates the impact of a one-year delay in the project with a 15% overrun. With the budget estimates being conservativeand project execution receiving full support from GOI, no significant overrun or lengthy delay is foreseen. Case III (80% production) shows that both the IFR and IER are still satisfactoryat the production. Case IV (100% production)is possible but not consideredlikely due to the wide range of blends and consequentdowntime. Case V (10% reduction in selling prices) can be considered unlikely as prices should not fall to this extent unless costs are similarly reduced. The test indicates that prices could decline somewhat in the face of competition and the project still show acceptable returns. Case VI (10% increase in prices) could increase somewhat in view of stable This will depend upon supply factors. is not likely although prices prices in the last 2-3 years. Case VII (15% overrun, one-year delay and maximum production 80%) shows that the combination of overrun, delay and production difficulties could make an otherwise acceptable project marginal. Case VIII (15% overrun, one-year delay and 10% decrease in prices) for the IFR is not considered likely as the price-cost relationship should continue. For the IER, however, international prices could be lower than calculated by IDA staff. The senistivity test on the phosphoric acid production as a separate project has been performed using a 6% drop in the selling price. The test shows the project returns 9% at $150 FOB per ton. Phosphoric acid has been contractedfor Indian delivery at $135 per ton CIF. However, it is probably that a fair price for use in an economic return would be $145 per ton to which $5 to $15 would have to be added for local costs, assumed in this case to be borne by an importer transport costs, and overhead. IndustrialProjects April 1971 Department with storage facilities, FACT COCHINII FROJECT TABLE2 of rupees) Base Case Streams Operating Costs Capital Costs Economic inancial Economic Financial P205 Return Return P20c Return Return ______ -_______ ________ _______ (millions Fiscal Year Ending March31 Period 1972 1973 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983 1984 1985 1986 1 2 3 4 64 129 118 48 5 6 7 8 9 10 11 12 13 14 15 Industrial Projects April 1971 61 118 112 48 25 48 46 19 168 260 289 289 289 342 343 345 345 346 346. 346 141 216 240 240 240 240 240 240 240 240 240 240 57 86 96 96 96 96 96 96 96 96 96 96 LnaitR ?tnaumnt NPK @ Rs. 928 195 353 113 422 422 422 422 422 422 422 422 490 knnom$c NPK e Rs. 690 147 264 309 316 316 316 316 316 316 316 316 384 P20t Rs. 1,200 69 110 124 124 124 124 124 124 124 124 124 151 Department 1W FACT COCHIN II Project Break Even Analysis a Selling Price Profit of Rupees 9z Re 928 86 Margin Rs 312 158,000 Tonx x 178,000 Tons x Rs 342 Rs 342 - _4 61 - 0 90% Capacity RS 124 86 Rs 75 436,500 Tons x Variable Costs Selling Price argin - _ R. 140 margin 586 436,500 Tons x Variable Costs Selling Price / Assuming Assuming 7/ NFK only / Variable 50% of project cost financed by debt maturing over 10 years interest on 50% of debt - assuming cryolite sold at variable cost costs exclude labor and supervision for this calculation. Conclusions Cash break-even Percent of total capacity Capacity in tons needed 1971 Department 32% 158,000 needed Percent of expected selling price RJ 928 needed 0 90% production Price needed 0 90% production Projects 61 in !/ April 26 26 - of RS928 Selling Price Variable Coats Industrlial Cash Millions 9 Volume Required Required Requirement 26 19 Fimed Coats Depreciation Debt Repayment Interest Price Break-Even Profit break-even 37% 178,000 of 77% Rs 710 78% Rs 726 LI ANNEX16 FACT Cochi.nII Project Annual Foreign Exchange Savings at Normal Production (90%) (Millions Gross Foreign 436,500 -95,400 6,750 103,500 Exchange Savings tons tons tons tons NPK NPK @ $85 each Urea @ $60 each Cryolite @ $250 each P2 0 5 @ $145 each of Dollars) Cryolite P 0 * *37.1 .7 $1.9 $15.9 Less Foreign ExchangeCosts Sulfur - 98,280 tons @ $30 each PhosphateRock - 311,850 tons @ $24 each Ammonia - 50,940 tons @ 37 each Potash - 81,540 tons @ $40 each Ammonia - 3,510 tons @ $37 each Other supplies and spare parts Depreciation costs Total Foreign ExchangeCosts Net Foreign .1 .2 Exchange Savings Total OperatingCosts (Both Local & Foreign) IncludingDepreciation Less Duties Plus Interest on 50% of Debt Plus 10% on Equity Total Annual Costs B. Net Local CurrencyCosts Net Local Currency Costs Divided by Net Foreign Exchange Savings in NPK Industrial Projects April 1971 Department .5 - . - *3 17.6 .1 11.3 $13.8 $1.8 $3.7 (Millionsof Rupees) Re 267 - 8 Rs 9 -1 9 18 -48 -132 _ 23 Rs 83 6.0 Rs/$ Rs 106 - 0 - 286 Less Urea Transferred Less Foreign ExchangeCosts Less Handling Costs Saved Included .1 *7 Local CurrencyCosts * 2.9 7.5 1.2 Interest on 50% of capital A. 2.9 7.5 1.9 3.2 1 8 9 118 - - 1 85 -12 Rs 8 Rs 21 - 4.4 Rs/$ 5.7 Rs/$* FACT INCOME STATEM5NT3 FORECAST - COII3LIDATED FISCAL TEARS ENDING MACH 31 (amtltone 1972 1S73 1974 I775 1976 1977 of Rapeoz) 1978 1979 198 198.1 1982 1983 1984 1985 1986 1987 IDL, FESO ANDFEW Net Sales Cost of Sales Sales Admin., Other Inooes Profit Before 219 176 11 (3) 35 219 176 35 219 176 21 (3) 35 201 121 201 1°05 201 74 201 74 201 74 201 74 201 74 74 74 90 121 121 121 121 121 522 522 422 522 222 522 522 422 422 305 10 107 305 10 107 305 10 107 305 10 107 305 10 107 305 10 107 305 10 107 305 10 107 279 10 133 195 195 195 200 232 263 263 263 263 289 21 17 13 174 178 85 182 90 191 100 226 124 93 92 91 121 219 192 11 (3) 19 219 176 12 201 121 201 121 74 74 413 422 299 9 105 305 10 107 219 197 11 (3) 14 219 197 11 (3) 14 219 197 205 125 202 122 201 121 201 121 66 74 74 353 260 9 84 219 190 111 (3) 21 219 195 74 69 160 97 202 123 2 50 65 (3) 16 219 176 11 (3) 35 219 176 1 (3) 35 219 197 11 (3) 14 219 196 11 (3) 15 219 189 11 (3) 22 177 157 11 (3) 12 Expeoses & General - (Inc. P0E1 & FEW) & Taxes Interest (3) 14 (3) 35 Cochin Net Sales* Cost of Sales* Ad-oin., Sales&OGeneral Experoeoa Profit Before Interest & Taxes induced Ri 80 per ton Including amorttoation * ** 13 3 for orea transferred expeoses of deferred to Cochin 1973-1975 14 14 II is 8 million 6 6 per 6 6 6 6 6 6 6 6 6 6 year bg Cochin II Net Sales Cost of Sales Adjoin., Sales Before Profit & General Interest 195 155 7 33 Expenses & Taxes Net Sales and Coot of Sales have to customers, and (b) by charged a) See Annex 17 page 2 for b) See Annex 14 page 2 for been redueed eliminating assumptions essuoptions (a) by deducting fertiltoer purchased freight, sold interest as part and other distribution progrem. of the seeding osts used used Consolidated Before Profit & Taxes Interest Initemsotl/ Before Taxes Taxes 2/ Net Prtfit Estimated Net Profit 1/ j/ (Loss) See Annoe 19 for After alluassceo Irdutistal Projests Apr1l 1971 intorest for imes Dep-rtment on long-term caroy forwrd, 115 173 193 15L 72 86 31 29 25 34 30 (17) - 43 62 8i - - 143 - 167 - (17) 43 62 81 143 167 debt for each de,oloopment diviston. end other robote ta oonoesstorns. 26 - 6 ios 5 3 2 258 no 26o 120 261 120 148 140 141 1262 120 289130 159 FACT' COCHIN II PROJECT Major Assumptions Used in UDL and COCHIN I In Forecasts SALES (OOO's of metric tons) Ammonium Chloride Ammonium Sulfate Ammonium Phosphate 1972 155 112 10 10 11 .8 1973 172 165 12.8 45 12 1.5 - 227 197L 172 165 12.8 h5 12 1.8 - 287 1975 172 165 12.8 L5 12 1.8 53 2LIh 1976 172 165 12.58 45 12 1.8 85 212 1977- on 172 165 12.8 45 12 1.8 95 202 - 700 620 SETLLINGPRICES COSTS - 1971 Ammonia 515 200 Based on current input costs for present production and naphtha O Rs 110 per ton delivered for Cochin I. IndustrialProjectsDepartment April Other Products UPEA Cochin II Others 104 (Rs per ton) 700 4Oo Super Phosphate 700 FACT Booroe an Tears Piseal 1972 1971 Net Pr1ofit Before T--sx and V on I.og Term Debt Interest (15 yr-.) (I:L y3 .) (12 yre.) Dopreoiation of Deferred 1986 1987 263 263 289 26 26 26 26 26 26 26 289 289 289 289 190 1961 1962 1983 14 195 195 200 232 263 263 21 47 26 21 47 26 16 47 26 31 26 26 94 94 94 89 57 289 289 289 289 289 1974 1975 1976 1977 66 115 173 193 195 21 47 26 21 47 26 21 47 26 94 94 287 16 - 20 36 - 21 47 - 21 47 - 16 56 68 68 9b C-_l - - 8 8 8 52 30 65 - 66 65 24 24 - 56 24 - 56 33 10 3D _ 85 30 67 68 UDL C-I (18) (12) 162 314 285 281 321 291 102 73 138 81 48 (31) 10 54 1 50 (31) 51 (12) 90 7c (6) 0 64 12 36 50 98 (6) 16 10 60 23 2 2 30 5 13 85 2 25 26 13 2 26 27 2 23 27 10 13 1 6 22 17 12 5 22 19 12 5 22 19 12 5 19 19 12 3 12 19 1 5 19 1 1 19 19 16 9 2 13 2 25 27 3 13 68 70 76 56 58 58 55 34 25 21 19 2 67 9 135 16 15 4 2 10 44 26 44 21 50 44 17 85 44 13 90 44 9 100 44 6 105 44 5 310 44 3 120 44 2 120 44 1 l3 44 - 137 123 168 197 177 175 175 176 182 174 176 92 737 312 849 3 963 31 114 1077 113 190 107 1297 r15 1412 113 1525 UDL C_I C-_r C-II Reeched.led 001 Leone hupees) 21 47 26 2/ ity in Iw-resses Leng Term Lone Bank Borrowings 72 14 (1) Tota1 Dpreciaton A-ontintion Expeases 1W3 Ending March 31 of Indian (Milli.oa SOURCE of Funds F-recont Applioation - Debt WadAdvnoesa TOTAL SO218E 20 - 289 APPLICATION Pined ABeet3 UDL C_I Working Capital C-I Total Workiog Capita1 Acoroe-d E open Loon Bepaymets IFCI Goe.t UDL UDL C-I C-II C-I IOt an Credit Debt Re..hede3d 13 epoyeot Total.oIn. UDL C_I BpesMee Deferrd - Taxen Disideed. Ten Dsbt onLong Intert on GOI LmOn and Internet lIAdva,es 9 30 1 27 2 23 1 34 44 30 159 338 285 271 230 194 W TOTALAPPLICATION 3 34 Conh BMn3p1n (Deficit) Conh Balsee 1/ Per detcls3 ,/ Bs 52 =Jlion 3/ (a) RB 75 in 1971 for dllion debt PreJecte April 1971 neroice Departratn 10 20 - 10 91 111 1i0 358 97 208 166 524 in 645 2 ond 17 in 1971 Cad Ba 23 million ./ .eeAnnex 19 far Iadrstril1 to An.exes refer (24) 10 Coebin Ij by diioa.n in 1972 for Coohie I, (b) Ba 27 sillio. Bal.o1s far Coehin in 1971; Ba 7 eilion II in 1972 sad Ba 3 illi.o in 1973 for UDL; (e) Balaaoe fwr Coehin LIIL FACT Coverage Long-Term Debt Service of Rupees) (in millions Years Endring March 31 Fiscal 1979 1980 1981 1982 1983 1984 1985 1986 1987 1-4 74 107 14 74 107 14 74 107 19 74 107 35 90 107 35 121 107 35 121 107 35 121 107 35 121 107 35 121 133' 94 94 94 94 89 57 26 26 26 26 287 289 (50) 289 - (85) 289 (90) 289 (100) 289 (105) 289 (nO) 289 (120) 289 (120) 289 (120) 289 (120) 267 287 239 204 199 1a9 184 179 169 169 169 169 1972 1973 1974 1975 1976 1977 12 2 - 22 50 - 21 65 - 16 66 33 15 74 84 14 74 105 56 76 76 102 94 Sub Total Less Taxes 70 148 162 217 267 - - - - A. Total 70 148 162 217 10 20 8 19 6 17 5 -* 27 SOURCES UDL C-I C-II Profit Before Interest and Taxes Depreciation and Forecasts 1973 - Amortization - RflUIREMENTS UDL C-I Intereste* C-II 30 Total UDL C-I C-II Principal** Total Times Covered * Assuming interest ** After is Rescheduiing.See Projects April 1971 financed 1 7 1 5 1 2 1 - - - - - - - - - - - -* 15 14 13 11 10 8 6 5 3 2 1 - 23 34 30 26 21 17 13 9 6 5 3 2 1 1 - - - 19 1 1 19 19 16 9 2 25 21 19 16 9 2 26 22 18 10 2 9.4 16.9 79.5 32 18 - 28 39 - 28 40 - 27 40 3 26 40 10 5 34 17 5 5 5 34 19 34 19 31 19 50 67 68 70 76 56 58 58 55 34 94 91 0.9 1.6 1.8 by project furds ard charged Page 2 attached. Department 2 10 3 12 19 80 B. Total Industrial _a 3 12 - 15 14 104 106 82 2.1 2.5 3.5 to Cochin II capital costs 75 79 2.8 3.0 until 1975 68 2.9 5 43 31 4.4 5.9 6.9 7.7 FACT Long Term Debt Repayment Schedule A. UDL DIVISION FY 72 F72 FY 74 14.3 5.7 10.0 5.7 3.9 4.4 FY 75 FY 76 10.0 5.7 8.8 5.7 6.9 6.o 5.0 5.0 5.0 After FY 77 Reschedul-ing F Y 79 Arrears on March 31, 1971 FY 80 FY 81 FY 82 1.1 FY 83 FY 64 FY 85 FY 86 FY 87 THIRD STAGE - GOI Normal Arrears 50.0 28.8 75.6 FOURTHSTAGE- GOI Normal Arrears 47.2 2.8 .5 .5 .5 .5 5.0 5.o 5.0 4.5 2.7 12.2 .6 .8 WAYSAND MEA4N- GOI Arrears 12.5 2.5 2.5 2.5 2.5 2.5 11.2 2.2 2.2 2.2 2.2 2.4 12.3 2.5 2.5 2.5 2.5 2.3 20.5 3.4 2.3 21.5 3.4 2.3 21.5 3.4 2.3 21.5 3.5 2.5 21i5 21.5 21.5 19.2 3.4 2.3 12.6 12.6 12.6 12.6 12.6 12.6 12.6 12.6 12.1 - - 3.0 100 17.0 19.0 19.0 19.0 19,0 19.0 19.0 19.0 16.0 9.0 2.0 66.6 68.2 70.0 76.0 56.1 58.1 58.1 54.8 33.9 24.6 20,8 19.0 16.0 9.0 2.0 IFCI Normal INTEREST Arrears . COCHINI - Normal Rescheduled Arrears GOI 186.6 17.1 11.7 215.4 - 4.5 1.2 ITALIAN CREDIT Normal C. COCHINII Normal TOTAL Industrial 112.9 - GOI 190.0 - 683.1 49.9 Projects April 1971 Department roF FACT ALAROSS2'T SORNUASTS FISCAL YEARSEMAIMAMARCH31 (Million. DIVI8 ASSETS 3 1972 1975 1976 1977 of I0di. 1978 MApR..0) 1979 1981 1980 1982 1983 12& 1985 1966 1987 1077 3.78 116 206 USC1 178 116 206 1297 178 116 206 13.12 178 316 206 1.525 178 116 206 O-rr0nt ka0et0 CMAh Other current 7DL C-I C-I3S- -. at. C-mreet Amete Total DOL C-C C-Cl Fixed Aset. Tote Lees Depr-.ti.6on Net Fixed Amaet 358 1o 165 54 - 1o 166 104 - 20 178 140 50 III 178 128 140 208 178 122 190 178 116 206 229 280 388 557 698 058 1,145 8459 178 737 178 116 206 116 206 1,578 1,462 1,349 1,237 963 178 11.6 206 1,691 320 2,026 1,913 1,798 320 .90 330 320 320 490 490 330 330 320 490 201 320 490 282 320 490 330 320 490 330 320 490 330 320 320 320 320 320 490 490 490 4397 490 490 490 330 330 330 330 330 330 330 673 (172) 1,011 (230) 1,092 11340 (402) 1,130 (496) 1,140 (590) 1,140 (684) 1,140 (778) 1,140 (872) 1,140 (961) 1,140 (1,018) 1,140 (1,033) 1,140 (1,070) 1,140 (1,096) 1,140 (1,122) 1,140 (1,122) 771 784 738 644 550 456 362 268 179 122 96 70 44 18 18 701 4 4 4 4 4 4 (308) 4 4 4 4 4 16 8 958 1,071 59 183 185 173 229 253 253 67 68 70 76 56' 309 312 302 364 9 125 209 33 100 7 99 183 101 87 5 73 156 166 74 TotAl Long Term Debt Less COrrent Y4twittLee 476 (67) 477 (68) Net Long Tem Debt 4309 283 Tlgni= 3178 16 206 317 490 66 4 MApensee (Market Deeeloet) Deferred 1,024 63.5 320 24 Irestat_t. 523. 178 116 206 1,299 1,184 1,346 1,412 4 i,484 4 1,511 1,533 1,509 -4 1,58 678 1,765 1,846 1,935 2,048 179 253 LiAILrTCCS AND IAPTAL COrreet LiabilitieM Aocs,Ad E p-ne Trade L-,, O-erdrmTt, Goarene,t PVmbles a-A Advomee 19) M tr8iMf Debt (See A-n LTA;}Utime T7ta1 Ourrent 109 1446 253 149 253 253 159 253 163. 253 3.69 253 179 253 179 253 179 253 58 58 55 34 25 21 19 16 9 2 368 370 420 452 436 437 438 443 448 441 434 3 38 129 187 61 1 24 102 177 b3 19 B0 160 36 14 58 4 18 103 2 6 84 65 46 27 11 2 24 9 37 122 12 474 (70) 428 (76) 352 (56) 295 (58) 237 180 125 (53) (55) (34) 92 (25) 68 (21) 46 (19) 27 (16) 11 (9) 2 (2) 309 340 352 295 237 lO 125 92 68 46 27 11 2 350 (0) 416 62 440 440 440 440 440 440 232 365 494 440 532 440 143 440 445 b40 (43) 589 666 770 866 240 350 478 583 682 805 885 934 982 1,029 1,106 1,210 1,306 1,184 1,299 1,346 1,412 1,484 1,511 1,509 1,533 1,538 1,678 1.3:1 1.S:l 1.9,1 2.3:1 2.4:1 2.5,1 2.8:1 3.1:1 3.4:1 9/91 6/94 4/96 59 59 59 59 59 432 Losg TormoDebt UDL UDL C-I C-II C-I IPC1 oc-ersont CreOit Ita}i-n v1.1 1 2 Sauity Sh-e Capital S-rp1lu (Deficit) Tetal 114,1it/r TOTALIHIACITISS 958 CAPITAL AIND .7:1 Ratio 0,,re,t Net Leeg Temn Debt,/Nfity 1/ 8. Asner 7 for ae.segstiOne P-8e.ote Ininotriel April 1971 63/37 Ratio Deprtent for Coc-hi. I sesottg 1,071 .9:1 54/.6 cepital. 47/53 38/62 UDLand Cochin I -oon-t 30/70 rewe.ieble 23/77 forecasted 17/83 on basis 12/88 coesletemt sith C-ohib CI. 40o 963 440 440 1,061 1,176 1,403 1,501 1,636 1,765 1,846 1,935 2,0348 3.6,1 3.8,1 4.1,1 4.411 4.7 1 2/98 1/99 O/1Oo O/100 0/A V k. 710 AGAIT ;et AFGHANISTAN 1S4INDIA eo- W7¢ |S PLANTS AND PROPOSEDMAJOR FERTILIZER PRESENT a- '-t,^ J IN SOUTHINDIA <,~\ /¢:,*.rrte tor {!r'. MAJORFERTILIZER PLANTS Csptd C_~~~~~~~~~~~~~~~~~~~ Un,LerconsBtOicBO t -V c'-.--/ Propooed ~~~~~~~~~~~~~~~~~~~~~~~0 ggugermIhways unde, construction ~~~~~Railw.ys Broad Stote on unadnlerritory boundares boundcries .... ~~~~~~~~~~~~~~~~~~~~~~-...Iternat,o I '-7 Hi/MACHAL .V/T- WEST |-.-- -----.- k%~~~~~~~~~~~~~~~~~~~ S'-*, .5 fJ n'd KASHMIR JiAMMU > >E * '1,A P'RADOSH Nationo cap,tol '00 0 200 r PAKISTAN Cdqart,a 200 500 40:) 300 MILES 0) oo *00 300 600 70o Boo PUNA 30 f tewDelhi T _, ;iARYANA { 1_ l I B . T E ' . LI rTAR ( _.IM ~~~~~~~P0'AOESH ~ NEA ' BHUTAN BtRRf E 5 R A 'A S TH A A/ ~' ,M A SAM Y~~~~ ) X \ - 0 /t KANDU4 ) IFFO aSi> X \. - 12 -. v- -* i * kMrCHA14YA S AKISTAN( t f ( i 'i 91ENVGAL 0X \& ! <BURMA ,0 , ~~~~~ 00' r AzsARASH RA,f 7.'vft8A a 7 t OO4ARAMS 17 i0 < 18 l i5~~~~ f t >S 7AMAGUNOAML o1 ?07ROMAAMA 9 -) MORR2J1 -X V J ay ,/_,-- k 0/PANSIObS OROMAN.Dfi 4 B eNnA Se ngo/ / A N7f'A Arobion ZUARI0005 1 ~ ~ ~ ~~~ ~ ~ ~ ~~~~~~~~~~~10y Y,~~~~~~~~~~~~~~~~~~~ Uhl~ f;" MANr,AL* B-gal- r' o '0. : MAY 1971 15LAND3 MAY J. ~~~~~~~~~~~~~~~~~~~~FCT 197100-3 ~ ~~~~~ ~ ~~~ ~ -Roadsj h X$ 54/D ~~~~~~~~~~~~~~~~~~~~ E5RD- 33,