JOB SAFETY ANALYSIS

advertisement
BAWTP1A Project
JSEA Ref No: AWTP
JOB SAFETY & ENVIRONMENTAL ANALYSIS
DESCRIPTION OF ACTIVITY: Unloading Pipes from Trucks
Date:
New
Crew:
Time:
JSEA developed by
(participants)
Supervisor:
Revised
Superintendent (Sign Name & Position):
Reviewed by:
HSE Professional (Sign Name & Position):
Approved By Superintendent / Section
Manager
(Sign Name & Position):
Plant, Tools & Equipment required
Mobile Crane, Hungry Beams
PPE in accordance with Site Induction
requirements
Step
Number
1
Job Steps
Steps with High Residual risk scores must be
approved by Discipline Manager
Civil Manager - Syd Phillips
Mechanical & Electrical Manager – Tony Victor
Potential Hazards
Controls
Residual Risk
Assessment
C
Pre-operation Inspection of Load
BAWTP1A – Safe Work Method Statement
Nil

Conduct a visual inspection of the load.

Ensure the load is securely chained down.

Ensure there are no loose items within the load.

Ensure the load has not moved in transit.

Review the load delivery docket and identify the
load as being correct.

With reference to the delivery docket determine
the weight of the load to be lifted and ensure the
capacity of the Crane (in relation to extension) is
not exceeded.
Page 1 of 4
P
Responsibility
R
Crane Driver
Truck Driver
Rigger
BUN1A-L-FM-0010-01[2]
BAWTP1A Project
JSEA Ref No: AWTP
JOB SAFETY & ENVIRONMENTAL ANALYSIS
DESCRIPTION OF ACTIVITY: Unloading Pipes from Trucks
Fall from height
Set up Mobile Scaffolding if the load is
2

Person responsible for erecting the mobile
scaffold must hold a basic scaffolders ticket. If
there are no qualified/experienced workers
available, the scaffold must be ordered from an
external provider who can supply and erect as
per the minimum standards.

Utilise safe manual handling practices,
including share lifting if required.

A pre-work inspection of the scaffold must
be conducted to ensure adequate access, work
platforms and hand railing is in place. If in
doubt, do not use the scaffold.

Two mobile platforms are to be above
truck’s tray, 1800mm high above ground. The
mobile scaffold should be secured against each
side of the trailer to reduce the fall height from
the load.

Install “Hungry Beams” along the sides of
the trailer to retain pipes should they move
when un-restrained.

It is the truck driver’s responsibility to
remove the securing chains from the load.

Person responsible for slinging loads must
hold a basic scaffolders ticket.
more than 1800 high
Collapse, potential falls
REFER JSEA UN-LOADING TRUCK
WITH HIGH LOAD
Manual handling, potential body strain
REFER JSEA MOBILE SCAFFOLDING
Un-loading
Fall from height
REFER JSEA CRANE LIFT
Collapse, potential falls
3
Manual handling, potential body strain


BAWTP1A – Safe Work Method Statement
3
C 13
Scaffolder
3
C 13
Crane Driver
Truck Driver
Rigger
Un-load pipes one at a time.
Pipes to be placed on hardwood dunnage
and not stacked.
Page 2 of 4
BUN1A-L-FM-0010-01[2]
BAWTP1A Project
JSEA Ref No: AWTP
JOB SAFETY & ENVIRONMENTAL ANALYSIS
DESCRIPTION OF ACTIVITY: Unloading Pipes from Trucks
UNCONTROLLED ENERGY CREATES POTENTIAL – Have you considered each of the following Energy sources?
(Tick to Indicate Each Energy Source You Have Considered & Controlled)
Mechanical
Electrical
Falling objects
Chemical
Gasses/Liquid/Vapour
Thermal
Pressure
Radiation
Biological
Points to Consider when Completing this JSEA:
(this list is not inclusive – simply a prompt)
 Does a work procedure/ existing JSEA relate to this job?
 Have all relevant personnel been trained in the appropriate procedures?
 Do all relevant personnel hold the required competencies / authorisations
required for the task(s)? – Have these been identified?
 Have all relevant parties been notified and included?
 Is signage required?
 Are there special PPE requirements?
 Is there an MSDS that needs to be referred to and made accessible?
 Is there a permit required for the job and is it available?
 Have all existing and recommended controls been noted on the above
table and explained to those involved?
 Are any new hazards being introduced – if so, are they adequately
controlled to ensure an acceptable level of risk is maintained?
 Are there any mechanical aids or special tools / equipment that need to
be made available?
 Have the monitoring requirements been considered?
 Environmental Issues: Erosion and sediment controls/ chemical and oil spills/
fauna and flora/ dust/ noise/ vibration/ public complaints
BAWTP1A – Safe Work Method Statement
Page 3 of 4
Kinetic / Stored
Solar
Human Force
Personnel participating in this job/task activity
Name
Signature
Name
Signature
BUN1A-L-FM-0010-01[2]
BAWTP1A Project
JSEA Ref No: AWTP
JOB SAFETY & ENVIRONMENTAL ANALYSIS
DESCRIPTION OF ACTIVITY: Unloading Pipes from Trucks
QUALITATIVE MEASURES OF IMPACT – CONSEQUENCE
LEVEL
IMPACT
1
Insignificant
2
Minor
3
Moderate
4
Major
5
Catastrophic
EXAMPLE OF CONSEQUENCE
Minor Injury; low plant damage < $1,000; minor loss of productivity; no environmental impact
Medical Treatment Injury / Restricted Work injury; plant damage < $100K; interruption to
productivity; environmental release immediately contained
Extensive injury (LTI), plant damage $100K - $500K; loss of productivity 1 to 5 days; loss of
production; environmental release off site with no detrimental effects;
Permanent Disability; plant damage $500K - $1M; loss of productivity >5 days; toxic
environmental release off site with detrimental effect
Fatality. Losses in excess of $1M. Permanent off–site contamination
QUALITATIVE MEASURES OF LIKELIHOOD / PROBABILITY
LEVEL
A
B
C
D
E
MEASURE
Common
Has
Happened
Could
Happen
Not likely
Practically
impossible
DESCRIPTION
The event is expected to occur in most circumstances
Will probably occur in most circumstances
GUIDE
Once per week
Might occur at some time
Once per year
Could occur at some time
May occur only in exceptional circumstances
Once per ten years
Once per life of facility
(10 – 30 years)
Once per month
H = High risk Immediate action required, activity must not start or be stopped if started. Highest level of Management needs to be involved.
M = Medium risk Monitoring controls are required. Management responsibility must be specified.
L = Low risk.
Identify hazards and implement controls. Manage by routine processes. Ie inspections / observations
BAWTP1A – Safe Work Method Statement
Page 4 of 4
BUN1A-L-FM-0010-01[2]
Download