8-450 TONNE MOBILE CRANE HIRE 24 HOURS / 7 DAYS SITE

advertisement
Phone:
Fax:
“Simple Logistics
for Complex Lifting”
61 2 9624 1944
61 2 9624 1233
PO Box 299, Winston Hills NSW 2153
info@melrosecranes.com.au
www.melrosecranes.com.au
ABN 73 083 164 845
8- 450 TO N N E M OB IL E CR AN E H IR E 24 H OU R S / 7 DA Y S  S IT E I N S P ECT IO N S  C OM P UT ER A N AL Y SI S  O H& S  CIT Y & RT CR A N ES  TR A N S PO RT SO LUT IO N S
MAN BOX – SAFE WORK METHOD STATEMENT – PART 1
Company:
SWMS Prepared By:
Date:
Project:
SWMS Approved By:
Ref No:
Work Activity/Task:
Accepted By:
Area/Zone:
CRANE AND MAN BOX USE
Mobile Crane Type:
Procedures (in steps)
Possible Hazards
1. Pre-start check. Travel
to site
Slip, trip, fall.
3
Poor visibility, tyre conditions.
3
Maintain three points of contact and adequate
grip on safety boots free of mud or oils when
completing daily pre-start logbook.
Clean windows and mirrors before driving.
Oil, water, fuel leaks.
3
Vehicular collisions.
2. Arrive on site
3. Plan work strategy
D:\726889101.doc
Risk Rate
Unit No:
Safety Controls
Residual
Risk
5
Responsibility
Driver/Operator
6
Driver/Operator
Spill kits kept in cranes to contain spills.
6
Driver/Operator
1
Travel as per Statutory Road Rules & Permits.
5
Driver/Operator
Fire hazard.
2
Check condition of fire extinguisher.
6
Driver/Operator
Collisions with other site plant.
1
Park plant/crane in safe area.
6
Driver/Operator
Unfamiliar with site, unstable ground,
overhead obstacles, underground
services.
Personal injury.
2
Complete site induction and site inspection.
Obey all site safety rules and signage.
6
Crane crew/client
2
5
Crane crew/client
Confusion over work to be performed.
2
6
Injury to workers or public.
2
Minimum PPE to be worn is hard hat, safety
glasses, high visibility clothing and steel capped
boots.
Crane crew to have tool box meeting with client,
supervisor.
Approved traffic control, permits, barricades and
signage.
Client/crane crew/
supervisor
Client/crane crew/
supervisor
Version 2
Issued: 13-Apr-20
Page 1 of 6
5
Procedures (in steps)
4. Set up crane, (with fly jib
as required)
5. Rig load to be lifted
6. Lift and control load
D:\726889101.doc
Possible Hazards
Risk Rate
Safety Controls
Residual
Risk
5
Responsibility
Unable to set up crane safely.
1
Specific site inspection.
Collisions with other plant, crushing.
1
Dogman/rigger to guide crane into position.
6
Crane crew
Soft, uneven, unstable ground,
suspended slab – outriggers sinking.
Crushing when extending outriggers,
slewing or placing counterweights.
1
5
Crane crew
5
Crane crew
Possible manual handling injuries when
packing under outriggers.
Collisions to plant or obstacles when
slewing crane, electrocution.
3
5
Crane crew
5
Crane crew
Placing rigging gear on hook – hand,
finger and/or manual handling injuries.
Incorrect boom length, working radius
and configuration. Crane malfunction.
3
5
Crane crew
5
Crane crew
Crush injuries and/or damage to plant
due to incorrect fly installation.
1
5
Dogman/rigger
Lifting gear not suitable. Defective lifting
gear eg; cuts, gouges, nicks, bends,
twists, excessive rust, missing tags,
broken safety catches, links stretched,
uncertified.
Trapping of hands or fingers.
2
5
Crane crew
5
Crane crew
Slip, trip, fall.
2
5
Dogman/rigger
Load tipping, sliding.
2
5
Dogman/rigger
Falling loads, crushing injury.
1
5
Crane crew/client/
supervisor/foreman
Not understanding signals – collisions,
crushing injuries.
1
Site inspection. Extra timber pads or road plates
under outrigger pads. Engineers report required
Co-ordinate all functions with dogman/rigger.
Keep clear of crush zones ie; articulation point of
Franna cranes.
Share load if too heavy, use proper manual
handling technique.
Clear tail swing area, watch for overhead
obstacles and keep mandatory distances from
powerlines. Distance from 132,000 volts 3m,
132,000 to 330,000 volts 6m, 330,000 volts and
over 8m.
Wear riggers gloves. Share load using proper
manual handling technique.
Check crane computer and all crane functions.
Critical radius check by doing ‘empty hook’ test
lift and refer to crane chart.
Configure crane and attachments by
manufacturer’s procedures by competent
dogman/rigger only.
Crane crew to ascertain loads to be lifted
(known weight, engineer etc) ensure correct,
certified lifting gear used only. Lifting gear must
be checked for defects before use, if defective
withdraw from use immediately.
No crane functions without clear signalling from
dogman/rigger.
Maintain three points of contact and ensure
footwear has sufficient grip when walking on
load. If a fall distance of 2m or more is likely
then fall arrest is required eg; safety railing,
safety harness worn.
Dogman/rigger to ensure crane hook is plumb
with load, no dragging.
Loads not to be lifted over personnel. All
personnel except dogman/rigger to keep clear
until load positioned.
Only dogman/rigger to signal crane. Check radio
operation if using and carry whistle for backup.
5
Dogman/rigger
Version 2
1
1
2
2
Issued: 13-Apr-20
Page 2 of 6
Crane crew
Procedures (in steps)
6. Lift and control load
(cont)
7. Place load
8. De-rig crane
9. Leave site
D:\726889101.doc
Possible Hazards
Risk Rate
Safety Controls
Residual
Risk
5
Responsibility
Swinging loads.
2
Taglines attached must be 16mm dia rope.
Windy conditions.
2
Crane operator’s decision on use.
5
Operator
Electrocution.
1
5
Crane crew/spotter
Tipping while mobilising crane onsite.
2
5
Crane crew
Load out of sight of operator – possible
collision, crushing injury.
1
5
Crane crew
Trapping body injuries.
1
5
Operator
Toppling or slipping of load.
1
5
Dogman/rigger
Trapping of hands or fingers.
2
5
Operator
Manual handling injuries.
2
5
Crane crew
Slips, trips, falsl.
2
5
Crane crew
Collisions with obstacles/ personnel or
plant.
2
6
Crane crew
Vehicular, pedestrian collisions.
1
Crane and load to keep mandatory distances
from live power. Vigilance of live cables at all
times.
Keep boom short and load close to ground,
bridle load to crane. Vigilance for other plant or
obstructions.
Use radios where possible. Check clarity of
radio with operator. Carry spare full battery and
whistle.
Crane operator to take signals from
dogman/rigger only.
Load stability to be checked by dogman/rigger
before de-rigging.
Dogman/rigger only to signal crane operator and
co-ordinate retraction of outriggers.
Share load handling ie; rigging gear, outrigger
pads, timbers, etc.
Maintain three points of contact when accessing
crane deck, cabin or support vehicles.
Obey site safety rules/speed limits.
Dogman/rigger or competent person to guide
crane off site.
Travel as per Statutory Road Rules and Permits.
5
Driver/operator
Version 2
Issued: 13-Apr-20
Page 3 of 6
Dogman/rigger
SWMS ANALYSIS OR EXTRA PROCEDURES REQUIRED (MAN BOX)
Procedures (in steps)
Possible Hazards
10. Safe Operation of a Man
Box
Inappropriate man box.
1
Crane tip over/two block hook/over
wind winch drum.
Freefall crane winch.
1
Crane tip over.
1
Falling from height.
1
Falling objects.
1
Collision with overhead hazards.
1
Only a certified man box/work box to AS1418.17
is to be used.
All crane function limiting switches are to be
active and tested before use.
A crane with freefall must have a positive lock
out fitted to prevent freefall. All winching is to be
by power up or down only.
Crane capacity to be a minimum of 1000kg at
its furthest radius of the task performed. No
other lifting by crane is allowed whilst the
workbox is attached.
Man box inducted personnel only. Safety
harnesses to be worn and fixed to anchor points.
All materials to be secured within the work box.
All tools to be fitted with lanyards and attached
when used. Control working area, eg;
barricading, bunting or vigilance. Wear safety
helmets at all times.
Secure radio communications and vigilance.
Equipment failure.
1
Overload man box or crane.
D:\726889101.doc
Risk Rate
Safety Controls
Residual
Risk
5
Responsibility
Supervisor/crane crew
5
Crane crew.
5
Operator/supervisor
5
Supervisor/operator
5
5
Supervisor/crane crew/
client
Dogman/rigger
5
Crane crew
Inspect all plant is in good order before use.
5
Crane crew
1
Do not exceed WLL of man box or crane.
5
Crane crew
Incorrect crane signalling.
1
5
Crane crew
Adverse conditions.
1
5
Supervisor/crane crew
Fall from height.
1
Competent dogman/rigger only to signal crane
operator.
The man box is not to be used when wind
speeds are in excess of 25km/h, electrical
storms or any other adverse weather conditions
that could compromise the safety of personnel.
Personnel do not enter or leave the man box
when elevated except in an emergency or when
a risk analysis shows this is the safest way to
access a structure (procedure to be developed).
5
Supervisor/crane crew
Version 2
1
Issued: 13-Apr-20
Page 4 of 6
RISK ASSESSMENT MATRIX
Likelihood of injury or illness
Very
Likely
Likely
Unlikely
Very
Unlikely
1
1
1
2
3
2
3
4
Medical attention and several days off work
2
3
4
5
First aid needed
3
4
5
6
Severity of injury or illness
Fatality/permanent disability or ill health
Long term illness or serious injury
1 – top priority; act immediately
4 – slight; within 24 hours
2 – priority; before continuing
5 – minor; within one week
3 – serious; by end of shift
6 – low priority; act when possible
1.
ELIMINATION
Can the work process, substances or plant creating the hazard be eliminated?
2.
SUBSTITUTION
Can the work process, substance or plant be substituted for something safer?
3.
ISOLATION
Enclosing the hazard, eg; placing barricades around the perimeter of the cranes operating area.
4.
ENGINEERING CONTROLS
Means changing process, equipment or tools to minimise the hazard exposure.
5.
ADMINISTRATION CONTROLS
Develop measures to ensure that the work is performed safely through safe work procedures to reduce exposure to hazards.
6.
PPE
Personal protective equipment is the last resort in responding to work place hazards and should be used only as an interim measure.
D:\726889101.doc
Version 2
Issued: 13-Apr-20
Page 5 of 6
SAFE WORK METHOD STATEMENT – PART 2
Personnel & Qualifications:
Safety duties and responsibilities:
Crane Operator/Driver
W/cover ticket & heavy vehicle licence
Dogman/Rigger
W/cover ticket
Dogman/Rigger
W/cover ticket
Training required to complete work:
Drive, operate crane safely; obey site safety rules
Guide crane, rig and place loads safely; obey site safety rules
Guide crane, rig and place loads safely; obey site safety rules
Engineers Details / W/cover Approvals / Permits:
Plant/Equipment: Crane Type:
Certified lifting gear, ie; chains, slings, shackles, equalizers, brick cages, man boxes,
spreader bars.
Maintenance Checks: To manufacturer’s specifications
W/cover ticket / general OH&S induction / site induction / tool box meet/
man box induction
W/cover ticket / general OH&S induction / site induction / tool box meet/
man box induction
W/cover ticket / general OH&S induction / site induction / tool box meet/
man box induction
References:
OH&S Act, 2000. OH&S Regulations, 2001.
AS 2550.-2002 Parts 1-5 (Safe Use of Cranes)
AS 1418.-2002 (Crane, Hoist & Winch – general requirements)
AS 3775.2.-2004 (Chain Slings – care and use)
AS1666.2.-1995 (Wire-rope Slings – care and use)
AS4497.2-1997 (Round slings, Synthetic Fibre – care and use)
COP Moving Plant Onsite. COP Working at Heights
Crane Industry Council of Australia (CICA) “Crane Safety Manual”
Additional References:
Daily pre-start checks, monthly routine maintenance checks, annual CraneSafe
inspection, logs kept in crane.
Read, agreed and signed below by all employees on site:
I have read and clearly understand the details contained in this document. As a responsible person, I am aware of my obligations towards ensuring that all works will be carried out in a safe and
appropriate manner and in compliance with the details of this SWMS. I am also the person responsible for implementing, monitoring and controlling each hazard as identified in the SWMS.
Crane Operator: ......................................................................................
Sign: .................................................................................
WorkCover: .............................................................................................
Green Card: .....................................................................
Crane Operator: ......................................................................................
Sign: .................................................................................
WorkCover: .............................................................................................
Green Card: .....................................................................
Crane Operator: ......................................................................................
Sign: .................................................................................
WorkCover: .............................................................................................
Green Card: .....................................................................
Crane Operator: ......................................................................................
Sign: .................................................................................
WorkCover: .............................................................................................
Green Card: .....................................................................
D:\726889101.doc
Version 2
Issued: 13-Apr-20
Page 6 of 6
Date: ..........................................................
Date: ..........................................................
Date: ..........................................................
Date: ..........................................................
Download