COMPLIANCE REPORT OF OMAXE SPA VILLAGE AT SECTOR -78, FARIDABAD, HARYANA. PART A-SPECIFIC CONDITIONS: Construction Phase:(i) (ii) (iii) (iv) (v) (vi) The Project proponent will seek the permission of CGWA for abstraction of Ground Water before the start of Construction. A first aid room as proposed in the project report will be provided in both during construction and operation of the project. Adequate drinking water and sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile toilets. Open desiccation by the labourers strictly prohibited. The safe disposal of waste water and solid wastes generated during the construction phase should be ensured. All the top soil excavated during the construction activities should be stored for use in horticulture / landscape development within the project site. Disposal of muck during construction phase should not create any adverse effect on the neighboring communities and be disposed taking the necessary precaution for general safety and health aspects of the people , only in approved sites with the approval of competent authority. Construction spoils , including bituminous material and other hazardous materials , must not be allowed to contaminate watercourses and the dump sites for such material must be secured so that they should not leach into the ground water and We have already received NOC from Central Ground Water Authority and a copy of the same has been send to your office.. A first Aid room has been provided both during construction and would be provided during operation of the project. Adequate drinking water and sanitary facilities are provided for construction workers at the site. The waste water and the solid waste generated during the construction phase being disposed off as per the norms. The top soil excavated during construction activities has been stored at one place and shall be used for development of horticulture / landscape within the project site. Muck including other construction waste during construction activities being disposed off such that they have no adverse effect on the neighboring communities and special precautions are taken for general safety and health aspects. Construction spoils including bituminous materials stored away from the surface water and are stored on plastic sheet to prevent leaks and spills and are not allowed to contaminate water courses , and also it is assured (vii) (viii) (ix) (xi) (xii) (xiii) (xiv) any hazardous waste generated during construction phase , should be disposed off as per applicable rules and norms with necessary approvals of the Haryana State Pollution Control Board. The diesel generator sets used during construction phase should be low sulphar diesel type and should conform to Environment (Protection ) Rules prescribed for Air and Noise emission standards. that they do not leach into ground water. The D.G. Sets are used as power back-up. The low sulphar diesel is used as fuel in order to reduce the pollution load. The D.G Sets are acoustically enclosed and conforms to the rules made under Environment (Protection) Act,1986 prescribed for Air and Noise. The diesel required for operating DG It shall be done. Sets shall be stored in underground tanks and if required , clearance from chief controller of Explosives shall be taken. Ambient noise level should conform Ambient noise level conform to to residential standards both during residential standards both during day and night . Incremental pollution day and night and it will be loads on the ambient air and noise maintained during the construction quality should be closely monitored phase.. Latest reports are during construction phase , so as to enclosed for your ready reference. conform to the stipulated standards. Fly ash should be used as building Fly Ash being used through Ready material in the construction as per the Mix Plants in which Fly Ash is provisions of Fly Ash Notification of being used as one of the September , 1999 and amended as ingredients of Concrete. on 27th August,2003. Ready mixed concrete must be used Ready mixed concrete is being in building construction . used for construction in order to reduce the water demand. Storm water control and its refuse as Storm water Control and its reuse per CGWB and BIS standards for shall be as per CGWB and BIS various application. standards. Water demand during construction Pre mixed concrete and other best should be reduced by use of pre- practices are involved during the mixed concrete , curing agents and construction in order to reduce the other best practices referred . water demand and it also conserves the natural resources. Permission from competent authority We have already received NOC for supply of water shall be obtained from CGWA and the copy of the prior to construction / operation of the same is already sent to you. project. (xv) Roof should meet prescriptive requirement as per Energy Conservation Building Code by using appropriate thermal insulation material to fulfill requirement. Roof designing are as per Energy Conservation Building Code Standards and appropriate thermal insulation materials shall be used in order to conserve energy. (xvi) Opaque wall should meet the It shall be done as per the norms prescriptive requirement as per of the Energy Conservation Energy Conservation Building Code Building Code. which is proposed to be mandatory for all air conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. (xvii) The approval of the competent It shall be done. authority shall be obtained for structural safety of the building due to earthquake , adequacy of fire fighting equipments etc, as per National Building Code including protection measures from lightening etc. If any forest land is involved in the proposed site , clearance under Forest Conservation Act shall be taken from Competent Authority. PART-B GENERAL CONDITIONS:(I) (ii) (iii) (iv) (v) The Environmental safeguards contained in the EIA / EMP Report should be implemented in letter and spirit. Six monthly compliance report should be submitted to the HSPCB and Regional office , MOEF, GOI, Northern Region, Chandigarh. The project proponent will sent one copy of the EMP Report to Additional Director, Regional Office , MOEF, GOI, Sector-31, Chandigarh and to the Chairman, Haryana State Pollution Control Board, Panchkula for their reference. The SEIAA, Haryana reserves the right to add additional Safeguard measures subsequently, if found necessary . Environmental Clearance granted will be revoked if it is found that false information has been given for getting approval of this project. All other statutory clearance such as the It is being done. It shall be done. It shall be done. All Environmental safeguards shall be followed by the project proponent both during construction and operation of the project. NOC from Civil Aviation approvals for storage of diesel from chief controller of Explosives, Fire Department , Civil Aviation Department , Forest conservation Act, 1972 etc. shall be obtained, as applicable by project proponents from the respective authorities before the operationallization of the project. (vi) These stipulations would be enforced among others under the provisions of Water (Prevention and Control of pollution) Act,1974 , the Air (Prevention and control of pollution )Act, 1981, the Environment (Protection )_Act, 1986, the public Liability (Insurance )Act, 1991 and EIA Notification, 2006. (vii) The project proponent will not violate any judicial orders / pronouncements issued by the Hon”ble Supreme Court / High Courts. Department has already been sent to your office. A copy of Environmental Clearance & consent to establish is made available at site office.. Agreed.