City of Westminster Item No. Decision-maker Date Title of Report Cabinet Member for Economic Development and Transport November 2003 Interim safety measures for Lord Hills Bridge, Paddington following bridge assessment and risk analysis. Classification Report of For General Release Director of Planning and Transportation Wards Involved Bayswater, Westbourne Policy Context To maintain the City’s highway network through planned maintenance and improvements. Financial Summary The estimated cost of proposals in this report for which financial approval is sought amounts to £150,000. These proposals are fully funded by Transport for London. 1. Summary 1.1. This report provides: Details of the results of the Feasibility Study for identifying interim measures in respect of Lord Hills Bridge in Paddington following a Bridge Assessment and Risk Analysis. And seeks approval to: 2. 2.1. Implement the recommendations of the Feasibility Study for Interim Measures at Lord Hills Bridge. Recommendations That approval be given to capital expenditure of £150,000 to enable a central reserve to be installed over Lord Hills Bridge. These works are fully funded by Transport Grant from Transport for London being available in 2003/04. 1 2.2. 3. That the Director of Planning and Transportation be authorised to create a temporary shared cycle tracks on the footways of Lord Hills Bridge, subject to the receipt of no objections to the statutory consultation required. Background Information 3.1 Lord Hills Bridge in Paddington is owned and maintained by Network Rail. The bridge has been assessed by Network Rail as part of the national assessment and strengthening programme and rated at 7.5 tonnes, considerably below the 40 tonne EU loading requirement. There is therefore an urgent need to implement either a weight restriction and/or interim measures to safeguard the structure and public safety. 3.2 The responsibility for upgrading bridges owned by Network Rail to the new standards falls to the City Council. A legal agreement was entered into with Network Rail (or Railtrack as it was at the time) to enable the assessment to such bridges carrying public highway to be undertaken. 3.3 The agreement provides for the City Council to closely monitor the management and control of the work that is being undertaken by consultants instructed by Network Rail. Network Rail commenced the assessment programme in November 1998 and it was originally programmed that their work would be completed by August 2000. However a combination of operational difficulties, delays in obtaining possession of the railway tracks for access to carry out structural inspections, and project management issues , resulted in major slippage to their programme. 3.4 Council Officers have been particularly mindful throughout the assessment process that Lord Hills Bridge is on the proposed diversion route associated with the closure of Bishops Bridge Road as part of the Paddington Bridge Project. Any Interim Measures arising out of the assessment process therefore need to be implemented before the closure of Bishops Bridge Road. As such, Council Officers have been pressing Network Rail for some considerable time to complete the assessment process to determine whether interim measures are needed to protect the structure. 3.5 The assessments are now complete. It was intended that Network Rail would manage the next phase which includes undertaking both a ‘Feasibility Study for Interim Measures’ and a ‘Feasibility Study for Strengthening’. However, due to difficulties with the assessment work, it was agreed that the City Council would directly manage the further work thus regaining control of the programme. 3.6 The City Council obtained Network Rail’s approval to directly employ the consultant used in the assessment work to carry out the feasibility studies. These studies are essential to determine the extent of any work required and the financial liabilities to the City Council. This information also enables the City Council to bid for grant funding from TfL 3.7 The Departmental Contracts Board (DCB) granted a waiver to the Contracts Code and Consultant WSP Ltd have been appointed to undertake the Feasibility Studies for Interim Measures and Strengthening. Financial approval for this work has already been granted and is fully funded by TfL. 2 4.0 Results of the Feasibility Study for Lord Hills Bridge 4.1 WSP Ltd has now completed a risk analysis as part of their Feasibility Study for Interim Measures on Lord Hills Bridge. The results of the study recommend a reduction in the carriageway width over the bridge to reduce the ‘live load’ and improve the load carrying capacity of the structure. Implementing these measures prior to the closure of Bishops Bridge Road will obviate the need to apply a weight restriction and safeguard the proposed diversion route for all types of vehicle. 4.2. The consultants' report recommends that the carriageway width reduction measures should take the form of a central reservation as this provides the optimum increase in the live load capacity of the bridge, by avoiding loading the centre of the bridge. 4.3. The central reservation works are to be in the form of a double row of barriers approximately 1.5m apart, which look very similar to road safety barrier. The barriers are to be in place for the duration of the closure of Bishops Bridge Road and until permanent measures are developed to increase the strength of the bridge. A plan showing the location of the bridge and the extent of the works is shown in Appendix 1. Traffic Implications 4.4. To install the barriers safely in the central reservation, a closure of Lord Hills Bridge over a single weekend will be required. Traffic Orders to temporarily close the road have been applied for in advance. Because of the short time scale available to implement the works it is anticipated that a full road closure will be required. However, a closure in one direction only is also being investigated. Subject to Cabinet Member approval it is anticipated that the works will take place over the weekend of 29/30 November or 6/7 December 2003. 4.5. A consequence of reducing the carriageway width on the bridge is that only two lanes of traffic will be able to use the bridge at any one time. At the moment it is possible for three lanes of traffic to pass on the bridge. This is particularly helpful as vehicles can negotiate buses using the bus stop on the bridge outside the Royal Oak Tube Station without interrupting traffic flows in the opposite direction. If the carriageway width reduction is implemented this will no longer be possible. If the carriageway width reduction scheme is implemented it will no longer be possible for Network Rail or London Underground contractors to park vehicles at night on Lord Hills Bridge when undertaking works at the station on the railway line. Officers are in discussion with Network Rail and London Underground about alternative arrangements. 4.6. Officers are mindful that any additional traffic congestion on Lord Hills Bridge is likely to result in tail-backs onto the Harrow Road. 3 4.7. To avoid additional traffic congestion as a result of vehicles not being able to negotiate buses using the bus stop, it is proposed that the bus stop outside the Royal Oak (Hammersmith and City Line) tube station be temporarily relocated. This will result in bus passengers either having to walk approximately 75 metres further to reach the tube station or remain on the bus for a few extra minutes (at no extra cost) to Paddington Station. From there they can make more extensive connections with the London Underground network. Approval in principle to re-locate the bus stop has been received from Transport for London - London Buses. 4.8. The erection of barriers in the centre of the carriageway, and the difficulty vehicles may have if they want pass cyclists on the bridge, has been considered. The footways on both sides of the bridge are wide enough to accommodate cyclists and pedestrians it is therefore proposed to create a temporary cycle lane in one or both footways on the bridge. If objections are received following statutory consultation, then it may be appropriate to require the cyclists to remain in the carriageway. 5. 5.1. Other Network Rail Bridges in Paddington It must be noted that Network Rail have assessed other bridges crossing the railway lines out of Paddington, these are: Westbourne Terrace Bridge Ranelagh Bridge Westbourne Park Bridge (Great Western Road) 5.2 There are some concerns regarding their load carrying capacity and minor protection measures to the footway to prevent vehicles overloading substandard beams beneath on both Westbourne Terrace and Ranelagh Bridges may be necessary. If required these would be easily implemented and would not affect traffic flow. 5.3. In respect of Westbourne Park Bridge (Great Western Road) the current view is that some carriageway restriction may be necessary, although these should not affect overall traffic flow. 5.4. A further report to Cabinet Member will be made in respect of these structures on completion of the consultants' work. 6. Financial Implications 6.1 Provision exists within the Capital Programme as follows: Interim Measures for Lord Hills Bridge 4 2003/04 2004/05 2005/06 TOTAL £000 £000 £000 £000 130 10 10 150 This is a provisional amount which is fully funded by TfL Transport Grant. 6.2 The total capital expenditure as a result of this report is £150,000, for which financial approval is sought. 6.4 The revenue implications of the capital expenditure of £150,000 assuming an asset life of 10 years over the next four years would be as follows: Capital Charges £000s 7. 2004/05 2005/06 2006/07 2007/08 18 19 20 20 Legal Implications 7.1. There are no direct legal implications arising from the issues discussed in this report. 7.2. The Council has powers to create shared use cycle paths from footways using powers contained in section 65 HA80 of the Highways Act 1980. 8. 8.1. 9. 9.1. Staffing Implications There are no staffing implications arising from the issues discussed in this report. Performance Plan Implications There is no specific reference in the Transportation Performance Plan. & Infrastructure 10. Consultation 10.1 This report relates to Westbourne and Bayswater wards. 10.2 Ward Members have been briefed on the measures set out in this report and any views received will be forwarded to the Cabinet Member. 5 11. Health and Safety Issues 11.1 All works undertaken will be closely monitored and carried out to the requirements of the Health and Safety at Work Act 1974 etc and the Construction (Design and Management) Regulations, 1994. 12. Co-operation with Health Authorities 12.1 There are no significant implications for the health and welfare of residents arising from the issues discussed in this report. 13. Conclusion 13.1 The implementation of a central reserve over Lord Hills Bridge is considered essential to safeguard the structural integrity of the bridge, particularly as the bridge is likely to carry increased traffic once Bishops Bridge Road is closed on 11 January 2004. The proposed measures are temporary and will stay in place whilst Bishops Bridge Road remains closed and until a permanent strengthening solution can be implemented. 13.2 The central reserve must be installed and operational prior to the closure of Bishops Bridge Road. 13.3 The introduction of the central reserve over Lord Hills Bridge will require the re-location of the bus stop currently located outside the Royal Oak Tube Station and Transport for London – London Buses has given its support for relocation. IF YOU HAVE ANY QUERIES ABOUT THIS REPORT OR WISH TO INSPECT ANY OF THE BACKGROUND PAPERS PLEASE CONTACT ANDREW FOSTER ON 020 7641 2541; fax 020 7641 2658; email afoster1@westminster.gov.uk Background Papers The documents used or referred to in compiling this report were: 1 Maintenance Management of Bridges and Other Highway Structures – March 2003. 6 For Completion by Cabinet Member Declaration of Interest I have no interest to declare in respect of this report …………………………………….. Signed ……………………..………… Date I have to declare an interest State nature of interest …………………………..…………………………….. ………………………………………..……………………………………………. …………………………………….. Signed ……………………..………… Date (N.B: If you have an interest you should seek advice as to whether it is appropriate to make a decision in relation to this matter.) For the reasons set out above, I agree to the recommendation(s) in the report and reject any alternative options which are referred to but not recommended. Signed …………………………………………. Cabinet Member for Economic Development and Transport Date …………………………………………….. NOTE: If you do not wish to approve the recommendations, or wish to make an alternative decision, it is important that you consult the report author, the Director of Legal and Administrative Services, the Director of Finance and, if there are staffing implications, the Head of Personnel (or their representatives) so that (1) you can be made aware of any further relevant considerations that you should take into account before making the decision and (2) your reasons for the decision can be properly identified and recorded as required by law. Note to cabinet Member: The decision will now be published and copied to the Members of the relevant Overview & Scrutiny Committee and may not be implemented until five working days have elapsed from publication to allow the Overview and Scrutiny Committee to decide whether it wishes to call it in. 7 Appendix 1 Location Plan and Extent of Works 8