Introduction This report documents the energy consumption patterns for the building under study, identifies areas of opportunity for energy savings, and determines the cost effectiveness of selected options. The recommendations provided in this report always take into consideration the architectural integrity of the building, the proper functioning of its mechanical equipment, and the health and safety of its occupants. The Meridian Township Municipal Building located at 5151 Marsh Road in Okemos, Michigan, is a two-story steel framed structure set into a hill to the east. The original construction date for the building is 1971. There has been one additions to the south side of the building in 1992. Major improvements were made to the building’s energy systems in the 1990’s. The building currently houses the Township Hall and most of the administrative functions of the Township including the public access cable studio. Two site visits, including one at night, were made to the Meridian Municipal Building to inspect, photograph, and document its physical characteristics. The Energy Management System for the building was also viewed. Dennis Antone, the Facilities Superintendent, and LeRoy Harvey, the Recycling Coordinator, were in attendance at an initial project meeting. They provided a CD with the construction plans of the building as well as other written historical information. They also provided information regarding occupancy, building maintenance, and expected outcomes for the energy study. An occupant comfort survey was also undertaken. Space heating for the building, as well as domestic hot water, is produced using natural gas. All other energy needs are provided using electricity. Gas and electric utility bills for the 12 months of 2009 were provided for the study and have been reviewed. Spreadsheets containing this data are provided in the Appendix. We always remind our clients that utilities charge penalties for late payments (as much as 2%). No late payments were found. It is also important to maintain good record keeping of utility bills in order to accurately track costs and spot changes in consumption patterns. Building owners should always require actual readings each month by the utility. There was one estimated reading for both gas and electricity for the Meridian Municipal Building. This did not effect the quality of the study.Executive Summary A complete analysis of how the Meridian Municipal Building and its HVAC systems are responding to monthly weather patterns was conducted. It appears that the building is using significantly more gas energy for heating than should be the case. The need for cooling is driven more by internal heat loads than exterior air temperatures. The building has an energy management system which is programmed to alter building temperature settings for energy savings. The HVAC systems are regularly maintained. This study identified 2 O&M (Operations and Maintenance) no cost/low cost items which could be undertaken to reduce gas consumption. The building model analysis indicates that the roof of the building is a significant source of heat loss. It is recommended that roof deck insulation be installed at the time of re-roofing. The benefits of insulating the roof has been evaluated in this report. There are 5 exterior wall types for the building. These are for the most part adequately insulated. The building has all double pane glass. The doors are insulated or have double pane glass. The slab edge is properly 1 insulated. If the 1 shell ECM (Energy Conservation Measure) items for saving gas energy were undertaken, the gas consumption for the building would be reduced by about 12%. The building energy model indicates that mechanical ventilation constitutes the largest source of heat loss. There are 2 Air-Handling Units (AHUs) located in the third floor mechanical room which serve the building. A central boiler on the second floor supplies hot water to the AHUs for space heating. This report evaluates for its replacement. Each AHU has separate ground mounted, air cooled, DX condensers. One is relatively new, the others are older. When these A/C units reaches the end of life, units with an EER of 12 to 14 is recommended. The AHUs can easily be modified to provide for demand controlled ventilation. This is a low cost high savings opportunity. Energy recovery ventilation is a possibility for both AHUs. If the 3 HVAC ECM items for gas savings were undertaken, the gas consumption of Meridian Municipal Building would be reduced by about 40%. A complete analysis of all the electrical equipment in the building was also undertaken. This study identified 8 O&M (Operations and Maintenance) no cost/low cost items which could be undertaken to improve electrical energy performance. Several areas of the building are evaluated for installation of occupancy sensors to control the lighting. Further study is recommended to identify a cost effective strategy to reduce HVAC power consumption. Installing variable frequency drives (VFDs) on the AHUs is one means to accomplish that task. These 2 electrical ECM (Energy Conservation Measure) items have reasonable costs and modest paybacks. The fluorescent lighting systems in the Meridian Municipal Building were updated to T8 technology in the late 1990’s. A group re-lamping project using 28 watt lamps is recommended for these fixtures. Re-lamping the few incandescent fixtures with compact fluorescent lamps will produce quick low cost savings. The exterior lighting at the Meridian Municipal Building constitutes 11% of the total lighting consumption. These fixtures all use high pressure sodium lamps. These can be re-lamped and re-fixtured using more efficient fluorescent induction technology. 4 ECMs relating to lighting were identified. Typical of lighting efficiency, these measures are a good investment reducing lighting consumption by 25%. All the O&Ms and ECMs are summarized in the table below. A subset of the O&M and ECM items, marked by an X, is recommended for implementation. Items shown in Green indicates that a utility incentive is available. Please refer to the report text for implementation information. A. O&M and ECM Summary Table TEA Items O&M or ECM Report Recom Description Ref. mended Page Gas O&Ms 12 O&M #1 Check Accuracy of Gas Meters Estimated Project Cost ($) 2 Cost Pay- Energy Est. Savings back Savings Life ($/yr) Years MBtu/yr (yrs) O&M #2 Maintain Door Weatherstripp ing Gas ECMs 13 14 X 15 X 16 X ECM #1 - Add Roof Insulation ECM #2 Demand Controll Ventilation ECM #3 Energy Recovery Ventilation ECM #4 New Condensing Boiler Electric O&Ms 22 22 22 22 23 23 23 O&M #3 Small Kitchen Appliances O&M #4 Efficient Office Equipment O&M #5 Purchase Energy Star O&M #6 Activate Computer Sleep Mode X O&M #7 Power Down Equipment X O&M #8 Vending Machine Controls O&M #9 Premium Efficiency Motors O&M #10 Radiant Foot Warmers Electric ECMs 3 $14,398.00 $2,069.61 7.0 222,300 Life $2,000.00 $4,294.48 0.5 421,974 Life $14,000.00 $3,388.49 4.1 327,122 20 $18,000.00 $3,223.72 5.6 332,000 20 24 X 25 X 28 28 30 31 ECM #5 Occupancy Sensors ECM #6 Variable Frequency Drives Lighting ECMs X ECM #7 - Relamp T8 Fluor Fixt X ECM #8 - Relamp w/ CFL 16W R X ECM #9 - Relamp HID w/ InducFluor ECM #10 Refixture HID w/ InducFluor X $650.00 $81.23 $8,000.00 $735.92 10.9 38,324.0 20 $5,436.00 $1,028.75 5.3 25,480.2 10 4,862.0 15 $13.86 $9.62 1.4 80.5 20 $2,200.00 $222.41 9.9 7,123.6 16 $8,500.00 $340.81 Recommended $42,299.86 $12,248.70 ECM/O&M Totals 4 8.0 24.9 11,644.8 25 3.5 1,118,64 2.3 Building Description The Meridian Municipal Building was built in 1971. It is a steel framed structure built in 2 sections. There is a one story Town Hall Meeting Room on the west connected by two entry vestibules to a two story building on the east housing the township office functions. The original building area is 19,232 SF not including the third floor mechanical room. A two story addition, containing 6,298 SF not including its third floor mechanical room, was constructed on the south side of the original structure in 1992. The total gross area of the building is 25,530 SF. A floor plan for the building is provided in the Appendix. B. Photo of Meridian Municipal Building OCCUPANCY The Meridian Municipal Building has from 52 staff members who regularly occupy the building. There are an additional 50 to 60 people who visit the building daily. The building has its own janitorial staff. A Town Hall meeting room is used in the evenings for public events.OPERATION The Meridian Municipal Building is in use from 6:30 AM to 4:30 PM Monday through Friday. The building is closed an additional 14 days throughout the year. The building has 2 heating/cooling zones controlled by an energy management system. Night time and seasonal temperature setbacks are currently being practiced. Regular HVAC maintenance is provided through an outside contract with DEEM. 5 WALLS The above grade exterior walls on the west side of the original Meridian Municipal Building are insulated steel stud framing or concrete block with brick veneer. These walls have R-values ranging from 8 to 10. On the north and east sides, where the first floor walls are set into a hill, the construction is poured concrete. These walls have an R-value of about 5. Most of these walls have subsequently been finished off and insulated from the interior. There is a small portion of the poured concrete wall which is directly exposed to exterior air temperatures that is not insulated. The addition built in 1992 has a similar structure. The second floor walls of the addition have higher insulation levels at an R-value of about 18. ROOF The roof structure of the Meridian Municipal Building is constructed similarly for both the original and the addition. Steel roof framing forms a gable within which the mechanical rooms are located. The roof deck is 3” nominal wood with asphalt shignles applied over it. The insulation design for the roof is unusual and not uniformly effective. 3 1/2” fiberglass blankets are stapled to the underside of the roof deck. The insulation level of this assembly was devalued to R-8.33. The best practice for cathedral roofs like this is to put nailable rigid insulation on top the wood deck and apply the shingles over that. It would require 3” of new rigid insulation to bring the roof assembly up to ASHRAE 90.1 standards. This report evaluates for the savings potential of this procedure. WINDOWS The original Meridian Municipal Building has thin and tall windows regularly spaced around the building, mostly on the second floor. Some have operable sash. This is not the best configuration of glass for the utilization of natural daylight. The addition adopts the rhythm of window placement of the original building, but the windows are wider with normal sill heights. All the windows are double pane. Should glass need to be replaced in the future, high performance glazing with a Low-E coating and filled with argon gas should be specified. If free passive heat from the sun is desired, special care must be taken in ordering glass with high solar heat gain, otherwise, glass designed for the southern climates, which block most solar heat, will be the standard offering. Replacing windows that are already double pane is not cost effective and is not evaluated for in this report.DOORS The Meridian Municipal Building has a number of door locations. The public entries have full glass entry doors. The remainder of the exterior doors are insulated hollow metal doors. These all appear to be in good condition with weatherstripping which should be checked for effectiveness annually. Due to high cost and minor energy savings, replacement of exterior doors is not evaluated. Replacement doors should have high performance glazing as indicated in the window discussion. Fiberglass service doors would have superior insulation value and longer life. AIR INFILTRATION The windows in the building are mostly fixed and not considered a significant source of air infiltration. Weatherstripping on the exterior doors, if not maintained, can be a source of unwanted air infiltration. Fortunately, the building entries open into air lock vestibules which help to prevent exterior air from directly entering occupied spaces. DHW Domestic hot water is supplied to the building by a gas-fired, tank type, water heater. The unit is a Bradford White MI403T6EN12 40 gallon tank. It has an 80% combustion efficiency. The copper pipes to this unit are insulated. The temperature setting is below the maximum recommended 120°F. There is no circulation pump. 6 VENTILATION The building energy model indicates that the Meridian Municipal Building has large volumes of mechanical ventilation which constitute the majority of the heat loss from the building and consume a large amount of electricity to operate. There are two sets of public restrooms which are mechanically vented by one central exhaust fan. The 1 1/2 HP motor of the fan is connected to the building Energy Management System (EMS). According to the control cycle commentary in the drawings for the 1992 addition to the building, the exhaust fan runs continuously during occupied hours and is deactivated at night and over weekends. This should be confirmed by retro-commissioning. The Meridian Municipal Building has 2 air handlers located in the third floor mechanical rooms; one serving the original building and one serving the addition. Each air handler provides conditioned fresh exterior supply air whenever heating or cooling is required. Both have the capability to provide up to 100% fresh air for cooling when exterior conditions permit. The air handling units are controlled by the EMS. Relief air is exhausted from the system to match the amount of fresh air introduced to the building in order to equalize pressure in the building. According to the control cycle commentary in the drawings for the 1992 addition to the building, exterior air and relief air vents are closed when the building is unoccupied. Only interior air continues to be circulated at these times. This set of conditions should be confirmed by retro-commissioning. The current system of providing fresh air to the building can be improved in two ways. The proximity of the outside and relief air ductwork provides the opportunity to establish demand controlled ventilation, by using carbon dioxide sensors to control when and how much fresh air is provided to the building. Energy recovery ventilators could also be used to reclaim up to 60% of the heat used to warm the incoming fresh air stream. SOLAR ENERGY The building has some solar heat gain through the windows on the south side of the building. In northern climates solar energy can help to heat buildings. However, east and west facing windows can be a nuisance in the summer. The Meridian Municipal Building has deep foot roof overhangs which provides good summer sun shading to the south facing windows but does little for the east and west facing glass. Vertical blinds work best for blocking unwanted sun on east and west facing windows. Horizontal blinds are ideal for south facing windows. Some of the occupants of Meridian Municipal Building are provided with interior blinds to block unwanted sun and heat. Windows adjacent to offices provide significant natural day light, the distribution of which can be improved with horizontal blinds. Electric lighting appears to be used less in offices with natural light. The tall thin windows, which are the dominant window type at the Meridian Municipal Building, are not as useful in providing day light. The building has sufficient hot water needs that a solar thermal water heating system might be cost effective. The building also has a large roof area unobstructed by trees which is suitable for the installation of a solar electric system using PV (photovoltaic) panels. Such systems are currently very expensive. Government or utility incentives, such as tax credits, rebates, or feed in tariffs, have recently become available to defray the cost of a PV system. The Meridian Municipal Building requires electrical energy efficiency improvements before considering such a PV installation. 7 HEATING & COOLING The Meridian Municipal Building has two HVAC systems. The two air handlers are equipped with heating coils, with hot water supplied by a boiler, and cooling coils, with cooling refrigerant provided by separate ground mounted direct expansion air cooled condensers. There is also some as some finned tube radiation, convectors, and ceiling unit heaters supplied by the boiler to provide heat to the building. The boiler system is unusual in that the gas burner unit is attached to a vertical water storage tank. The system relies upon combustion air brought into the mechanical room via an atmospheric damper. It does not have a flue damper. The efficiency of this system is pegged at 78% and its capacity was identified as 1.35 million Btus per hour. The maximum heat loss of the building was calculated to be 650,000 Btus. This boiler system could be replaced with two much smaller, full modulating, condensing boilers and sequenced for high efficiency operation. The efficiency of the new system could reach 95%. The original two story north end of the Meridian Municipal Building is cooled by a new 25 ton air cooled condensing unit - McQuay ACZ025ACT - with a good EER rating up to 14. The one story Township Hall has a separate much older condensing unit, without a name plate, of perhaps 10 ton capacity. The newer two story south end of the building has two original 8.5 ton condensing units - C100G0 by Inter-City Products Corp. The 3 older units have EER ratings of 9 or below. This is considered at the low end of current technology. These units may be reaching the end of life. When the units require replacement in the future, EER ratings of 14 or more are available and would provide a good return on the added investment. This report does not evaluate for replacement air-conditioning equipment because of the costs involved. The HVAC systems in the Meridian Municipal Building are controlled with an energy management system which was installed in the 1990’s by Johnson Controls under an energy performance contract. The HVAC systems are currently maintained by a company other than Johnson Controls. The EMS software has been updated to the latest version M5 and is sufficient for the needs of the building. The control devices are a mixture of pneumatic and digital models. Movement toward full direct digital controls is recommended as the system ages. LIGHTING The fluorescent lighting in the Meridian Municipal Building was retrofitted in the 1990’s at the inception of the performance contract with Johnson Controls. All of the fixtures were re-ballasted with T8 low power ballasts and 32 watt lamps. The lamps in these fixtures should be at the end of useful life. A group re-lamping project using energy saver T8-28 watt lamps is recommended. The exit signs were all converted to LED in the 1990’s. All but a few incandescent fixtures have been re-lamped with CFLs. CFL equivalents are specified in the report. The cable TV studio uses high wattage incandescent fixtures. There are LED alternatives for this specialized use. The design of this lighting is beyond the scope of this report. The exterior lighting around the Meridian Municipal Building uses high pressure sodium (HPS) technology. Exterior lighting accounts for almost 20% of the total lighting consumption. It is currently on a central photocell control. A night time lighting survey indicated that some of the exterior lighting is not functioning, presumably because the lamps or ballasts have failed. These fixtures can be re-lamped or replaced with new fixtures using more efficient induction 8 fluorescent technology. This technology offers better light quality, silent operation, instant on, improved lamp life, and dual level lighting capabilities. OCCUPANT COMFORT SURVEY 27 people responded to an occupant comfort survey for the Meridian Municipal Building. A majority of the respondents indicated dissatisfaction with the heating and cooling in the building. About 1/3 of respondents were also dissatisfied with the humidity and air quality. Further investigation might want to be done to reveal the exact nature of the complaints. This information can inform the process for energy efficiency. Occupant comfort should be a top priority in any project. Natural Gas Billing Information The natural gas billing information for 12 months was received and input to a spreadsheet for analysis. This entire record is printed out for reference in the Appendix to this report. This information is also available in electronic format upon request. An abbreviated set of data for the gas consumption, along with summary information, is provided below. This period encompasses the 2009 calendar year. C. Gas Cost/Consumption Chart M/Yr CCF $Total $ Service $Net $/CCF J 3,455 $3,440.87 $16.00 $3,424.87 $0.991 F 3,128 $3,116.72 $16.00 $3,100.72 $0.991 M 2,617 $2,385.53 $16.00 $2,369.53 $0.905 A 1,690 $1,532.93 $16.00 $1,516.93 $0.898 M 543 $432.78 $16.00 $416.78 $0.768 J 436 $364.03 $16.00 $348.03 $0.798 J 335 $291.09 $16.00 $275.09 $0.821 A 828 $614.27 $16.00 $598.27 $0.723 S 1,731 $1,372.85 $16.00 $1,356.85 $0.784 O 2,021 $1,903.91 $16.00 $1,887.91 $0.934 N 2,546 $2,321.35 $16.00 $2,305.35 $0.905 D 3,310 $3,504.41 $16.00 $3,488.41 $1.054 Total 22,640 $21,280.74 $192.00 $21,088.74 $0.931 Client - Meridian Township Building Area - 25,530 SF Total Gas Cost - $21,280.74 Building - Municipal Building Avg CCF Cost - $0.931 Cost/SF - $0.8335 Utility - Consumers Energy Total CCF Use - 22,640 Net Gas Cost - $21,088.74 9 Service - Gas General - GS2 EUI (Btu/SF) - 88,680 Natural Gas Consumption Analysis The following chart shows the gas consumption for the Meridian Municipal Building in CCF (100 cubic feet) per month for the analysis period from January to December of 2009. The total annual base line consumption for domestic hot water (DHW) (shown in blue) is 5,426 CCF with an annual cost of $5,054.26 The remainder of the consumption, 17,305 CCF, was for space heating (shown in red) totaling $16,119.45 for the year. The chart clearly shows the consumption for space heating at a peak in January, then decreasing each consecutive month to a low in May, no consumption during two summer months, and then beginning again in August, and increasing each consecutive month to a new peak in December. The next chart shows Heating Degree Days (a measure of how cold a month is) for the Lansing area for the same study period as gas consumption. The HDD data was adjusted to match the days included in each monthly consumption reading. The Heating Degree Day (HDD) total for 2009 was 6,952.5 which is within 0.5% the historical average of 6,982 Degree Days. The heating consumption of the building as shown in the previous chart follows a U curve corresponding fairly well with the monthly HDD in the winter of 2009, but not as closely in the fall. There is an unexpected large increase in gas consumption in August and September. 10 Building Consumption Model A mathematical thermal model of the Meridian Municipal Building was created based on construction drawings, and measurement & examination of the building envelope and the HVAC equipment. The Table below summarizes the key parameters of the model. F. Bldg Model Summary Roof Slab Edge Walls Windows Metal Door Infiltration Heating Efficiency Area-SF U-value 14,398 0.12 466 0.58 10196 0.215-0.522 1726 0.50 258 0.33 Volume Air Change 295,667-CF 1.00 AFUE 78% Based on the building consumption model, the relative heat loss for each construction component of the building was calculated and is displayed in the following chart. 11 The building ventilation/infiltration rate, at 57%, is by far the largest heat loss component. Because of its size, the roof constitutes the second largest heat loss at 19% of the total. Heat loss from the walls is third at 11%. The double glazed windows account for 9% of the heat loss. The slab edge looses 3%. The metal doors are minor at only 1% of the total heat loss each. The building model is next used to estimate gas energy consumption based on the actual Heating Degree Days experienced by the building for each month of the heating season. The model includes internal heat loads from electrical consumption which would offset demands on the heating system. This estimate is then charted to compare with the actual gas consumption as shown below. 12 The building energy model has underestimated the annual natural gas consumption for space heating for the Meridian Municipal Building by over 66% of the actual. The model significantly underestimates consumption during the first 5 months of the year. This level of underestimate continues in the last 5 months of the year, although the November difference is less and the December estimate meets the actual. In order to get the December data points to meet, the building energy model was modified to reduce the insulation levels of all walls and the roof. The efficiency of the boiler was also reduced. And the ventilation rate was raised. Before these changes, the estimate was off by over 80%. It would highly instructive to plot the gas consumption for the months of 2010 to see how well the model holds up and if this apparent excessive use continues. It is believed that the boiler which provides space heating to the building may be operating when not really needed. The fact that there is space heating consumption in August is one indication of this. However, this does not explain the excess consumption for the rest of the year, when the boiler should be in operation. The discussion which follows later in the report on water heating will likewise indicate excessive gas consumption for this use. The size of this excess prompts a recommendation for further investigation. Testing the gas meter and measuring the amount of ventilation air are two areas on which to concentrate. Opportunities for Gas Savings The gas consumption analysis has identified 2 O&M items (Operations and Maintenance) and 4 ECMs (Energy Conversion Measures) which will produce significant savings and have worthwhile return on the investment made. O&M #1 - Have Accuracy of the Gas Meter Checked The analysis of the gas consumption for space heating for the Meridian Municipal Building indicates nearly 1/3 of the consumption cannot be accounted for by the building energy model. The size of the baseline gas consumption, assumed to be only for domestic water heating, also appeared to be higher than expected. In order to confirm this suspicion, this report gathered water heating usage on other recent TEA reports for similar facilities. The following table lists these facilities, their characteristics and occupant load, and the amount of energy used to heat the domestic hot water. Facility Superior Twp Hall Employees Visitors Vehicle Wash 24 Hour Use MBTU MBTU/Emp 12 15 X 13,576 1,131 McKinley Corp. Ctr. 60 30 Lansing City Hall 325 1000 Ann Arbor Twp Hall Meridian Service Center 7 20 7 10 Meridian Municipal Bldg 52 50 Meridian Public Safety 20 40 X X 187,000 3,117 X 1,047,600 3,223 X 41,400 123,600 5,914 6,180 483,580 9,300 372,300 18,615 X 13 The facilities are listed according to their consumption levels of MBTU/Employee which is displayed in the last column of the table. The Superior Township Hall is a modest sized sprawling one story facility with 24 hour police presence with vehicular storage but no washing. It has the lowest domestic hot water consumption per employee. The next level of consumption is for two larger facilities. McKinley Corporate Center is a four story office building similar in size and function to the Meridian Municipal Building. The Lansing City Hall is a much larger 14facility with 24 hour police presence. The third level of domestic water consumption is characterized by facilities that have vehicular washing. Ann Arbor Township Hall is a smaller building with fire station attached. The Meridian Service Center is a one story building with large vehicular maintenance facilities including washing. The Meridian Municipal Building, which has no 24 hour use and no vehicle washing, is the next in the table. Its level of domestic hot water consumption appears to be 2 to 3 times higher than might be expected. The Meridian Public Safety building, which is located on the same campus, has apparent hot water consumption even beyond that by twice as much. Clearly the data in the gas consumption record for the Meridian Municipal Building indicates something is wrong. Checking the gas meter is one place to begin an investigation. O&M #2 - Maintain Weatherstripping on the Entry Doors and Garage Doors The entry doors to any building are subject to the most use and abuse of any other component. When closed, the entry doors should be able to stop air from passing into or out of the building. This is accomplished with proper weatherstripping and door sweeps. The doors to the Meridian Municipal Building may be a source of uncontrolled air infiltration to the building. Annual inspection and adjustment or replacement of weatherstripping is a low cost measure which will provide not only energy and dollar savings but also increased comfort for staff and visitors. ECM #1 - Add Roof Insulation When the Roofing Needs to be Replaced Discussion: The wood roof deck is insulated from below by stapling fiberglass insulation to the underside of the roof. This is an unusual insulation detail which likely provides less insulation value than anticipated. The calculated insulation level of the roof has been reduced from 14.35 to 8.35 to account for lack of uniformity in application of the insulation. ECM #1 recommends that the correct insulation procedure for this roof assembly would be to apply insulated nail base panels to the top of the wood roof deck. The asphalt shingles would be applied over the top of the insulated panels. This procedure can only be accomplished at the time of re-roofing, whenever the need for that occurs. An evaluation for the addition of insulation with an R-value of 15 (3” of polystyrene) was undertaken. The cost of the insulation was set at $3.00/SF which includes labor. This does not include the new roofing or associated costs. The dollar savings are based on the current price for natural gas which is $0.931/CCF. The nail base insulation should last the life of the building. The calculations for this ECM are summarized below. Total potential energy savings are: 222,300 MBtu. 14 ECM #1 Add Roof Insulation Area-SF 14,398 Add 3" New Polystyrene R-15 U-value 0.0428 CCF $0.931/CCF Saved 2,223 $ Saved/Yr $2,069.61 $3.00/SF Pay Back $ Cost $14,398.00 Years 7.0 Consumers Energy offers rebates for insulation under its custom program which must be approved before implementation. The rebate is for gas $5.00 per MCF. The total rebate would be 2,223 CCF/10 X $5 = $1111.50. The Consumers rebate would lower the payback to 6.4 Years. ECM #2 - Provide Demand Controlled Ventilation Discussion: The Meridian Municipal Building is provided with mechanical ventilation as required by code. Exterior air is brought into the return air duct of the two air handlers serving the two sides of the building. According to the control cycle commentary in the drawings for the 1992 addition to the building, ventilation air is only provided during occupied hours. It is not known exactly how much fresh air is being provided, but the building energy model suggests that it is around 5,000 cfm. The mechanical code requires 15 cfm per person. At maximum occupancy. This would amount to 15 cfm/person X 60 people = 900 cfm. This level of ventilation will more than satisfy the current best practices of ASHRAE 62.1 for ventilation for acceptable indoor air quality. Clearly there is room to reduce the ventilation rate for the building. ECM #3 recommends the installation of demand controlled ventilation. Fortunately all of the mechanical equipment required for this ECM is already in place. All that is required is the installation of carbon dioxide (CO2) sensors and including this input to the programming of the EMS for the fresh air intake dampers. This would be a low cost energy conservation measure which could yield large energy savings. ECM #2 assumes a reduction of the ventilation rate by a modest 35%. Costs are established as follows: installation of sensors at $500 each, $500 to reprogram EMS, and $500 professional engineering fee. Total potential energy savings are: ECM #4 Demand Based Ventilation Heating Savings 372,500 MBtu Gas 49,474 MBtu Electric Existing Ventilation cfm 5,000 Reduced Grand Totals $0.931/CCF Pay Back Reduction cfm Saved $ Saved/Yr $ Cost Years 35.0% 1,750 3,725 $3,467.98 $2,000 0.6 kWh Reduced Air-Conditioning Savings CCF 10.9% Saved 14,500 $0.057/kWh $826.50 $4,294.48 $2,000 0.5 Consumers Energy offers rebates for demand controlled ventilation under its prescriptive incentive program. The rebate for gas is $0.05 per SF of area controlled. The total rebate would 15 be 25,530 X $0.05 = $1,276.50. The Consumers rebate would lower the payback to 0.17 Years. Be aware that Consumers does not rebate for items with a payback below 1 year. ECM #3 - Install Energy Recovery Ventilators Discussion: There is opportunity to produce additional HVAC energy savings through the installation of Energy Recovery Ventilators (ERVs) for each of the two HVAC systems at the Meridian Municipal Building. By installing the ERVs, up to 65% of the heating energy and 50% of the cooling energy can be recovered from an exhaust air stream and put back into the building via the new fresh air stream. The humidity in the air can also be transferred between air streams. An ERV has few moving parts and can be very cost effective. Modern mechanical codes allow an ERV to be installed in place of required economizers. Each of the two air handlers would require its own ERV unit which could be installed within its respective mechanical room. The control for these units would be networked with the the CO2 sensors mentioned in ECM #2 and programmed into the EMS. This option modifies the existing return and intake air ductwork to accommodate connection to the ERV. All air intake would first pass through the ERV before being delivered to the return air supply. The ERV would exhaust the relief air stream which eliminates problems with positive or negative air pressure in the building. The savings potential for the energy recovery ventilators summarized below is in addition to the savings provided by ECM #2 and is based on the reduced ventilation rates set forth in ECM #2. Installed costs are based on the following: $4,000 for each ERV, $2,000 for each air handler for labor and material for ductwork modifications, and $1,000 each system for engineering and programming of EMS. Specification sheets on ERVs from one manufacturer are included in the Appendix. Total potential energy savings are: 296,800 MBtu (Gas) and 30,322 MBtu (Elec) ECM #3 Install ERVs Heating Savings Cooling Savings Ventilation cfm Energy CCF $0.971/CCF 2,145 Reclaimed Saved $ Saved/Yr 65% 2,968 $2,881.93 Energy kWh $0.057/kWh Reclaimed Saved $ Saved/Yr 50% 8,887 $506.56 $ Saved/Yr Totals $3,388.49 Pay Back Installed Cost $14,000.00 Years 4.1 Consumers offers rebates for the gas and electricity savings of this ECM through a custom application process which must be pre-approved before implementation. The rebate amount is $5 per MCF for gas and $0.08 per kWh for electricity. The total rebate for ECM #3 would be 2,968 CCF/10 = 449.7 MCF X $5/MCF = $1,484 plus 8,887 kWh X $0.08/kWh = $710.96 for a total of $2,194.96. The Consumers rebate would lower the payback to 3.5 Years. ECM #4 - Install New Boiler System 16 Discussion: Boiler technology has advanced greatly over the last decade. The existing boiler serving the Meridian Municipal Building is unusual is unusual in that the gas burner unit is attached to a vertical water storage tank. The system relies upon combustion air brought into the mechanical room via an atmospheric damper. It does not have a flue damper. The efficiency of this system is pegged at 78% and its capacity was identified as 1.35 million Btus per hour. The maximum heat loss of the building was calculated to be 650,000 Btus. This boiler system could be replaced with two much smaller, full modulating, condensing boilers and sequenced for high efficiency operation. New modulating condensing boilers can reach efficiencies of 94-96%. Replacement of the existing boiler is a relatively straight forward measure. Costs for this measure was set at $9,000 per boiler. One complicating factor may be how to vent the new boiler. The calculations below show a reasonable pay back for this ECM. Total potential energy savings are: 332,000 MBtu. Size ECM #4 Gas Savings 2 New Boilers Weil-McClain Ultra New CCF $0.971/CCF MBtu AFUE Saved $ Saved $ Cost Pay Back 310 95% 3320 $3,223.72 $18,000.00 5.6 Consumers Energy offers rebates for new boilers under its prescriptive incentive program. The rebate for gas is $3 per 1000 Btu of capacity. The total rebate would be 620 X $3 = $1,860. The Consumers rebate would lower the payback to 5.0 Years. The above analysis assumes that no other energy efficiency measures are taken in the building. If ECMs #2 and #3 were accomplished, the savings from a new boiler would be less because the heating needs of the facility would be reduced. Therefore, the payback would become longer. However, ECMs #2 and #3 would reduce the heat loss of the building substantially and, therefore, smaller boilers may be used which would reduce implementation costs and improve the payback for new boilers. There are numerous possible combinations of ECMs and O&Ms. Each combination may have different interactions between energy saving processes. Further exploration of interactions between study recommendations may be required depending on the package of energy efficiency measures selected to pursue. Electricity Billing Information The electricity billing information for the Meridian Municipal Building for 12 months was received and input to a spreadsheet for analysis. This entire record is printed out for reference in the Appendix to this report. This information is also available in electronic format upon request. An abbreviated set of data for the 12 month period of electricity consumption, along with summary information, is provided below. This period encompasses the 2009 calendar year. I. Electricity Cost/Consumption Chart M/Yr kWh KW $Total $Access $EE $RE KW $Total kWh $Total $/kWh $/KW J 24,480 77 $2,376.03 $25.00 $0.00 $0.00 $933.24 $1417.79 $0.058 $12.120 F 29,600 77 $2,596.81 $25.00 $0.00 $0.00 $933.24 $1638.57 $0.055 $12.120 M 29,760 80 $2,591.73 $25.00 $0.00 $0.00 $969.60 $1597.13 $0.054 $12.120 17 A 31,280 80 $2,626.75 $25.00 $0.00 $0.00 $969.60 $1632.15 $0.052 $12.120 M 40,080 105 $3,990.06 $25.00 $32.27 $0.00 $1,470.00 $2462.79 $0.061 $14.000 J 39,600 115 $4,110.87 $25.00 $32.27 $0.00 $1,610.00 $2443.60 $0.062 $14.000 J 37,120 108 $3,868.00 $25.00 $32.27 $0.00 $1,512.00 $2298.73 $0.062 $14.000 A 42,800 103 $4,147.83 $25.00 $32.27 $16.58 $1,442.00 $2631.98 $0.061 $14.000 S 35,040 94 $3,002.69 $25.00 $32.27 $16.58 $1,139.28 $1789.56 $0.051 $12.120 O 30,000 88 $2,638.67 $25.00 $32.27 $16.58 $1,066.56 $1498.26 $0.050 $12.120 N 29,040 77 $2,489.00 $25.00 $32.27 $16.58 $938.63 $1476.52 $0.051 $12.190 D 28,240 77 $2,628.65 $25.00 $32.27 $16.58 $938.63 $1616.17 $0.057 $12.190 Totals 397,040 $37,067.09 $300.00 $258.16 $82.90 $13,922.78 $22,503.25 $0.057 $12.758 Client - Meridian Township Building Area -25,530 SF Total Elec Cost - $37,067.09 Building - Municipal Building Avg kWh Cost - $0.056 Cost/SF - $1.45 Utility - Consumers Energy Total kWh - 397,040 Net kWh Cost - $22,503.25 Service - Gen Sec Demand EUI (Btu/SF) - 53,063 Demand Cost - $13,922.78 The Meridian Municipal Building is on a general secondary demand rate. The charges for this rate are complicated. Not only is the Township charged for each kWh that is consumed (though at a lower rate than non-demand customers) but also a capacity charge based on the highest peak electrical demand in KW each month. The consumption data is displayed in a chart on the following page. The third column above shows the monthly KW demand which is highest in the summer months and lowest in the winter months. Besides kWh and KW, the utility also monitors the power factor, a measure of how efficiently electricity is being used. If this should drop below 80%, the utility may charge extra for this. The power factor reached a low of 88% in July and a high of 95% in December.Electricity Consumption Analysis The following chart shows the electrical consumption for the Meridian Municipal Building in kWh (kiloWatt hours) per day for each month of the analysis period from January to December of 2009. This is good way to view electrical consumption because it removes the variation of days in each monthly billing period. The chart shows a low in December which is taken as the baseline consumption (shown in yellow). Consumption increases above the baseline (shown in blue) occur in all other months. The consumption from May through October looks like air-conditioning use. The increased consumption above the baseline in the other months may be due to longer operational hours for lighting, the use of personal electric space heaters in the building, or other changes in how the Municipal Building is operated. 18 Displayed next is a chart showing the monthly Cooling Degree Days, a measure of how hot a particular month was, for the Lansing area for the same days each month to match the electrical consumption data. Comparing the two charts, it appears that what is happening on the inside of the building is more important than exterior summer temperatures in determining the amount of cooling required for the building. The next chart displays the estimated base electrical consumption broken down into several estimated components including: lighting, HVAC and exhaust fans & pumps which run year round, office and electronic equipment, kitchen appliances, the server room, the cable studio, and the elevator. This chart represents an estimate of expected consumption based on an inventory of all electrical devices in the building and their likely use characteristics. 19 This estimated base consumption (shown in brown) is then superimposed over the actual metered electrical use in the following chart. There is a significant portion of the baseline consumption (shown in grey) which is unassigned because the exact source of consumption is unknown. The consumption used for cooling in the summer months is clearly visible (shown in blue). The extra electrical consumption in the winter months (shown in orange) is assumed to be mostly related to heating the building including: additional fan run time, operation of some unit heaters and fan coils, and personal electric space heaters. 20 The following pie chart displays the annual totals for each component of electrical consumption as a percent of the total. Cooling is the largest use category at just over 20% of the total. The second highest category, at just under 20%, is for lighting. Exterior lighting constitutes almost 20% of that amount. The third largest use is for the operation of cable studio at 18% of the total. Next at 11% is the power used to operate the HVAC system. The server room and office equipment in the building each consume 8% of the total. 6% is in the unassigned category. The extra winter space heating load also amounts to 6%. The kitchen equipment and elevator, each at about 1%, are minor electrical uses. 21 Finally, the results of the electrical consumption analysis is summarized in the Energy Use Profile Table below. O. Electrical Energy Use Profile Component Annual kWh Annual $ kWh Annual $ KW % Energy Use Lighting 78,744 $4,463.19 $2,761.26 19.8% Fans/Pumps 45,325 $2,569.03 $1,589.39 11.4% Office 33,521 $1,899.96 $1,175.46 8.4% Kitchen 5,528 $313.33 $193.85 1.4% Server Rm 31,770 $1,800.72 $1,114.06 8.0% Cable Studio 70,600 $4,001.61 $2,475.69 17.8% Elevator 4,448 $252.10 $155.97 1.1% Space Heat 22,668 $1,284.81 $794.87 5.7% Cooling 81,171 $4,600.77 $2,846.37 20.4% Unassigned 23,266 $1,318.73 $815.86 5.9% Totals 397,040 $22,504.25 $13,922.78 100% Opportunities for Electricity Savings The elecrical consumption analysis has identified 8 O&M items (Operations and Maintenance) and 6 ECMs (Energy Conversion Measures) which will produce significant savings and have worthwhile return on the investment made. O&M #3: Post Handout for Energy Efficiency in Small Kitchen Appliances Provided in Appendix The recommendations provided in the handout can reduce energy consumption for small kitchen appliances by 10% or more. Education for building occupants is one of the most important parts of any energy efficiency or conservation project. O&M #4: Review Handout for Energy Efficiency in Office Equipment Provided in Appendix The recommendations provided in the handout can reduce energy consumption for office equipment by 10% or more. Education for building occupants is one of the most important parts of any energy efficiency or conservation project. O&M #5: Purchase Flat Screen Energy Star Rated Monitors in the Future The Meridian Municipal Building contains a large number of computers. Most of the computer monitors are older CRT models. Newer computers with LCD monitors are more efficient. Look for Energy Star rated equipment when making future purchases. 22 O&M #6: Institute Policy to Activate Sleep Mode in Operating Software The operating system on the computers at the Meridian Municipal Building are capable of using much less energy when placed into a sleep or hibernation mode. If it is not yet universal policy to enable this energy saving feature on all computers, it is highly recommended that this be explained to the staff and fully implemented. The United States EPA provides free software for networked computers for activating power saving options network wide. Normally, computers should also be turned off after working hours; see O&M #7. O&M #7: Turn Off Electronic Equipment that is Not in Use Some electronic equipment, such as televisions, computers, printers, and copiers use significant amounts of power. These should be turned off when not actively in use. Notices to encourage this behavior should also be posted. Even when turned off, some equipment will continue to draw power so as to enable their instant on capabilities. This so called ‘phantom’ energy loss can be remedied by using power strips which sever the connection to the electrical system. There are also smart power strips that turn off only pre-selected equipment. See fact sheet in the Appendix. Consumers Power offers a $10 incentive for smart power strips. O&M #8: Install Controls on Vending Machines There is one chilled beverage machine in the Meridian Municipal Building. This uses a lot of energy on lighting to advertise the product and on keeping the product chilled. If your vending contract is about to expire soon, you can request that an Energy Star beverage machine, which will use 1/2 to 2/3 less energy to operate, be installed. You can also purchase simple equipment to convert the existing machine to Energy Star efficiency. Product literature for this option is included in the Appendix. Consumers Power offers a $50 incentive for beverage machine controls. O&M #9: Replace Motors on Fans & Pumps with Premium Efficiency Models If a motor should need to be replaced in the future, there is a premium efficiency model available from most motor manufacturers. Premium motors use 1 to 10% less energy and should provide a good pay back on the extra replacement cost. A fact sheet on buying premium efficiency motors is included in the Appendix. As an example, there are 5 HP motor which operate the fans in the air handling units. An analysis for replacing one of these motor is shown below. The analysis is for the cost differential of replacement between a standard energy efficient motor and one with a premium efficiency rating. The payback is a bit longer than normally encountered because of the demand rate issue. 23 Replace Existing Motor with Premiu m Efficienc y Model Qty 1 HP 5.0 OldEff NewEff 85.5% 89.5% kWsaved 0.146 Hrs 5840 kWhsaved 854.0 $/kWh $ Saved 0.056 $52.20 $ Cost Payback Dif $215.00 4.1 Consumers Energy offers an incentive for premium efficiency motors at a rate of $8 per HP. The total Consumers rebate would be 5 HP X $8/HP = $40. This would reduce the payback for O&M #9 to 3.3 years. O&M #10: Use Radiant Foot Warmers to Replace Space Heaters There may be electric space heaters in use in the building during the winter. A typical space heater has a top rating of 1500 watts. At current electricity rates one of these heaters costs about $0.16 per hour to operate. Radiant foot warmers may be able to serve the same function with only 150 watts of power. Potential power savings could reach 1.35 kWh for each hour of use. Radiant heat can be delivered directly to an occupant’s feet. This radiant effect is known to increase occupant thermal comfort at lower air temperatures. The appendix includes information from a specific manufacturer on a number of radiant foot warmer products. Energy savings for using one foot warmer in regular use is estimated at 1.35 kWh and total $ savings are: (3 months/yr x 4 weeks/mo x 5 d/wk x 8 hr/d x 1.35 kWh/hr) X $0.057/kWh = $36.94 per heating season plus $17.22 in demand savings for a total of $54.16. At a retail price of $75 for the foot warmer, a simple payback in a little over a year is achieved. ECM #5: Install Occupancy Sensors for Lighting Control Discussion: The switches operating lighting fixtures in the Meridian Municipal Building may be left on when nobody is using the space being illuminated. This unwanted use of electricity can be eliminated through the installation of occupancy sensors. The sensors would automatically activate the lighting whenever a person enters a room and turn them off when the space is unoccupied. The chart below shows a sample of room types to consider. A time savings of 3 hours per day of building operation is assumed. The dollar savings for occupancy sensors in facilities on a demand rate only take into consideration the kWh savings. No credit is taken for demand savings because these rooms are just as likely to be occupied at peak times. Therefore, the dollar savings are lower than normal. Restrooms and Private Offices can easily be served by a switch mounted sensor. Even so, the payback is long because the wattage being controlled is small. Larger rooms like the Plan Room and the Mail Room will cost a little more to accomplish, but since there are more fixtures being controlled, the payback is better. See a specification sheet provided in the Appendix. Total potential energy savings are: ECM #5 Occupancy Sensors Watts Installed 4,862 MBtu Hr/Day Saved Annual kWh Saved 24 Price $/kWh Annual $ Savings Sensor $ Cost Payback Years Men RR/1st Flr (3 Fixt) Women RR/1st Flr (4 Fixt) Men RR/2nd Flr (3 Fixt) Women RR/2nd Flr (4 Fixt) Private Office (2 Fixt) Plan Room (6 Fixt) Mail Room (11 Fixt) Totals 153 204 153 204 102 450 561 3 3 3 3 3 3 3 119.3 159.1 119.3 159.1 79.6 351.0 437.6 1425.1 0.057 $6.80 $60.00 0.057 $9.07 $85.00 0.057 $6.80 $60.00 0.057 $9.07 $85.00 0.057 $4.53 $60.00 0.057 $20.01 $150.00 0.057 $24.94 $150.00 0.057 $81.23 $650.00 8.0 8.8 9.4 8.8 9.4 13.2 7.5 6.0 Consumers Energy offers an incentive for occupancy sensors at a rate of $0.09 per watt controlled. The total Consumers rebate for the above mix would be 1,425.1 W X $0.09/W = $128.26. This would reduce the payback for ECM #5 to 6.4 years. ECM #6: Install Variable Frequency Drives (VFD) on Air Handlers Discussion: The building is served by two air handlers which currently run at constant speed. The installation of a Variable Frequency Drive (VFD) would change the speed of the fan to allow air flow to vary with the demand for heating or cooling. Earlier ECMs for gas savings recommend the use of demand controlled ventilation and energy recovery ventilators. If these are implemented, the temperature differences between supply and return air would be reduced. Therefore, the volume of air flow could be reduced to provide the same comfort levels. The power consumed by an induction motor varies with the cube of the speed. This reduction in power use by the air-hander’s fan motor will produce significant energy savings ranging from 15% to 75%. The actual energy savings for VFDs varies widely depending on the configuration and operation of each HVAC system. This analysis assumes a power savings of 30% which produces a reasonable payback. Quotes for installation of a VFD should include solid engineering design appropriate to the selected HVAC system and estimated energy savings. Total potential energy savings are: 38,324 MBtu. ECM #6 Install VFD on Air Handlers AHU #1 & #2 Existing Fan Power kWh Annual Installed Payback Fan HP kWh/Yr Reduction Savings $ Savings $ Costs Years 10 37,440 30.0% 11,232 $735.92 $8,000.00 10.9 Consumers offers rebates for VFD installation through its prescriptive application process. Care should be taken during the design of the VFD system that all requirements for this rebate are met. The rebate amount is $60 for each HP (Horsepower) being controlled. The total rebate would be 10 HP X $60/HP = $600. The Consumers rebate would lower the payback period to 10 years. Discussion on Demand Power Reduction As noted in the discussion on electrical billing, nearly half of the cost of electricity for the Meridian Municipal Building is due to KW demand charges. The only way to reduce this cost is to lower the peak demand. Some of the ECMs in this report will reduce peak demand somewhat 25 and other ECMs will not effect demand. An effort should be made to determine what time of day and what day of the week the peak demand is occurring. Then equipment which may not need to be on during this time can be operated in a different time period. This is called load shifting. Some improvements in lowering demand through load shifting can be accomplished through the HVAC energy management system. For non-HVAC equipment, changes in staff activities would be necessary. A simple example is the use of equipment like battery chargers. They may only be used on rare occasion, but if that should occur at peak consumption, its power draw will trigger a larger demand charge. Perhaps operating battery chargers at night, which may already be the case, would be the best choice.Lighting ECMs Discussion The complete inventory of all lighting fixtures for the Meridian Municipal Building is provided in the Appendix. A sampling of lines from the inventory presented below indicates what information was collected. The inventory is color coded for each lighting ECM type. P. LIGH TING INVE NTO RY Merid ian Muni cipal Buildi ng ID # RM NAME ECM# ECM#1 7 ECM#8 ECM#9 0 HRS FIXT FIXT /DAY ID TYPE 1st Floor 101 Town Hall Mtg 24 101 Town Hall Mtg 2 101 Town Hall Mtg 24 102 Trustee 2 103 Coat 104 Storage C C X C RT24 RT24 Exit RT24 No Access No Access LAMP TYPE FIXT QTY 4F4ACTA 1 4F4ACTA 24 LED 1 4F4ACTA 3 WATT S WATTS NEW NEW NEW WATT /FIXT /DAY LAMPS W/FIXT W/DAY SAVE 98 98 3 98 2352 4704 72 588 0 0 F28T8 78 F28T8 78 F28T8 78 1872 3744 72 468 0 0 480 960 0 120 0 0 Each room has an identification number (keyed to the floor plans also in the appendix), a location name, daily hours of lighting use, a fixture ID, a fixture type, lamp type, quantity of fixtures, fixture wattage, and total watts per day. New fixture lamp type, new fixture watts, new watts per day, and watts saved are also provided. This inventory can be used as an aid for purchasing new equipment and tracking the effected fixtures during retrofit implementation. The inventory is available in spreadsheet format, if requested. The inventory reveals that all of the linear fluorescent fixtures have been retrofitted with T8 low power ballasts and 32 watt lamps. The lamps in these fixtures should be at the end of useful life. A group re-lamping project using energy saver T8-28 watt lamps is recommended. The exit signs have all been converted to LED technology. All but 2 incandescent fixtures have been re-lamped with CFLs. CFL equivalents are specified in the report. 26 The exterior lighting uses high pressure sodium technology. Exterior lighting accounts for almost 20% of the total lighting consumption. These HID fixtures can be relamped for replaced with more efficient fluorescent induction technology. This technology offers better light quality, silent operation, instant on, improved lamp life, and dual level lighting capabilities. The night time lighting survey indicated that only 4 of the 6 lamps in the oldest light poles were non-functional. These fixtures are on a separate account being billed on a per fixture basis regardless of the lamp technology being used. It is believed that mercury vapor is the technology and that the lamps are very old and the ballasts are failing. contact the utility to have these replaced so that they are functional for the Township. The 4 Lighting ECMs which follow address the different fixture types in the Meridian Service Center.ECM #7 – Re-lamp Existing 4 Foot Fluorescent Fixtures with 28 Watt T8 Lamps Discussion: There are 356 fluorescent fixtures in the Meridian Municipal Building which currently use modern T8 technology. The current 32 watt lamps have been installed long enough that they should be close to the end of their lifetime. ECM #7 recommends that, if the facility has not undertaken a complete re-lamping of fluorescent tubes and it has replaced lamps only upon failure, conducting a total re-lamp of these 4 foot fluorescent fixtures with 28 watt T8 lamps could be cost effective. Other benefits of this procedure would include increased light levels and increased lamp life. Each lamp replaced would save about 4.5 watts of power consumption. If the facility wanted to decrease the light levels slightly, 25 watt lamps are also available. ECM #7 is coded light green in the lighting inventory. The specification below is accompanied with a fact sheet in the appendix. Material Specification: Fluorescent Lamps - 4 Ft, T8, Triphosphor, 4100 K, 85 CRI; TCP - F28T8/841 This ECM analysis assumes labor would be paid to install the new lamps. Maintenance savings amounting to $1.50 per lamp (prorated over 10 years) are included in the calculations. The rated lifetime of the new T8 lamps can be up to 36,000 hours for the 24 hour fixtures. Removed lamps should be recycled as hazardous waste. Costs for recycling are included in the calculations. Estimated Annual Energy Savings - 7,467.5 kWh 25,480.2 MBtu Implementation Costs Implementation Savings No. of Lamps - 906 Cost per Lamp - $3.00 Labor per Lamp - $3.00 Total Cost - $5,436.00 $value KWH Savings - $425.65 $value KW Demand Savings - $468.20 $value Maintenance Savings - $135.90 Total Annual $ Savings - $1,028.75 27 Simple Payback Period - 5.3 Years Payback Period with Rebate of $0.75 per lamp from Consumers – 4.6 Years ECM #8 - Re-lamp Existing Flood lamps with CFL Equivalent Discussion: One of the Storage Rooms has a fixture that uses 75 watt flood lamps. ECM #8 recommends re-lamping this fixture with new compact fluorescent flood lamps. This CFL will produce light equal or better in color, quality, and quantity to that of the original incandescent and last about 4 times longer. The change in watts consumed from incandescent to CFL would be 75 to 16. ECM #8 is coded purple in the lighting inventory. The specification below is accompanied with a fact sheet in the appendix. Material Specification: Spring Lamp Compact Fluorescent TCP 2R3016. This ECM analysis assumes labor would be paid to install the new lamps. Maintenance savings are limited to the cost of one incandescent lamp replacement at $1.50 each. The lifetime of the new CFL is 8,000 hours. Broken or failed CFLs should be recycled. Estimated Energy Savings - 23.6kWh/year 80.5 MBtu Implementation Costs No. of Lamps – 1 Cost per lamp - $8.86 Labor per Lamp - $5 Total Cost - $13.86 Implementation Savings $value KWH Savings - $1.35 $value KW Demand Savings - $6.78 $value Maintenance Savings - $1.50 Total Annual $ Savings - $9.62 Simple Payback Period – 1.4 Years Payback Period with Rebate of $8.00 per fixture from DTE – 0.6 Years ECM #9 - Re-lamp Existing High Pressure Exterior Fixture with Fluorescent Induction Equivalent Discussion: There are 22 exterior wall pack lighting fixtures in various locations at the Meridian Municipal Building, such as over pedestrian entry doors, in roof soffits, flag pole flood, etc, which use 50 watt high pressure sodium technology. ECM #9 recommends re-lamping these fixtures with a new screw-in fluorescent induction lamp. The current fixture uses 66 watts. The new lamp would use 40 watts while providing light equal in lumens to current levels, and, since its color temperature is 5000 K, the visual quality of the light will be much improved. These wall packs are good candidates for relamping because they are on 10 hours a day on average. ECM #9 is coded beige in the lighting inventory. The specification below is accompanied with a fact sheet in the appendix. 28 Material Specification: Venus Induction Series - 40 Watt This ECM analysis assumes labor, to disconnect the HID ballast, would be paid to install the new lamps. Maintenance savings are limited to the replacement cost of the HPS lamps pro-rated over 7 years. The lifetime of the new lamp is 60,000 hours. Estimated Energy Savings- 2,087.8 kWh/year 7,123.6 MBtu Implementation Costs Implementation Savings No. of Lamps -22 Cost per Lamp - $75 Labor per Fixture - $25 Total Cost - $2,200.00 $value KWH Savings - $119.00 $value KW Demand Savings - $65.69 $value Maintenance Savings - $37.71 Total Annual $ Savings - $222.41 Simple Pay back Period – 9.9 Years Consumers may offer a rebate for this ECM through its custom application process which must be pre-approved before implementation. The total incentive would be 2087.8 kWh X $0.08/kWh = $167.02. This would reduce the payback to 9.1 years. Note: A new fixture using this technology, also available for a rebate from Consumers at $45 per fixture could be installed instead, though at a longer payback. There is also a 23 W replacement producing greater savings if reduced light output is desired. ECM #10 - Replace Existing HPS Exterior Fixtures with Fluorescent Induction Equivalent Discussion: There are 17 exterior HPS lighting fixtures in use at the Meridian Municipal Building. They are on poles along the drive-ways. The current fixtures use 100 watt HPS lamps consuming 130 watts per hour of operation. ECM #10 recommends replacing these fixtures with new fixtures using fluorescent induction technology. The new fixtures would use 75 watts while providing light equal in lumens to current levels, and, since the color temperature is 5000 K, the visual quality of the light will be much improved. These light fixtures are good candidates for replacement because they are on 10 hours a day on average. ECM #10 is coded blue in the lighting inventory. The specification below is accompanied with a fact sheet in the appendix. Material Specification: #EGW-EC-100W (Wall Pack) by Everlast Induction Lighting in Jackson, Michigan This ECM analysis assumes labor to install the new fixtures. Maintenance savings are limited to the replacement cost of the HPS lamps pro-rated over 7 years. The lifetime of the new lamps is 100,000 hours. 29 Estimated Energy Savings- 3,412.8 kWh/year 11,644.8 MBtu Implementation Costs Implementation Savings No. of Fixtures - 17 Cost per Fixture - $450 Labor per Fixture - $50 Total Cost - $8,500.00 $value KWH Savings - $194.53 $value KW Demand Savings - $117.14 $value Maintenance Savings - $29.14 Total Annual $ Savings - $340.81 Simple Pay back Period – 24.9 Years Payback Period with Rebate of $45 per fixture from Consumers – 22.7 Years 30 Lighting ECMs Summary There are 537 lighting fixtures documented for the Meridian Municipal Building in total. 401 fixtures, about 75%, are recommended for an energy efficient retrofit or replacement. Following implementation of the 4 Lighting ECMs previously documented, it is estimated that the consumption of energy for lighting would drop by 22%. 31 The costs and savings information for the lighting efficiency recommendations are summarized in the chart below. The total lighting project would save 12,991.70 kWh annually. The total dollar project cost estimate is $16,149.86. The project would save $1,602.58 annually with a simple payback of 10.1 years. Incentives offered by Consumers Energy would reduce the economic payback to about 9.1 years. S. Lighting Retrofit Summary Table kWh SAVED $ SAVED $ COST PAYBACK Rebate ROI ECM #7 7,467.5 $1,029.75 $5,436.00 5.3 4.6 ECM #8 23.6 $9.62 $13.86 1.4 0.6 ECM #9 2,087.8 $222.41 $2,200.00 9.9 9.1 ECM #10 3,412.8 $340.81 $8,500.00 24.9 22.7 TOTALS 12,991.7 $1,602.58 $16,149.86 10.1 9.1 Whenever replacing lamps, it is a good time to clean the fixture and lens surfaces to get more light out of each fixture. Yellowing, cracked, or missing lenses should be replaced. When replacing linear fluorescent lamps and ballasts, some fixtures may be in very bad shape. Some common problems are: the pin holders are broken, lamps are difficult to install, ballast covers won’t reinstall, and the lens doors don’t close. In such cases it may save time and money to replace the entire fixture. Be sure to special order because T8 technology is not yet standard in new fixtures. Lastly, removed fluorescent lamps and ballasts should be properly recycled. Recycling costs have been added to the ECM costs for all linear fluorescent options. A fact sheet on recycling of CFLs and linear fluorescent lamps is included in the Appendix. Appendix Report Certification Form Gas & Electric Billing Histories Floor Plans Weatherstripping Information Energy Recovery Ventilation Specifications Condensing Boiler Specifications 32 Handout - Energy Efficiency in Small Kitchen Appliances Handout - Energy Efficiency in Office Equipment Intelligent Surge Protector Information Vending Machine Controls Premium Efficiency Motors Radiant Foot Warmers Occupancy Sensor Information Lighting Inventory Lighting Specification Sheets Lamp Recycling Information Glossary of Energy Terms 33