Milestone Review Panel Report: Progress of the Government Commitments to the Public Advocate Reports Fourth Quarter Report July 2013 Version 250713 1 Contents Version 250713 .......................................................................................................................... 1 Contents ..................................................................................................................................... 2 Milestone Review Panel – Summary of Findings ....................................................................... 4 Milestone Panel’s comments on progress of implementation of projects related to the Government’s response to recommendations .......................................................................... 5 Recommendation 1 ............................................................................................................................. 5 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................... 6 Milestone Panel’s Response Recommendation 1 ........................................................................... 9 Recommendation 2 ........................................................................................................................... 10 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 13 Milestone Panel’s Response Recommendation 2......................................................................... 15 Recommendation 3 ........................................................................................................................... 16 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 18 Milestone Panel’s Response Recommendation 3......................................................................... 18 Recommendation 4 ........................................................................................................................... 21 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 23 Milestone Panel’s Response Recommendation 4......................................................................... 26 Recommendation 5 ........................................................................................................................... 27 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 29 Milestone Panel’s Response Recommendation 5......................................................................... 33 Recommendation 6 ........................................................................................................................... 34 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 36 2 Milestone Panel’s Response Recommendation 6......................................................................... 37 Recommendation 7 ........................................................................................................................... 38 Progress against the Government’s commitments and symbols used to indicate progress achieved. .................................................................................................................................. 40 Milestone Panel’s Response Recommendation 7......................................................................... 41 ATTACHMENT 1: Milestone Review Panel Background .......................................................... 42 ATTACHMENT 2: Milestone Review Panel Terms of Reference .............................................. 44 ATTACHMENT 3: ACT Government Responses to the Public Advocate Interim Report ......... 47 ATTACHMENT 4: Progressing the commitments made in the Government response to the recommendations of the Public Advocate’s Review ............................................................... 50 ATTACHMENT 5: Progress since the March Quarter ............................................................... 53 Related Processes ............................................................................................................................. 56 The Future of PA2 Program .............................................................................................................. 57 3 Milestone Review Panel – Summary of Findings As this is the final report of the Milestone Review Panel, we wish to thank the Directorate for its support. It is pleasing to report that ten of nineteen projects are now complete and that a further six are anticipated to be complete by December 2013, and because of their complexity, the remaining three will continue into 2014-15. The Panel was particularly impressed by the discipline installed by the project management process which has been embraced throughout the Directorate. The Panel is confident that governance arrangements are in place to deliver the IMS which will provide a platform for addressing many of the issues raised by the Public Advocate’s report, such as accurate recording of information, timely responses and support for frontline staff. This will be critical in facilitating cultural change and improved service delivery, particularly in areas such as OOHC, early intervention and kinship assessments. The recruitment, retention and training of quality staff are essential for the success of the new service delivery model. These will be ongoing issues for the Directorate. In relation to recruitment and retention, the Panel notes that there are a number of new strategies in place. In relation to training, a strategy has been developed and new methods for delivery are being explored. In time, training modules will be incorporated into the IMS system. Further, the IMS system gives the opportunity for the child to be involved in the creation of their own comprehensive history and personal record. There is the potential to use this information to achieve improved outcomes in terms of their interactions with the wider Directorate and key stakeholders outside of the Directorate, taking into account privacy issues. The committee was particularly impressed with the demonstration it received on IMS for Bimberi. This initiative, when applied to other areas of OCYFS, will be the single biggest factor in changing both the culture of service delivery and the ease with which CSD staff carry out their respective roles. This initiative involves a review of policies and the development of technology which provides for consistent application of these policies in an interactive and user-friendly manner. Training modules can be attached to each function and staff have the ability to comment on the usefulness of the technology, together with suggestions for improvement in real time. 4 Milestone Panel’s comments on progress of implementation of projects related to the Government’s response to recommendations Recommendation 1 Develop a Strategic Framework for implementation over the next three years. This should encapsulate evidence based practice, supervision and mentoring mechanisms, case management, planning and review, risk management and assessment processes and forensic investigation, that will result in environment of good practice. ACT GOVERNMENT RESPONSE: AGREED The Office for Children, Youth and Family Support has launched a quality improvement program focussed on refreshing the service culture to ensure better outcomes for children, young people and their families. A strategic framework has been drafted and a staff consultation process is underway. The framework for Care and Protection Services outlines its vision, mission and core values and identifies five key areas of focus including: o Accountable and responsible decision making o Effective engagement with the service sector o Developing workforce capacity and capability o High quality services for children, young people and their families and o Compliance and quality. A key action under the strategy is to develop the Integrated Management System as a single information system which will give all staff access to the key documents, processes and tools in a user friendly interface. The development of the Integrated Management System includes reviewing all existing policies and procedures and developing process maps and flow charts to provide guidance to staff on responsibilities and actions. In reviewing local Care and Protection policies and procedures, responsible officers will draw upon the policies of other Australian jurisdictions. The Integrated Management System will bring into one system the three core operational frameworks, namely: o The Practice Framework o The Case Management Framework and o The Risk Assessment Framework. Each of these frameworks has been developed in line with evidence based practices. The Integrated Management System will, in effect, deliver a caseworkers toolkit which provides clear directions for practice and a set of practice aids and tools. 5 Recommendation 1: Projects to progress the Government Response: Integrated Management System (IMS) Quality Improvement Tools 5 Year Out of Home Care Strategic Plan Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 1 COMMENT PROGRESS PRACTICE IMPROVEMENT Implementation of an Integrated Management System which includes the development of: -standardised policies and procedures -deployment process flowcharts for all procedures -accountability package -online Care and Protection Services “Knowledge Portal” -an Integrated Management System for Care and Protection Services -implementation Review Report While substantial activity is occurring in the IMS project the size and scope of the project means technical project progression has been relatively slow. Activities such as the change management and training subcommittees have been ongoing, as have wider consultative mechanisms such as town hall presentations. In June 2013 the IMS has commenced a policy steering committee to improve collaboration and has started road testing a technology solution for the portal. During 6 the quarter to May team building has been a key resourcing focus. At the end of May the IMS team has added 3 new personnel to drive IMS work. A further two positions are going through recruitment action. For 2013-14 the IMS will be presenting an updated project plan to the Strategic Projects BOM to demonstrate how the deliverables will be achieved for the July meeting. Quality Improvement Tools -case conference process used routinely for 13-16 year olds The case conferencing project is complete and the model is implemented. At the end of April (the last formal monthly report) the project was continuing to prove effective in achieving alternative outcomes for young people coming into contact with the care and protection system. Effort is now being applied to embedding the process into policies and procedures. A review of the project outcomes was commenced in May 2013. -case audit tool developed The case audit tool project is complete. The case audit tool has been developed and tested. Some aspects of the work will be absorbed into business as usual work. The finalisation and lessons reports are being completed and will include recommendations for embedding outcomes and learnings into policy and procedure work. -audit of Out of Home Care standards of Out of Home Care agencies Three OOHC audits have been completed and another commenced as at the end of May. Workshops, follow up 7 meetings and clarification processes have been coordinated. This project is on track and will be completed early in 2013-14. -operating Viewpoint Interactive System The Viewpoint project has progressed dramatically. An MOU with FaHCSIA has been agreed, procurement is complete, hardware customisation has commenced and preliminary training has commenced. The status reflects issues the project faced with technical, cooperative and legal barriers experienced early in the project. The deliverable deadline is likely to be achieved. PLANNING FOR OUR FUTURE A 5 Year Out of Home Care Strategic Plan Substantial progress has been made on the OOHC Strategy. This includes extensive internal and external stakeholder engagement, coordination of resourcing and milestone development. To address some earlier milestone slippage PMO funds have been made available for 2012-13. In addition, looking forward, new Budget funds were approved to support OOHC Strategy development. Much of the proposed time frame is achievable, and the project is subject to minor rescoping for the 2013-14 financial year. GROWING STAFF CAPABILITY Refreshed Supervision Model The supervision project is complete. Up until the end of April (the last formal reporting month) team leader groups were ongoing, the supervision tool was reviewed and an 8 evaluation report had been drafted. Further training has been scheduled for November 2013. The project finalisation report is nearing completion as is the lessons register. The evaluation report, once approved, will be supplied to the’ Solving Workplace Issues Together Team’. Milestone Panel’s Response Recommendation 1 Recommendation 1 Milestone Panel Comments Pleasing progress has been made in implementing this recommendation. The Integrated Management System is a key to service delivery reform in CSD. It will take many months to complete this project. Considerable effort is being put into making sure that this is a comprehensive, holistic and easy to use system. CSD understands the importance of this project and is monitoring its progress closely. Its success will require a great deal of cooperation and understanding between CSD and Shared Services and considerable funding. Considerable work has been done to develop the basis for a strategic plan for out of home care which is on track for finalisation in 2015. After early technical and legal barriers, the Viewpoint project is progressing well and when finally implemented will be an important tool to help listen to the views of children. Case conferencing has been implemented in an attempt to achieve alternative outcomes for young people coming into contact with the Care and Protection system and a case audit tool has been developed and tested. 9 Recommendation 2 Implement this Strategic Framework through a change management process that will address the current reactive culture. This should include the use of employee focus groups so that all staff have a common understanding of the desired culture that reflects the actions of a statutory child protection organisation. Such a change management should include a review of the current systems and processes. ACT GOVERNMENT RESPONSE: AGREED The Government acknowledges that due to the increased demand and staff shortages during the period reviewed, the focus of Care and Protection workers has been on the assessment of risk and protection of children from harm. Of necessity this has meant a more reactive work style. With the increase in staff and a range of change management processes underway case workers are now able to refocus on a more pro-active and planned approach. A Care and Protection Services Change Management Committee has been formed which includes staff from across Care and Protection Services from all levels including case workers, administrative staff, managers, the executive and the Executive Director, Policy and Organisational Services. Under the agreed Terms of Reference this Committee has been established to:‘provide strategic leadership and coordination to strengthen reform implementation in Care and Protection; and, drive the development and implementation of the Care and Protection Services Integrated Management System and complementary projects.’ Increased Management Capacity In May 2012 the Office for Children, Youth and Family Support implemented a new structure which provides increased capacity for quality monitoring and improvement activity. The Senior Director position has now been filled and this position will take primary responsibility for quality activities and change management across the Office for Children, Youth and Family Support. Within Care and Protection Services the former Practice Support Unit has been refocused as the Quality Practice and Compliance Unit. Refocus of Roles and Responsibilities In recognition of the need for increased management support and a focus on quality practice Care and Protection Services now has an additional Senior Manager. The Senior Manager, Protection will focus on ensuring that the intake, appraisal and family support functions work to protect children at risk and enable a sharper focus on restoration efforts when children first enter care. The Senior Manager, Care is able to focus on ensuring that children in the long term care of the Director-General have their needs met. The Out of Home Care purchasing function will join this branch alongside the long term care orders team to ensure improved alignment to meet children’s needs. 10 Workforce Capability The ACT Government provide $5.015 million over 4 years in the 2011-12 Budget for 10 additional Care and Protection Services staff to assist frontline services, with a focus on improving quality and compliance. In assisting the service to move away from a crisis response, the Family Work Team (formerly the Response and Intervention Team) will promote planned and proactive work with families and will have a greater focus on supporting families, and where possible prevent the need for children and young people to be taken into care. It will also have a strong focus on restoration of children to their natural families. Case Conferences A Case Conference will be held as a mechanism to divert young people from entering statutory care through voluntary care agreements. It is anticipated that this will provide wraparound services to address the needs of young people and their family within an inclusive and participative framework. This process will strengthen the diversionary pathways for young people away from statutory care systems. Legislative Review The Government will review the Children and Young People Act 2008 with particular attention on enhancing a more pro-active and planned approach to intervention. Contact with Parents A project to develop an improved service model for the provision of transport and supervised parental contact has commenced. The design and implementation of this model will be supported by the establishment of a Steering Committee and stakeholder working group from across the government and nongovernment sectors. Actions to Focus on Early Intervention and Prevention The Public Advocate has also identified that in some of the cases reviewed a more proactive approach is required to keep children out of care to the greatest extent possible. A Differential Response Model Is applied as part of the intake process. These responses range from intensive statutory interventions through to voluntary engagement, the giving of advice or assistance and referring on to and working alongside other agencies in a co-ordinated and child-centred way. Child, Youth and Family Support Program The ACT Government provided $8.5m over 4 years in the 2011-12 Budget for this program which provides funding to 27 organisations within the ACT to provide a range of services that will actively support vulnerable children, young people and families. The services within this program will be delivered within an integrated and collaborative service model. The model is premised on joined up service delivery and is in the first stages of implementation. 11 One component of the Child, Youth and Family Support Program is the Intensive Family Support Service which works directly with the statutory Care and Protection Service to prevent children coming into care or support the restoration of children and young people to their family. This program will complement the services provided through the three Child and Family Centres. These centres provide a range of preventative and early intervention services for families in an accessible environment which facilitates referral to a range of support services. Care and Protection Services and the Australian Federal Police have forged a closer working relationship and are pursuing the option of placing an officer from the Sexual Abuse and Child Abuse Team (SACAT) with the Care and Protection Services Intake service and a corresponding placement of a Care and Protection case worker with SACAT. This initiative will facilitate cooperative and more seamless support for traumatised children and young people. 12 Recommendation 2: Projects to progress the Government Response: Implementation of an Integrated Management System; Case Conferencing Service Model Supported Contact and Transport Legislative Review Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 2 COMMENT PROGRESS PRACTICE IMPROVEMENT Implementation of an Integrated Management System which includes the development of: -standardised policies and procedures -deployment process flowcharts for all procedures -accountability package -online CPS “Knowledge Portal” -an Integrated Management System for CPS -implementation Review Report While substantial activity is occurring in the IMS project the size and scope of the project means technical project progression has been relatively slow. Activities such as the change management and training subcommittees have been ongoing, as have wider consultative mechanisms such as town hall presentations. In June 2013 the IMS has commenced a policy steering committee to improve collaboration and has started 13 road testing a technology solution for the portal. During to the quarter to May 2013 team building has been a key resourcing focus. At the end of May the IMS team has added 3 new personnel to drive IMS work. A further two positions are going through recruitment action. For 2013-14 the IMS will be presenting an updated project plan to the Strategic Projects BOM to demonstrate how the deliverables will be achieved for the July BOM meeting Expansion of case conferencing service model The case conferencing project is complete and the model is implemented. At the end of April 2013 (the last formal monthly report) the project was continuing to prove effective in achieving alternative outcomes for young people coming into contact with the care and protection system. Effort is now being applied to embedding the process into policies and procedures. A review of the project outcomes was commenced in May 2013. PLANNING FOR OUR FUTURE Supported Contact and Transport At the end of May 2013 the contact and transport project had delivered information sheets based on the current service model and stakeholder engagements. The project will close by the end of June 2013. The elements of the project that go to the support and contact design options will be allocated to the Placements module of the IMS. The elements of the project that go to OOHC contact 14 procurement will be allocated to the OOHC Strategy project. The finalisation and lessons report will reflect upon the changing nature of the project and the destination of resources and inputs. LEGISLATIVE REVIEW Legislative Review The project stalled over the quarter with the project manager being on leave and also diverted to other tasks. Segmenting the in-scope and out-of-scope suggestions and detailed mapping of the links between feedback and legislation is the last stage to finalising the draft report. Milestone Panel’s Response Recommendation 2 Recommendation 2 Milestone Panel Comments The Panel’s comments on practice improvement and case conferencing can be found at Recommendation 1. The Panel notes that there is still a considerable amount of work to be done to finalise a review of the legislation in this area. It has been difficult to define the scope of the Legislative Review relevant to the recommendation. This has now been done and four issues have been identified for further investigation. The Supported Contact and Transport Project has delivered a range of information sheets for carers, parents and children and young people about contact as it is now, and the concept of ‘supported’ (rather than ‘supervised’) contact. These have been provided to the target populations to gather feedback. The work done on the policy questions about reforming the service model has been packaged out to the Placements module in the IMS project, and the work done on procurement and contracting questions has been included in the 5 year Out of Home Care Strategy. The project was technically closed as at the end of June 2013. The project manager for the closing project is drafting the project closure documentation and developing a lessons-learned register to ensure that any information gathered is not lost. The closure report will outline the allocation of any tasks and the project managers of the IMS and OOHC Strategy are aware of the transfer. 15 Recommendation 3 Develop a staff training and development regime and ensure that this meshes with the strategic framework and is tailored towards the acquisition and development of skills, particularly for caseworkers and their supervisor. Training should be linked to competencies, and be included in the process for advancement to higher duties. ACT GOVERNMENT RESPONSE: AGREED Care and Protection Training Program: A revised training program of core training for case workers was approved in December 2011. It is expected that all new case workers complete their core training modules within a 12 month period. This core training includes: o The Children and Young People Act 2008 o Reporting child abuse and neglect o Case management practice o Risk assessment o Effective practice with involuntary clients o Record keeping and case noting o Working with Aboriginal and Torres Strait Islander People. Additional training is provided to all Care and Protection Services staff on a regular basis, including: o Communicating with children and young people. o Working with refugee clients Individual Performance Plans All staff in the Directorate are required to have an Individual Performance Plan which incorporates an assessment of their current capabilities and a plan to meet any identified gaps. Tracking Training The Directorate has a new online Learning Management System designed to make it easier for staff to register for internal training courses and to keep track of the training they have completed. This system has now been implemented and will assist in addressing training needs and gaps of all Care and Protection Services staff. Supervision Project The Office for Children, Youth and Family Support has a Supervision Framework which articulates the commitment to regular supervision for all staff. Team Leaders and Managers have undertaken training in supervision. An experienced trainer from Learning and Community Education commenced work on a twelve month Supervision Project in March 2012 to strengthen the confidence and competence of Managers and Team Leaders in supervision practice. The project 16 acknowledges the importance of reflective supervision as a learning focused activity that contributes to good case management practice aimed at improving outcomes for the children, young people and families who come in contact with Care and Protection Services. This project will improve the staff satisfaction with the quality of the experience of supervision, support child protection staff to act with appropriate autonomy and consolidate and collate a consistent set of tools. A Training Sub Committee of the Change Management Committee has been established to develop the training program that will be required to ensure changes are implemented. Immediate Training Priorities In the next 6 months training will be provided to case workers on listening to the voice of children and young people. This training will provide the opportunity for staff to focus on techniques and strategies that can be used to ensure children’s voices are heard. All Care and Protection Services staff will also attend training on good decision making, including recording and communicating decisions. 17 Recommendation 3: Projects to progress the Government Response: Quality Improvement Tools A refreshed supervision model CPS Training Program refreshed and commenced Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 3 COMMENT PROGRESS PRACTICE IMPROVEMENT Quality Improvement Tools -case conference process used routinely for 13-16 year olds The case conferencing project is complete and the model is implemented. At the end of April 2013 (the last formal monthly report) the project was continuing to prove effective in achieving alternative outcomes for young people coming into contact with the care and protection system. Effort is now being applied to embedding the process into policies and procedures. A review of the project outcomes was commenced in May 2013. 18 -case audit tool developed The case audit tool project is complete. The case audit tool has been developed and tested. Some aspects of the work will be absorbed into business as usual operations. The finalisation and lessons reports are being completed and will include recommendations for embedding outcomes and learnings into policy and procedure work. -audit of OOHC standards of Out of Home Care agencies Three OOHC audits have been completed and another commenced as at the end of May. Workshops, follow up meetings and clarification processes have been coordinated. This project is on track and will be completed early in 2013-14. -operating Viewpoint Interactive System The Viewpoint project has progressed dramatically. An MOU with FaHCSIA has been agreed, procurement is complete, hardware customisation has commenced and preliminary training has commenced. The status reflects issues the project faced with technical, cooperative and legal barriers experienced early in the project. The deliverable deadline is likely to be achieved. GROWING OUR STAFF CAPABILITY A refreshed supervision model The supervision project is complete. Up until the end of April (the last formal reporting month) team leader groups were ongoing, the supervision tool was reviewed and an 19 evaluation report had been drafted. Further training has been scheduled for November 2013. The project finalisation report is nearing completion as is the lessons register. The evaluation report, once approved, will be supplied to the’ Solving Workplace Issues Together Team’. CPS Training Program refreshed and commenced Over the quarter the project has focused on building on the training matrix. In particular aligning CSD core capabilities, CPS Core training, Professional Development and planned training with general staff training needs, PA2 report outcome training, and Auditor-General report training and IPPs. This is an iterative process and the project as scoped is on track. Training on decision making At the end of May 2013, 207 staff had undertaken decision making training. The training content has been provided to implement an online/ accessible training solution. This project will be finalised in June 2013. Milestone Panel’s Response Recommendation 3 Recommendation 3 Milestone Panel Comments Growing staff capability is crucial to successful implementation of all the new policies and procedures developed over the past twelve months and to the effective use of new tools. The improvement of supervision and the development of appropriate training have been a focus for CSD. It is an iterative and ongoing process which will continue to require attention. The Panel notes that training on decision making has been undertaken and the content has been provided to implement an online and accessible training solution. 20 Recommendation 4 Development and formalisation of on-going review mechanisms. There is a clear need for an internal monitoring and performance review process, dealing with complaints and ensuring that “duty of care” and natural justice is adhered to. In addition, an external oversight function, such as an Office of Children’s Guardian, should be engaged to carry out a micro review, based on the method of the Review, at 3,6,9, and 12 months to monitor practice improvements or otherwise, to report finding directly to the Director-General. ACT GOVERNMENT RESPONSE AGREED IN PART The ACT Government agrees to the recommendation in relation to internal monitoring and performance review. A decision on the need for additional external oversight capacity will be made following the performance report by the Auditor General. An alternative mechanism will be established to monitor the implementation of change over the next twelve months. Complaints Unit The establishment of a Complaints Unit has commenced with the appointment of a project officer in February 2012. Current complaint processes have been reviewed and consultation is occurring regarding new processes. Decision Making Review Panel An Office for Children, Youth and Family Support Decision Making Review Panel was appointed in April 2012. Clients who are unhappy with a decision can request a review of the decision by the Panel which includes both CSD and independent members. Training in good decision making will be rolled out to all Office for Youth and Family Support staff. The outcomes of this project will improve the transparency of decision making by staff at all decision making points. Case Audits Care and Protection Services senior management are developing a case audit tool. The aim of the tool is to assess compliance with policy and legislation and quality of practice. The Operations Managers will undertake a random sample of cases on their floor every two months and these will be analysed and trends identified. These trends will inform changes to procedures and policy. Quality Improvement The newly appointed Office for Children, Youth and Family Support Senior Director will commence a Quality Improvement Initiative across all areas of the Office for Children, Youth and Family Support. The findings of this review and other inputs including the views of practitioners will inform the scope of this initiative. Out of Home Care Standards 21 The current pilot Out of Home Care Standards will be finalised and external audits of Out of Home Care services against the standards will occur over the next twelve months and beyond. Audit and Review Committee The Community Services Directorate Audit and Review Committee will monitor the implementation of the recommendations of this Report as part of its oversight responsibilities to monitor the outcomes of all audits conducted of Directorate functions. This committee is led by an independent chair and includes two other independent members who advise the Director-General. This Committee meets bi-monthly. Milestone Reviews The Minister for Community Services will establish a Review Panel to monitor the progress of the Office for Children, Youth and Family Support against the actions outlined in this Government Response to the Public Advocate’s Review and report on a quarterly basis for the next twelve months. The Public Advocate together with an external member of the Community Services Directorate’s Audit and Review Committee and the Chair of the Children and Youth Services Council will be invited to form the Review Panel. The Review Panel will report to the Minister under the auspice of the Children and Youth Services Council. Children’s Guardian The ACT Government Response to the Interim Report Agreed that this recommendation should be further considered as part of the Performance Audit by the Auditor General. Following receipt of the report from the Auditor General the ACT Government will consider the current roles and functions of the statutory oversight bodies and whether to establish additional external oversight from an Office of the Children’s Guardian. 22 Recommendation 4: Projects to progress the Government Response: Quality Improvement Tools Finalisation of Out of Home Care standards Complaints Unit Embedded Decision Review Panel Embedded Training on decision making Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 4 COMMENT PROGRESS PRACTICE IMPROVEMENT Quality Improvement Tools -case conference process used routinely for 13-16 year olds The case conferencing project is complete and the model is implemented. At the end of April (the last formal monthly report) the project was continuing to prove effective in achieving alternative outcomes for young people coming into contact with the care and protection system. Effort is now being applied to embedding the process into policies and procedures. A review of the project outcomes was commenced in 23 -case audit tool developed -audit of OOHC standards of Out of Home Care agencies -operating Viewpoint Interactive System May 2013. The case audit tool project is complete. The case audit tool has been developed and tested. Some aspects of the work will be absorbed into business as usual work. The finalisation and lessons reports are being completed and will include recommendations for embedding outcomes and learnings into policy and procedure work. Three OOHC audits have been completed and another commenced as at the end of May 2013. Workshops, follow up meetings and clarification processes have been coordinated. This project is on track and will be completed early in 2013-14. The Viewpoint project has progressed dramatically. An MOU with FaHCSIA has been agreed, procurement is complete, hardware customisation has commenced and preliminary training has commenced. The status reflects issues the project faced with technical, cooperative and legal barriers experienced early in the project. The deliverable deadline is likely to be achieved. PLANNING FOR OUR FUTURE Finalisation of Out of Home Care standards (incorporated into the Delivery of an Out of Home Care 5 Year Strategic Plan). The finalisation of the OOHC Standards is incorporated into the OOHC Strategy project. STAKEHOLDER ENGAGEMENT AND FEEDBACK Complaints Unit Embedded The complaints unit has received over 30 complaints, completed around 20 24 complaints, held over 40 face to face interviews, around 50 telephone interviews and undertaken multiple pieces of work (follow ups and stakeholder meetings) in the current quarter. In total 142 complaints have been made since inception. A decision was made to recruit to a SOGC position. The project has started reporting business as usual activities, and is practically complete. Finalisation will occur in June 2013. Decision Review Panel Embedded To the end of May 2013 two new referrals were made and accepted by the panel. Reflecting on this project demonstrated the only remaining activity is to evaluate the panel process. This is an ongoing activity, which is now part of business as usual operations. The project will be moved to completion in June, and the finalisation and lessons register will be completed. GROWING OUR STAFF CAPABILTY Training on decision making At the end of May 2013, 207 staff had undertaken decision making training. The content has been provided to implement an online/ accessible training solution. This project will be finalised in June 2013. 25 Milestone Panel’s Response Recommendation 4 Recommendation 4 Milestone Panel Comments CSD has made a decision to adopt National OOHC standards which will inform practice guidance and be incorporated into the OOHC Strategy. These will be included in service funding agreements and the guidelines incorporated into the IMS. The complaints unit has been embedded although its work was slowed by staffing constraints, which are being resolved with a recruitment action. Complaints are being handled in a consistent, timely and meaningful way. There is a clear destination for evidence-based, external expert review of disputed decisions with the decision review panel as well. 26 Recommendation 5 Review all kinship care and current processes. There is a need to improve initial assessments, include the needs of the children and young people to ensure their “voice” is heard, develop comprehensive case planning that includes the level of support required where there is evidence that the family needs the ongoing involvement of the statutory body, and create a review process to determine those kinship families that no longer require ongoing support. ACT GOVERNMENT RESPONSE AGREED The ACT Government acknowledges the complexity and difficultly kinship carers face when caring for children and young people and managing their own relationships with the children’s parents and family. Kinship Care Support Team The 2011-12 ACT Government Budget provided additional funding of $1.7m over four years to establish a new Kinship Care Support team. The Kinship Care Support team will take responsibility for completing comprehensive kinship carer assessments for all new kinship placement arrangements. The team will also support and advocate for and on behalf of kinship carers. Therapeutic Support for Kinship Care placements The Australian Childhood Foundation will be contracted to provide therapeutic support for kinship care placements, mirroring the therapeutic foster care program, OnTrack. Review of Existing Kinship Care Arrangements In the next twelve months the Quality, Practice and Compliance Unit will review the files of all existing kinship placements and undertake a review to ensure the placement remains in the best interest of the child or young person and that the family has the level of support they need. Support for carers The Directorate will continue to fund Relationships Australia to provide mediation and relationship counselling to kinship carers to assist them in managing the complexities that caring for kin brings. Consulting with Children and Young People In July 2012 Care and Protection Services will commence a trial of the Viewpoint ACASI (audio computer assisted self interviewing) web based program. Viewpoint is a software tool for consulting with children and young people and is being used in the United Kingdom and in Western Australia to enhance the participation of children into their care plan. Viewpoint is a software program, which can be installed onto computers and provides children with the opportunity and means of expressing their views regarding issues about being looked after. 27 Care Planning and Reporting Tools As part of the implementation of the Integrated Management System, Care and Protection Services will modify the current Care Plans and Annual Review Reports templates to promote a more planned and individualised approach to the needs of each child. Plans for children during the risk assessment, appraisal and placement phase will be developed as Action Plans to ensure a focus on the immediate needs and risk to children. Plans developed after the child is in a stable placement will be developed as Care Plans to focus on the ongoing, longer term needs and the coordination of supports. The Public Advocate will be consulted in the development of new planning tools. Out of Home Care Strategy The first Joint Planning Committee meeting was held in May 2012 to commence development of the 5 year Out of Home Care Strategy. A project officer has been appointed to undertake this work which aims to ensure adequate supply and quality of Out of Home Care placements for children in the care of the Director-General. 28 Recommendation 5: Projects to progress the Government Response: Implementation of an Integrated Management System Quality Improvement Tools Comprehensive Kinship Package Finalisation of Out of Home Care standards A 5 Year Out of Home Care Strategic Plan Complaints Unit Embedded Decision Review Panel Embedded Training on Decision Making Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 5 COMMENT PROGRESS PRACTICE IMPROVEMENT Implementation of an Integrated Management System which includes the development of: -standardised policies and procedures -deployment process flowcharts for all procedures -accountability package -online CPS “Knowledge Portal” -an Integrated Management System for CPS -implementation Review Report While substantial activity is occurring in the IMS project the size and scope of the project mean technical project progression has been relatively slow. Activities such as the change management and training subcommittees have been ongoing, as have wider consultative mechanisms such 29 as town hall presentations. In June 2013 the IMS has commenced a policy steering committee to improve collaboration and has started road testing a technology solution for the portal. During to the quarter to May team building has been a key resourcing focus. At the end of May 2013 the IMS team has added 3 new personnel to drive IMS work. A further two positions are going through recruitment action. For 2013-14 the IMS will be presenting an updated project plan to the Strategic Projects BOM to demonstrate how the deliverables will be achieved for the July BOM meeting Quality Improvement Tools -case conference process used routinely for 13-16 year olds The case conferencing project is complete and the model is implemented. At the end of April (the last formal monthly report) the project was continuing to prove effective in achieving alternative outcomes for young people coming into contact with the care and protection system. Effort is now being applied to embedding the process into policies and procedures. A review of the project outcomes was commenced in May 2013. -case audit tool developed The case audit tool project is complete. The case audit tool has been developed and tested. Some aspects of the work will be absorbed into business as usual operations. The finalisation and lessons reports are being completed and will include recommendations for 30 embedding outcomes and learnings into policy and procedure work. -audit of OOHC standards of Out of Home Care agencies - -operating Viewpoint Interactive System Comprehensive Kinship Package -Review of all current kinship carer needs completed -Comprehensive case planning for current kinship carers completed -Assessment of new Kinship Carers by Kinship Team Three OOHC audits have been completed and another commenced as at the end of May. Workshops, follow up meetings and clarification processes have been coordinated. This project is on track and will be completed early in 2013-14. The Viewpoint project has progressed dramatically. An MOU with FaHCSIA has been agreed, procurement is complete, hardware customisation has commenced and preliminary training has commenced. The status reflects issues the project faced with technical, cooperative and legal barriers experienced early in the project. The deliverable deadline is likely to be achieved. To the end of May 96 per cent of kinship carer reviews have been completed. 7 carers chose not to undertake reviews as they were satisfied with CPS engagement. There were 86 open support cases. New kinship carer assessments is hampered by resourcing, but is provided as required. A review of the project demonstrated the results reported actually reflect business as usual processes and this project is able to be closed. The finalisation and lessons register is addressing any ongoing issues, and making suggestions for embedding the work into the wider CPS policy and procedures matrix. 31 PLANNING FOR OUR FUTURE Finalisation of Out of Home Care standards A 5 Year Out of Home Care Strategic Plan Substantial progress has been made on the OOHC Strategy. This includes extensive internal and external stakeholder engagement, coordination of resourcing and milestone development. To address some earlier milestone slippage PMO funds have been made available for 2012-13. In addition, looking forward, new Budget funds were approved for 2013-14 to support OOHC Strategy development. Much of the proposed time frame is achievable, and the project is subject to minor rescoping for the 2013-14 financial year. STAKEHOLDER ENGAGEMENT AND FEEDBACK Complaints Unit Embedded The complaints unit has received over 30 complaints, completed around 20 complaints, conducted over 40 face to face interviews, around 50 telephone interviews and undertaken multiple pieces of work (follow ups and stakeholder meetings). In total 142 complaints have been made since inception. A decision was made to recruit to the SOGC position. The project has started reporting business as usual activities, and is practically complete. Finalisation will occur in June 2013. Decision Review Panel Embedded To the end of May two new referrals were made and accepted by the decision review panel. Reflecting on this project demonstrated the only remaining activity is to evaluate the panel process. This is an ongoing activity that 32 is now part of business as usual operations. The project will be moved to completion in June 2013, and the finalisation and lessons register will be completed. GROWING OUR STAFF CAPABILTY Training on decision making At the end of May 2013, 207 staff had undertaken decision making training. The content has been provided to implement an online/ accessible training solution. This project will be finalised in June 2013. Milestone Panel’s Response Recommendation 5 Recommendation 5 Milestone Panel Comments A review of kinship carer needs has been completed. A number of cases have been identified which require further support. The assessment of new kinship carers by the Kinship Carer Team is hampered by resource difficulties and requires attention. 33 Recommendation 6 Cultural Awareness The culture of all children/young people must be identified and appropriately supported, and the best use of available resources should be made to support Aboriginal and Torres Strait Islander children/young people. In addition, the development of a program to support the cultural safety of children/young people from other cultures particularly recently arrived refugees is strongly supported. All staff commencing in Care and Protection Services should receive training in cultural awareness. ACT GOVERNMENT RESPONSE AGREED Aboriginal and Torres Strait Islander Services Service Redesign Community Services Directorate has recruited a senior Aboriginal Executive to work with the Directorate over a 12 month period to redesign service delivery for Aboriginal and Torres Strait Islander people. This project includes substantial consultation with the local community and research into better practice methods from other jurisdictions and internationally. Implementation of new service delivery models will commence at the conclusion of the design phase in September 2012. The roles and responsibilities of Aboriginal and Torres Strait Islander Services staff within statutory child protection processes will be revised through the redesign of the Aboriginal and Torres Strait Islander Service and the development of Care and Protection Services Integrated Management System process. Improving Cultural Care Plans Within Care and Protection Services a Project Officer has been appointed to the Quality and Compliance Unit to rethink the model currently in place for the development of cultural care plans. Community consultation will occur, along with the identification of key partners in the community that could lead and / or contribute to cultural care planning. Training The 2012-13 Budget includes additional funding to strengthen Care and Protection Services. Included in this initiative will be the development and roll out of training in ensuring cultural safety for children in care. The Aboriginal and Torres Strait Islander Engagement Service Is one component of the Child, Youth and Family Support Program. It has two aims: (1) to promote access and engagement of Aboriginal and Torres Strait Islander children, young people and their families with mainstream services and (2) to develop and improve the cultural competence of services working with Aboriginal and Torres Strait Islander children, young people and their families. A model for the Aboriginal and Torres Strait Islander Engagement Service is currently being developed by the Aboriginal Justice Centre, Northside Community Service and Relationships Australia, in partnership with Aboriginal and Torres Strait Islander elders. 34 Culturally and Linguistically Diverse Services Training Through the new Child, Youth and Family Services Framework, Companion House will receive funding to provide an annual calendar of training including tailored training sessions (services and topic specific) designed to increase culturally competent practice. Companion House will also deliver a service that will be cross-culturally and trauma sensitive, responsive to the needs of children and their families and have a primary outcome of addressing significant issues that impact on children, young people and families. The service will have the capacity to provide a therapeutic model for individuals, family groups and peers. This service will include a range of strategies to build capacity of services to engage successfully with young people and their families who have experienced torture, trauma and refugee experiences. Data Collection From 2013-14 Care and Protection Services will collect and collate data on the language and family cultural background of all children coming into Care. This data will be used to gain a greater understanding of which cultural groups are most represented and therefore of the cultural training that is required. 35 Recommendation 6: Project to progress the Government Response: Increased Practitioner Cultural Competence Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 6 COMMENT PROGRESS PRACTICE IMPROVEMENT Increased Practitioner Cultural Competence The cultural care plan element has achieved 98 per cent coverage of Aboriginal and Torres Strait islander children and young people in care with care plans. The reorganisation of ATSIS has meant some of the planned activity has been held over. A review of the deliverables with the project manager revealed that the activities as scoped are now being acted upon as part of business as usual operations. This project has moved to a practical close. The finalisation report is addressing how the remaining activities will form part of business as usual. The cultural identifiers (main language spoken at home) 36 element of the project does not have a dedicated project manager. Steps are being taken to ensure CHYPS is able to capture the cultural data. Interim options are being structured, and the work is being considered in the context of IMS changes. This project is a candidate for inclusion in the broader electronic record project. Milestone Panel’s Response Recommendation 6 Recommendation 6 Milestone Panel Comments Cultural care plans for Aboriginal and Torres Strait Islander children and young people in care have been established and activities have been embedded into ‘business as usual’ operations. The cultural identifiers (main language spoken at home) project is not yet complete. Steps are being taken to ensure that the cultural data is captured in CHYPS and further work is being considered in the context of IMS changes. This project is a candidate for inclusion in the broader electronic record project. The Panel was pleased that training in culturally competent practice has been included in the contract for services delivered by Companion House under the Child, Youth and Family Services Program. 37 Recommendation 7 Improved Record Keeping. Care and Protection Services needs to determine whether the primary record keeping function will be a paper file or an electronic system as currently neither function will be a paper file or an electronic system as currently neither function is efficient of effective. The decision needs to be supported by policy and include a mechanism for the child or young person to be able to access their record should they make the request. Staff need to be trained in evidence based case recording where the decisions and reasons for decisions are diligently recorded, and include the signature of the decision maker or delegated officer. In addition, CHYPS the current electronic system needs updating. Case management programs from other jurisdictions may serve to guide purchase of this enhancement. ACT GOVERNMENT RESPONSE AGREED Record Keeping Systems The Community Services Directorate acknowledges the importance of record keeping and the need to consider moving to total electronic records management for improved transparency and decreased administrative burden. Preliminary assessments of the capacity for CHYPS to be a complete electronic record system have occurred. Further work will inform a business case for an appropriate technological solution. Funding for this business case will be subject to future Budget considerations and will be weighed against competing priorities. The advantages however of an electronic system are still essential to service delivery. Access to critically important information from different sites and remotely is essential for effective service delivery when considering risk issues for children and young people. Paper files at present are still considered the official record. The Directorate will review the information and training that is provided about the use of electronic and paper files to increase awareness of obligations to ensure the paper record when finalised is complete. The Integrated Management System will include a comprehensive Practice Framework, and a Risk Assessment and Case Management Framework. This will incorporate specific risk processes and tools to guide the recording of decisions and the reasons for decisions. Staff will be provided with training in these processes as the system is implemented. Legislation Review The proposed review of the Children and Young People Act 2008 will incorporate consideration of the administrative burden on staff and the removal of unnecessary red tape. The current Act is 771 pages long and includes a large number of compliance requirements. Once the Integrated Management System is completed it is proposed to review the legislation to see if all of these requirements are necessary in the legislation, or if some are better incorporated into policy and practice guidelines. 38 Increased Staffing As Care and Protection Services approaches full staffing there is greater capacity for staff to complete administrative and record keeping tasks that may have been of a lesser priority in times when there were severely diminished resources. Additional positions available from the staffing initiative for Care and Protection Services in the 2012-13 Budget will further support this capacity for frontline case workers to have adequate time to ensure compliance with administrative requirements. 39 Recommendation 7: Projects to progress the Government Response: Training on decision making Scope Electronic Record Legislative Review Progress against the Government’s commitments and symbols used to indicate progress achieved. Traffic Light Legend Deliverable is complete Action is on track for completion on time and within scope Action requires attention. There may be difficulty in achieving some parts of the project scope, or there may be a delay in completion Action will not be delivered on time or to the scope requirements Work not commenced on the action yet PROGRESS OF PROJECTS TO ACHIEVE THE COMMITMENT IN THE GOVERNMENT RESPONSE TO RECOMMENDATION 7 COMMENT PROGRESS GROWING OUR STAFF CAPABILTY Training on decision making Health Passport At the end of May 2013, 207 staff had undertaken decision making training. The content has been provided to implement an online/ accessible training solution. This project will be finalised in June 2013. The health passport project has stalled. The project manager has been temporarily re-allocated to operational work. Some activity has occurred in the national environment. 40 PLANNING FOR THE FUTURE Scope Electronic Record The electronic record project remains on hold. The scale and scope of what can be achieved in a project considering the electronic record is dependent upon available resources. The 201314 Budget provided some resourcing to set up a project response, and this is a focus for the following quarter. LEGISLATIVE REVIEW Legislative Review The project stalled over the quarter with the project manager being on leave and also diverted to other tasks. Segmenting the in-scope and out-of-scope suggestions and detailed mapping of the links between feedback and legislation is the last stage to finalising the draft report. Milestone Panel’s Response Recommendation 7 Recommendation 7 Milestone Panel Comments Implementation of this recommendation is far from complete. The electronic record project was previously on hold but the 2013-14 Budget has provided some guidance for the project and it has now commenced. The Health Passport project had stalled but has recommenced. This aspect of the Legislative Review relates to the reduction of red tape. Once the IMS is completed it is proposed to see if the compliance requirements are necessary in the legislation, or if some are better incorporated into policy practice and guidelines. 41 ATTACHMENT 1 Milestone Review Panel Background Members Chair: Mrs Narelle Hargreaves (Chair, Children and Youth Services Council) Member: Ms Anita Phillips (Public Advocate of the ACT) Member: Mr Graham Bashford (Deputy Chair, Community Services Directorate Internal Audit and Review Committee). Background During 2011 and 2012 two significant reviews of Care and Protection Services (CPS) were completed by the Public Advocate. These reviews resulted in the following reports: The Public Advocate’s Report - Stage 1 Interim Report – A Review of the Emergency Response Strategy for Children in Crisis, released on 14 October 2011; and The Public Advocate’s Stage 2 Report - Emergency Response Strategy for Children in Crisis in the ACT which was released on 30 May 2012. The Public Advocate’s Report of 14 October 2011 made the following recommendations: 1. Urgently Review the Operations and Management Structure of the Emergency Response for Children in Crisis in the ACT; 2. Improve Emergency Response Processes; 3. Monitoring and Provision of Placements; 4. Early Intervention; and 5. Specific recommendations in relation to Northern Bridging Services. The ACT Government has delivered the majority of the commitments made in the Government Response to the Interim Report. Those that have not been delivered are linked to the deliverables of the second Public Advocate report and an Auditor-General’s review. The Public Advocate’s Stage 2 Report - Emergency Response Strategy for Children in Crisis in the ACT made seven major recommendations which in summary are: 1. Develop a Strategic Framework; 2. Implement the Strategic Framework through a change management process that will address the current reactive culture; 3. Develop a staff training and development regime; 4. Develop and form on-going review mechanisms; 5. Review all Kinship Care and current processes; 6. Cultural Awareness; and 7. Improve Record Keeping The Milestone Review Panel (Panel) was established as part of a response to Recommendation 4 of the Public Advocate Stage 2 Report. The Government response to Recommendation 4 advised: 42 The Minister for Community Services will establish a Review Panel to monitor the progress of the Office for Children, Youth and Family Support against the actions outlined in this Government Response to the Public Advocate’s Review and report on a quarterly basis for the next twelve months. Methodology The ACT Government’s response to the ACT Public Advocate’s report: Review of the Emergency Response Strategy for Children in Crisis in the ACT outlined commitments to improving the integration and coordination of services for vulnerable children. The Government’s commitments can be found at Attachment 3. The Community Services Directorate (CSD) is responsible for implementing the ACT Government’s commitments. The Panel is responsible for monitoring the progress made by the CSD in implementing the Government’s commitments to improve services for vulnerable children. Progress against the Government’s commitments to the Public Advocate’s recommendations is the base of analysis for the Panel’s quarterly report. To date, the Panel has met at three and six months intervals and will meet again at nine and twelve month intervals. Secretariat support to the Panel will be provided by the CSD. Prior to each meeting of the Panel, the Office for Children, Youth and Family Support (OCYFS) within the Community Services Directorate (CSD) provides the Panel with qualitative information and quantitative data and a draft Summary Report. Information provided by OCYFS details the progress made towards implementing the Government commitments during the previous three months. The draft Summary Report forms the basis of each Milestone Review Panel Report. During each meeting of the Panel, the OCYFS assists the Panel’s considerations by providing presentations on the Projects being implemented. When required, the OCYFS provides other information requested by the Panel, further qualitative information on a specific project and/or further quantitative data relating to a specific project. The Panel draws on the information and data provided by the OCYFS to complete a Milestone Review Panel Report (Report). The Reports comprise qualitative information and quantitative data provided by the OCYFS and the Panel’s comments and conclusions on the progress achieved. The Panel is not required to make recommendations to the Minister regarding the progress achieved. Following the Panel’s finalisation of the Report, the Panel provides a copy of the Report to the Minister for Disability, Children and Young People through the auspice of the Children and Youth Services Council. The Minister releases the Report publicly. The Panel’s term ceases on completion of the final (twelfth month) Report. The Terms of Reference for the Panel are at Attachment 2. 43 ATTACHMENT 2 Milestone Review Panel Terms of Reference FUNCTION Purpose The ACT Government’s response to the ACT Public Advocate’s report: Review of the Emergency Response Strategy for Children in Crisis in the ACT outlined commitments to improving the integration and coordination of services for vulnerable children. The Community Services Directorate is responsible for implementing the ACT Government’s commitments. Role The Milestone Review Panel will monitor and report against progress made to address the service needs of vulnerable children by: reviewing information provided by the Community Services Directorate through the means of a spreadsheet that identifies the milestones to be attained and the actions taken to attain the milestones; and compiling a Milestone Review Report which reports on the actions taken by Community Services Directorate against the identified milestones. The Milestone Review Panel will not be required to make recommendations to the Minister or make public statements regarding the Community Services Directorate’s progress. MEMBERSHIP Composition of the Milestone Review Panel The Milestone Review Panel members are Mrs Narelle Hargreaves, OAM – Chair Mr Graham Bashford Ms Anita Phillips Community Services Directorate officials may attend each meeting. Term of Appointment Appointments to the Milestone Review Panel will cease following completion of the final (twelfth month) progress report. Vacating position on the Milestone Review Panel Members are to notify the Minister for Disability, Children and Young People in writing of their intention to vacate their position on the Milestone Review Panel, with a copy to the Chair. Role of Chair 44 The role of the Chair is to facilitate orderly and constructive discussion between Milestone Review Panel members. In the event a spokesperson is required, the Chair is the spokesperson for the Milestone Review Panel. In the event Milestone Review Panel members are unable to agree about any issue relating to the monitoring of, or progress against, the commitments made in the Government response to the ACT Public Advocate’s report, the Chair’s decision will be final. Secretariat support Secretariat support to the Milestone Review Panel will be provided by the Community Services Directorate. The Secretariat will – compile agendas and associated papers/information in preparation for Milestone Review Panel meetings; take minutes at scheduled meetings, provide a liaison between the Community Services Directorate and the Milestone Review Panel; and assist the Milestone Review Panel to prepare quarterly Milestone Review Reports to be provided to the Minister for Disability, Children and Young People. OPERATION Meetings The Milestone Review Panel will convene as close as possible to the following dates– 26 September 2012; 14 December 2012; 14 March 2013; and 14 June 2013 All meeting papers, including the Community Services Directorate’s progress report against commitments, will be provided to Milestone Review Panel members no later than one week prior to the Milestone Review Panel’s scheduled meeting date. Quorum In order for decisions to be made at meetings the Chair plus one Milestone Review Panel member must be present. If a quorum is not able to be reached a substitute Milestone Review Panel meeting must be scheduled to occur as soon as practicable. When necessary, agreement on decisions can be reached out-of-session. Reporting 45 The Milestone Review Panel will provide a copy of the Milestone Review Report to the Children and Youth Services Council for their information only. Through the auspice of the Children and Youth Services Council, the Milestone Review Panel will provide the Milestone Review Report to the Minister for Disability, Children and Young People no later than the last working day of – October 2012 - 3 month Milestone Review Report; January 2013 – 6 month Milestone Review Report; April 2013 – 9 month Milestone Review Report; and July 2013 - 12 month Milestone Review Report. Remuneration Members of the Milestone Review Panel will receive remuneration in accordance with the ACT Remuneration Tribunal Determination2011 (No 1). Contact details Secretariat Milestone Review Panel Mr David Matthews Phone: 6207 4433 Email: david.matthews@act.gov.au 46 ATTACHMENT 3 ACT Government Responses to the Public Advocate Interim Report The ACT Government Response to the Report of the Public Advocate Interim Report was provided on 22 November 2011. Progress has been made to implement the Government’s commitments. The Government is committed to ensuring this progress is sustained. Interim Report Recommendation 1 Urgently review the Operations and Management Structure of the Emergency Response for Children in Crisis in the ACT. The Public Advocate of the ACT should be engaged and resourced to immediately undertake Stage Two of this Review. The ACT Government Agreed in Part to this recommendation. Progress: The Public Advocate completed the second stage of her review in accordance with the terms of reference outlined in the Government Response to the Interim Report and provided her Final Report on 1 June 2012. The Auditor General has commenced a Performance Audit of Care and Protection Services and a final report of this review is due to be presented to the Assembly during late 2012. Interim Report Recommendation 2 Emergency Response Processes: The Director-General Community Services Directorate, be called upon to immediately establish a reception centre/facility as part of the Emergency response for children in crisis. The ACT Government Agreed to this recommendation. Progress: A property suitable to be used as a Reception Centre was provided by Housing ACT and fitted out in December 2011 to provide a welcoming and safe environment for children who come into care and do not have an immediate placement with either extended family or foster care. The Centre has been used on three occasions since its establishment. The operation policy and procedures have been drafted and a checklist for operational use has been finalised. Early response to the model has been positive and it is meeting a critical need, particularly for sibling groups who have experienced trauma and are best placed together. The Director General, Community Services Directorate, authorises that an Operations Policy and Procedures Manual for caseworkers and direct care staff be finalised and implemented as a matter of priority. 47 Progress: The development of clearer policies and procedures were prioritised into four areas: intake and risk assessment, placements, kinship care and restoration of children to families. Policies and procedures have been drafted and consultation with the sector has been completed regarding the placement policy and kinship care model of service. The Integrated Management System project commenced in February 2012. The project aims to provide caseworkers with tools and improved processes to assist in their decision making, access to revised policies, procedures and delegations and improved compliance requirements. The change process will be implemented throughout 2012-2013. Interim Report Recommendation 3 Monitoring and Provision of Placements: The position of Children’s Guardian be resourced and formalised under the auspice of the Public Advocate of the ACT. The ACT Government Agreed that this recommendation should be further considered as part of the Performance Audit by the Auditor General. Progress: The Performance Audit being undertaken by the Auditor General will include consideration of the roles and responsibilities of statutory oversight bodies. Interim Report Recommendation 4 Early Intervention: Response and Intervention Teams should be relocated out to the regions. The ACT Government Agreed in Part to this recommendation. Progress: A realignment of Care and Protection Services has been finalised. In the new structure the teams will continue to be located in the central Moore Street Civic building but will be operationally separated into North and South Canberra teams. The new structure aims to provide a child and family the same case worker from the time of the initial report of risk through the appraisal process. Community based Care and Protection Workers are being re-located to the three Child and Family Centres to provide outreach services. The placement of these Child Protection community workers will encourage additional community engagement and increased coordination of services across agencies and a community level. The workers will have a renewed focus on pre-natal work, and engage with families at the earliest possible point. 48 Interim Report Recommendation 5 Recommendations specifically in relation to Northern Bridging Support Services: An independent mediator be engaged to conduct mediation between NBSS and CPS. In addition, immediate payment of outstanding monies must be arranged. The ACT Government Agreed to this recommendation. Progress: All outstanding invoices have been paid. Mediation has been offered to Northern Bridging Services but to date. As for the previous report we have aligned the progress indicators to a traffic light system for progress. The meaning of the traffics lights used is outlined over page. 49 ATTACHMENT 4 Progressing the commitments made in the Government response to the recommendations of the Public Advocate’s Review The ACT Government Response to the Report of the Public Advocate released on 1 June 2012 provided an update on progress against the The Public Advocate’s Report Stage 1 Interim Report – A Review of the Emergency Response Strategy for Children in Crisis (Attachment 3). This report indicated that any remaining work commitment from the Government Response was dependent upon the second Public Advocate report and an Auditor General’s report which is currently underway. Apart from several specific items, the program of work to achieve the Government’s commitment to the second Public Advocate’s Report (Public Advocate’s Stage 2 Report Emergency Response Strategy for Children in Crisis in the ACT) is being implemented under the Office for Children Youth and Family Support (OCYFS) quality agenda that has been defined as Refreshing the Service Culture. For 2013-14 OCYFS have revised the nature of the Refreshing the Service Culture agenda, in particular how the agenda is articulated. The OCYFS vision is to be a leading organisation committed to delivering the best possible life outcomes for the ACT’s children and young people. The mission is to ensure that ACT children, young people and their families are strong, safe and connected. The Refreshing the Service Culture agenda provides a framework across the OCYFS for delivering a continuous quality improvement agenda. This quality agenda reflects on the experience, advice and ideas emerging from change to draw meaningful and usable concepts in a systematic and focussed framework to build a better service system. The Refreshing the Service Culture framework has five major pillars: Practice Improvement Planning for the Future Stakeholder Engagement and Feedback Growing our Staff Capability Legislative Review The objective is to use this approach to respond to a range of drivers to ensure a consistent whole of OCYFS approach can be used to effectively deal with multiple points of inquiry and practice improvement suggestions. While change and reform take time to embed given the sensitivity of the client base and the breadth and depth of reforms, successful implementation of Refreshing the Service Culture will mean that OCYFS is focussed on responsive client service and stakeholder relations, refreshed in its identity as a selfreflective learning organisation, realigned organisationally to support the service agenda and positioned to deliver good outcomes for children, young people and their families. Figure 1 provides a perspective on how Refreshing the Service Culture interacts with direction setting and supports the OCYFS objective. 50 Figure1: What Does Refreshing The Service Culture Look Like? Canberra Plan Govt Priorities DIRECTION SETTING ACT GOVERNMENT Strategic Framework Office Risk Register OFFICE OF CHILDREN YOUTH AND FAMILY SUPPORT Policy Data and Research Care and Protection Service Strategic Risks ‘Participation’ Agenda COMMUNITY SERVICES DIRECTORATE Business Support Budget Expectations Youth Support Early Intervention and Prevention Business Plans Risk Registers Performance Plans Work Health and Safety GOVERNANCE: OCYFS EXECUTIVE + STRATEGIC BOM + EXTERNAL PARTICIPANTS CONTINUOUS IMPROVEMENT OCYFS STAFF REFRESHING THE SERVICE CULTURE Practice improvement Planning for the future Stakeholder engagement Growing our staff capability Legislative Reform Partners Children & Young people Stakeholder groups External review OCYFS QA process DRIVERS Staff Audit and Review Clients “ACT children, young people and their families are strong, safe and connected” 51 To understand the practical impact of the Refreshing the Service Culture agenda, it is possible to map the PA Report recommendation to the pillars of the quality reform agenda. The broad alignment of the pillars of the Refreshing the Service Culture agenda and the recommendations from the PA are demonstrated in Figure 2. This also demonstrates how the practical project reporting can be aligned to external reporting bodies, and how a number of the activities arising from the Government’s commitments (for example, the Integrated Management System) will deliver action under more than one Public Advocate recommendation. Figure 2: Alignment of Refreshing the Service Culture with the PA report The Milestone Review Panel has been a useful and positive external review point for some of the activity under the Refreshing the Service Culture agenda. It is worth observing that in an ongoing sense the Refreshing the Service Culture agenda is governed primarily through the OCYFS Executive Team which monitors projects, management actions and related activities that are aligned to the five reform pillars. The OCYFS Executive Team is supported directly by external groups such as the Strategic Reform Group of the CSD Board of Management and the CSD Audit and Review Committee and indirectly by independent Statutory Officers, the `Children and Youth Services Council’ and regular internal and external stakeholder communications. 52 ATTACHMENT 5 - Progress since the March Quarter The June quarter report covers the three months from March to May 2013 inclusive. As this fourth quarter report for the Milestone Review Panel will be considered at the commencement of the 2013-14 financial year, some additional information is reported on what is known up to end of June 2013. . To the end of May overall technical program completion has increased to 60 per cent, an increase of 10 percentage points from the March quarter report. This section considers some of the context for the quarter, discusses project finalisation, key achievements and outlines exceptions to overall positive progress. Context Over the fourth quarter OCYFS has been deeply engaged in the primary resourcing phase of the year. In particular, OCYFS leadership were tied closely to Budget development and savings implementation processes. The typical Budget development process was accompanied by ‘Strategic Service Planning’ and ‘Capacity Improvement Program’ processes in which OCYFS participated. Regular operations have been affected by the implementation of agreed savings initiatives that were announced by the Executive Director on Monday 15 April 2013.This has directly affected the Youth Connections team in Youth Services, the Policy Data and Research team structure and staffing at the Child and Family Centres. Concurrently substantial change and implementation management issues are linked with the Aboriginal and Torres Strait Islander Service realignment process. Many staff and the OCYFS Leadership Group members have been positively engaged in looking at improvements to the working environment through a grouping of personnel under the ‘Solving Workplace Issues Together Team’. Over the reporting period there were typical seasonal variations in staff availability associated with the Easter period and school holidays. This had some impact across the program, particularly at the program delivery level. It has been problematic that across Youth Justice Case Management and Care and Protection there has been a short term spike in vacancies. While these are being managed closely, this has placed additional workload pressure across the organisation. Project finalisation In the third quarter report the program was reporting a range of strategic successes, where the technical project indicators suggested progress was slow, but that project completion was imminent. This was a strategic success because it demonstrated that while technically there was some negative progress sentiment, most of the projects behind schedule where approaching closure, compared to an environment at the start that perceived OCYFS typically started projects but did not necessarily complete them. This strategic success is amplified at the end of the 4th quarter. In May we are reporting five projects as complete. These include: 1.3 Expansion of case conferencing service model 1.4a Develop Quality Improvement Tools - Case Audit Tool 53 1.5 Comprehensive Kinship Care Package. 1.6a Increased practitioner cultural competence –cultural care plans 4.1 Implement Refreshed supervision model A further four projects will be completed by the end of June, including: 4.2 Training on decision making delivered (Accountable and responsible decision making) 3.1 Embed Complaints Unit 3.2 Embed a Decision Review Panel 2.2 Supported contact and transport. To be clear, these projects completions are due either to the achievement of the deliverables, or by virtue of the project activities merging into business as usual activities. Indeed, closing the project does not mean that the activities cease. Each of these projects will provide project finalisation reports and lessons learnt registers, and these documents include information about improvements available for the operation of OCYFS and recommendations about how the content is to be integrated into existing processes or operations. They do not provide ongoing monthly updates. At the June Strategic Reform BOM it was agreed to cease one project from the program. The project ‘1.2 OCYFS Structural Alignment’ was due to evaluate the implementation of the OCYFS structural refresh, however this has been confounded by a number of alternative processes and is not relevant compared to the initial context. Key Achievements Of the projects remaining in the program there are some positive highlights including: The IMS has resolved some resourcing problems and has engaged with CPS to road test the Intake and Appraisals module. At least three audits of OOHC providers have been completed and are in the negotiation/feedback loop. The Viewpoint interactive software has been procured, is being customised and training has commenced with CPS users. Information guides in relation to supported contact and transport have been developed and will be released to carers and providers. Decision making training has been provided to 207 personnel, of which 90 were in May. While the focus for the Panel is on progress towards achieving project milestones, it is instructive to consider where change is now becoming evident from projects being closed. Some of these examples include: A direct reduction in the use of VCAs that would otherwise not have occurred in cases involving teenage young people, and a team structured to undertake case conferencing; A tool for operation managers to utilise to audit case files to provide assurance on processes and compliance Effective information sharing, regular communication, structured assessment of needs and carer reviews in place for a majority of kinship carers and a corresponding decrease in the number of complaints and requests for support by kinship carers; 54 The practical coverage of all Aboriginal and Torres Strait Islanders children and young people with cultural care plans, and reviews being undertaken for effectiveness; A detailed revised Supervision framework that is available for use across CPS – indeed CSD -, which is evidence-based and practically focussed drawing on experience gathered in the field; A majority of staff has been trained in effective decision making and have an operational framework to consider when in doubt; Stakeholders are aware of and utilising a complaints mechanism that is considering the complaints in a timely and meaningful way. Disputed decisions have a clear destination; can be reviewed by experts who are capable of providing advice and these options are embedded in the OCYFS structure. While this may not translate immediately to changes in outcomes across the board at the level of individual cases, these are critical steps to seeing such improvements over the longer term. Exceptions While there are positives, there continue to be some slippages as well. As at the end of May there are five projects that are reporting Amber (requires attention). These projects, including the mitigations, include 1.1 The Integrated Management System: the project is behind schedule and is demonstrating limited technical project progress scheduling due to resourcing issues and delivery delays. Additional scoping has been required to ensure coverage of the Auditor-General recommendations. To address these issues three new people have been applied to the project team, there is recruitment action under way for two more personnel, some clever IT work around adopting existing technology which may deal with the portal issue (effectively the adaptation of the Bimberi portal solution to DPS IMS), detailed negotiations on the Intake and Appraisal module are concluding and the remaining modules are less complicated and intricate. 1.4 Quality Improvement Tools - Viewpoint: The amber status reflects delays experienced early in the project that were caused by external factors. The project is moving at pace and is reaching implementation, albeit behind schedule. 1.6 Increased practitioner cultural competence -cultural identifiers: This subproject has been without a defined PM since commencement. Steps are being taken to scope the needs as time permits. This project may be integrated in a better scoped electronic record project. 2.1 Deliver out of home care strategic plan: The project manager was off this project for three months, and decision makers adjusted the optimal schedule downward by 12 months. The project is now progressing against revised milestone expectations and should achieve deliverable dates. On the upside PMO have provided some resourcing to assist delivery, the 2013-14 budget confirms $200,000 will be provided to the OOHC strategy, and a project to analyse baseline financials has been scoped with procurement under way. Assuming the PM remains focussed, resources are applied as agreed and the scope is not adjusted, then long term delivery is okay. 3.1 Embed complaints unit: there has been little technical progress and there are staffing issues to complete the final deliverable. Recruitment is underway. We have 55 also undertaken a detailed review of the project and this revealed most activity is now ‘business as usual’ so it will progress to finalisation. There are two projects reporting Red (unlikely to meet deadline): 1.4. Quality Improvement Tools - Health Passport: minimal progress has been recorded as the project manager has been allocated to a different function, in front line provision, since March. This is a direct consequence of vacancy increases. The project is being monitored and the manager has returned to the project in June. 1.5 Legislative Review: Originally the project was scheduled to have a decision making scoping document available by the end of February. Due to a range of factors, particularly the over allocation of the project manager, and a period of leave, the paper will not be ready until the end of June, early July. Related Processes Similar to the reporting for the first three quarters, there are processes that affect the delivery of the program outside of the control of the OCYFS but that interface with the progress of the PA2 program. The Auditor-General’s Report During the fourth quarter period OCYFS developed a Cabinet Submission and government response to the Auditor-General Report. At the time of creating this report, the Public Accounts Committee has not outlined whether it would be undertaking an enquiry into the report. Cabinet has approved the Government Submission proposed by OCYFS and it has been supplied to the Public Accounts Committee. The Submission was accompanied by a preliminary action plan. The action plan seeks to identify actions that have already been achieved, or are underway through an alternative process, identify those that have a need for medium term consideration and those that have a longer term horizon. OCYFS, through the Refreshing the Service Culture agenda, is considering the most appropriate vehicles to respond to the recommendations that are not already underway through the PA2 program and other OCYFS QA processes and the methods for addressing the gaps will be either new project responses, management actions in business unit planning or other activities that will address the issues raised. These responses, when defined, will be delivered based upon a prioritisation of resources, that largely follows the sequence: continue meeting statutory requirements under the Children and Young People Act re-assess the scope and deliver on the system level reforms already agreed and underway, such as this program of projects adjust business unit plans in OCYFS to incorporate ongoing savings requirements, adjust the business unit plans in OCYFS to incorporate required management actions to implement actions that improve outcomes commence any new project based responses. Budget 56 On June 4 2013 the ACT Treasurer presented the Budget for the ACT Government for 201314 (see: http://apps.treasury.act.gov.au/budget). As observed in the third quarter report, OCYFS had sought funding to support some of the PA2 program response. It is pleasing to report that: Funding of $200,000 for 2013-14 was provided for the Out of Home Care Strategy. This funding will assist develop the evidence base, scope an accreditation and regulation system and support stakeholder engagement; and Funding of $250,000 over the period 2013-14 to 2014-15 to upgrade the CHYPS System. This funding achieves the short term implementation of technically feasible changes and provides scoping funds for a whole system replacement. Concurrent with the new budget funding OCYFS will be participating in the whole of government savings agenda. The Government announced they were seeking to cease some initiatives, achieve general savings and undertake service re-profiling. The net effect of the Budget will be considered through regular business unit planning, looking through the lens of the Refreshing the Service Culture agenda, with a view to achieving the lowest impact on the operations of the OCYFS. The Future of PA2 Program As the new financial year approaches, there is an opportunity to revisit the overall program and project logic to refresh assumptions and inputs to ensure they remain valid and meaningful. Indeed, with substantial time since the commencement of the program, some projects have finished, some have been reshaped, some have slipped and new and additional pressures have emerged. To that end, there is a process underway to update the PA2 review response program. With nine projects effectively closed and one removed due to a shift in need, there will be nine projects remaining in the PA2 program in 2013-14. These are: 1.1 Develop Integrated Management System 1.4b Develop Quality Improvement Tools-Audit OOHC 1.4c Develop Quality Improvement Tools-Viewpoint 1.4d Develop Quality Improvement Tools-Health Passports 1.6b Increased Practitioner Cultural Competence - Cultural Identifiers 2.1 Deliver Out of Home Care Strategic Plan 2.3 Scope requirements to move to Electronic Record 4.3 CPS Training Program Refreshed and commenced 5.1 Legislative Review Of these nine projects, on current scheduling, six will be completed before the end of calendar 2013, including: 1.4b Develop Quality Improvement Tools-Audit OOHC 1.4c Develop Quality Improvement Tools-Viewpoint 1.4d Develop Quality Improvement Tools-Health Passports 1.6b Increased Practitioner Cultural Competence - Cultural Identifiers 57 4.3 CPS Training Program Refreshed and commenced 5.1 Legislative Review This leaves three that will go beyond calendar 2013, including: 1.1 Develop Integrated Management System 2.1 Deliver Out of Home Care Strategic Plan 2.3 Scope requirements to move to Electronic Record To assist with ongoing reporting and visibility of the project responses into 2013-14 three main steps will occur. For projects that that will be completed before 31 December 2013 project managers will be asked to submit a refreshed one-page ‘project overview’ before the commencement of 2013-14. This refresh will put forward a revised and firm timeframe for the remaining milestones and deliverables, identify any material dependencies and risks and consider an estimated residual budget for 2013-14. Of special note is that the Electronic Records project will be appropriately scoped, based on the success of the Budget negotiations, and to accommodate a range of ICT projects that are aligned with the notion of refreshed ICT. For projects that remain beyond calendar 2013 project managers will be asked to refresh the entire project plan. Again, the objective would be to ensure the projects remain clearly scoped toward a hard and achievable deadline, the risk plans are updated and the budgets are transparently outlined (including consulting and PMO resources). These project plans would be used as a living governance document, rather than a compliance tool, and would be used for progress measurement with the project manager. To support the project reporting and logic, a revised ‘program plan’ will also be provided to the Strategic Reform BOM for endorsement which narrates the program, realigns the projects into the Refreshing the Service Culture agenda and identifies the system level costs of the program. 58