EAST AYRSHIRE COUNCIL CABINET MEETING – 18 MARCH 2015 UPDATE ON PROPOSED CONSERVATION AREA REGENERATION SCHEME (CARS) FOR DALMELLINGTON & WATERSIDE (DOON VALLEY) CONSERVATION AREA Report by Acting Executive Director of Neighbourhood Services PURPOSE 1 The purpose of this report is to: update members on the outcome of the application to Historic Scotland for a Conservation Area Regeneration Scheme (CARS) for Dalmellington and Waterside (Doon Valley), to consider the way forward with regard to an application to Historic Scotland for a CARS for Dalmellington, and to consider the options for tackling vacant and derelict buildings in Waterside (Doon Valley). BACKGROUND 2 On the 4 June 2014 Cabinet agreed to submit a CARS 6 bid for Dalmellington & Waterside Conservation Areas to Historic Scotland and to commit £0.65M subject to the success of the bid, and to appoint a full time temporary CARS officer to deliver the project subject to the success of the bid and consultation with Trade Unions. 3 An application was submitted by the deadline of 31 August 2014, based on reports prepared by conservation accredited architects, quantity surveyors and other relevant professionals. The total proposed project cost was £1.849M with East Ayrshire Council providing £0.65M, the property owners providing £0.361M with the balance (£0.838M) to be made up from the funding bid to Historic Scotland. OUTCOME OF THE CARS APPLICATION 4 On the 12 January 2015 we received a letter from Historic Scotland advising that our application had been unsuccessful. However, Historic Scotland did indicate that as they did not allocated the full £10M of funding for round 6 that it is their intention to invite applications in 2015 from some of those schemes that were rejected and that they are content to discuss a resubmission for Dalmellington Conservation Area. However they considered that the inclusion of Waterside made the project too big and complex to be delivered through a single CARS bid with Dalmellington. PROPOSED WAY FORWARD 5 Some discussions have been undertaken with Historic Scotland following receipt of the decision letter but it is proposed that the Planning Service meet with representatives from Historic Scotland so that their advice regarding the future submission of a CARS bid for Dalmellington Conservation Area can be fully explored and taken on board. However from the discussions completed to date it is anticipated this is likely to require further technical and financial support to enable additional survey work on key buildings to be undertaken and to update and provide more detailed costs. It has also been suggested that further work should also be undertaken to engage more fully with property owners and to look at potential end uses for vacant buildings in the conservation area. It would be intended to resubmit a bid for a Dalmellington CARS by the end of September 2015, with a proposed scheme start date of April 2016 if the bid is successful. 6 As part of the submission to Historic Scotland, Draft Conservation Area Appraisals were prepared for Dalmellington and Waterside. It is intended to carry out public consultation on these drafts and once finalised that they be submitted to a future meeting of Cabinet for approval as non-statutory guidance to support the proposed East Ayrshire Local Development Plan. 7 Waterside Conservation Area including the area designated as a Scheduled Ancient Monument is of national importance but the condition of many of the remaining buildings is of very serious concern. Due to the number and size of vacant buildings in Waterside that are without any established end use Historic Scotland took the view that a CARS was not the appropriate way forward. Accordingly if there is a desire to save some of the nationally important buildings there is a need to explore how best to progress the regeneration of the area with both Historic Scotland and the current owners of the site. One potential key step forward would be to obtain support to undertake an options/feasibility appraisal with two main objectives, namely (1) to identify, for key vacant buildings such as the former Palace Bar, the railway station and blast engine house, a potential way forward and use and (2) to examine potential operational and management structures that need to be put in place by those with a responsibility for the site so that the site and buildings are not lost to future generations. Therefore, it is suggested that further discussions are held with the owners of the key buildings and community representatives and a separate report is prepared for a future Cabinet meeting on the way forward following these discussions. FINANCIAL IMPLICATIONS 8 Cabinet in June 2014 agreed to the provision of technical and financial assistance, as required, through the existing framework agreement to help prepare the information for the Dalmellington and Waterside CARS submission, at a maximum cost of £60,000, utilising funding from the Restoring Communities Programme. Approximately £41,000 was spent on the technical & financial assistance for the initial Dalmellington and Waterside CARS bid. To enable the resubmission of a bid for a Dalmellington CARS to be progressed (on the back of existing and future discussions with Historic Scotland) it is proposed that further funding, not exceeding £30,000, be allocated from available resources within the current 2014/15 and future 2015/16 Restoring Communities Programme budget. 9 The 4 June 2014 Cabinet also agreed to commit £0.65M for the Dalmellington & Waterside CARS scheme subject to the success of the bid. To give the resubmission of the Dalmellington CARS bid the best chance of success it is suggested that the Council revised contribution is based on the original bid minus that which specifically relates to Waterside buildings, this being a total of £0.563M. The total proposed project cost would be approximately £1.235M, seeking a contribution of £0.597M from Historic Scotland, and £0.075M from property owners. The Council funding would come from the same budgets as previously proposed (i.e. £0.2M from the Capital Regenerating Fund budget, and £0.363M from the revenue budget within the Restoring Communities Programme). It should be noted that projects supported by capital funds will be required to fulfil specific criteria, and in relation to revenue expenditure, if the bid is successful, that the reduced revenue funding of £0.363M to cover the Council’s contribution can be made available from April 2016 over a 5 year period from the Restoring Communities Programme. PERSONNEL IMPLICATIONS 10 Historic Scotland has indicated that a temporary full time qualified project officer would be required to deliver the resubmitted Dalmellington CARS, if the bid is successful as part of Historic Scotland’s minimum funding criteria. The Council’s experience in these types of regeneration projects indicates that a dedicated project officer would be required to deliver the Dalmellington CARS Project and ensure the best return from both the Council’s and Historic Scotland’s investment. The costs for appointing a member of staff to cover this project would be built into the grant funding bid, but would be required to be part funded by the Council from revenue identified in paragraph 9 above. 11 This full time post can be approved as required under the Scheme of Delegation. LEGAL/POLICY IMPLICATIONS 12 The duty to formulate proposals for the preservation and enhancement of Conservation Areas is contained within Section 63 of the Planning (Listed Building and Conservation Areas) (Scotland) Act 1997. 13 Draft Conservation Area Appraisals for the Dalmellington and Waterside Conservation Areas were prepared as part of the original bid submission. Once public consultation is completed and the Conservation Area Appraisals are finalised they will be submitted for approval as non-statutory guidance to support the East Ayrshire Local Development Plan. As such the guidance would be a material consideration in the determination of planning applications. COMMUNITY PLANNING IMPLICATIONS 14 The proposals are entirely consistent with the current and emerging Community Plan. RISK MANAGEMENT IMPLICATIONS 15 The main risk resulting directly from this report is the cost of the technical and financial assistance without any guarantee that the resubmitted Dalmellington CARS bid will be successful or that the studies in relation to Waterside will lead to the successful redevelopment and reuse of its buildings. However if the CARS application is not successful, the information will provide essential background information that will potentially assist the regeneration of the targeted buildings utilising other funding sources. If funding is not secured there is a distinct possibility, particularly in the Waterside, Dunaskin site, that some of East Ayrshire & Scotland’s rich industrial heritage could be lost. 16 If the application is successful all offers of grant will be subject to a condition requiring that “The Grantee shall take professional advice to ensure that adequate insurance cover exists to protect the existing structures and the contract works against all risks of loss or damage and to provide an indemnity in respect of all potential liabilities arising from the contract works, having first carried out the relevant risk assessments and ensured compliance with the Health and Safety at Work Act 1974 and those relevant statutory provisions made there-under.” This wording has been agreed with the Council’s Risk Manager.” RECOMMENDATIONS 17 It is recommended that Cabinet agrees: (i) to the provision of further technical and financial assistance as required through existing framework agreements to help prepare additional information for the Dalmellington CARS resubmission, at a maximum cost of £30,000, utilising funding from the Restoring Communities Programme; (ii) to delegate to the Acting Head of Planning & Economic Development the preparation and submission of a bid to Historic Scotland for grant assistance to establish a Conservation Area Regeneration Scheme for Dalmellington; (iii) to confirm in principle funding of up to £0.2M from the Capital Regenerating Fund budget to the Dalmellington CARS projects subject to the success of the bid; (iv) to confirm up to £0.363M of funding from the revenue budget within the Restoring Communities Programme to the Dalmellington CARS projects if the bid is successful; (v) to the appointment of a full time, five year temporary CARS post to deliver the Dalmellington CARS, subject to the bid being successful, ; (vi) To report back to Cabinet in relation to the way forward for Waterside following further discussions with relevant building owners and community representatives; and (vii) To otherwise note the content of the report. Chris McAleavey Acting Executive Director of Neighbourhood Services 13 March 2015 FV-DMcD (CMcK/KD) LIST OF BACKGROUND PAPERS 1. Cabinet Report – 4 July 2012: Marketing of 30-38 John Finnie Street, 1-3 Dunlop Street, & 12 Strand Street, Kilmarnock & Proposed Conservation Area Regeneration Scheme(CARS) for Galston Conservation Area, & John Finnie Street & Bank Street, Kilmarnock Conservation Area. 2. Cabinet Report – 4 June 2014: Proposed Conservation Area Regeneration Scheme (Cars) For Dalmellington & Waterside (Doon Valley) Conservation Area. Members wishing further information should contact Karl Doroszenko, Development Planning and Regeneration Manager, Tel: 01563 576751 Implementation Officer: David McDowall, Acting Head of Planning and Economic Development