OVERHEAD VS UNDERGROUND Presented by Mark Contor, Engineering & Operations Manager, Northern Lights Inc., May 2015 “Why not put all overhead power lines in underground?” This is a question that surfaces whenever there is a large wind or snow storm that damages overhead power lines and causes prolonged outages, or when someone objects to their trees being trimmed or feel the overhead lines are not aesthetically pleasing. A quick search on the internet will provide an astute and objective reader numerous credible white papers and business studies that can be perused and researched to generally provide a consistent answer. Some studies have been funded by states that are vulnerable to hurricanes and tornados, some are subjective opinion to support their argument, and others paint a one color fits all answer. Ultimately, it comes down to basic economic and operational factors for each individual utility and specific line based on their own unique and often complex characteristics. These complexities are not transparent or readily understood by the general public and can be even more confusing when neighboring utilities have different economic and operational characteristics. The following is a more in-depth look at many of these unique and complex factors as well as insight to NLI’s system and service area as well as direct bury vs. cable in conduit: Topography and Ground Conditions - Rocks, water table, wetlands, slope stability, valleys, mountains, rivers, etc. These conditions tend to be much more conducive to overhead power. Stringing wire up and over avoids the obstacles. It can be faster and less expensive. Actual replacement cost of overhead vs underground for each specific line segment depends on numerous things such as: How many taps, service drops and other manmade obstructions are involved i.e. phone lines, gas lines, paved roads / driveways, water/sewer lines, septic lines, private power lines, cable TV, fiber optic cables, manicured lawns, fences, buildings, ditches, culverts etc. Converting overhead to underground in areas congested with these obstructions significantly increases the cost per foot of underground. Rather than simply going over the top, crews spend considerable time locating, hand digging, directional boring, sometimes installing conduit, pull rope, below grade warning ribbon, installing shoring or sloping the excavation for worker safety, back filling and compacting trenches, pulling in cable and then landscape restoration. The 2015 projected price to replace one foot of existing Page 1 of 7 single phase underground cable with direct bury (no conduit) is $26.50 per foot. This is because since its initial installation 30 to 40 year ago we now have to deal with the above mentioned utilities and improvements. To rebuild a single phase overhead line costs about $16 -$17 per foot. As our member line density continues to increase these underground costs will also increase. How many accounts, taps, service drops does the line serve and what type of accounts (commercial loads)? The more service drops and taps the more costly to convert from overhead to underground. Underground pad mount transformers are about double the cost of overhead. Cable terminations cost a lot more and take more time to install. Pad mount (underground) load break or sectionalizing switches can cost 10 to 20 times more than overhead and there are not as many options in equipment or features. Longevity of line. Underground cable has lower life expectancy than overhead wire (sometimes 20 to 40 years less). Remaining life of existing overhead line. Replacing an overhead line with 15 years or more useful life is generally a low priority compared to replacing or repairing other aging infrastructure such as: existing outage plagued underground cable, old substations, antiquated power conditioning and sectionalizing equipment, upgrading and replacing generation facilities, replacing old poles where underground is not an option, tree trimming, replacing wore out equipment etc. Outage costs – What is the outage frequency, extent of damage, cause and outage duration. Sometimes overhead is better, sometimes underground is better. Who is paying for conversion or installation? Private developers or the utility. Is it a main feeder and how much load on the line? Can the line regularly be taken out of service for repair, additions or changes? Is the line regularly switched and used to shift load between substations. For operationally efficiency, cost and availability of equipment overhead is preferred, and it does not get buried in snow and brush. Generally, overhead electric service does not have to be taken out of service to cut in new services, install taps, transformers, and power quality equipment. Unless there is an underground junction hut with available space underground requires the line to be de-energized to add these features. This can be a huge issue if the line has a lot of load, a lot of members, commercial businesses, water & sewer, communications, schools etc. Service interruption can be avoided with underground if the utility has funding and right of way to install loop feeds to isolate the section of line being taken out of service. However, it is much easier to establish loop feeds in cities and suburban areas with blocked streets rather than rural areas which tend to be long radial feeds with no parallel or looping right of way opportunities. Would the overhead to underground conversion be direct buried or would it require conduit and spare conduit? Due to increased heating, cable in conduit significantly Page 2 of 7 increases the cost, both to install the conduit and because the heating reduces the ampacity of the cable which may require larger cable to compensate for the loss of ampacity which then also increases the size of the conduit. What are tree vegetation management costs for the segment of line being considered and or NESC required clearances from other structures? In some instances the additional cost of converting to underground may be justified because of narrow right of way and public safety concerns. Other Factors Include: System wide how much line would the utility have to convert? Many utilities similar to NLI started building out their lines in the 1930’s when there was virtually no reliable underground cable and equipment available. Consequently, the largest percentages of most electric systems were built out overhead. NLI’s system was financed over many decades through member aid to construction and low interest financing through the U.S. Department of Agriculture Rural Electrification Administration program. NLI has almost three times more overhead than underground. Its old underground is failing faster than its overhead. To convert large sections of existing overhead to underground is very expensive and not always practical. Unlike new line extension it does not generate new load or establish new territory and receives no aid to construction (financing) from developers or new members. Financing for these projects is only supported through electric rates and monthly service fees. Cost conscientious members and member elected Boards are reluctant to finance or increase debt to replace existing lines with no or very little return on investment or that don’t significantly improve power quality or increase the cooperatives equity. A cost that receives no consideration is the utilities huge cost to finance the Call Before You Dig law for buried facilities. To cover 3 states and 6 counties NLI has to pay 3 different one call services (811) to receive Call Before You Dig notifications. Then NLI pays either NLI personnel (including vehicle and equipment) or a contractor to actually field mark the cable location. In 2014 NLI received 6,200 locate requests that had to be screened by NLI dispatchers or contract locating services. Of these 6,200 calls NLI had to pay locating personnel to drive to the location, hook up equipment and perform almost 3,000 locates. The total 2014 annual cost for this was over $150,000. As underground facilities and human development expand this expense also increases. It takes longer and more equipment to locate underground faults than over overhead faults. After the specific location of the underground fault has been located the crew must notify dispatch who calls 811 Call Before You Dig. Then the crew waits about 2 to 4 hours on overtime before a locator(s) arrives to locate all the other buried utilities in the vicinity before they can Page 3 of 7 start digging to repair the faulted underground cable. This significantly increases the outage cost and the outage duration. Phone locates in Idaho generally require about 2 hours while Sanders County phone locates may take as long as 4 hours for the locator to drive from the east side of Missoula. This waiting time is often misunderstood by members without power who question crew productivity. Cost of wire Underground vs. Overhead (not including labor, equipment or terminations) - In 2015 underground 1/0, 260 mil wire was $2.20 per foot. Overhead 1/0 ACSR was $0.235 per foot. Underground cable includes a neutral wire so to fairly compare the cost of single phase wire you double the cost of the overhead wire which then makes overhead $0.47 cents per foot. However, for a 3 phase line there is still only one neutral so the cost per foot cost for 3 phase underground cable is $6.60 and overhead is $0.94. Underground transformers and junction huts routinely get damaged by snow plows. This is a problem at Schweitzer as well as all areas when there is a large snow event. Underground is much more vulnerable to lightning. Underground is out of site and damaged by excavators who don’t follow Call Before You Dig laws. This is similar to loggers and members falling trees into overhead lines. Because underground is out of site new property owners and contractors tend to be unaware or ignore our easement rights and encroach on our right of way when building, excavating, installing new roads and landscaping. They remove ground reducing required depth or place large amounts of fill or obstructions over the line. Years later when the encroachment is discovered it is hard to determine when it was done and who was responsible. This is similar to members who occasionally build under the overhead lines however these encroachments are easier to discover. Grounding - Long stretches of underground (especially in conduit) make it more difficult to install or add system grounds. Good grounding is essential for electric systems to operate properly. Underground can be more confusing to map and for line crews to determine feed directions. Underground is difficult and expensive to install in narrow road right of way corridors or where there is a lot of steep cut and fill slopes, other utilities, drainage ditches or fencing. Underground is very susceptible to washouts on steep slopes or sandy loams. Repairing underground in the winter when it’s buried in snow or under frost is slow and difficult. Outage Expense Overhead vs. Underground NLI Based on the total footage of overhead wire compared to the total footage of underground Page 4 of 7 wire over a 10 year period revealed there is no significant difference in cost. The average cost per ft. of overhead outages was $.0456 per ft. and underground was $.0458 per ft. Cost of Installing New Underground VS Cost of Replacing Old Underground New Services constructed with underground cable can usually be installed fairly quickly and is much less labor intensive than replacing old existing cable. The new member understands the ground is going to be disturbed and is responsible for any cosmetic clean up or landscaping rehabilitation. If there are road bores, poor plowing or digging conditions or other obstructions the member is required to pay to provide the ditch and conduit and pay for the directional bores and vacuum trucks. All these costs are the utilities responsibility when it comes time for cable replacement. And as previously stated after the cable is installed and additional utilities and improvements are made these costs significantly increase. Direct Buried Cable (DBC) VS Cable In Conduit (CIC) Direct Bury Cable DBC is cheaper and faster to install. Causes less ground disturbance at time of initial installation because it is generally buried with a plow tooth where CIC requires trenching, backfilling and compacting. Faster and cheaper to fix faulted cables or cut into for adding taps and services. DBC causes a lot more ground disturbance to replace which is problematic in yards and under driving surfaces. For this reason NLI usually requires lots in subdivisions to have cable in conduit. DBC does not offer the same amount of cable protection as CIC. With Direct bury the ground helps dissipate heating caused by current, whereas conduit traps the heat which reduces the ampacity of the wire and reduces the life. Direct bury cable can be replaced while leaving the existing cable in service. Cable in conduit requires the old cable to be de-energized so it can be pulled out and new cable installed. Cable In Conduit CIC is a lot more expensive to install. Pinpointing the location of faults in CIC is sometimes harder than DBC. CIC offers greater cable protection. CIC does not dissipate heat caused by current as efficiently as DBC and therefor the cable ampacity is less and or larger cable needs to be installed to compensate. When CIC faults and the cable needs to be repaired there are 2 options; 1) Cut the conduit and add a cable splice which is much faster, cheaper and minimizes outage time. However, once a splice is added the cable cannot be pulled out and new cable installed at a later time. Page 5 of 7 2) Pull the faulted cable out and pull all new cable in which takes a lot of time, and more money. It also increases the outage restoration time because it requires all new cable and terminations and requires more equipment. The advantage is the cable can usually be pulled out and replaced at a later date. Conduit (CIC) occasionally gets damaged or gets water infiltration. Over time this infiltration plugs the conduit and eliminates the ability to pull the old cable out and new cable in. Therefore, replacement sometimes requires trenching a new ditch and installing new conduit. Sometimes spare conduits are added to eliminate this problem. However, experience has shown after 15 plus year’s unused conduit is prone to getting broke and infiltration which renders it useless and ends up being a waste of money. To replace cable in conduit the crew has to de-energize the line to pull out the old cable and pull new cable in. The member is out of service during this time. This is not the case with direct bury cable. Overhead Issues Overhead is more susceptible to tree damage from wind and snow. Overhead is more susceptible to bird and squirrel caused outages. Overhead may be a concern with raptor related issues in certain areas. Aesthetically, the public prefers underground rather than overhead. Overhead requires more money to side clear right of way. Underground requires clearing but generally requires only minimal low level side trimming. Overhead presents additional concerns of tree related fires and public exposure to downed wire. NLI’s basic philosophy of replacing overhead with underground is determined by economics, operational efficiency, terrain and opportunity. That being said we have replaced several significant portions of outage prone overhead line with underground when conditions and timing make it economically feasible. These conditions typically include several of the following: Areas with a lot tree related outages. Overhead lines that have come to the end of their useful life or need to be relocated. Areas that have relatively favorable terrain and plowing conditions - Few large rocks, stable ground (no swamps, creeks, steep sandy slopes prone to washout etc.) Low member density. This reduces a lot of additional expense for hand digging, directional pipe bores, vacuum trucks to avoid damaging other buried facilities, and it minimizes the cost to convert, transformers, service drops and taps. Page 6 of 7 Lateral taps or lightly loaded feeder lines that do not require expensive sectionalizing and power conditioning equipment. Or don’t require frequent switching and load transfer between substations. Lines that are not in or adjacent to narrow road corridors with a lot of cut and fill slopes and don’t crisscross roads / highways, creeks, gas lines, phone lines, yards. We have converted several long sections of overhead to underground. Some were converted with FEMA funding during the ice storm of 1996/1997. Some were funded by NLI on long stretches of relatively flat terrain going through U.S. Forest Service land to replace old overhead lines. Some were done in conjunction with large developments, highway projects or where the developer contributed to the conversion. When terrain allows most new services are designed to be underground and we may require developers and new service applicants to install underground lines in areas that we know will be susceptible to tree related outages. As our aging overhead lines near the end of their useful life and underground cable technology and equipment improves NLI will look at opportunities to convert more overhead to underground where and when conditions are favorable. However, in NLI’s service terrain and for reasons mentioned above converting overhead to underground may not always be the most economical and operationally the best solution. Page 7 of 7