The State of Ohio Department of Transportation Project 10-8028 Daily Report HAR/HAN-68-10.62/20.01/0.00 Co-Rt-Sec Wed. 09-01-2010 Date Shelly Paving Supervisor Skilled Laborer Start Quit Total Ken Fern 4 6 06:30 a.m. 05:00 p.m. 10.5 hrs. Justin Pearson QC 07:00 a.m. 04:30 p.m. 09.5 hrs. Description of Work Ref Item Location 0007 407 (HAN) 06.070 mi ~ 08.110 mi, Lane 1 (Tack Coat) 0009 446 (HAN) 06.070 mi ~ 08.110 mi, Lane 1 (Asphalt Concrete Surface) 0019 614 (HAN) 06.070 mi ~ 08.110 mi (Work Zone Center Line) Weather Temperature 67o - 91o Precipitation 0.00” Rain Day? N Pay Items Ref Code Location Quantity 0009 01 (HAN) 06.070 mi ~ 08.110 mi, Lane 1 (Asphalt Concrete Surface) 0019 01 (HAN) 06.070 mi ~ 08.110 mi (Work Zone Center Line) 749.50 cy 2.04 mi General Remarks 407—Tack Surface was clean and dry; tack was sprayed w/clean nozzles; uniform coverage was achieved. See Spreadsheet for daily totals. 446—Surface Course Paved Surface Course from Hancock County 68 SB, Lane 1; 6.07 – 8.110 mile marker; 2.04 miles paved today (plus mailbox approaches and drives). Monday’s tonnage total 105.14 + 1511.00 = 1616.14 tons (TE217) Add today’s total with 614—Work Zone Center Line, Class II Striped 6.07 – 8.110 mi. marker Asphalt Pavement Check: 8.110 - 6.07 = 2.04 x 5280 = 10,771.2 x 15 x 1.5 = 242,352/12 = 20,196/27 = 748 x 2.016 = 1507.968 ton; contractor placed 1511.00 tons, for a difference of 3.032 tons, heavy Equipment---paver, 3-vibratory steel drum rollers, tack truck, water truck, foreman truck, pick-up, tractor w/ broom attachment, enclosed tool trailer, street sweeper, striper, and broker trucks **Larry Norris was on the job site today; and Dan Rettig stopped by the job site also. Employee 13204 Jeromy Piehl 13204 Jeromy Piehl 13218 Penny Kessler 13218 13218 Hours Reg. O.T. Remarks 4.5 3.5 Comp Used Penny Kessler 2.0 Paving Penny Kessler 1.5 Transport 446 cores to Test Lab Previous Day 8.0 Calendar Home Next Day