Alterations: RAF/2012/00027 Questions and Answers 1. Question Documents collection Answer Documents available and downloadable on the RAF website, under procurement: www.raf.co.za 2. Question What is the CIDB grade? Answer Minimum is CIDB GB grade level five or above. 3. Question Compulsory Briefing Session Answer Advertised compulsory briefing date is 01st October 2012 as published on the bid document on the 21/09/2012 and Sunday Times on 23/09/2012, The additional date 3/10/2012 for the briefing session was due to error made by government printing works not to publish the advertisement as requested by RAF on 21/09/2012, thus a decision was made to accommodate service providers. 4. Question When is the closing date? Answer Closing date has been extended from 15 to 22 October 2012 @ 11h00. 5. Question What is meant by Proposal on the implementation of the projects as per floor plans provided? Answer 1|Page This is a method of statement. 6. Question What do you mean Price/Unit? Answer Price per unit must be disregarded 7. Question Page 68 will you please just give me an example by filling the first column together with notes by Tenderer. Answer This are comments that the service provider will note if necessary. 8. Question How many copies do you need when we submit our Tender document on the closing day? Answer 4 copies plus original 9. Question Please provide notes on Floor plans Answer SIMPLIFIED SCOPE OF WORKS a) BASEMENT i. 85mm high Concrete floor slab ii. Fire rated dry walls iii. Fire Rated Double doors with door furniture complete. iv. Paint walls inside & out v. Paint doors both sides vi. Paint Ceilings vii. Light fittings & switches (incl. electrical work) viii. Ventilation b) GROUND FLOOR 2|Page i. ii. iii. iv. Fit power pole with 1 cluster (1 white, 1 red, 1 data) (including electrical work) Remove existing carpet tiles Prepare for new timber floor Supply and install new Beech ‘timber’ floor inclusive of transition strips c) FIRST FLOOR i. ii. iii. iv. v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. New dry wall (red) where indicated New doors complete with all new door furniture New glazed panels (900 and/or 1200mm high full height) New power/data clusters to Manager’s offices against brick walls (in existing power skirting) (including electrical work) New power/data clusters to Manager’s Offices against dry wall (pull into drywall and fit flush) (including electrical work) New power pole + power/data cluster to Manager’s offices constructed of screens only (purple) (including electrical work) New power pole with power/data cluster for each printer (including electrical work) New power pole with 2 x power/data cluster for each bank of desks (including electrical work) New power/data cluster to each meeting room in dry wall (including electrical work) New doors with door furniture complete. Paint dry walls inside & out Paint doors both sides New glazed shop front to match existing to close off the area between 2 columns next to meeting room. COC for electrical work 10. Note Add power poles 11. Question How is Preliminaries and General priced? Answer 3|Page As agreed with service providers during the two compulsory briefing sessions, the pricing will be standardised as follows: Please quote as per below categories in percentage. R0-R250 000 R251 000-R500 000 R501 000-R750 000 R751 000-R1 000 000 R1 001 000 – R1 250 000 R1 251 000- R1 500 000 R1 501 000 and above 12. Question Service Level Agreement Answer Please initial each page and sign; submit with the bid response. 13. Notice/Additional Information Floor plan packs distributed on the 01/10/2012 were wrong; please ensure that you have the right plans which were distributed from the 03/10/2012. 4|Page