PM-2.5 FEM Requirements for Met One BAM

advertisement
PM-2.5 FEM Requirements for
Met One BAM
Glenn Gehring, Technology Specialist
Tribal Air Monitoring Support (TAMS) Center
541-223-1402
[email protected]
To obtain a NAAQS designation
• FEM equipment must be operated in
accordance with FEM certification
• PM-2.5 network collocation and siting
requirements must be met
• You must follow your approved QAPP
(the QAPP must comply with all relevant CFRs)
Zero calibration at deployment
Collocation
Refer to: 40 CFR Part 58 Appendix A section 3.2.5
• 15% of PM-2.5 (FEM or FRM) sites must be
collocated (round up) – must have at least 1
• FRM collocation must be with same EPA FRM
method designation
• FEM collocation - 50% of the 15% required
collocations must be with FRMs and 50% with
FEMs of the same EPA FEM designation – The
first collocation MUST be with an FRM
• Must run FRM at least once every 12 days
[Most tribe will fall under the FEM (C) scenario where you have fewer than 7 sites and are
only required to have one collocated site for your PM-2.5 network. In this situation, if you
are using a FEM it must be collocated with a FRM. If your network needs two collocated sites
the second collocation must be with another FEM that has the same EPA FEM designation
number as the primary monitor. Basically, 50% of monitors used for collocation must be FRM
and 50% FEM (If FEMs are used in the network), with the FRM being first. If you need three
collocated sites the third monitor used for collocation must also be a FRM.]
PM-2.5 Probe Siting
Refer to: 40 CFR Part 58 Appendix E
• Overall probe height: 2–15 Meters above ground level (Microscale is 2-7
meters)
• Horizontal distance from obstacles: must be at least twice the height the
obstacle protrudes above the sampler inlet (two times the height
difference away) with at least 270 degrees unobstructed.
• Rooftop - horizontal distance from obstacles: at least 2-meters - should be
away from minor sources such as furnace, incineration or food service
exhausts flues – you should also avoid areas too close to residential areas
with wood burning stoves
• Horizontal distance from the dripline of a tree: must be at least 10meters and should be at least 20-meters.
• Collocated horizontal separation (for low vols): within 4-meters of each
other and at least 1-meter apart (you should also have a maximum of 1
meter vertical separation)
• Distance from road: 2-10 meters for microscale - see chart for other scales
PM probe distance from roads
Other PM-2.5 FEM Requirements
• Monthly flow verifications with NIST traceable
standards
40CFR58 Appendix A, Section 3.2.3
• Semi-annual flow audits (at least every 6-months)
40CFR58 Appendix A, Section 3.2.4
• PEP audits - 5 per year, minimum
40CFR58 Appendix A, section 3.2.7
• 75% data completeness
• Data Certification
• Maintained in accordance with manual
• QAPP compliance and appropriate documentation
http://ecfr.gpoaccess.gov/
Always check
with your EPA
Region’s Quality
Assurance folks
AND Refer to
the CFRs.
Download
Related flashcards

Elementary mathematics

20 cards

History of mathematics

17 cards

Mathematical analysis

32 cards

Special functions

14 cards

Numeral systems

15 cards

Create Flashcards