NJ Water Environment Association Dealing with Contract Claims John Napolitano & William “Mickey” Conway Johnson & Conway, LLP September 12, 2011 Agenda 1. Basics 2. Types of Claims 1.Claims by Contractor or Vendor 2.Claims by Owner 3.Claim Avoidance 4.Lien and Bond Claims 3. Litigation of Claims 2 Napolitano & Conway 4/8/2015 What is… A Contract Typical Contract • An agreement between two or more persons • Professional Services Contracts include agreements with Accountants, Engineers, Architects and Attorneys •Creates an obligation to do or not to do a particular thing. •Essentials • Competent parties & subject matter • A legal consideration mutuality of agreement and mutuality of obligations A Claim • To demand as one’s own or as one’s right; to urge; to insist; cause of action; demand for property or money • Procurement Contracts include agreements for the purchase of equipment, chemicals, supplies, etc. • Service Contracts include agreements for maintenance, laboratory services • Construction Contracts include agreements for improvements to real property, including installation and repair of pipelines and physical plant improvements 3 Napolitano & Conway 4/8/2015 Typical Documents Required •Bid Bond, as required by N.J.S.A. 40A:1121; 10% of bid amount, not to exceed $20,000.00 • Consent of Surety, pursuant to N.J.S.A. 40A:11-22; required for all improvements to real property in excess of $100,000 an unconditional guarantee to provide the required performance and payment bonds (Construction Contracts) • Statement of Ownership, pursuant to N.J.S.A. 52:25-24.2 •Subcontractor Identification Form, pursuant to N.J.S.A. 40A:11-16 (Construction Contracts) • Bidders’ Acknowledgment of Revisions or Addenda N.J.S.A. 40A:11-23(a) •Business Registration as required by N.J.S.A. 52:32-44 •Public Contractor’s Registration Form N.J.S.A. 34:11-56.51 (Construction Contracts) • Prevailing Wage Compliance Declaration N.J.S.A. 34:11-56.25 et seq. •Equipment Certification as required by N.J.S.A. 40A:11-20 (Construction Contracts) •Non-Collusion Affidavit as required by N.J.S.A. 52:34-15 •Bidder’s Corporation Resolution, evidence of the Authority to bind the bidder where bidder is a corporation or a partnership •Bidder’s Checklist for Mandatory requirements N.J.S.A. 40A:11-23.2 •Bidder’s Qualification Form, which is a series of questions regarding the bidder’s history and previous experience •Americans with Disabilities Act, 42 U.S.C. § 12101 •Affirmative Action - No Discrimination, N.J.A.C 17.27-5.2 4 Napolitano & Conway 4/8/2015 Typical Contract Terms •Types of Payments • Lump sum - contract is awarded based upon a single price •Scope of Work: a general description of the work that is anticipated to be performed under the contract or the goods to be supplied. • Unit Price - provides for payment • Integration of Contract Documents: based upon individual increments most contracts provide that the contract of work documents include the contract general • Allowances - contract provides conditions, the drawings and the each bidder with a specific dollar specifications. amount for work that cannot be • Subcontracts: most contracts provide adequately specified that the contractor agrees to bind each • Alternatives - additional or subcontractor to the terms of the general optional work that the owner may construction contract. want done; usually dependent • Permits: This sets forth who is upon price responsible for getting the permits for • Time of Completion: N.J.S.A. construction and who pays permit fees. 40A:11-17 requires that the amount of working days for each contract be specified. 5 Napolitano & Conway 4/8/2015 Typical Contract Terms cont. •Suspension of Work, no damage for delay provisions: N.J.S.A. 40A:11-11 provides that to limit a contractor’s remedy for the contracting unit’s negligence, bad faith, active interference, tortuous conduct or other reasons uncontemplated by the parties that delay the contractor’s performance to give a contractor an extension of time for performance under the contract is void under public policy. However, the provision can be drafted such to limit the contractor’s right to additional compensation to actions by the contracting unit and not third parties. •Liquidated Damages: A contract may provide for a daily damage amount for a contractor’s failing to complete the project on time. Liquidated damages are normally used when actual damages would be difficult to quantify and must bear a rational relation to what anticipated damages could be on the project. Extremely high liquidated damage provisions may be invalidated if a court determines that they constitute a penalty. N.J.S.A. 40A:11-11. 6 Napolitano & Conway 4/8/2015 Typical Contract Terms cont. •Prevailing Wages: A contract for construction, reconstruction, demolition, alteration and maintenance work shall provide that all contracts in excess of $2,000 in a case of an Authority and $10,750 in the case of a municipality shall require the contracting unit to pay prevailing wages for all contracts for work defined in N.J.S.A. 34:11-56.25 and require that certified payroll records be submitted to the contracting units for each employee on the project. •Indemnity Provisions. Most contracts provide to the greatest extent allowable by law the contractor shall hold harmless and indemnify the owner, its employees and engineers for any and all claims that arise out of the contractor’s performance of the contract, including attorney’s fees and cost of suit. 7 Napolitano & Conway 4/8/2015 Typical Contract Terms cont. Termination Provisions Termination for Default: contracts will provide for a termination of the contractor for his material failure to properly follow the contract specifications, violation of laws, failure to make adequate progress, general poor performance and bankruptcy of the contractor. These termination provisions must be carefully drafted and followed, including any and all notice provisions required. Generally, the termination provision will provide adequate notice be given to the contractor and a time for the contractor to cure his default. Termination for Convenience: this provision provides that an owner may terminate the contract for reasons other than the default of the contractor. Generally, it will provide that in the event the owner terminates the contract for its convenience, the owner is responsible to pay the contractor for all of the work the contractor has performed to date, including reasonable costs of termination. The AIA documents also allow for the contractor to be paid for his anticipated profits of the work not performed. Termination by Contractor: generally, the contract will allow a contractor to terminate its agreement with the owner in the event the owner’s failure to make timely payments in accordance with the contract provisions. Again, there is normally a notice provision which will allow the owner to cure any default. 8 Napolitano & Conway 4/8/2015 Typical Contract Terms cont. • Application for Payments •Changes to Work Provisions: a contract shall provide for changes in the • Payment for stored materials: work which were not originally as provided for in N.J.S.A. contemplated in the original design 40A:11-16.4 and/or scope of work. These provisions • Retainage - N.J.S.A. 40A:11normally provide that the contractor 16.1 limits retainage to two submit a price, either lump sum or unit, percent (2%) for contracts in for the changes in the work. The best excess of $100,000. practice would be that these changes be • Final Estimate Payments approved as to scope and price prior to provides for the release of the work beginning and an executed retainage, all documents that change order be issued. In cases where need to be provided including a price cannot be agreed to, many warranties, release of liens from contracts provide that the owner may contractor and subcontractors. direct the contractor to perform work on a time and materials basis. 9 Napolitano & Conway 4/8/2015 Typical Contract Terms cont. •Liens: provision addresses the times when a subcontractor or material man may file a lien against the project funds. •Maintenance Bond, supplying of a maintenance bond up to two years in accordance with N.J.S.A. 40A:11-22. • No Waiver Provision - a general provision that provides that in the event the owner does not enforce a specific provision during the course of the contract term, it does not waive enforcement of the provision in the future • Alternate Dispute Resolution Pursuant to N.J.S.A. 40A:11-50 all construction contracts must include an ADR provision as a prerequisite to filing a lawsuit. This provision does not apply to bid protests. • No Oral Agreement Provision - the contract may only be modified by a writing executed by all parties. • Insurance Provisions - Provides the types and amounts required for the contractor to provide. Usually requires the owner, employees and consultants list as additional insured on the policy. These provisions should be reviewed by the owner’s insurance consultant to determine if the policies as specified are generally available in the market place to contractors. • Warranty/Maintenance Period Typically contractor warrants that its work is in conformance with the specifications and drawings and agrees to repair any defective work for a period of one year. 10 Napolitano & Conway 4/8/2015 Bid Challenges – The Initial Claim cont Type 1 – Challenge to bid award The law requires that a publicly bid contract be awarded to the lowest responsive and responsible bidder or vendor. Challenger alleges that it is the lowest responsive and responsible bidder. A bid challenge to the award must be based upon a material aspect of the bid. The most common challenges refer to the failure of the low bidder to submit the proper paperwork with its bid. The typical nonwaivable defects are: •Failure to • submit a consent of surety. • submit an equipment list. • enclose business registration certificate. • enclose subcontractors identification form pursuant to N.J.S.A. 40A:11-16, statement of ownership pursuant to N.J.S.A 52:2524.2, bid bond as required by N.J.S. A. 40A:11-21. •Ownership Disclosure 11 Napolitano & Conway 4/8/2015 Bid Challenges – The Initial Claim cont Type 2 – Challenge to Specification When a bidder or supplier at least three days prior to the bid opening file a challenge to the specification usually alleging the specification unfairly favor a particular contractor or product. A successful challenge will result in a rebid with revised bid documents. 12 Napolitano & Conway 4/8/2015 Claims by Contractors or Venders In order for a contract claim for additional compensation to be valid, the contractor must prove both entitlement and actual damage. To show entitlement, the contractor must show that claim resulted from events or situations not the fault of the contractor and measurable additional expense. 1. Extra Work – The simplest claim for additional compensation usually arises when contractor alleges it was required to perform work or supply items that were not set forth in the bid documents 2 .Differing Site Conditions - The contractor alleges the situation it encountered in the field was different from that which was indicated in the bid documents and as a result it incurred additional expense. 3. Delay Claim – The contractor alleges the project has taken longer than scheduled and as a result it incurred additional costs 13 Napolitano & Conway 4/8/2015 Claims by Contractors or Venders cont 4. Weather Delays – The contractor alleges as a result of unusually severe weather the project completion was delayed or its productivity was reduced causing additional expense. 5. Time Extensions – A request for additional time to complete the project it may or not include a request for additional compensation 6. Municipal Mechanics Lien – A claim by the general contractor or subcontractor for money it earned but was not paid. It places a lien on the contract funds in the possession of the owner. 7. Prompt Payment Claim – A claim by a contractor that owner failed to make payment in a timely manner as required by statute. The law entitles the contractor interest on those payment not made timely. 14 Napolitano & Conway 4/8/2015 Claims by Owners 1. Liquidated Damages – A per diem amount as set forth in the contract the owner is entitled to from the contractor for each day the contractor is late in completion of the work. Delay in completion must be the fault of the contractor. 2. Warranty Claim – A claim by the owner, as provided for by agreement, to have a contractor or manufacturer repair defective or broken work. Owner does not have to prove fault. It occurs after the project is completed and accepted and within the warranty period. 3. Defective Work – A claim by the owner that the contractor did not construct or supply work in accordance with the bid documents. The owner must prove the contractor was at fault. 15 Napolitano & Conway 4/8/2015 Claims Avoidance 1. Contract Documents – Proper planning, investigation and review of the contract documents will limit claim; spend the time and effort to develop a complete set of contract documents. 2. Schedule – Establish a rational project schedule for the project completion; tract the contractor submitted schedule and modify as necessary during construction. This will allow the owner to determine whether any delays are the result of contractor or owner actions. 16 Napolitano & Conway 4/8/2015 Lien & Bond Claims 1. Liens on Public Jobs (2A:44-126) a. Who can file: GCs, Subs and second tier subs and suppliers. b. Lien rights for certain public improvement projects are governed by the Municipal Mechanic's Lien Law (2A:44-126). Only certain public projects in New Jersey can be liened, those considered to be “municipal” projects: where the owner is a county, city, town, public commission, public board or municipality. Projects owned by the State and its subdivisions are not lienable. N.J.S.A.2A:44-126. c. To preserve the right to file a lien on a Municipal job the contractor or supplier must file a notice within 20 days of the first performance of the work or delivery of materials. The notice must be filed with the municipal clerk, or appropriate official (depending on the owner.) N.J.S.A. 2A:44-128. d. State and state subdivision jobs- no lien rights. 17 Napolitano & Conway 4/8/2015 Lien & Bond Claims cont 2. Bond Claims by Subs and Material men- Prior to commencing work or delivering materials, a subsub-contractor or supplier who may be beneficiary on a bond must prefile a notice to preserve its right to make a claim against a payment bond on a public job. Prior to delivery of materials notice must be filed with the Contractor by certified mail that Doka is a beneficiary under the bond. N.J.S.A. 2A:44-145. As owners, not so concerned about this b/c they are claims against the bond. 3 . Default- Performance Bond Claims Work: where contractor is in material default exercise rights under Performance bond to have bonding company complete the project a) What is material defaultcontractor terminates performance without justification; material deviation from schedule; failure to make payments to subs; uncorrected problems with the work; bankruptcy insolvency of contractor b) How to Proceed- after cure period expires, notify bonding company and require Bonding Co to Perform; bonding company steps in shoes of contractor. 18 Napolitano & Conway 4/8/2015 Litigation of Claims 1. Litigation v. Arbitration 1. Contract Arbitration/Agreed Upon Arbitration 2. Pros and Cons- Arbitration less discovery, fewer depositions and motions, etc. Also may get to Arbitration date faster; Litigation- easier to schedule (attorneys have to abide by court mandates vs consent scheduling in arbitrations); Cost paying for arbitrators 2. Litigation Procedure- Timing- process 1. Bid issues and other construction claims often commenced with an Order To Show Cause- abbreviated litigation schedule 2. Complaint- standard mode of commencing case; Answer due in 35 days, other parties can be brought in 3. Discovery- process by which information is exchanged between parties. 1. Interrogatories are written questions, must be answered 2. Document demands call for exchange of documentation related to claims and defenses 3. Depositions- question and answers between attorneys and key witnesses 4. Expert reports and depositions- key to most construction cases are experts 4. Motions- discovery issues; summary judgment; motions in limine 5. Trial- timing, witnesses, jury/non-jury 19 Napolitano & Conway 4/8/2015 Litigation of Claims cont 3. Preparation for litigation of Claims 1. Record keeping- organization of all job records including emails, meeting minutes, correspondence, requisitions, invoices, delivery slips, etc. Key because this is how the case is won and lost; when potential claims ariseattorneys should be involved in creating and preserving paper trail 2. Spoliation Issues- under NJ law, must be careful correcting defective work without notice to the defaulting contractor. Must provide an opportunity to correct and then, if not correct, provide opportunity to observe, photograph and document existing conditions prior to demolition, correction or covering up same 3. Experts- if not using own professionals consider claims or other expert prior to litigation (during job if large potential claim exists) 4. Indemnity Clauses- often determines who pays for litigation and who defends. Different types of clauses (indemnify and/or defend, option of owner, etc) dictate terms. 20 Napolitano & Conway 4/8/2015 Litigation of Claims cont 5. Settlement Agreements- 95% of all cases settle. Some important terms to include in settlement agreements: 1. If work is contemplated in settlement agreement, it is essentially a new contract. Need scope and all protective clauses or refer to existing terms of contract. If extra payments for work, make sure within contract/LPCL threshold. If Bonding company is taking over work or finishing, avoid documents that release BC or its contractors from liability. 2. If payments from any party to owner or from GC to subs, include default provision in case payments are not made. Default should include automatic judgment, attorney’s fees and costs and interest and escalated settlement amount. Also look for personal guarantees in the event of payment. 3. Look to recover costs incurred to owner through existing contract provisions 4. Reason for settlement- juries unpredictable; avoid precedential bad decisions, very expensive, staff time, also at times jobs are ongoing so settlement helps get jobs completed which is key objective 21 Napolitano & Conway 4/8/2015