Strategies for Rapid Scale up of Nuclear Capacity U C Muktibodh Executive Director (Engg.) NPCIL 5th Nuclear Energy Conclave, New Delhi 06 Sept 2013 Inspiration for Growth • • • • Electricity Demand Clean source of energy Sustainability Energy security Present Status of Nuclear Power REACTOR TYPE AND CAPACITY CAPACITY (MW) CUMULATIVE CAPACITY(MW) 20 reactors (18 PHWRs+2BWR) at 6 sites in operation at Tarapur, Rawatbhata, Kalpakkam, Narora, Kakrapar and Kaiga 4,780 4,780 2 PWRs under advanced stage of completion at Kudankulam (2x1000 MW) 2,000 6,780 PFBR under construction at Kalpakkam (1 X 500 MW) 500 7,280 Projects construction Launched (XI Plan) KAPP-3&4 (2x700 MW PHWR) RAPS-7&8 (2x700 MW PHWR) Total by 2017 2,800 10,080 MW Nuclear Capacity – Under Construction & Planned in XII Plan 22,700 MW (Construction + Planned) 2000 MW Advanced Stage of completion 3300 MW 17,400 MW(Planned) Under construction •Planned to be launched in XII Plan- •KAPP-3&4 : •2x1000 MW LWR, Kudankulam, TN •KK-1&2 : ( 2x700 MW PHWR) •2x1650 MW LWR , Jaitapur, Maharashtra 2x1000 MW LWR •RAPP-7&8 •2x1500 MW LWR: Kovvada, AP (2x700 MW PHWR) •2x1100 MW LWR : Mithi Virdi,Gujarat •500 MW PFBR •2x700 MW PHWR : Gorakhpur,Haryana Units under construction will be completed in XII Plan . •2x700 MW PHWR :Chutaka,M.P •2x700 MW PHWR :Mahi-Banswara, Raj •2x700 MW PHWR : Kaiga,Karnataka •2X500 MW FBR: Kalpakkam, TN •1X300 AHWR: Site being identified NPPs in Operation & under Construction Gorakhpur, Haryana NPPs under Planning PHWR Site LWR Site FBR Site 2 X 700 MW Chutka, MP 2 X 700 MW Mahi-Banswara, Rajasthan 2 X 700 MW Mithi Virdi, Gujarat Kovvada, AP 2 X 1100 MW 2 X 1500 MW Jaitapur, Maharashtra 2 X 1650 MW Kaiga, Karnataka 2 X 700 MW Kalpakkam, TN 2 X 500 MW Kudankulam, T.N . 2 X 1000 MW Nuclear Power Programme • Three stage nuclear power programme • PHWRs in the first stage Pressurised Heavy Water Reactors • Evolved through plant sizes of 220, 540 to the present 700 MWe • Matured indigenous technology with impeccable safety record • Standardised plant size of 700 MWe • Standard plant design • Exploring single or two standard seismic designs • Use of Integrated Engineering Environment tools for engineering • Project implementation through Mega ePC packages • Target construction period of 5 years FOR 2012-13 A.F = 90.43 % Continuous Run (more than a year) RAPS 5 - 400 days (continuing) Year Wise Electricity Generation 35000 30000 Million Units 25000 20000 15000 10000 5000 0 Series1 2008-09 2009-10 2010-11 2011-12 2012-13 14927 18803 26472 32455 32863 Light Water Reactors • LWRs, as additionalities, being implemented through international collaboration. • Business model formulated for optimisation of cost and for meeting design & safety requirements. Strategies • Public outreach programs • CSR activities • Early Site selection and commencement of Pre-project activities • Design standardisation • Supply chain support • Project implementation Support from Industry • Indian industry has developed capability to supply NPP equipment & components • The rapid expansion programme will require industry support for maintaining supply chain for high quality equipment, meeting project schedules. Conclusion • NPCIL is poised for the rapid expansion programme • Synergy between NPCIL and Indian industry is a key element to meet the programme • The programme can be realised in a national mission mode with the support of all stakeholders THANK YOU