Nuclear Inter Jura 2014 ROSATOM Rosatom State Nuclear Corporation Legal aspects of the BOO model when developing new nuclear power plant and construction projects Ilya Smirnov, Deputy CEO, General Counsel Olga Kirillova, Senior Legal Counsel 21 October 2014 Akkuyu NPP Power Generation JSC Factual background ROSATOM AKKUYU NGS AŞ 435 nuclear power plant units are under operation around the world 72 nuclear power plant units are under construction around the world (10 units – since 2013) Only one NPP (4 units) is under construction under the BOO model 2 TOPICS COVERED AKKUYU NGS AŞ ROSATOM Types of project models Akkuyu NPP project structure Major challenges Lessons learned Questions 3 Newcomers AKKUYU NGS AŞ ROSATOM which way to follow Turkey Bangladesh Vietnam Jordan Nigeria Belarus Kazakhstan Egypt … 4 Akkuyu Nuclear Power Plant is the First Rosatom BOO Construction Project Outside Russia AKKUYU NGS AŞ ROSATOM Akkuyu Project Features • First Nuclear Power Plant in Turkey • First Rosatom ВОО (build-own-operate) project. Under the IGA, Rosatom is responsible for engineering, construction, operation and maintenance of the plant. • Legal basis: Intergovernmental Agreement, May 12, 2010 • Project design: AES-2006 (VVER-1200) • Total capacity: 4,800 MW. (4 x 1200 MW) • Implementation period: 2011-2023 • Total cost ~ $ 20 bln • Power Purchase Agreement for 15 years, fixed price terms • Support of the Russian and Turkish Governments • Maximization of Turkish personnel construction and operation of the plant. • Job creation potential – up to 10 000 for the construction only involvement Akkuyu site, Turkey 5 in Project Cooperation Between Russia and Turkey Covers a Wide Range of NPP Related Construction, Operation and Infrastructure Issues ROSATOM Russian / PC responsibilities Joint responsibilities AKKUYU NGS AŞ Turkish responsibilities NPP engineering, design field supervision Construction and assembly works Site allocation Construction management/ Supervision /Startup and Commissioning Physical protection Infrastructure development, grid connection Design documentation Emergency planning Nuclear island and other special equipment and materials Public outreach Fuel supply Ownership of NPP until decommission Site infrastructure Spent fuel management (subject to a separate IGA to be concluded) Operation, maintenance and upgrade Wholesale of electricity Decommissioning and decontamination Financing Nuclear liability insurance Radioactive waste disposal / treatment 6 Project organization structure AKKUYU NGS AŞ ROSATOM Board of Directors (shareholders) Rosatom State Corporation Project sponsor PC management General responsibility for Project implementation Rusatom Overseas CJSC Shareholder/ developer Akkuyu NPP JSC Tailor-made JSC incorporated in Turkey. Carries functions of customer, license applicant, NPP owner and GR coordinator in Turkey Operator, Owner of the NPP and electricity produced Owner’s Engineer* • • • • Technical expertise Cost control Schedule control Quality control OJSC «INTERRAO Worley Parsons» Rosenergoatom Concern OJSC Technical customer Licensing consultant • • EPC 1** Hydrotechnical * Tender will be tentatively run in 2014 ** EPC structure to be further discussed EPC 2** Nuclear island EPC 3** Turbine island Development of technical assignment for the design documentation Technical acceptance of equipment and services at all stages of project commissioning, NPP operation EPC 4** Auxiliary buildings 7 Equity Structure AKKUYU NGS AŞ ROSATOM Paid Capital – 4.36 Billion TL (source – Russian budget) Current Shareholders of AKKUYU NPP JSC Subject to consent to the Turkish Party under IGA 8 Stages of the project Single responsibility of the “Project company” for all stages of the project and deadlines 1 stage 2 stage Preparation Construction 3 stage O&M 4 stage Decom missio ning 13/12/10 2017 Akkuyu NPP JSC registration 03/11 1st concrete 2083 2017 Start site Construction survey license, Electricity generation license Commissioning 2023 – 1 unit 2024 – 2 unit 2025 – 3 unit 2026 – 4 unit 9 Lessons learned: Regulatory The comprehensive Nuclear Energy law and the Law of Civil Liability for Nuclear Damage need to be adopted Challenges in understanding of local regulations and their implementation Possibility of changes in regulations without consent of NPP owner No experience of the Turkish Party in regulating and licensing of NPP New electricity law market Lack of understanding of “nuclear” by government agencies and companies challenges Public fear of nuclear 10 Lessons learned: Regulatory Setting up regulatory base prior to licensing Acceptance of the regulatory base of the supplier country in case of lack of host country base Established effective system of consultations with government bodies and relevant agencies Working groups on the key issues of project implementation and NPP operation INIR mission to Turkey (November 2013) Work with public opinion Student’s education, training for officials, regulatory bodies’ personnel Assistance in development of regulatory basis and regulatory agency expertise SOLUTIONS 11 Lessons learned: Host Country Undertakings Challenges No responsibility of the host country for Meeting deadlines in decision making which may lead to schedule delays Cost overruns in case of delayed construction Issues touched upon by the IGA but referred to separate IGA’s that may be concluded in the future Cooperation regarding the nuclear fuel cycle Reprocessing spent fuel of Russian origin in the RF 12 Lessons learned: Host Country Undertakings Setting forth the financial responsibility of the host country for ensuring infrastructure solutions (INIR) Local government owned companies among equity partners Country guarantees to purchase fixed amount of electricity at a predetermined price Alternative to treasure guarantees – entering into a Host Government Agreement Negotiating follow up IGA’s or Host Government Agreements 13 Lessons learned: Amending local laws IGA Local laws 14 Strategy of Operating the NPP Open Issues ROSATOM Option AKKUYU NGS AŞ Challenges and Limitations 1: Who is employed at the NPP? 1.1. 100% Akkuyu staff 1.2. Own operating staff, outsourced supporting staff 1. Development and implementation of business processes 2. Language of operation (initially Russian) vs language of examination for licensed operators (???) 3. Recognition of diplomas and engineering qualification 4. Licensing in Turkey of the personnel educated in Russia 2: Who provides outsourced services? 2.1. Concern Rosenergoatom 2.2. Foreign provider 1. Contract to provide operating services 2. Authorization by TAEK 3. Liability (incl. nuclear) of the service provider 4. Requirements of TAEK to be developed 15 Strategy of Operating the NPP In-house vs. Outsource ROSATOM AKKUYU NGS AŞ Own Operating Personnel Outsourced Services (while retaining knowledgeable customer capability): Physical Protection (except for own Security Service) Administrative and supporting functions Repair and maintenance work, replacement of spent fuel Transportation logistics Retail sale of electricity Rad waste management Training of personnel Metrology and monitoring 16 HR Strategy General Considerations ROSATOM General Considerations Staffing: 1. 2. 3. 4. 5. AKKUYU NGS AŞ Safety Quality Economic Efficiency Industry benchmarking Availability of qualified local personnel in Turkey 1. Deputy CEO for Operations (new open position introduced into the org.structure) 2. His direct reports: • Chief Engineer • Director for Safety and Quality Control – dotted line reporting to the CEO 17 HR Strategy Open Issues ROSATOM Local staff vs Expats? Development of specialized higher education in TR vs training at the Akkuyu Training Center AKKUYU NGS AŞ 1. What is the optimal headcount of the NPP (currently 0.8 person per 1 Mwt)? 2. Where shall we hire people from? 3. How Much – Where – When: What level of personnel localization in different categories of employees can (should) be achieved at the initial phase, in 5 years and in 10 years? 1. Program of training of licensed personnel (required for application to TAEK for the construction license – burning issue for Q1 2015) 18 AKKUYU NGS AŞ ROSATOM AKKUYU NGS AŞ İlginiz için çok teşekkür ederim! Thank you for your attention! www.akkunpp.com