SEMICON/Japan Industry Briefing December 5, 2012 Executive Summary • The Program has achieved critical momentum • Tools selected for program demonstrations – Broad coverage of tool set and Supplier base – Tool optimization added to program scope • Coordinating across Industry on precompetitive opportunities Global 450mm Consortium • A public/private program based at the College of Nanoscale Science and Engineering in Albany, NY • Driving effective industry 450mm development – Coordinate test wafer capability supporting development – Demonstrate unit process tool performance – Improve tools with Suppliers to ready for customer operations • G450C Members – – – – – – CNSE / Research Foundation GLOBALFOUNDRIES Intel IBM Samsung TSMC G450C Program Organization GM/VP and Coordinator Paul Farrar, CNSE VP/GM, Industry / Strategy VP/ GM, Internal / Operations Frank Robertson, Intel John Lin, TSMC Director, Integration (Samsung) • • • • Director, Program Lithography Coordination Engineering Director (GLOBALFOUNDRIES) (Intel) Etch Engineering Director (Samsung) CMP/Thermal/Cleans CVD/PVD/Implant Engineering Director Engineering Director (TSMC) (IBM) Co-directors, Fab Operations (CNSE/TSMC) Industry consortium coordinated by not-for-profit entity Leveraging New York State funding, matched by all industry participants Broadly-shared management of Program execution >60 staff on board now; >150 by 2014, with ~60 Supplier engineers on site 4 Development and Technology Intercept Targets G450C Program Early 450mm Development Early Development of Silicon and factory integration / automation standards, interoperability test beds for component and standards verification; early tool development ISMI 32/22nm Equipment Performance Metrics Test Wafers to support development and demo Tools for Consortium Demonstrations (unit process) 14nm G450C Demonstrations 450mm and 300mm tools progress synchronously through technology generations 10nm and beyond Ready for IC Makers Nominal “nm” = ITRS M1 Half Pitch Full set of process and metrology, automation ------ 2010 2011 2012 2013 2014 2015 2016 5 Test Wafer Support for Tool Development 2011 2012 2013 Tool Demo / Improvement Supplier Tool Development Alpha 2014 Beta Pre-production Increasing scope and complexity of process / metro capability Wafer pool coordination for multiple use, re-use, reclaim Bare Wafers G450C TW Metrology Cleans, Blanket Films, Etch, etc. Imprint /Spacer doubling, 300mm Coupons 193i on 450mm Manufacturing Execution Systems, Engineering Data Collection and analysis tools, Virtual Fab logistics for globally-distributed tool set 6 Demonstrations Drive Tool Improvement 2012 2013 Development 2014 2015 2016 Tool Ready for Customers Demo Tool Tool Improvements as Indicated by Pareto Supplier Testing Increasing tool maturity and data-based confidence EMA Report G450C Demo Baseline Report Demo Report Tech Transfer EMA Test Plan MDC Gauge Study PDC DOE Marathon Standardized methods and consistency across all tools 7 450mm Equipment Development Tool Selection Overview • Immediate objective: – Select at least one Supplier for Priority 1 and 2 tools for negotiation of Demo / full flow @ CNSE • Criteria: – Technical and commercial scores from RFQ – Balance across competitive Supplier base – Benefit to all Members and NY State • Process: – Research Foundation RFQ – Member selection teams used pre-agreed criteria – Management Council approved recommendation Closing deals with selected Suppliers 10 450mm Cleanroom in CNSE (NFX) Cleanroom ready by January 2013; First tools installed March 2013 450mm OHV is ready, could carry 300mm FOUP in 450mm inter-bay 4 stockers with 1000 bins ready in Feb 2013 G450C 11 G450C Test Wafers/ Operations Wafer Availability • Initial order for 6000 sc-Si (SEMI M76) – Growing capability to meet 2013 need • Initial order for 2000 cast wafers (SEMI M74) – Provision for wafer handling needs • Bring up additional supply in 2013 – > 15,000 wafers and progress to prime quality (SEMI M1) needed next year – Exploring engagement with multiple Suppliers Establish roadmaps for cost / quality learning 13 Wafer Industry Support Model • Suppliers providing tools for the program get access to test wafers at significant discount to individual purchase • Program expansion: – Suppliers without tools in the program can also get discounted cost if they return wafers and provide data – Suppliers may take advantage of program volume aggregation to procure wafers at consortium cost • Wafer pool managed for budget, allocation to needs • Pass on our costs beyond program capabilities for TWs Adjust for wafer costs, reuse/regen, scrap rates, etc. 14 Wafer Cost Sharing • To support 450mm development and maintain Consortium budget, wafer cost will be shared with industry • G450C will be loaning wafers for a given duration, at a shared cost (wafers available for purchase at 100% of G450C cost) • G450C cost share represents a considerable discount from independent small volume purchases • Factors for cost share will include usage/needs, reuse/regen, wafer loan duration, scrap, etc. • Test wafer process/metrology capability ‘Menu Card’ being developed for industry needs For wafer request/loan discussion, more information available at: http://www.g450c.org/wafer-loan.aspx 15 Wafer Quality Continues to Improve Defects / Wafer 2010: > 3000 defects/wafer 2011: ~ 175 defects/wafer 2012: ~50 defects/wafer August 2012: ~5 defects/wafer recent ~ 66 Defects per wafer reducedusing significantly Year-to-year comparison >90nm defect sizeMost recipe @ 38nm (@ 90nm sensitivity) Migrating to 40nm and below sensitivity 16 Wafer Quality Roadmap & Reclaim Capability Wafer quality roadmap 2012 1H 2013 2H 2014 1H 2H 1H Mechanical Wafer 2015 2H 1H 2016 2H 1H 2H M74 Spec Q2, 2013 Test / Mon Wafer Prime Wafer M76 Spec •SFQR meet (~90% area) •Particle (~70% pass rate) Q2, 2014 M1 Spec Q1, 2015 Epi Wafer M62 Spec Wafers meet SEMI spec FEOL wafer reclaim capability Supplier side Process Film G450C On-site ★ Tool/service Poly SiN PR 10 11 12 2013 1Q 1 2 2013 2Q 3 4 5 2013 3Q 6 7 8 2013 4Q 9 10 11 12 ★ Oxide FEOL 2012 4Q Cleaning tool Supplier ★ ★ ★ 17 Test Wafer Routes (Menu Card) Front End Route name Route Description 5 Oxide film - thermal 110A A Oxide film - thermal 1000A B Oxide film - thermal 5000A 4 Oxide film - PECVD 1000A D Implanted wafers E PR wafers F PR wafers + implant G PR wafers I patterned wafers J Nitride film - LPCVD 1000A K Nitride film - LPCVD 2000A L Poly film (1000A) M Poly film (3000A) O Nitride film - PECVD 200A Q TiN film (1000A) V Bare wafers W Bare wafers Mechanical Metals Route name Route Description 4a Oxide film - PECVD 1000A C Low-K film N Ni film P TiN film (600A) R W film S TaN film T Cu films U Al film Vbe Bare wafers Metrology Readiness • Metrology capability expanding to support virtual test wafer operations Tool Type Forecasted Ops Ready In Japan Forecasted Ops Ready in New York Advanced Bare Wafer Inspect Operational Operational Ellipsometer/ Scatterometry Operational 1st Tool Operational 2nd Tool Ready December 2012 4 pt Probe Operational Operational Supplier Hosted Metro Site AFM January 2013 Operational TXRF January 2013 Operational Opaque Film Thickness Operational Operational Macro Inspection Operational Operational Defect Review SEM March 2013 May 2013 April 2013 19 G450C Operations - CNSE Cleanroom 11 tools installed in NY cleanroom, 3 in progress Existing space allows for 3-4 additional metrology tools incoming 2H’12 / 1H’13 20 20 On Site Equipment Progress - Films PECVD Uniformity example SiN Thickness uniformity SiN: 5.06 % 1.46 % Ox: 14.5 % 1.62 % Throughput Compatible to 300 mm Ox Q2, 2012 Q3, 2012 5.06 % 1.46 % 14.5 % 1.62 % 21 Wet Clean and Wafer Recycling Wet Cleaning: Optimizing early tool Bar brush Recycled Recent optimization oxide wafer: Front side Back side 22 On Site Equipment Progress: Defects Particle Inspection A: on site • Passed qualification (in July) – Current particle sensitivity 38nm – Continue improving to 30nm Particle Inspection B: off site • To be moved in soon – Bare Si wafer particle sensitivity demo < 30nm – Target sensitivity at ~ 25nm 23 Summary and Opportunities – Test Wafer Operations Summary • • • • • • Silicon supply capability improving across the industry G450C operations have resulted in cleaner wafers Proven logistics in place, continuous improvement underway Processed wafer loans increasing Multiple Wafer Carrier suppliers in place and progressing well G450C expanding equipment base in existing clean room Your Opportunities • Leverage G450C Wafer Bank to accelerate your equipment development • Engage G450C for wafer loan requests via website http://www.g450c.org/wafer-loan.aspx 24 Lithography Update G450C Lithography Tool Roadmap 2012 2H 2013 1H 2H 2014 1H 2H 2015 1H 2H 2016 1H 2H 300mm Imprint 193i Coupon, EUV Coupon 193i patterning access at Supplier site Positive 450mm Imprint + Spacer Coupon + Imprint Potential G450C tool @ CNSE Lithography Strategy • Imprint solution before optical lithography available – Imprint + Spacer extends resolution to 14-15 nm (2013 - 2014) • Pull in early 193i tool to 2H14 • Expect 193i Litho full demo capability 2015 - 2016 Working on an Industry solution to accelerate 450mm scanner development 28 Imprint as Interim Patterning Measure 450 mm tool is completed, operational by end of 2012 Explore spacer process to extend ~20nm to 10 nm Litho, Etch, Films engineering team developing templates and processes to prepare patterned test wafers Work with Suppliers to build up complete process Coupons – 193i / EUV Imprint 30nm 1:2 40nm 1:2 29 300mm Nano Imprint Performance Good CDU, Line edge Successfully etched SiN & APF Poly Spacer etch on-going Good CDU, LER; Profile OK, Rdl ~15nm Coating at Supplier site Solving particle issues Working on re-work issue SiN & APF (amorphous carbon) etching 450mm Nano Imprint Status 450mm tool is ready in Nov, (Austin) –tuning process Template design: 22nm ok, verify 14nm capability Poly spacer for pitch doubling – on going Negotiate 1st phase patterning wafer capacity in Austin 450mm Demonstration Test Methods (DTM) Equipment Performance Metrics (EPM) • “1X nm Range” technology targeted for 2013-14 G450C demonstrations – “ITRS 14 nm Nominal” – Snapshot in continuum of technology progression – Performance of 450 mm and 300 mm tools advances in lock-step • Update Process (by end of 2012): – Suppliers propose competitive performance at ‘14 nm” without revealing sources of guidance or disclosing customer IP – Consortium staff take best Supplier proposals for each tool type to propose EPMs – Consult with Suppliers for aligned output – Validate EPMs meet Member Companies needs • Implementation – Ensure Demo test plans allow for full range of tool performance – Report the data for each tool with comparison to Demo EPM 34 Updated Equipment Performance Metrics Millisecond Anneal Example Attribute 14nm targets for demo Units Metrics sec 1E-4 ~ 1E-1 (0.1msec to 100msec) C/sec > 1E+4 Peak temperature Within Wafer uniformity (3σ ) C <10 Mean peak temperature Wafer to wafer uniformity (3σ ) C <5 Center-to-edge variation through ramp range C < 10 Pulse width (measured at peak-50C) Ramp-up Speed (250 - 1350C) Agreed with all Suppliers Publish update by EOY Ramp-down Speed (1350C to 650C) Overshoot (250C - 1350C) C/sec > 100 C <2 Setting Time (250C - 1350C) to within 1% of set point sec < 1E-5 Slip-free process at maximum temperature C 1300 (1350) Residual oxygen concentration (400-1100C) ppm <5 Defects, PWP On bare Si ≥ 30nm, mechanical transfer only #/cm2 < 0.0028 Defects, PWP Backside on Si ≥ 50 nm, mechanical transfer only #/cm2 < 0.28 Defects, PWP On bare Si ≥ 26nm (with process) #/cm2 < 0.007 Defects, PWP Backside on Si ≥ 50 nm (with process) #/cm2 < 0.28 Demonstration Test Methods (DTM) Overview 36 Demonstration Test Methods (DTM) DTM Components Duration 2-6 months • Equipment Maturity Assessment (EMA) includes a couple of dozen parameters with clear categorization of the tool characteristics based on defined criteria, as well as compliance with applicable standards; output is a report recommending pre-test actions and testing levels • Test planning is based on the tool maturity, goals for reliability, throughput of the tool and confidence objectives, combining any Supplier pre-data with demo testing via Bayesian statistics • Gauge Studies run for all metrology needed for the demo to ensure adequate Precision/Tolerance ratios • Mechanical Dry Cycle (MDC) - nominally 5000 cycles of the wafer movement functions without process for reliability and mechanical handling defect data • Passive Data Collection (PDC) - a test of process stability on a baseline recipe for each application. • Initial data is analyzed and a Baseline Characterization Report issued; decisions are made about subsequent testing or reversion to tool development to address any hurdles • Sensitivity Analysis - DOE optimization of the recipe(s) and RSM characterization of the process window(s) • Marathon - 24/7 manufacturing simulation to capture tool productivity and reliability performance using E10 states over a significant period, running process with sample testing to capture rates/variability, defectivity and tool-specific performances like step coverage, gap fill, LER, etc.. • A final report is drafted, the Supplier has opportunity for comment, recommendations for tool improvement are made and demo is completed with web publication 37 Demonstration Test Methods (DTM) Standardized Reports Executive Summary Demo Test Background • History and previous testing • EMA Report • Test Plan Test Results • Process Capability Performance − Gauge study − PDC − Sensitivity Analysis (SA) − Marathon Test • Equipment Performance − MDC − Marathon Test • Others − CoO, Standards compliance, software & user interface, factory integration Conclusions Supplier Input 38 Compliance with SEMI Standards Required (www.semi.org) • SEMI E5: SECS II • SEMI E30, E30.1, E30.5: GEM ("Fully GEM Compliant" as well as GEM Compliant per section 8) • SEMI E37: HSMS • SEMI E37.1: HSMS-SS • SEMI E39, E39.1: Object Services Standard: Concepts, Behavior and Services • SEMI E40, E40.1: Standard for Processing Management (PJM) • SEMI E87, E87.1: Specification for Carrier Management (CMS) • SEMI E84, E84.1: Specification for Enhanced Carrier Handoff Parallel I/O Interface • SEMI E90, E90.1: Specification for Substrate Tracking (STS) • SEMI E94, E94.1: Specification for Control Job Management (CJM) Stream 7 Process Program Management for recipes (E5, E30) Definition and measurement of equipment reliability, availability, and maintainability during program testing will conform to SEMI E10-0304 39 100% Compliance to Safety/Ergo Requirements Self-audit completed and findings released (all medium to high risk nonconformances are to be addressed): • S2-0200: Safety Guidelines for Semiconductor Manufacturing Equipment including Operational Hazard Analysis covering tool installation, operation and maintenance (per S2-0200) completed for tool install operation / maintenance • S8-0308: Safety guidelines for ergonomics engineering of semiconductor manufacturing equipment • Environmental Characterization Data Summary Work Sheet 6 per International Semiconductor Manufacturing Initiative (ISMI) guideline #06124825A-ENG completed and provided electronically prior to shipment It is an absolute requirement that all equipment must be safe to operate and maintain at any stage of maturity Equipment spare parts and modules must either be small and light enough to handle safely during maintenance, and clearances adequate, or ergonomic handling aids must be provided 40 Further Standards-related Requirements • Footprint, height and weight dimensions of the Equipment as well as the move-in packages must conform to SEMI E72 specifications • The Equipment loadport must have a RF ID reader compatible with RFID tags (model numbers TIRIS multipage MicroTag RI-TRP-DR2B) on the FOUP per SEMI E99 • The system must have adequate PGV docking interface exclusion zone per SEMI E64-0600 modified as needed for the SEMI E154 450mm load port • The Equipment configuration must have a minimum of one load port that confirms to latest revision of SEMI E154 • The Equipment load port must be capable of receiving 450mm FOUPs confirming to SEMI E158. • The Equipment load port must be capable of receiving lots delivered by 450mm Personnel Guided Vehicles (PGVs) G450C will require SEMI M74 Mechanical Wafer, M76 Developmental Test Wafer and M1 Prime Wafer Standards and use SEMI-compliant carriers for all program test wafer pool /demo purposes 41 Facilities-Related Standards • The Equipment must comply with the current versions of the (U.S.) National Electric Code - NFPA 70 and Uniform Fire Code - NFPA 79 • The Equipment must be designed to SEMI F47 “Specification for Semiconductor Processing Equipment Voltage Sag Immunity” • All Equipment and materials which will come into direct contact with the wafer or FOUP should be grounded per SEMI Spec E78-0706. • All Equipment enclosures must have an IEC ingress protection rating of IP31 or better • SEMI E6-1296 facilities interface datasheets completed and provided electronically prior to shipment It is recommended that the 450mm Equipment is designed to EU regulatory requirements including, but not limited to, Machinery Directive 98/37/EC, Pressure Equipment Directive 97/23/EC, Electromagnetic Compatibility Directive 89/336/EEC, and Low Voltage Directive 73/23/EEC as applicable 42 Industry Collaboration and Engagement Global Supply Chain Ecosystem Example: G450C Linkages Core G450C Program Process & Metrology Guidelines & Requirements Regional Tool Suppliers not in G450C core program Regional 450mm Opportunities Wafer Pool Wafer Suppliers Tool Suppliers w/G450C Demos • Component Suppliers • Infrastructure Providers EEMI 450 Adjunct Tool Demos and CIP projects KSIA I450Metro … + R&D entities: FhG IMEC … Standardization Opportunities Global Standards Regional Cooperation G450C Program Activities EHS optimization Guidelines Compliance testing Facilities optimization Equipment optimization Discussion this week with ESG-J Facilities Council Standardization WG G450C Groups Back End (Die Prep) WG TBD: Harmonize microcontamination specs TBD: Metrology collaboration 46 Precompetitive Cooperation • Identified top facilities project objective with M+W • Identified top standardization focus areas with SEMI • Defined pilot project: tool installation at CNSE with adaptor plate and consolidated points of connection • F450C membership defined and first meeting with G450C rolled out project priorities toward proposals • Workshop planned with SEMI, F450C and G450C for early 1Q13 to explore further work • 14nm EPM update with standards guidance based on Supplier tool agreements to be published by end of year 47 Top Areas for Precompetitive Cooperation with SEMI and F450C (first targets) • Top Standardization interest areas – – – – – Aisle space / width, ceiling height General sizing/loading/dimensions EMO interface, control architecture Crane, gantry Templates • Top facilities project interest areas – – – – – – Gas interface boxes, VMBs, cooling water manifolds, etc. Minimize facilities POCs Standard hookups for power, PCW, CDA, PV, GN2, exhaust, datacom Improved AMC detection/response Pumps and pump frames, etc. He recycling (Backside cooling ), H2 recycling (EUV) 48 TEL Facilities Cost Reductions in Albany 49 G450C Page 50 Summary • G450C has launched with full industry momentum • Significant progress towards the 450 mm transition is continuing in all areas of the supply chain • Collaboration and synchronization remain critical for a cost effective and timely 450 mm transition 51 Questions and Discussion 450 mm Reference Materials Location and Contact Information • Guidelines and other public documents, including Wafer Loan Program Details, Demonstration Test Methods and Equipment Performance Metrics can be found at: http://g450c.org • For further information or to engage in opportunities with the Global 450 mm Consortium program: Dave Skilbred G450C Program Coordination Director david.skilbred@g450c.org 518.441.7656 53