) August 16, 2012 Presented By: Teresa Driskell • • • • This course will provide an introduction to the written instructions for administrating an FDOT project found in CPAM How to use the Specifications for a Contract A brief update on the July 2010 Specification Workbook How to use the Standard Index CPAM provides for… • Uniform treatment of all Contractors • Consistent handling at all levels • Keeps Contracts valid and enforceable CPAM can be found online on the State Construction Office website at http://www.dot.state.fl.us/construction/manuals/ManualsMain.shtm The people responsible for writing each section are shown adjacent to each section CPAM is now published as a Single Searchable to Printable File!!! Now you can actually find the whole manual – Quickly! Pre-Construction Construction Post-Construction Purpose Authority Background Definitions General Addendums Guidance Documents / Flow Charts • Scope Development • Phases of plans review Phase I Review (Roadway) Phase II Review (Roadway) and Bridge plan reviews Phase III Review and Stage 3 (90%) Bridge Plans 100% Plans • Checklist Guidance Document 1-1-A • Initiating Specification/Alternative Contracting Techniques Flextime Special Working Hours & Periods Special Events Schedule Compressed Time or Time Priority Incentive/Disincentive No Excuse Bonus Time plus Money (A+B) Lane Rental Liquidated Savings Special Notices/Directions to Contractor • Guidelines for Establishing Contract Duration http://www.dot.state.fl.us/construction/SchedulingEng/GuidellinesForEstabli shingContractDuration.pdf • • • • Documentation Prosecution Training Forms • Guidelines for Community Awareness Process • • • • Contractor’s Schedule Schedule Distribution Schedule Revision Withholding Progress Payments • Affected Parties Comprehensive list but not limited to • Scheduling After receipt of Notice of Award and prior to any work beginning • Notice Errors and Omission Clarification of plans and special provisions Dispute Review Board members Florida Department of Environmental Protection – File number • Agenda Guidance Document 3-1-A Sample Preconstruction Conference Agenda (1) Project Description. (2) Delineation of lines of authority. Names and emergency telephone numbers for the Contractor, Department and others will be entered into the record and established issues escalation matrix. (3) Proposed Starting Dates - Contractors and subcontractors -- flextime (selected projects) - lead-in time and number of shifts or extra hours they propose to be working, etc. (4) Each utility representative to give an up-to-date report of the status of utility adjustments, relocations, removal, and new installation. In addition, the utility representative shall furnish the names and phone numbers of contact persons who will be available on call. A Contractor/utility meeting schedule shall also be established. (5) Contractor to discuss errors and omissions in the plans that are known to exist. Preconstruction minutes should reflect the Contractor's knowledge of errors or omissions in detail. (6) Maintenance of traffic plans review and discussion. (Remind Contractor, plans must have written approval before construction activities can begin.) Also, Alternative Traffic Control Plans must have written approval before work begins. (7) Construction schedules and progress chart submittals. When appropriate, establish meeting schedules (weekly-monthly) and locations to discuss job progress and to determine controlling work items for the next review period. Reiterate that schedules should be submitted within 7 calendar days before the monthly estimate cut-off date. (8) Business and Community Impact Plan. (9) Hurricane or other emergency evacuation plans should be discussed (i. • Training Requirements MUST have completed training directly related to the operation being inspected • Documentation Become familiar with Contract Documents Know what is required and how the finished product is evaluated Know how payment will be made • Preparation for Inspection Pre-Operations Meeting Record-keeping preparation Equipment Preparation • Documenting the Inspection Daily Work Report • Guidance for approval / disapproval of QC Plan Excellent checklist available in this Section for this purpose • Responsibilities • Format • Sample Letters • Project Specific and Regional DRB Member Selection Three Party Agreement Meeting Use of the DRB Payment • Request for Hearing • Preparation for Hearing • Recommendation of the Board • Role of Consultant CEI The authority of the CCEI’s lead person, such as the Senior Project Engineer, and the Project Engineer shall be identical to the Departments Resident Engineer and Project Engineer respectively and shall be interpreted as such. • Pre-Service Phase to evaluation • Performance Standards – Attachment 4-1-1 • Identification of Errors, Omissions, or Contractual Lapses • Initial Assessment of Responsibility for Errors, Omissions, or Contractual Lapses • Consultant Contract Termination • Daily Work Reports (Technicians) This Section has an excellent list of items to be included each day on a Daily Work Report • Diary (Project Administrators) Become familiar with Contract Documents Know what is required and how the finished product is evaluated Know how payment will be made • Affidavit The signed and notarized affidavit shall become a part of the contract file. • Contractor Failure Withholding of payment Suspension or Revocation of Contractor’s Certificate of Qualification Section 5.3 Subletting of Contract • Sublet Agreements are approved at District or local Resident Office Contractor uses Form No. 700-010-36 • Notify the PA of any violations Section 5.4 Contract Wage Requirements • Required on Federal-Aid Projects over $200,000. • Certified Payrolls must be submitted by Contractor Must include Statement of Compliance • Failure to Submit Required Records may result in suspension of further payments Section 5.5 Equipment Rentals • Notification to PA in writing of intent to use rental equipment via Form No. 700-010-11 • PA will cross check any Notices of Rental Agreement with DWR for equipment/operator information Section 5.6 Utility Relocation • When Utility Work is performed by the Contractor • When Utility Work is performed by the Others The Utility will bear the cost of the work Required to follow FDOT Standards Utilities required to follow Utility Accommodation Manual & Permit • Non-Reimbursable Utility Work The Utility will bear the cost of the work Most Utility work falls within this category Utilities required to follow Utility Accommodation Manual & Permit Record all activities on Daily Work Report Complete the Notice of Utility Construction Work, form No. 700-010-48, at the beginning and end of non-reimbursable work. • Reimbursable Utility Work Department pays to relocate Record all activities on the Daily Work Report Daily Work Reports will be used to verify UAO’s invoice for payment – Utility Work Agreements and Certification Process; Procedure No.710-010-050 Complete the Notice of Utility Construction Work; Form No. 700-010-48 • Fed Approval on Supplemental Agreements and contract changes Fed and non-Fed quantities • Construction Zone Accident Reports Engineer’s Maintenance of Traffic Evaluation at Crash Site, Form No. 700-010-64 • • • • Buy America Product Certification – Change of Source FHWA Final Inspection Notice to FHWA of Final Acceptance • Job Guide Schedule • Methods of Acceptance • Defective Materials Review Article 6-4 of the Standard Specifications PA will process with a Disposition of Defective Material (DDM) Form No. 700-011-01 The same process will apply when an Engineering Analysis Report (EAR) is required Attachment 5-8-1, Resolution of Defective Material Flow Chart • Process Reviews • Major Categories (asphalt, base concrete…) • FDOT VT verifies Contractor’s QC according to the Job Guide Schedule • FDOT Technician provides the Random Numbers for testing • FDOT Technician verifies the Random Samples Guidance Flow Charts Available • Certification Disbursement of Previous Periodic Payments to Subcontractors, Form No. 700-010-38 • Notice of Non-payment • Processing for Falsification of Payment to Certification Section 7.2 Time Extensions Two Main Groups • 7.2.5 Other Reasons Additional Work Added by Supplemental Agreement • Controlling Items of Work must be delayed 50% or more of the day • The Work Plan or CPM Schedule calls for work on that day • Work has started on the project Other Time Extensions • The critical path must be negatively affected • Flow chart and Sample Letters at the end of Section 7.2 • Contractor’s Time Extension Request, Form No. 700-010-56 Section 7.3 • • • • • • SA’s and Unilateral Payments Used for Extra or Unanticipated Work Used to settle Disputes or Claims Quantity Overruns Requires Certification of Funds from Comptroller Project Limit Extensions Specification Changes Labor Equipment Material Complete in duplicate and give one copy to the Contractor at the end of each day Section 7.3 SA’s and Unilateral Payments • Funds must be encumbered prior to SA being executed or notice to proceed given to the contractor • HB 1681 (2005) no need for SA on quantity overruns Original Contract Amount of $5 million or less – 2.5% Allowable Unencumbered Overruns Amount Original Contract Amount over $5 million requires encumbrance Federal Aide Participating/Non-participating Section 7.3 SA’s and Unilateral Payments • Supporting documentation for SA’s and UP Entitlement Analysis and Engineer’s Estimate see Guidance Document 7-3-A Daily Work Reports Letters Project Schedule Contract documents Section 7.3 SA’s and Unilateral Payments • Sources of information Certified Labor Burden (Spec. 4-3.2.1) Certified Equipment List (Spec. 100.1) Notice of Intent to file Claim DRB recommendation Statewide averages Guidance Documents and sample letters at the end of Section 7.3 Section 7.4 Contingency Supplemental Agreements and Work Orders • Contingency Pay Items/SA Maximum funding amounts Initial Contingency Amount Pay Item Contingency Supplemental Agreement Certification of Funds Availability No additional contract time Section 7.4 Contingency Supplemental Agreements and Work Orders • Work Orders Shall not be executed prior to the Contingency item Description and Reason Numbering Entitlement Analysis and Engineer’s Estimate Negative Work Orders - LS Project Limit Extension Section 7.5 • • • • • • • • Construction Contract Claims Recognition Claims involving a Utility Documentation Claim File Analysis of Claim Package Entitlement Analysis Claim Settlement Claim denial/Appeal Guidance Documents and Sample Letters at the end of section 7.5 Section 8.1 F.A.I.N. Resolution • Federal-Aid Ineligibility Notice Failing to meet the specifications Unqualified staff Material sample failures Buy American • How does it work Section 8.2 Environmental Commitment Compliance • Assures effective environmental compliance within all areas of environmental concern during the construction project Section 8.2 Environmental Commitment Compliance • PA Notifies Permit Agencies and District Environmental Office of permit activity start/end date. • PA monitors Permit Expire Dates – Notify District Permit Coordinator 6 months before expiration – if the project will not be complete by then • PA surveys treatment area/structure elevations for as built plans and permit closeout Section 8.2 Environmental Commitment Compliance continued When the Technician finds non-compliance: • Notify the PA • PA will direct the Contractor to correct the problem immediately • PA may issue a stop work order for activity causing serious problems Section 8.2 Environmental Commitment Compliance continued National Pollutant Discharge Elimination System • Where NPDES permits apply PA gets Contractor Signature on Contractor Cert/Prep of Docs – NPDES General Permit for Discharge Form No. 650-040-05 • Prime and subs working with erosion control devices – 650-040-07 • Must be signed by Owner or Officer • False Cert subject Owner to Fine/Prison Section 8.3 Operation Within Railroad Right of Way • Formal documents are handled by PA, RE and District Rail Coordinator Approved RXR Protection Plan Liability Ins for self and subs 72 Hour to 45 day notice approval from Rail Road • The Contractor must notify the RR when working in the vicinity of the tracks – including under the tracks. No exceptions unless approved in writing by the RR. Section 8.3 Operation Within Railroad Right of Way • Notice of Reimbursable/Nonreimbursable Utility Construction Work, Form No. 700-010-48 used for work done by RXR on a Reimbursable Agreement on projects involving work by RXR staff &/or RXR contractor. • Federal dollars held until pavement markings and advanced warning signs in place and in “good shape.” • PA must note “good shape” condition of RXR MOT devices in Remarks section of Utility Work Form No. 700-010-48 for Federal Approval. • The PA prepares the Post-Construction Inventory Report, Form No. 700-010-49, for National RXR-highway Crossing Inventory at completion of work. Section 8.4 Shop and Erection Drawing Process • Handled by Contractor, EOR, PA, State and District Design Staff. • Standard Specification 5-1.4 & Plans Prep Manual (No. 625-000-007, Volume I, Chapter 28) • Details – What is required of the players during the process is covered very comprehensively Section 8.4 Shop and Erection Drawing Process Project Engineer’s Role Monitor/Encourage/Log • Monitors – Who in the Review chain has the shop drawings • Encourages – Players to stay on schedule • Logs – Maintains Updated Tracking Logs of Drawings in Approval process. Flow charts at the end of Section 8.4 for Structural and Nonstructural drawing approval process. Section 8.5 Contract Delinquency Handled by PA, RE, DCE and CO • Time is up and the work is not complete • Can suspend qualification = to late days • Can suspend qualification of affiliates from who the Contractor derives material support – Staff/equipment/finances • Affects Contractor’s future Capacity Section 8.6 Contract Default When Defaulted… A Contractor • May be removed from the Job site & replaced with the Surety • Has no right to Administrative Hearing • Continues to be liable for LD’s until completion • Where the Surety Refuses work or becomes unreliable the Department may seize materials and equipment on job and hire others to complete. Section 8.7 Contractor Non-Responsibility for Construction Contract Contractor who demonstrate an inability or unwillingness to comply with contract requirements in a timely and proficient manner on a project will be declared non-responsible. Resident Office function is to make recommendation. Section 8.8 • • • • • • State Arbitration Board Creation of the Florida Legislature Use only after Final Acceptance If DRB exists it must have been used Claims ˂ $250K Law requires Up to $500K can be agreed to by both parties Up to $1 Million per contract can be agreed to Either party may request it to be binding Section 8.9 Contract Termination MAY BE DONE FOR ANY REASON by the FDOT District Construction and Central Office Function Section 8.10 Noise and Vibration Abatement • Involvement by Technician, PA and RE Section 8.11 Contractor Initiated Submittals • NCR, RFC, RFI, RFM and CSIP • Monitor • Process • Track • Section 8.11.8 Tracking Logs 17 key items listed for consideration in REQUIRED electronic spreadsheet • Departments Traffic Control Plan At Pre-con Contractor must furnish a letter stating he will be utilizing the Department’s plan or substituting an alternative • Alternative Traffic Control Plans Contractor may not start work until that Alternative plan is approved by Resident Engineer and added to the contract by SA Must by signed and sealed by a Florida PE Must be submitted on 11” x 17” set of plan sheets • Modification of Active Traffic Control Plan NO TCP Mods – except Enhancements or Emergencies before the RE approves Enhancements are defined as “not changing traffic patterns” Mods Must be approved and added to the contract by SA • Design Standards – especially 600 Series • List of trained flaggers must be submitted to PA prior to construction • Maintenance of Traffic Review Report 700-010-08 Worksite Traffic Supervisor (WTS) signs the report Contractor conducts inspections daily (including nighttime reviews) Contractor submits the MOT report weekly PA reviews Always show when deficiencies are corrected (See page 3 of MOT Review Report) • Recommended action to shut down a project due to MOT deficiencies Severe hazard or life threatening – correct immediately . Failure to correct the hazard immediately is basis to shut down the project. Deficiencies in which the contractor has been given written notice – correct within 24 hours. If not corrected PA shall deduct payment for the uncorrected areas from the date shown on the MOT Review report – Form No. 700-010-08. The WTS shall be disqualified is corrective action is not completed within the 24-hour time limit on 3 notifications in 12 months. • Other Requirements Inspect MOT operations provided by Utility within the project limits (when required by contract) Count and certify approved each day devices Project personnel (CCEI or in-house construction) will report crashes occurring within the project limits as described in Section 9.3.5. WTS will coordinate with adjacent projects WTS/Contractor will check reflectivity of payment markings and in the event of failure, provide for re-application of the pavement markings as required by Specification section 710. • Provides for Standardization of Regulatory Sign placement in the Work Zone • PA notifies PIO two weeks in advance of new regulatory speed limits will be posted and notified again when all signs are in place • PA make sure Contractor removes any conflicting signs • Any traffic crash occurring in the Work Zone is reported to the PA • Form No. 700-010-64, Engineers MOT Evaluation at Crash Site is completed by the PA or delegate • If MOT devices may have contributed to the crash, Contractor makes changes needed (CPAM 9.3.6 and 9.3.8) PA and RE must approve changes • Fatality or any disabling injury occurs, or there is a serous crash involving 3 or more people, notify District Safety Office by phone immediately • FHWA “Alert Bulletin Procedure” criteria for immediate reporting death of 5 or more persons 10 or more vehicles school bus fatalities or disabling injuries Interstate closed for more than 6 hours Major road closed for more than 24 hours District Safety Office will report to State Safety Office then to FHWA Section 10.1 Pile Lengths Section 10.2 Prestressed / Precast Concrete Components • Section established procedure for obtaining production lengths and driving criteria • Provides a written process for dealing with defective components Section 10.3 • • • • Concrete Construction Describes Bridge Deck thickness checks Mass Concrete Plans and Pours Crack Inspections Concrete Pre-Operation Meetings and Pour Notices Section 10.4 Paint/Asbestos Removal, Handling and Disposal • Specific Qualifications are required by both Contractor and Technician to perform this work Section 10.5 Drilled Shafts • Section established procedure for obtaining drilled shafts lengths outlines requirements for Drilling Logs Section 10.6 Underwater Bridge Construction Inspection • Section describes Initial, Progress and Final inspections Section 10.7 Post-Tensioned Bridges • A MUST READ FOR ANYONE WORKING ON THIS TYPE OF BRIDGE Section 10.8 Auger Cast Piles • Only used for noise wall foundations on FDOT Projects Section 10.9 Structural Steel and Misc. Components • Section provides process for evaluation and disposition of major defects Section 10.10 Bridge Issues that MUST involve SCO • Describes bridge construction issues and when/how to involve the SCO Section 10.11 General Structures Construction Issues • New Section added in June 2010 establishes procedures to notify District Structures Material Office of in-service dates, inspections and load ratings Section 10.6 Underwater Bridge Construction Inspection • Section describes Initial, Progress and Final inspections Section 10.7 Post-Tensioned Bridges • A MUST READ FOR ANYONE WORKING ON THIS TYPE OF BRIDGE Section 10.8 Auger Cast Piles • Only used for noise wall foundations on FDOT Projects Section 10.9 Structural Steel and Misc. Components • Section provides process for evaluation and disposition of major defects Section 10.10 Bridge Issues that MUST involve SCO • Describes bridge construction issues and when/how to involve the SCO Section 10.11 General Structures Construction Issues • New Section added in June 2010 establishes procedures to notify District Structures Material Office of in-service dates, inspections and load ratings Section 11.1 Asphalt Quality Assurance Referee System for Non-CQC Projects • Referee form 700-030-12 Section 11.2 Testing and Correction of Surface Deficiencies on Asphalt Pavement • This Section describes when, who and how testing and correction is performed Section 11.3 Asphalt Mix Temperature Control • This Section describes when and how asphalt mix temperature is controlled and who is responsible Section 12.1 Project Acceptance Types of Acceptance • Final Acceptance • Partial Acceptance • Conditional Acceptance Inspection prior to Acceptance • Semifinal Inspection • Final Inspection Section 13.1 Contractor’s Past Performance Rating Key Items • • • • • Maximum Capacity Rating – Admin Rule 14-12 F.A.C. Provide a copy to the Contractor at the Pre-con Interim performance ratings Communication is key DCE has the final say if appealed by the contractor Sample letters and Flow Chart at the end of section Section 13.2 Constructability Grades Consultant Designed Projects • Professional Services Consultant Work Performance Evaluation, Procedure No. 375-030-007 • Constructability Evaluation, Form No. 375-030-08Z In-House Designs • Constructability Evaluation, Form No. 375-030-08Z Design-Build Projects • Professional Services Consultant Work Performance Evaluation, Procedure No. 375-030-007 • Constructability Evaluation, Form No. 375-030-08Z Section 13.3 Contractor Survey Project Administrator will mail a coy of the Contractor Survey with the Final Acceptance Letter. http://www.dot.state.fl.us/construction/download/ContractorLetterwithSurvey.pdf Questions? The Standard Specifications can be found online on the State Specifications and Estimates Office website at http://www.dot.state.fl.us/specificationsoffice/ The Standard Specifications can be accessed by clicking on the Specification Book icon and you can either access a particular Section or the entire book! Division I General Requirements and Covenant Division II Construction Details Division III Materials Division I covers the first 106 pages in the Standard Specification Book When the items covered in Division I change, they are added to the Contract as Special Provisions It is similar to CPAM as the Sections are broken down by Pre-Construction, Construction and Post-Construction issues Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Section 8 Section 9 Proposal Requirements and Conditions Award and Execution of Contract Scope of the Work Control of the Work Control of Materials Legal Requirements and Responsibility to the Public Prosecution and Progress Measurement and Payment Division II makes up the bulk of the Standard Specifications Information is arranged within “groupings” or specification number based on a specific material or construction operation Each Specification Section is tied to a Master Pay Item number • • Section 110 is Clearing and Grubbing Pay Item for Clearing and Grubbing is 110-1 Division III of the Specification Book contains information regarding all materials utilized on a project • • • • Physical and Chemical Properties Composition Sampling, Certification and Verification information Specific properties of different types of material within a group Make certain that the appropriate Section in Division III is also reviewed prior to inspecting materials When a Specification is added, changed or updated it is placed in a Workbook Workbooks are published each January and July and are included in Contracts let after each of those dates The current July, 2010 Workbook contains 46 of these “new” Specifications These “revised” specifications become part of a Contract as Supplemental Specifications • The Supplemental Specifications included in a Contract will be your first point of reference over the Standard Specifications In addition to Special Provisions and Supplemental Specifications you may find additional directives in your Contract documents Technical Specifications are written for an operation or materials specific to the Contract Developmental Specifications may be added to your Contract where the SCO wants to “try out” a new specification or provision in a real life situation before adding it to the Workbook When Standard Specifications are updated/changed they are shown in a Workbook. The Workbooks can be found on the same website as the Specifications. WHAT DO YOU DO WITH A SIGN THAT LOOKS LIKE THIS? HOW ABOUT THIS ONE? IS THERE ANYTHING WRONG WITHG THESE DRUMS? OR THESE? DO YOU LIKE THIS TYPE III BARRICADE? DO WE HAVE CRITERIA TO MAKE AN OBJECTIVE DECISION ABOUT ACCEPTING DEVICES SUCH AS THESE? 102-9 TEMPORARY TRAFFIC CONTROL DEVICES 102-9 Temporary Traffic Control Devices. 102-9.1 Installation and Maintenance: Install and maintain temporary traffic control devices as detailed in the plans, Index 600 of the Design Standards and when applicable, in accordance with the approved vendor drawings, as provided on the QPL. Erect the required temporary traffic control devices to prevent any hazardous conditions and in conjunction with any necessary traffic re-routing to protect the traveling public, workers, and to safeguard the work area. Use only those devices that are on the Qualified Products List (QPL) or the Approved Products List (APL). Immediately remove or cover any devices that do not apply to existing conditions. All temporary traffic control devices must meet the requirements of National Cooperative Highway Research Program Report 350 (NCHRP 350) and current FHWA directives. Manufacturers seeking evaluation must furnish certified test reports showing that theirproduct meets all test requirements set forth by NCHRP 350. Manufacturers seeking evaluation of Category I devices for inclusion on the QPL shall include the manufacturer’s selfcertification letter. Manufacturer’s seeking evaluation of Category II and III devices for inclusion on the QPL shall include the FHWA WZ numbered acceptance letter with attachments and vendor drawings of the device in sufficient detail to enable the Engineer to distinguish between this and similar devices. For devices requiring field assembly or special site preparation, vendor drawings shall include all field assembly details and technical information necessary for proper application and installation and must be signed and sealed by a Professional Engineer registered in the State of Florida. Manufacturers seeking evaluation of Category IV devices for inclusion on the QPL must comply with the requirements of Section 990 and include detailed vendor drawings of the device along with technical information necessary for proper application, field assembly and installation. Ensure that the QPL number is permanently marked on the device at a readily visible location. Notify the Engineer of any scheduled operation, which will affect traffic patterns or safety, sufficiently in advance of commencing such operation to permit his review of the plan for the proposed installation of temporary traffic control devices. Ensure an employee is assigned the responsibility of maintaining the position and condition of all temporary traffic control devices throughout the duration of the Contract. Keep the Engineer advised at all times of the identification and means of contacting this employee on a24-hour basis. Keep temporary traffic control devices in the correct position, properly directed, clearly visible and clean, at all times. Ensure that all traffic control devices meet acceptable standards as outlined in American Traffic Safety Services Association (ATSSA’s) “Quality Standards for Work Zone Traffic Control Devices”. Immediately repair, replace or clean damaged, defaced or dirty devices. EXAMPLE EXAMPLE EXAMPLE WHERE CAN I GET THE QUALITY GUIDELINES? Design Standards are prepared to encourage uniform application of designs and standard details Support various engineering obligations for design, construction, inspection, maintenance Design Standards http://www.dot.state.fl.us/rddesign/rd/rtds/10/2010Standards.shtm Select the desired Standard Booklet, Interim Standards or Standards Modification by clicking on their underlined symbol. The dates shown under Standards Modifications are the effective dates of the Modifications. For additional information concerning the Standards see PAGE 2. You can also view updates on the Structures Design Website. You can view the Standards, Interim Standards as well as Modifications – made in the same 6 month increments as the Specifications! Year Standards Booklet Interim Standards 2010 S I 2008 S I 2006 S I 2004 S I 2002 S I 2000 S I 1999 1998 1994 N/A N/A N/A I I I Standards Modifications Jan 1, 2011 Jul 1, 2010 Jan 1, 2010 Jul 1, 2009 Jan 1, 2009 Jul 1, 2008 Jan 1, 2008 English July 1, 2007 English Jan 1, 2007 English July 1, 2006 English Jan 1, 2006 English July 1, 2005 English N/A Jan 1, 2006 Metric July 1, 2005 Metric N/A N/A N/A The beginning of the Index provides Abbreviations and Symbols – a type of dictionary for the same information shown on project plans The Index is broken out into Sections Each Section deals with a specific type of work The Standard Index is revised every six months – January and July Revised sheets will be referenced and made a part of the Contract either by incorporating the sheet into the Plan Set or referencing the revised sheet with a plan note Revised sheets can be found by clicking on the “I” for Interim Standards or the Standard Modifications column on the website