2/12/14
CPUC – Energy Division
Cathy Fogel – Market Studies lead
Dan Buch – Spillover lead
DNV GL
Fred Coito – Contract lead
Other staff may be involved with studies
Opinion Dynamics
Mary Sutter – Roadmap lead
Tami Buhr – Residential Spillover lead
Itron – Nonresidential spillover lead
NMR may be involved with later efforts as well
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
2
Roadmap has an estimated budget of $4 million
No change expected to this budget
All studies within this roadmap are managed by the CPUC ED
EM&V Plan shows that the roadmap includes PCG Coordination and five distinct studies
Began regular PCG meetings
First meeting occurred 1/8/14
Regular meetings are the 2 nd Monday of the month; 1:30 – 3 PM Pacific
Added a small study (Market Studies Needs Assessment)
Kept all five other studies for now, but subject to change
Prioritizing spillover studies
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
3
Studies we are currently moving forward with
1. Market Studies Needs Assessment ($74 K budget)
2. Residential Spillover ($1.1 million budget - $98K currently allocated)
Studies we plan to start moving forward within the next month
3. Nonresidential Spillover ($1.1 million budget)
Studies currently on hold, but possible for later in the cycle
4. Sector-Specific Market Effects Studies ($1 million budget)
5. Sector-Specific Tracking of Market Transformation Indicators ($456K budget)
6. Market Transformation Assessment ($270K budget)
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
4
(1)
Objective
To allow Commission Staff to collect data on key markets at regular intervals, identify and field high-priority market research within the 2013-2014 cycle, and track market research across contracts groups and evaluation efforts.
Research Questions
Within which markets do the CPUC /IOUs already have good data?
Which market studies are worthwhile for the CPUC /IOUs to undertake and what is their relative priority?
What is an appropriate framework for conducting market study research and what are the structural and communication requirements of such a framework?
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
5
(2)
Data Collection Activities
Literature Review
Depth Interviews with 20 stakeholders
Secondary review
Stakeholder Meetings / Webinars
Timeline
Memo for public review by end of April
Stakeholder meetings currently planned for May and June (dates not yet determined)
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
6
Objective
To produce spillover estimates for the residential sector and to verify CPUC assumption of a 5% spillover value
Research Questions
What energy efficient measures are being installed without use of program incentives or as a direct result of program intervention?
Why did customers install/purchase these measures without program support?
What savings result from participant and non-participant spillover?
What percent of those savings are attributable to program interventions?
Current Status – budget allocated for the following tasks:
Write full EM&V plan
Create participant self-report survey battery
Work with other EM&V consultants to include battery in planned surveys
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
7
Market Studies
Use results from the Market Studies Needs Assessment to prioritize next set of market studies
Flesh out plans for designated studies and obtain stakeholder comment
Possibly begin newly designated market studies
Spillover
Residential
Complete current tasks
Begin to implement evaluation plan
Nonresidential
Write EM&V plan
Begin to implement evaluation plan
Market Studies EM&V Roadmap - Stakeholder
Presentation - 2/12/14
8
Visit http://www.energydataweb.com/cpuc/search.aspx
; select “2013-
2014” program cycle and search “Market”. Public comment may be posted to the Public Document Area through February 20, 2014.