OPERATING PROCEDURES FOR EASTERN REGION (as mandated by the IEGC clause 5.1(f)) Revision-0: July 2016 Eastern Regional Load Despatch Centre 14,Golf Club Road, Tollygunge Kolkata – 700033 ERLDC: POSOCO Table of Contents Chapter 1 ........................................................................................................................................ 5 1. General .......................................................................................................................................... 5 1.0. Introduction ........................................................................................................................... 5 1.1. Scope ..................................................................................................................................... 5 1.2. Objective................................................................................................................................ 5 1.3. Maintenance of Operating Procedures .................................................................................. 5 1.4. Structure of the Operating Procedure Document .................................................................. 6 1.5. List of Annexure(s) and Reference Documents .................................................................... 6 Chapter 2 ........................................................................................................................................ 7 2. Frequency Management ................................................................................................................ 7 2.0. Frequency Standard ............................................................................................................... 7 2.1. High Frequency Conditions ................................................................................................... 7 2.2. Low Frequency Conditions ................................................................................................... 8 2.3. Broad Guidelines for Issue of Over drawl messages ............................................................. 9 Chapter 3 ...................................................................................................................................... 12 3. Voltage Management .................................................................................................................. 12 3.0. Introduction ......................................................................................................................... 12 3.1. AVRs of Generators ............................................................................................................ 12 3.2. VAR Exchange by constituents for Voltage and Reactive Control..................................... 12 3.3. VAR generation / absorption by generating units ............................................................... 12 3.4. Transformer Taps ................................................................................................................ 13 3.5. Control of Voltage at grid substations/generating stations .................................................. 13 3.6. Switching off the line reactors in case of low voltage ......................................................... 14 Chapter 4 ...................................................................................................................................... 15 4. Outage Planning .......................................................................................................................... 15 4.0. Introduction ......................................................................................................................... 15 4.1. Objective.............................................................................................................................. 15 4.2. Scope ................................................................................................................................... 15 4.3. Outage Planning Procedure: ................................................................................................ 15 4.4. Outage planning not covered in Annual Outage plan.......................................................... 16 4.5. Procedure for Availing the Outage in Real Time ................................................................ 17 Chapter 5 ...................................................................................................................................... 19 5. Switching Coordination .............................................................................................................. 19 5.1. Introduction ......................................................................................................................... 19 5.2. Switching of System Elements for first time ....................................................................... 19 5.3. Switching of Important Elements ........................................................................................ 19 5.4. Other Precautions to be taken during Switching ................................................................. 20 5.5. Charging of partly constructed EHV O/H line from one end as an anti-theft measure ....... 21 5.6. Procedure for certifying successful trial operation of new transmission element ............... 22 Chapter 6 ...................................................................................................................................... 25 6. Periodic Reports and Event Information..................................................................................... 25 6.0. Introduction ......................................................................................................................... 25 6.1. Objective.............................................................................................................................. 25 2|Page ERLDC: POSOCO 6.2. 6.3. 6.4. 6.5. Periodic Reports .................................................................................................................. 25 Event Information ................................................................................................................ 26 Reporting system ................................................................................................................. 26 Grid Incidence/Disturbances and Categorisation ............................................................... 27 Chapter 7 ...................................................................................................................................... 28 7. Network Security and Congestion Management ........................................................................ 28 7.0. Introduction ......................................................................................................................... 28 7.1. Network Security ................................................................................................................. 28 7.2. Periodic auditing of protection system ................................................................................ 37 Chapter 8 ...................................................................................................................................... 39 8. Scheduling and Despatch Procedure ........................................................................................... 39 8.0. Introduction ......................................................................................................................... 39 8.1. Scope ................................................................................................................................... 39 8.2. Objective.............................................................................................................................. 39 8.3. Description of the procedure ............................................................................................... 39 8.4. Procedure for revising ISGS schedule downwards on account of surrendering of share by beneficiaries ................................................................................................................................... 40 Chapter 9 ...................................................................................................................................... 52 9. SCADA System Operation ......................................................................................................... 52 9.1. Introduction ......................................................................................................................... 52 9.2. Energy Management System ............................................................................................... 52 9.3. Communication System....................................................................................................... 52 9.4. SCADA Features ................................................................................................................. 52 9.5. Operational Requirements ................................................................................................... 52 Chapter 10 ...................................................................................................................................... 54 10. Metering and Settlement System............................................................................................. 54 10.0 Introduction ............................................................................................................................ 54 10.1 Metering and Data Collection .......................................................................................... 54 10.2 Automated Meter Reading (AMR) .................................................................................. 54 10.3 Data Processing ................................................................................................................ 54 10.3.1 Energy Accounting .......................................................................................................... 55 10.3.2 Pool Account Operation ................................................................................................... 56 3|Page ERLDC: POSOCO Annexures Annexure: I Generation capacities in Eastern Region...................................................................... 57 Annexure: II List of Generating Units and their Capacities…………………………………………58 Annexure :III Captive Power Stations in Eastern Region and Their Capacities ............................... 61 Annexure: IV Deviation rate at different frequencies ......................................................................... 62 Annexure: V Format message for violation of IEGC ........................................................................ 63 Annexure: VI List of 765/400kV & 400/220kV ICTs and their tap Positions ...................................... 64 Annexure: VII Reactive Compensation Details ................................................................................... 65 Annexure: VIII Format for message to be issued by ERLDC for Real Time Outage clearance .......... 67 Annexure: IX New transmission element charging and issue of certificate of successful trial run operation ...................................................................................................................................... 68 Annexure :X Format for Weekly Reports .......................................................................................... 79 Annexure :XI Format for Quarterly Reports ....................................................................................... 81 Annexure :XII Format for written report for event reporting ............................................................... 84 Annexure: XII (a) Format for Reporting System Disturbances ................................................... 85 Annexure :XIII Categorisation of Grid Incidences/Disturbances .......................................................... 88 Annexure :XIV List of Important Elements.......................................................................................... 89 Annexure :XV Automatic UFR load shedding Schemes and Feeder Disconnection to control overloading ...................................................................................................................................... 96 Annexure :XVI Power Demand Override ........................................................................................... 104 Annexure : XVI Special Protection schemes at Talcher and Kolar ..................................................... 105 Annexure :XVIII Islanding schemes in ER ......................................................................................... 108 Annexure :XIX Scheduling Formats ( Broad guidelines for the Formats) .......................................... 111 Annexure: XX Meter Locations ........................................................................................................ 114 Annexure :XXI Grid Maps.................................................................................................................. 124 Annexure :XXIII :- Format for Applying and Withdrawing congestion ............................................. 134 4|Page ERLDC: POSOCO Chapter 1 1. General 1.0. Introduction In compliance to the IEGC (Indian Elecricity Grid Code) clause no 5.1(f) this internal Operating Procedure for Eastern Region is developed in consultation with the regional constituents of Eastern Region. Eastern Region Grid system comprises of the states of Bihar, Jharkhand, Orissa, West Bengal and Sikkim and has an operating area of 4,25,423 sq km, which is about 13% of the total area of the country. Damodar Valley Coprporation (DVC) established under sub-section (1) of Section 3 of the Damodar Valley Corporation Act, 1948 in eastern region is an integrated utility similar to STU/SEB encompassing part of the states of West Bengal and Jharkhand and has its own generation, transmission and distribution facilities in its identified command area. Eastern Region is strategically located and has interconnections with all the other regions as well as with neighbouring countries like Bangladesh, Bhutan and Nepal. The IEGC brings together the different terms, encompassing all the utilities connected to / or using the Inter-State Transmission System (ISTS) and provides documentation in regard to relationship between various users of the ISTS. It lays down the rules and guidelines for planning, development, operation and maintenance of the grid in an efficient, reliable and economical manner. The internal operating procedure as prepared by ERLDC is to clearly specify the roles of each player in the grid i.e., Central Sector Generating and Transmission Utilities, State Utilities, Independent Power Producers, Traders, System Operators and other agencies operating in the power market to facilitate grid operation in efficient, secure, reliable and economic manner. 1.1. Scope This document describes the role of all agencies connected in the region in order to operate the grid in an integrated manner promoting efficiency, reliability and economy in conformation to the desired security standards and to meet the common interests of all the agencies. 1.2. Objective Objective of this document is to describe the procedures to be adopted for integrated system operation and roles of each agency and their responsibilities in the grid in compliance to the various provisions of IEGC. This document aims at operation, maintenance and development of regional power system in the most efficient, economic, secure and reliable manner. This document also aims to facilitate beneficial trading opportunities between utilities within as well as outside the region to harness bottled up power 1.3. Maintenance of Operating Procedures The Operating Procedure shall be maintained by ERLDC and reviewed periodically. However, in the event of any specific operational issues/philosophy requiring urgent revision of the procedure, the same may be expeditiously carried out in consultation with the Regional constituents. Further, whenever amendments are made in the IEGC, DSM, Open Access, Congestion management and related regulations, the operating procedure would be also be amended accordingly. 5|Page ERLDC: POSOCO 1.4. Structure of the Operating Procedure Document The Operating procedure of the Eastern Region system contains the following chapters . Chapter 1 General Chapter 2: Frequency Management Chapter 3 Voltage Management Chapter 4 Outage Planning Chapter 5 Switching Coordination Chapter 6 Periodic Reporting and Event information Chapter 7 Network Security and Congestion management Chapter 8 Scheduling and Despatch Chapter 9 SCADA system operation Chapter 10 Metering & Settlement System 1.5. List of Annexure(s) and Reference Documents For the purpose of understanding the operational aspects and issues, there would be a necessity to refer to various data, lists and parameters, external and internal cuments/lists, Grid Maps etc. A list of Annexure(s) had been shown at the beginning of this document. 6|Page ERLDC: POSOCO Chapter 2 2. Frequency Management 2.0. Frequency Standard IEGC vide its clause 5.2(m) has mandated that all Regional entities shall make all possible efforts to ensure that the grid frequency always remains within the 49.9-50.05 Hz band, Frequency is the most important indicator of the quality of supply and is the global parameter in the grid i.e. it is same throughout an inter-connected power system. Since Frequency essentially being a manifestation of the extent of load-generation balance of the National Grid as a whole, the system operator at ERLDC needs only to minimize the Area Control Error (ACE) of Eastern Region, provided the same deviates appreciably, in order to contribute towards system frequency regulation. Till AGC is implemented in the country, real time values of ACE of individual regional entities as well as Eastern Region as a whole would be monitored. A negative deviation of ACE indicates overdrawal or under-injection by the control area / regional entity. Conversely, deviation on the positive side indicates under-drawal or over-injection by the entity. 2.1. High Frequency Conditions In case the frequency is high (above 50.05Hz) and is in increasing trend then the following actions may be initiated: 2.1.1 Control area(s) within E. Region, with high positive deviation of ACE would be first advised (through their respective SLDC) to maintain their net interchanges as per schedule. In case any regional entity is under-drawing, ERLDC may advice concerned SLDC for considering surrendering of its share from ISGS, based on merit order. 2.1.2 ERLDC shall check whether the high frequency condition is due to the heavy underdrawal by any entity within the region or by neighbouring regions. In the latter case, the matter has to be brought to the notice of NLDC for necessary remedial action Control area(s) within E. Region. ERLDC shall advise the regional entities within ER to lift load shedding if any. 2.1.3 However, before taking up with other regions / NLDC, ERLDC would check the possibility of any backing down of the reservoir based hydro stations within state system. 2.1.4 ERLDC before advising any generation reduction at the hydro stations, in consultation with concerned SLDC, would check back whether such reduction would cause any adverse change in voltage levels or network loading in the ISTS. Similarly, the concerned SLDC would also assess the impact on its intrastate network. In case any problem is envisaged due to such generation reduction, the same shall be avoided. 2.1.5 Explore the possibility of running of Purulia Pump storage hydro units in pump mode, in consultation with SLDC, West Bengal. 2.1.6 Advise/remind the states to back down costly generation as per merit order by taking adequate support from SCADA. The applicable deviation rate as per CERC (w.e.f 17-02-14) is shown at Annexure IV. 2.1.7 If any ISGS (other than must run) is generating more than their schedule, advise the ISGS to reduce the over injection. 2.1.8 If the frequency is still high then as per the ”Central Electricity Regulatory Commission (Ancillary Services Operations) Regulations, 2015”, the NLDC shall trigger the RRAS(Reserve Regulation Ancillary Services) DOWN service to bring down the frequency within the permissible upper limit. 7|Page ERLDC: POSOCO 2.1.9 The Hydro stations of Bhutan power system exporting power to India (except Dagachhu HPS) are not covered commercially under ABT mechanism. Backing down advice on account of high frequency conditions may be issued to stations at Tala, Chukha and Kiruchu of Bhutan system only after all possible remedial measures are exhausted. However, in case the stations are noticed generating extra with respect to schedule issued , ERLDC shall attempt revising the generation schedule with due revision of constituents drawal schedule. 2.1.10 Backing down of the spilling hydro units or the run-off-the-river units for short duration may also be considered if all other options are exhausted. 2.1.11 If the frequency is still high, and action from underdrawing beneficiaries is not forthcoming, ERLDC shall suo-motto reduce the generation schedule of ISGS with corresponding downward revision of schedule of the concerned beneficiary. 2.2. Low Frequency Conditions If the frequency is less than 49.9 Hz. and has a decreasing trend, the following actions may be taken: 2.2.1 Control area(s) within E. Region, with high negative deviation of ACE would be first advised (through their respective SLDC) to maintain their net interchanges as per schedule. 2.2.2 ERLDC shall check whether the low frequency condition is due to the heavy over-drawal by regional entities or by the neighbouring regions. In the event of overdrawal by neighbouring regions, matter may be brought to the notice of NLDC through written messages with a copy/ies to the RLDC of the over drawing region(s). 2.2.3 If any unit of Purulia Pump storage is operating in pump mode and if the concerned beneficiary is over drawing, ERLDC shall advise the concerned SLDC for discontinuing the pump operation. 2.2.4 ERLDC may advise all regional entities / control areas, through their respective SLDCs to maximize their internal generation viz. hydro, thermal, IPP etc. in case margins are available. 2.2.5 Deviation Settlement Mechanism and related matters Regulations, 2014. already lays down appropriate financial and legal penalties for under-generation / over-drawal at low frequency. Nevertheless, if any ISGS is under-generating, it may be reminded to generate as per schedule. If such generation increase is not possible due to any technical constraints, the concerned ISGS may be advised to reduce its Declared Capability. ERLDC would then correspondingly reduce the drawal schedules of all concerned beneficiaries (including outside regions) and advise them to maintain their net exchanges as per their respective revised schedules. 2.2.6 The Actual receipt from the Hydro stations from Bhutan may be closely monitored under low frequency conditions. In case such receipt is less than the schedule, because of some technical reasons like low inflow etc., ERLDC may suo motto revise the generation schedule downwards with corresponding downward revision of drawal schedules of the respective constituents who have share on such stations. Such downward revision shall be duly informed to the concerned beneficiaries with an advise to curtail their drawal from the grid. 2.2.7 If the frequency is less than 49.9Hz. and has a falling trend, remind the SLDC(s) of overdrawing regional entity /entities telephonically to maintain frequency by picking up internal generation/ curtailing overdrawal. The estimation of over-drawal has to be done corresponding to nominal frequency (50.0 Hz) after applying requisite frequency bias correction on the exchange at the prevailing off-nominal frequency. 8|Page ERLDC: POSOCO 2.2.8 If the frequency is less than 49.9 Hz and it may appear that practically no control area is as such overdrawing, a general message may be issued to all regional entities requesting to estimate their respective actual net exchanges at 50.0 Hz (after applying necessary frequency correction factor on the existing interchange) and improve internal generation/ shed loads wherever the estimated actual drawal corresponding to 50.0 Hz exceeds the net scheduled drawal. 2.2.9 ERLDC may further examine the latest status of thermal units under outage (forced) and find out when the units are expected to be on bar and take up for expediting the same. 2.2.10 As a long term measure, It may be examined that whether a planned maintenance of any unit can be postponed without much affecting the AMP of other units. 2.2.11 Notwithstanding the above as per clauses 6.4.12 of IEGC, ERLDC may direct the SLDCs/ISGS/ other regional entities to increase/decrease their drawal/generation in case of contingencies e.g. overloading of lines/transformers, abnormal voltages, threat to system security. Such directions shall immediately be acted upon. In case the situation does not call for very urgent action, and ERLDC has some time for analysis, it will be checked whether the situation has arisen due to deviations from schedules. These shall be got terminated first, through appropriate measure like opening of feeders , if considered necessary by SLDC/ERLDC, before an action, which would affect the scheduled supplies to the long term, medium term customers or short term customers is initiated in accordance with Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in InterState Transmission and Related matters) Regulations, 2009 and Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008. 2.2.12 If the frequency is low then as per the ”Central Electricity Regulatory Commission (Ancillary Services Operations) Regulations, 2015”, the NLDC shall trigger the RRAS(Reserve Regulation Ancillary Services) UP service to bring the frequency at or above the permissible lower limit. 2.3. Broad Guidelines for Issue of Over drawl messages Violation Type and Category Frequency Violation Voltage Violation Loading Violation Duration for issuance of Message >50.1 Hz or <49.7 Hz Emergency Message will be issued if violation continues for at least 5 minutes 50.05-50.1 Hz or 49.9 Hz -49.7 Hz Alert Message will be issued if violation continues for at least 15 minutes 49.9 Hz -50.05 Hz Normal > 425 kV or <380 kV Emergency 415 kV - 425 kV or 390 kV - 380 kV Alert >390 kV to <415 kV Normal > Thermal Loading under n-1 contingency Emergency Message will be issued if violation continues for at least 5 minutes = Thermal Loading under n-1 contingency Alert Message will be issued if violation continues for at least 15 minutes < Thermal Limit under n-1 contingency Normal Message will be issued if violation continues for at least 15 minutes Message will be issued if violation continues for at least 15 minutes 9|Page ERLDC: POSOCO Zero Crossing Violation Deviation Violation 1 Failure (issued 14th time Block) Emergency Issued in 11th time block if the direction not changed for 10 time blocks Alert Zero Crossing done within 10 time Blocks Normal > 20% or 250 MW (whichever lower) Emergency Message will be issued if violation continues for at least 5 minutes 12%-20% or 150 MW to 250 MW (whichever lower) Alert Message will be issued if violation continues for at least 15 minutes <12% or 150 MW (whichever lower) Normal Note: 1. General Approach is to issue Alert Message before reaching Critical level 2. Generally every Alert is considered for maximum of 15 Minutes 3. Generally any Emergency considered for maximum of 5 minutes 4. Only after Emergency message, if correction does not effected in say 5 minutes, Non-Compliance Message will be issued Separately. Normal State: All system variables are within the normal range and no equipment is being overloaded. Alert State: All system variables are within acceptable range, all constraints are satisfied and a further contingency would cause an overloading any equipment. Emergency State: After the contingency, voltages at many buses are low and/or equipment loadings are exceeds short term emergency ratings. Format for issuance of violation message to the constituents within the region as per IEGC clause 5.4.2 is shown in Annexure V. 3. Feeder disconnection in case of over drawl As per provisions 5.4.2 (a) & 5.4.2 (b) of the Grid Code SLDC/ SEB/distribution licensee and bulk consumer shall initiate action to restrict the drawal of its control area ,from the grid, within the net drawal schedule and the SLDC/ SEB/distribution licensee and bulk consumer shall ensure that requisite load shedding is carried out in its control area so that there is no overdrawl. In order to maintain the frequency within the stipulated band and maintaining the network security, the interruptible loads shall be arranged in four groups for scheduled load shedding, unscheduled load shedding, loads to be shed through UFR / df/dt relays and loads to be shed under SPS identified at RPC level. Further there should not be any overlapping of loads belonging to different groups. In case of certain contingencies and/or threat to system security, the ERLDC may direct any SLDC/ SEB/distribution licensee or bulk consumer connected to the ISTS to decrease drawal of its control area by a certain quantum. In case repeated warning messages from ERLDC to curb over drawal does not yield any results, ERLDC will instruct the defaulting constituents to disconnect identified 10 | P a g e ERLDC: POSOCO radial feeders within their respective systems for reduction of over drawl. Concerned constituents should send compliance report to ERLDC in this regard after taking necessary action. List of feeder to be disconnected in case of over drawl is shown in Annexure-XV 11 | P a g e ERLDC: POSOCO 3. Chapter 3 Voltage Management 3.0. Introduction In compliance to the IEGC (Indian Electricity Grid Code) clause no 5.2(s) all regional constituents shall make all possible efforts to ensure that the grid voltage always remains within the following operating range Nominal (KV –Rms) 765 400 220 132 Maximum (KV –Rms) 800 420 245 145 Minimum (KV –Rms) 728 380 198 122 Eastern Region Grid has a very good spatial distribution of generation rendering a better voltage profile across 400 kV and 220kV network. However, in some pockets of system where radial loads are fed, occasional low voltage is experienced. Normally the 400kV system usually operates within the prescribed voltage limit as specified in the IEGC. However, in the event of low demand in Bihar or low import by NR and/or WR, substations like Jamshedpur etc. experience high voltage. On the other hand, due to high concentration of load in South Bengal, 400kV voltages at Jeerat and Subhasgram become low, particularly during summer peak. 400kV station at Jeypore, Sasaram, Jeerat etc. occasionally experience both low and high voltages due to the low fault MVA as well as large variation of active / reactive demand these stations. As the HVDC station Gajuwaka is also connected to Jeypore having low fault MVA, any power flow change associated with switching of filter banks operation render at times wide fluctuations in voltage at 400kV level. 3.1. AVRs of Generators As per the provisions of clause 5,2(k) of IEGC, all generating units shall keep their Automatic Voltage Regulators (AVRs) in operation and power system stabilizers (PSS) in AVRs be appropriately tuned. 3.2. VAR Exchange by constituents for Voltage and Reactive Control In line with clause 4.6.1(a) of IEGC each agency shall provide adequate compensation of its reactive requirements including appropriate reactive reserves, to support safe and secure power transfer on interconnecting transmission circuits. The agencies shall take action in regard to VAR exchange with the grid looking at the topology and voltage profile of the exchange point. In general, the regional entities shall endeavour to minimize the VAR drawl at interchange point when the voltage at that point is below the nominal value and shall not inject VARs when the voltage above the nominal value. In fact, the regional entities are expected to provide local VAR compensation so that they do not draw any VARs from the grid during low voltage conditions and do not inject any VARs to the grid during high voltage conditions. 3.3. VAR generation / absorption by generating units In order to improve the overall voltage profile, the generators shall run in a manner so as to have counter balancing action corresponding to low/high backbone grid voltage and to bring it towards the nominal value. In order to achieve the same, all generators shall generate reactive power during low voltage conditions and absorb reactive power during high voltage conditions as per the capability limit of the respecting generating units. The online tap changers (OLTC) on the generator transformer 12 | P a g e ERLDC: POSOCO wherever possible should also be used to achieve this. Off load tap changes should be used to take care of the seasonal variations in the voltage profile. 3.4. Transformer Taps In line with IEGC clause 6.6.4, the transformer tap positions on different 400kV class ICTs shall be changed as per requirements in order to improve the grid voltage. ERLDC shall coordinate and advise the settings of different tap position and any change in their positions shall be carried out after consultation with ERLDC. A list of tap positions for 765/400KV and 400/220kV ICTs / as on 30.06.16 is enclosed at Annexure VI. ERLDC shall maintain this list and incorporate due changes and reasons for change of 400/220kV ICT tap positions. Frequent on line tap changing may be avoided to the extent possible. Any measure to maintain the voltage profile within the operating range by way of change of ICT taps may be resorted to through detailed study and observing the real time voltage profile of the concerned station/s. As a part of such study, ERLDC shall duly examine from the weekly special energy meter data the pattern of VARh drawal by regional entities at various ISTS interconnection points at HIGH/LOW voltage. Effort shall be made to identify such ISTS points where regular VARh charge payment to regional pool takes place. Necessary measure shall be initiated to set optimum ICT taps so as to minimise such payment to pool. Based on SCADA data, voltage data on both high as well as low sides of 400/220kV and 765/400kV transformers would be examined by ERLDC on a half-yearly basis, through 2dimensional scatter plots, with one axis representing the primary side voltage and the other axis the secondary side voltage . If majority of the data are found to exist in the first or third quadrant of the plot, then scope does not exist for further improvement of voltage by tap changing. However, if more than 30% of the data occupy the 2nd or the 4th quadrant, then action for appropriate changing of ICT tap is initiated, which is further cross-checked by off-line simulation study. 3.5. Control of Voltage at grid substations/generating stations Following corrective measures in order of priority shall be taken by ERLDC operator for ISTS system and regional entities and by SLDC for state entities in the event of voltage going beyond the operating limits as stipulated in IEGC. 1.5.1 High Voltage: In the event of high voltage (e.g. 400 kV voltage going beyond 415 kV and having a rising trend) following specific steps would be taken by the respective grid substation/generating station at their own, with intimation to ERLDC, unless specifically mentioned by ERLDC/SLDCs. Before taking any voltage control action the reason for high voltage as observed /reported be carefully studied The network adjoining to the substation/s experiencing high voltage be also carefully studied and areas/substations /generating stations be identified where voltage control measures need to be taken in the following order of priority a) The bus reactor be switched in b) The switchable line/tertiary reactor are taken in ( a list of Bus reactors /line reactors and tertiary reactors available at ER grid is enclosed at Annexure VII c) The Generating units on bar at the stations in proximity to high voltage areas, absorb reactive power within the limits of their capability curves. d) Optimization of the filter banks at HVDC terminal (provided high voltage is being experienced in the vicinity of the terminal) e) Check the possibility of changing the transformer Tap if one side of ICT is witnessing High voltage while other side is having low voltage. 13 | P a g e ERLDC: POSOCO f) Checking possibility of rerouting /change of power flow on HVDC terminals so that loading on parallel EHV network can be altered that may result in reduction in voltage. g) ERLDC/SLDCs shall consider opening one circuit of lightly loaded multi circuit lines around the area /substation where high voltage is reported, ensuring security of the balance network. In case it becomes essential to switch out one of the circuits of interregional lines to mitigate high voltage at one or more inter-regional sub-stations, due consent would be obtained from the concerned neighbouring RLDC (s) and NLDC. 1.5.2 Low Voltage Condition In the event of low voltage(e.g. 400 kV voltage going below 390 kV and have a declining trend), following specific steps would be taken by the respective grid substation/generating station at their own, with intimation to ERLDC, unless specifically mentioned otherwise by ERLDC/SLDCs. However, before taking any voltage control action, the reason for low voltage as observed /reported is to be carefully studied. The network adjoining the substation/s experiencing low voltage to be also carefully studied and areas/substations /generating stations to be identified where voltage control measures need to be taken in the following order of priority a) b) c) d) e) f) g) h) 3.6. Close the lines which were opened to control high voltage after obtaining due permission from ERLDC/SLDCs. The bus reactor be switched out The switchable line/tertiary reactor be taken out All generating units on bar shall generate reactive power upto the limits of their respective capability curves. Optimization of the filter banks at HVDC terminal Check the possibility of changing the transformer Tap if one side of ICT is witnessing Low voltage while other side is having High voltage Operate hydro generator for VAR generation i.e. at lagging p.f. Check possibility of altering HVDC power flow settings on HVDC terminals so that loading on parallel EHV network goes down resulting in rise in voltage. Switching off the line reactors in case of low voltage In the event of persistent low voltage conditions, some of the line reactors are to be selected on the basis of line length, grid conditions, network topology etc., which can be switched off in order to improve the system voltage profile. The details of all shunt reactors in ER Grid are listed at Annexure VII of this document. The switching off of such line reactors and reviving them back would be carried out as per the instructions issued by ERLDC. 14 | P a g e ERLDC: POSOCO Chapter 4 4. Outage Planning 4.0. Introduction In reference to the clause 5.7.1 of IEGC, this chapter sets out the procedure for preparation of outage schedule for generating units and transmission elements of the region in a coordinated and optimal manner keeping in view the regional system operating conditions and maintaining load generation balance in the system. Adequate security margins shall be ensured while preparation of the generation and transmission outage programme. ERPC secretariat shall be responsible for preparation of the annual outage plan in advance for the financial year and be reviewed on monthly basis. 4.1. Objective 4.1.1 To formulate a coordinated outage programme of transmission lines and generating units for the regional grid considering all the available regional resources and taking into account transmission constraints as well as other requirements. 4.1.2 To minimise surplus or deficit, if any, in the requirement of power and energy and help to operate system within the grid standards. 4.1.3 To optimise the transmission outages of the elements of the Eastern Regional grid that should not affect adversely the regional grid operation but take into account the generation outage schedules, outage of SEB/STU systems thereby maintaining security standards. 4.2. Scope The scope of this chapter is applicable to all users viz. SEBs/STUs, ISGSs, IPPs, CTU, ISTS Licensees as well as RLDC, SLDCs, (vide clause 5.7.3 of IEGC). For the purpose of a coordinated maintenance programme, outage programme for the generating stations at Bhutan viz. Tala HEP, Chukha HEP Dagachhu HEP and Kiruchu HEP and its associated transmission system shall also be covered within the scope of outage planning procedure of Eastern Regional Grid system. 4.3. Outage Planning Procedure: 4.3.1 For the purpose of Load Generation Balance (LGB)/ Outage planning process, OCC (Operation Coordination Sub Committee) of ERPC shall, in general, be the forum for reviewing and deciding the outage planning. 4.3.2 It shall be the responsibility of the ERPC secretariat to analyse the outage programmes proposed by various agencies and, prepare a draft annual outage schedule for finalization of the annual outage plan for the following financial year by 30th November of each year. 4.3.3 All SLDCs/STUs, CTU, ISGS, IPPs, shall provide RPC Secretariat their proposed outage programmes in writing for the next financial year by 31st October of each year. These shall contain identification of each generating unit/ transmission line/ICT, the preferred date for each outage and its duration and where there is flexibility, the earliest start date and latest finishing date. 4.3.4 Each load serving control area shall be responsible to match its demand with the anticipated availability from its own plant(s) and availability from ISGS / other purchase / sale contracts. 15 | P a g e ERLDC: POSOCO 4.3.5 The SLDC/STUs along with the proposed outage programme, therefore, shall also furnish details of the anticipated load generation balance report(LGBR) to ERPC secretariat in order to facilitate preparation of the annual outage plan ERPC Secretariat after receiving the outage programme will study the following :i) Total power and energy availability( for peak and off-peak condition) ii) Monthwise availability and requirement iii) In case of both surplus and deficit, proper staggering of generation outage to reduce/ eliminate the deficit. iv) In case of only deficit efforts to be taken to even out high and low deficit by staggering of generation outage. v) The anticipated programme for bilateral transaction under STOA or otherwise by state beneficiaries 4.3.6 ERPC Secretariat shall then come out with a draft load generation balance report (LGBR) and draft outage programme for the next financial year by 31st December of each year for the Regional grid taking into account the available resources in an optimal manner and to maintain security standards. This will be done after carrying out necessary system studies and, if necessary, the outage programmes shall be rescheduled. Adequate balance between generation and load requirement shall be ensured while finalising outage programmes. 4.3.7 The final outage plan alongwith the Load Generation Balance report(LGBR) shall be prepared in consultation with NLDC and RLDC and intimated to NLDC, Users, STUs, CTU, other generating stations connected to ISTS and the RLDC for implementation latest by 31st January of each year as mutually decided in ERPC forum. 4.3.8 Shutdown planning of any element affecting power exchange with Bangladesh or Bhutan will be done in consultation with NLDC. 4.3.9 The above annual outage plan shall be reviewed by ERPC Secretariat on quarterly and monthly basis in coordination with all parties concerned, and adjustments made wherever found to be necessary. 4.4. Outage planning not covered in Annual Outage plan 4.4.1 Some of the outages not foreseen while finalising annual outage plan will be considered in monthly OCC meeting of ERPC. 4.4.2 Indenting Agency: The agency which gives the requisition for outage of any power system element shall be called Indenting Agency. Any of the following may request for outage of any power system elements: 4.4.2.1 Transmission Licensees / State Transmission Utilities 4.4.2.2 Generating Companies 4.4.3 Indenting Agency shall submit the proposed shutdown for the next calendar month latest by 3rd day of the current month to the RPC Secretariat as per Format IA / Format IB. In the said proposal apart from the main power system element(s) to be taken out of service and its purpose, the agency should also mention the duration of non-availability of each sub-station equipment such as bus section, CB, isolator or any other switchgear as well as non-availability of any protection feature or PLCC, in as much detail as possible. 4.4.4 In case of shutdown of inter-regional lines and intra-regional lines affecting the transfer capability of any inter regional corridor, the Indenting agency shall submit the shutdown proposal in both the concerned RPCs. To facilitate this, broad list of such lines is indicated at Annexure XIV which will be reviewed and updated by NLDC from time to time. The indenting agency may do an internal screening of its outage plan centrally to avoid multiple outages in 16 | P a g e ERLDC: POSOCO the same corridor simultaneously. Bilateral discussion between the agencies involved may also be done to minimize outage duration before submitting the outage plan to RPCs. 4.4.5 ERPC Secretariat shall compile all the received proposals and put up the same on its website by 5th day of the month as per Format IIA / Format IIB. 4.4.6 System Study sub-committee of ERPC shall study the impact of these outages and based on its recommendations, ERPC shall discuss proposed outages in the OCC meeting and prepare a list of approved transmission outages with the precautions to be taken. ERPC would attempt to schedule all their OCC meetings between 10th to 15th day of the month so that sufficient time is available both to the Study Committee before the OCC meetings as well as for ERLDC/NLDC (mainly to take care of further changes in the network topology and/or in load generation) after the OCC meeting. 4.4.7 While approving the shutdowns it shall be ensured that multiple outages in the same corridor are not be approved simultaneously. It also needs to be ensured that all other concerned entities also complete their maintenance works requiring the same shutdown during the same period so that multiple shutdowns of any particular element for maintenance work by multiple agencies are avoided. Multiple outages of transmission element for the same work during the year may also be avoided. 4.4.8 ERPC shall send the list of approved transmission outages to SLDCs/ERLDC/NLDC within 3 days of the OCC meeting and preferably latest by 18th of the month as per Format IIIA / Format IIIB. The same shall also be displayed on ERPC websites. 4.4.9 Any shutdown proposal which requires approval of two RPCs shall be considered approved only if it is approved in both the RPCs. 4.4.10 After the receipt of Format IIIA / Format IIIB from each RPC, NLDC in consultation with RLDCs may prepare a tentative readjusted timings/dates of transmission element outages for next month considering the principles set out in this procedure 4.4.11 In case of emergency in the system, viz., loss of generation, break down of transmission line affecting the system, grid disturbances, system isolation, RLDC may conduct studies again before clearance of the planned outage. 4.4.12 Vide clause 5.7.4 (g) of IEGC ERLDC is authorised to defer any planned outage in case of any of the following taking into account the statutory requirements: i) Major grid disturbances (Total black out in Region) ii) System isolation / separation iii) Black out in a control area iv) Any other event in the system that may have an adverse impact on the system security by the proposed outage. 4.5. Procedure for Availing the Outage in Real Time 4.5.1 The agencies involved shall ensure availing of outages as per the approved schedule time. 4.5.2 Request for outages which are approved by OCC must be sent by the owner of the transmission asset at least 3 days in advance to ERLDC by 10:00 hours, together with the details mentioned under 4.4.3 4.5.3 In case the owner is not availing the OCC approved outage, the same shall be intimated to the ERLDC at least 3 days in advance with a copy to MS/ERPC for approval from ERPC side. After due communication from ERPC, ERLDC will process accordingly. 17 | P a g e ERLDC: POSOCO 4.5.4 In case the owner is not availing the OCC approved outage, the same shall be intimated to the respective RLDC at least 3 days in advance. 4.5.5 In case the outage of inter-regional links or any 765 kV links or any links outage which need ATC revision, RLDCs shall forward the request for shutdown along with their consent and observation as per Format V to NLDC/other concerned RLDCs with clear observations regarding possible constraints /contingency plan and consent including study results by 10:00 hours of D-2 day. Other concerned RLDCs would forward their observations/consent/reservations by 16:00 hours of D-2. 4.5.6 A list of all the outages approved for the next day shall be forwarded to NLDC for all India compilation. 4.5.7 On the day of outage, the outage availing agency shall seek the code for availing outage from ERLDC/NLDC (wherever applicable). The agencies involved shall endeavour to avail the outage with in 15mintues of availing the code but not later than 30 minutes. In case, due to any contingency, the outage could not be availed within 30 minutes, a fresh code needs to be obtained by all concerned agencies stating the reason there of. Record of scheduled and actual time of outage and restoration shall be maintained at ERLDC/NLDC. 4.5.8 ERLDC shall prepare a monthly statement of scheduled and actual time of outage and restoration and forward the same to ERPC latest by 05th day of the next month with a copy to NLDC. 4.5.9 SLDCs shall prepare a monthly statement of scheduled and actual time of outage and restoration and forward the same to ERPC latest by 05th day of the next month with a copy to ERLDC.. 4.5.10 As any deviation in the outage from the schedule can affect other planned outages as well as affect reliability and electricity markets, indenting agency must strictly adhere to the shutdown timings 4.5.11 ERLDC if required shall conduct further system studies based on the system condition and approve the shutdown at least two day in advance. 4.5.12 While issuing clearance of the shutdown ERLDC shall clearly mention the following( vide format at Annexure VIII) i) Message no. ii) Name of the element /elements which shall remain under outage. iii) Name of the agency /agencies availing the outage. iv) Date and duration of the outage v) Nature of the outage vi) Reason for availing the shutdown vii) Specific network /system conditions to be maintained including impact of the outage viii) Sequence of switching instruction if any 18 | P a g e ERLDC: POSOCO 5. Chapter 5 Switching Coordination 5.1. Introduction Coordination of switching operations in the grid is important for ensuring safety of personnel and equipment as well as for ensuring adequacy and security of the grid. Before any operation of important elements of the Eastern Regional Grid is carried out on a User/STU system, the Users, SLDC, STU, CTU, licensee shall inform ERLDC, in case the Eastern Regional grid may, or will experience an operational effect. 5.2. Switching of System Elements for first time In line with Regulation 6 (1) of the Central Electricity Authority (Grid Standards) regulations 2010, no entity shall introduce an element in the ISTS of Eastern Grid without the concurrence of ERLDC in the form of an operation code. In case a new power system element in Eastern Regional grid is likely to be connected with the Inter-State Transmission System or is to be energized for the first time, from the ISTS, the applicant User/STU/CTU/licensee shall send a separate request in advance along (at least one week) with the confirmation of the following: Acceptance of ERLDC with regards to registration as regional entity Signed Connection Agreement if applicable Availability of telemetry of station/Element at the ERLDC/SLDC Availability of voice communication with the station at ERLDC/SLDC Interface meter installed and tested by downloading data and forwarding it to ERLDC Single Line Diagram Healthiness of Protection System/Protection Setting Statutory clearance has already been obtained 5.3. Switching of Important Elements In line with regulation 5.2 (a, b, c), of the IEGC no part of the Eastern Regional grid shall be deliberately isolated from the rest of the National/Regional grid except under an emergency conditions in which such isolation would prevent a total grid collapse and would enable early restoration of power supply or safety of human life; when serious damage to a costly equipment is imminent and such isolation would prevent it; when such isolation is specifically instructed by ERLDC. Important elements of the regional grid, which have a bearing on the network security, is compiled and issued by ERLDC as a separate document [IEGC 5.2 (c)]. The regional entities, users, STU, CTU, licensee shall obtain ‘operation code’ from ERLDC before carrying out any switching operation on any of the important elements of the Eastern Regional grid. Shut down of any 400 kV or 765kV bus at substation needs approval of ERLDC. In respect of double main and transfer switching scheme at 400 kV substations, ERLDC shall be informed whenever the 400 kV transfer bus at any substation is utilized for switching any line/ICT. In a 400 kV substation/power station switchyard having breaker and a half switching scheme, outage within the substation (say main or tie circuit breaker) not affecting power flow on any line/ICT can be availed by the constituents under intimation to ERLDC, however switching code must be taken from ERLDC control room for every such switching operation.. Further, while availing such shutdowns or carrying out switching operations it must be ensured that at least two Dias are complete even after such outage from the view point of network reliability. Any outage not fulfilling the above conditions needs the approval of ERLDC. Whenever any protection system such as Bus Bar protection, LBB protection, Auto reclose etc. at generating station or grid substation is required to be taken out of service for any maintenance work, an operational code would be taken from SLDC/ERLDC. 19 | P a g e ERLDC: POSOCO For switching of any 765 kV element, or element associated with inter-regional lines or element associated with power transfer to Bangladesh/ Bhutan/ Nepal, code of both NLDC as well as ERLDC is required. 5.4. Other Precautions to be taken during Switching In addition to the above, it is necessary that special attention be paid to maintaining the reliability of the system. The following areas need careful implementation by the concerned constituents / stations i. In case of a two-bus system at any substation it must be ensured that the segregation of feeders on the different buses is uniform. This would help in minimizing the number of elements lost in case of a bus fault. This is assuming the availability of bus-bar protection at such substation(s). ii. In 400 kV substations having a breaker and a half scheme, it must be ensured that the two buses at such substation remain connected at least by two parallel paths so that any line / bus fault does not result in inadvertent multiple outages. In case any element, say a line or an ICT or a bus reactor, is expected to remain out for a period say beyond two hours at such substation, the main & tie breakers of such elements should be closed after opening the line side isolator. This should be done after taking all suitable precautions to avert inadvertent tripping. This of course assumes that no maintenance is planned on such breakers / isolators. iii. When the circuit breaker controlling the line is under lockout it is not advisable to interrupt the charging current through an isolator. The following practice is to be adopted in such cases:a. De-energise the bus connecting the line with lockout CB and then open the isolator b. If due to some reason it is not possible to open the isolator in above mentioned way, it is to be opened in such a way that no charging current is interrupted through the isolator and the charging current is diverted to other parallel path. Such switching sequence could be possible in case of breaker and half scheme or Double breaker Scheme, which is as follows: i. Open the line from remote end first with direct trip (DT) disabled. With this now line remains charged from the end where CB has problem. ii. In case of breaker and half scheme open the isolator so that charging current is diverted to the parallel path and after that open the CB of parallel path. iii. In case of double breaker scheme open the isolator of the lockout breaker diverting the charging current to other CB and then open the CB. iv. In case of double main and transfer scheme open the isolator of lockout breaker so that divert the charging current through transfer bus coupler and then open the line through TBC circuit breaker. It is also recommended that while vacating a bus in such cases, the operators need to check the switching arrangement for individual feeders so as to avoid unintended loss of any feeder. iv. The substation operators must ensure the above condition even when any lightly loaded line is opened to control overvoltage. Such opening of lines is generally superimposed over other line outages on account of faults created by adverse weather conditions resulting in reduced security of the system. v. Single pole auto-reclose facility on 400 kV / 220 kV lines should always be in service. ERLDC’s approval would be required for taking this facility out of service. Likewise, in 20 | P a g e ERLDC: POSOCO case any transfer breaker at any 400 kV substations having two main and transfer bus scheme is engaged, the same would be informed to ERLDC. vi. All precautions should be taken to avoid switching on to fault particularly in case of Interconnecting Transformers. In order to avoid fault current through costly equipment generally the line shall be charged from the far end, wherever possible. vii. A transmission line shall preferably be charged from the grid substation. Dead line charging by a generator shall normally be avoided except during system restoration, black start, or in case where both ends of the transmission line are terminating at a generating station. viii. During test charging of transmission line for the first time, all safety precautions shall be taken and the transmission utility owning/operating the line shall satisfy the substation utility at either ends with regards to statutory/safety clearances. During test charging if the line does not hold even after two attempts, thorough checking of protection settings and line patrolling shall be carried out. ix. Operation code issued by ERLDC for switching shall become invalid if the switching is not completed within half an hour of issue of code. In case the switching operation is not completed within half an hour of the issue of operation code from ERLDC, and if there is a probability of further delay same code could be revalidated by ERLDC within that half an hour. The utility obtaining at one end shall intimate the other end utility. Charging of partly constructed EHV O/H line from one end as an anti-theft measure 5.5. A number of EHV AC and HVDC O/H lines that have been planned either as ISTS strengthening schemes or as ATS of identified generation projects are under various stages of construction / commissioning in different regions. Incidents of theft of conductor / tower members of these partly constructed new lines are observed to be on the rise. In view of this, CTU / ISTS licensees are compelled to keep the partly constructed line energised from one end, as an anti-theft measure. Requests for using existing 132kV / 220kV lines for the purpose of anti-theft charging are frequently received at ERLDC. In this regard, the following guidelines may be followed by all ISTS licensees / CTU / STU:a) Efforts to be made to charge the line as far as possible from the nearest distribution line (11kV / 33kV), after obtaining due approval from the concerned SLDC / DISCOM b) For this purpose, the CTU/ISTS Licensee to approach the concerned SLDC / STU at least 15 days in advance of the tentative date of anti-theft charging, with a detailed plan indicating length proposed to be charged, duration of such charging, height, spacing etc. of the individual phases / conductors, size of the conductor that would remain charged, , connection arrangement with existing distribution line etc. accompanied by a clear diagram. c) STU / SLDC after examining the proposal may accord approval, if feasible, with necessary modifications of protection scheme of their distribution system. d) In the event it is not possible to identify suitable distribution line for the anti-theft charging or obtain approval of the concerned SLDC, the owner of the line under construction shall approach, ERPC apprising the difficulties in charging from distribution line, with a detailed proposal for anti-theft charging from the nearest 132kV line or 220kV line. In general, charging from a line of voltage higher than 132kV should be avoided to the extent possible. 21 | P a g e ERLDC: POSOCO e) On receipt of such request, ERPC to constitute a committee comprising representatives from ERPC, NLDC, ERLDC, owner of the new line, STUs / SLDCs likely to be affected and CTU for a joint study on the effects of such interconnection on the integrated grid. f) The said committee within 15 days shall recommend the modifications required / actions to be taken for ensuring compliance to CEA Technical Standards on Grid Connectivity, CEA Regulation (Measures relating to Safety and Electricity Supply), IEGC, and Grid Standards so far as protection, speech and data communication and safety of personnel are concerned, besides reliability of the grid as a whole. However, if the above conditions are not satisfied, the committee may even advise the transmission line owner not to attempt anti-theft charging of the partly constructed line. g) On completion of the recommended modifications / precautionary actions, the line may be charged with due consent of the concerned RLDC. 5.6. Procedure for certifying successful trial operation of new transmission element Regulation 5(2) of CERC (Terms and Conditions of Tariff), 2014 provides for certification of successful trial operation of new transmission assets by RLDC. The same is quoted below: “Trial operation in relation to a transmission system or an element thereof shall mean successful charging of the transmission system or an element thereof for 24 hours at continuous flow of power, and communication signal from sending end to receiving end and with requisite metering system, telemetry and protection system in service enclosing certificate to that effect from concerned Regional Load Dispatch Centre” Procedure In accordance with the above provisions and as a part of NLDC/RLDC operating procedure, the procedure for interconnection of a new transmission element belonging to any transmission licensee has been formulated to enable RLDCs / NLDC monitor and certify secure and reliable interconnection of new elements. The details of the same are as follows: (i) All the Transmission Licensees intending to commission any transmission element, which is a part of inter‐state transmission system, shall intimate the concerned RLDC the details as given below, generally (10) days prior to the anticipated date of first test charging. a. Annexure A1: Intimation regarding anticipated charging of the line along with the list of the desired documents being submitted as per Format I. b. Annexure A2 : List of elements to be charged and Element Rating details as per Format IA c. Annexure A3 : Single line diagram of the concerned sub stations, along with status of completion of each dia/bus/breakers clearly indicating which elements are proposed to be charged. d. Annexure A4 : List of SCADA points to be made available (as per standard requirement, RLDC would need all MW and MVAr data, voltage and frequency of all the buses, all the breaker and isolator positions, OLTC tap positions, Main‐1/Main‐2 protection operated signals) 22 | P a g e ERLDC: POSOCO e. Annexure A5 : Location of Energy meters as per relevant CEA regulations f. Annexure A6 : Connection Agreement, wherever applicable along with all annexures. (ii) In addition to these documents, charging instructions, details of approval of the transmission scheme from the Standing Committee / CTU, availability of line reactors as per approved scheme, approval for changes in the approved scheme, technical parameters of the transmission element required for network modeling shall be made available by CTU/STU, as the case may be, to RLDCs/NLDC. (iii) Within 3 days of submission of above information by the Transmission Licensee, concerned RLDC shall acknowledge the receipt of the same, as per Format II, and seek clarifications, if any. The transmission licensee shall submit the desired information/documents to the concerned RLDC within next three days. (iv) The request for charging of new transmission element and towards start of the trial operation as per Format III shall be submitted by the Transmission Licensee to the concerned RLDC, generally three (3) days prior to the date of first time charging. There could be a separate schedule for test charging and the final schedule for trial operation, which may be mentioned in the Format‐I itself. The Transmission Licensee shall also submit the following documents in this regard: a. Annexure B1: Request for charging of the new transmission element along with the summary of the undertakings being submitted as per Format III b. Annexure B2: Undertaking in respect of Protective systems as per Format III A c. Annexure B3: Undertaking in respect of Telemetry and communication as per Format III B d. Annexure B4: Undertaking in respect of Energy metering as per Format III C e. Annexure B5: Undertaking in respect of Statutory clearances as per Format III D (v) On satisfying itself with the submitted information as stated above under Para 3, the RLDC would issue a provisional approval for charging to the Transmission Licensee as per Format IV within two days of receipt of above documents. On the designated day, the transmission licensee shall charge the transmission line and do trial operation as per the timeline mentioned in Format III, after obtaining the real time code from RLDC. All attempts would be made by the real time operating personnel at the concerned RLDC to facilitate charging and commissioning of the new element at the earliest, subject to availability of real time data and favourable system conditions. (vi) Post successful trial operation, following documents shall be submitted by the Transmission Licensee: a. Annexure C1 : Request for issuance of successful trial operation certificate as per Format V 23 | P a g e ERLDC: POSOCO b. Annexure C2: Values of the concerned line flows and related voltages as per local SCADA just before and after charging of the element. c. Annexure C3 : Special Energy meter (SEM) Reading corresponding to the trial run d. Annexure C4 : Output of Disturbance Recorders / Event Loggers (vii) Within three (3) working days of submission of the information mentioned above, RLDC concerned shall issue the certificate for successful completion of trial run of the transmission element as per Format VI. (viii) In case of an inter‐regional element, both the respective RLDCs would be involved and a copy of the communications may be forwarded to NLDC also in such cases. NLDC would issue certificate for successful completion of trial run of the transmission element as per Format VI. All the formats mentioned above have been enclosed as Annexure IX 24 | P a g e ERLDC: POSOCO 6. Chapter 6 Periodic Reports and Event Information 6.0. Introduction Timely and accurate reporting and exchange of information plays an important role in grid operation. This assumes more importance during an occurrence/ a disturbance or in crisis. Timely and accurate information flow under such conditions would help operators in making an informed decision and reduces uncertainty. This chapter describes the event information and reporting procedure in writing to all Regional entities, ERPC Secretariat/ERLDC/SLDC in accordance with the provisions of clause 5.9 of IEGC. This section in accordance with clause 5.5 describes the different periodic reports to be prepared by RLDC to be sent to all entities of the region and ERPC Secretariat 6.1. Objective The objective of this chapter is to define the incidents to be reported, the reporting route to be followed and information to be supplied to ensure a consistent approach to the reporting of incidents/events. The Objective of the periodic reports are to highlight performance of the Regional Grid, bring out the system constraints, reasons for not meeting the requirements, if any, of security standards and actions taken. 6.2. Periodic Reports 5.2.1 Weekly Report As per clause 5.5.1 (C) of IEGC, ERLDC shall be responsible for issuance of weekly report that shall cover the performance of the Regional Grid for the previous week. ERLDC shall ensure that such weekly report be available at its website. The report shall be sent to all Regional entities and ERPC Secretariat and shall contain the following i. Frequency Profile ii. Voltage profile for selected substations iii. Major Generation and Transmission Outage iv. Transmission Constraints v. Instances of persistent/significance non compliance of IEGC vi. Instances of congestion in transmission system. vii. Instances of inordinate delays in restoration of transmission elements and generating units The format for weekly report is shown at Annexure X 5.2.2 Quarterly Reports A Quarterly report ( vide clause 5.5.2 of IEGC)shall be issued by ERLDC to all Regional entities detailing the power supply positions during the last quarter, quality of supply, the system constraints being faced and the agencies responsible causing constraints. The format for quarterly report is shown at Annexure XI 5.2.3 Exceptional Reports In case of any contingency such as industrial unrest, natural calamity etc., there could be additional reporting requirements not covered in the above schedule. ERLDC shall inform all regional entities of any such exceptional requirements and the entities would extend all necessary cooperation in this regard. 5.2.4 Under frequency Relay(UFR) Operation Report 25 | P a g e ERLDC: POSOCO In accordance with clause 5.2(n) of IEGC , all distribution licensees / STUs shall provide automatic under-frequency and df/dt relays for load shedding in their respective systems, to arrest frequency decline that could result in a collapse/disintegration of the grid, as per the plan separately finalized by the concerned RPC and shall ensure its effective application to prevent cascade tripping of generating units in case of any contingency. They shall inform (through their respective SLDCs) any UFR operation that has taken place in their system and the areas affected with approximate quantum of load relief obtained 6.3. Event Information 5.3.1 Vide clause 5.9.5 any of the following events require reporting by ERLDC/ Regional entity i) Violation of security standards ii) Grid indiscipline iii) Non compliance of RLDC’s instructions iv) System islanding / system split v) Regional blackout / partial system blackout vi) Protection failure on any element of ISTS and or any item on the agreed list of the intra-state systems vii) Power system instability viii) Tripping of any element of the regional grid ix) Sudden load rejection in regional entity’s control area 5.3.2 Any tripping of an element of 220 kV and above or others as listed under the list of important elements of regional grid, whether manual or automatic, shall be intimated by the control centre of the regional entity to ERLDC in a reasonable time say within 10 minutes of the incident. Along with the tripping intimation, the reasons for tripping (to the extent known) and the likely time of restoration shall also be intimated. Such information can be on telephone, fax or e-mail. 5.3.3 Any operation planned to be carried out by a regional entity which may have an impact on the regional grid or on any of the important element, shall be reported by the concerned SLDC to ERLDC in advance. 5.3.4 Any operation planned to be carried out on the instructions of ERLDC which may have an impact on the system of a regional entity shall be reported by ERLDC to the concerned SLDC in advance. 5.3.5 The intimation and the exact time of revival of any element under the category of important events shall be furnished to ERLDC as early as possible. 6.4. Reporting system The details of event reports and periodic reports to be prepared and issued by regional entities / ERLDC are as follows: 5.4.1 5.4.2 In the event of tripping of any important elements, the preliminary event report with possible details shall be sent by the SLDC of the concerned regional entity to ERLDC within a period of three hours of the occurrence of the event and the detailed event report in the form detailed under the section 5.9.6(C) of IEGC (contents vide Annexure XII) shall be sent within the next day. Such report shall follow the telephonic / flash reporting by the concerned SLDC say within a reasonable time say within 10 minutes of the occurrence of the event as stated under Para 5.2(d) 26 | P a g e ERLDC: POSOCO 6.5. Grid Incidence/Disturbances and Categorisation As per the severity of any events/incidences CEA has formulated the guidelines for categorisation of Grid incidences and disturbances. Any event to be reported may therefore need to be categorised as detailed below 6.5.1. Grid Incident A Grid incident is tripping of one or more power system elements of the Grid like a generator, Transmission line, Transformer, Shunt Reactor, Series capacitor, Static VAR Compensator (SVC) etc, with no loss of grid supply or integrity of the grid at 220kV and above. Categorisation of Grid incidents based in increasing order of severity Category: 1 Tripping of one or more power system elements of the grid like a generator , transmission line, transformer, shunt reactor, series capacitor, Static VAR Compensator(SVC) etc which requires rescheduling of generation or load without total loss of supply at a sub-station or loss of integrity of the grid at 220kV (132kV in case of NER) Category:2 Tripping of one or more power system elements of the grid like a generator , transmission line, transformer, shunt reactor, series capacitor, Static VAR Compensator(SVC) etc which requires rescheduling of generation or load without total loss of supply at a sub-station or loss of integrity of the grid at 400kV and above (220kV in case of NER) 6.5.2. Grid Disturbance Grid disturbance is defined as tripping of one or more power system elements resulting in total failure of supply at a sub-station or loss of integrity of the grid, at the level of 220kV and above (132kV and above in case of NER) Categorisation of Grid Disturbance in increasing order of severity is described as under. Category 1: When less than 10% of the antecedent generation or load in a Regional Grid is lost Category 2: When 10% to less than 20% of the antecedent generation or load in a Regional Grid is lost. Category 3: When 20% to less than 30% of the antecedent generation or load in a Regional Grid is lost Category 4: When 30% to less than 40% of the antecedent generation or load in a Regional Grid is lost Category 5: When 40% or more of the antecedent generation or load in a Regional Grid is lost. ERLDC shall maintain a log (Vide Annexure XIII) of such incidences/disturbances and whenever such incidences/disturbances occur shall report in writing (vide Annexure XII) as enumerated at para 5.4 Note: i) Any forced outage of ISGS generator would cause rescheduling of generation and corresponding revision of drawal. Therefore, this should be treated as Grid incidence. 27 | P a g e ERLDC: POSOCO 7. Chapter 7 Network Security and Congestion Management 7.0. Introduction This chapter describes the actions required to be undertaken by system operators to maintain the security of the network at all times against any plausible contingencies /outages within the ER network as well as from any contingencies arising out due to incidences occurring in the rest of the National grid that may have an adverse effect on ER system. 7.1. Network Security 7.1.1. Background The Indian power grid is one synchronous grid viz “NEWS” Grid comprising of Northern, Eastern, North Eastern, Western region and Southern Region grid. With formation of the NEWS Grid, there has been sea change in the operational philosophy in system operation that has already yielded various benefits like peak/off peak demand management through diversity of time, surplus/deficit management due to seasonal resource variations, demand forecast errors, weather variations besides increased economic transactions, improvement in overall system security due to increased stability margin and a higher stiffness to the tune of 6500-7000 MW/Hz. Eastern Region is strategically located with synchronised interconnections with all the other regions of the NEW Grid besides having synchronous integrated operation with Bhutan Power system. Eastern Grid is also connected to Southern Region through two no HVDC interconnections having a total capacity of 3500MW capacity. The large number of synchronous interconnections of Eastern Region with other regions/neighbouring country like Bhutan and radial connection with Nepal and with Bangladesh through B-t-B HVDC link has also resulted in evolution of contingencies of critical nature under different despatch/demand scenarios. In addition, system may operate at times beyond the assumptions of the planner in line with various transmission security standards and associated criteria mentioned in section 3.5 of IEGC due to following reasons: a) Planned maintenance programme of the generators and transmission lines. It is imperative to ensure that such maintenance programmes are properly coordinated and do not result in reduced redundancy not envisaged during planning. b) The events beyond the control of operators such as extreme weather conditions affecting the reliability of transmission system, uneven demand growth or delay in commissioning of generators/transmission elements. 7.1.2. Measures to ensure Network Security and Reliability In order to maintain the security of the Regional power system, it is important that the planned outages of generation and transmission system particularly in the corridors of important flow-gates are properly coordinated. A list of important Regional Grid elements (vide clause 5.2(c) of IEGC) of the Eastern regional grid which have a bearing on the network security are shown at Anneure-XIV. It is therefore necessary to carry out operational studies in order to assess the grid security and network stability while finalizing the annual outage plan of these important elements. The outage planning should be reviewed during the quarterly and monthly review of ERPC OCC forum. Additionally, any opening of the important elements have to be carried out only after prior Intimation to ERLDC as enumerated in the ‘Outage planning Procedure’. In the event of tripping of any of the important elements, ERLDC need to be informed at the earliest time indicating the likely time of restoration. It is necessary that special attention is paid for maintaining the reliability of the system. 28 | P a g e ERLDC: POSOCO 7.1.2.1. Assessment of Transfer Capability (Total Transfer Capability(TTC) and Available Transfer Capability(ATC)) While a Transmission system is built, inherent design margins are kept in order to take care of reliability and security issues, future generation growth, ROW issues, cost optimisation etc. The interregional interconnections as have been planned and over the years had also taken care of such margins. However, since power flow takes place as per the laws of physics and with more and more AC interconnections between Areas/Regions the transfer between two or more regions gets restricted because of factors like generation despatch conditions, loop flows between regions, upstream or down stream network limitations, voltage and angular differences between critical buses etc. Thus the Total transfer capability between areas is equal to or less than the aggregated design capacity of interconnection/s and therefore need to be assessed through power system studies well in advance considering the load / generation balance forecast to a fair degree of accuracy. “Total Transfer Capability (TTC)” means the amount of electric power that can be transferred reliably over the inter-control area transmission system under a given set of operating conditions considering the effect of occurrence of the worst credible contingency. “Transmission Reliability Margin (TRM)” means the amount of margin kept in the total transfer capability necessary to ensure that the interconnected transmission network is secure under a reasonable range of uncertainties in “Available Transfer Capability (ATC)” means the transfer capability of the inter-control area transmission system available for scheduling commercial transactions (through long term access, medium term open access and short term open access) in a specific direction, taking into account the network security. Mathematically ATC is the Total Transfer Capability less Transmission Reliability Margin. STOA- Bilateral+Collective ATC Medium Term Open Access Long Term Access TTC Reliability margin It is therefore imperative that the exchanges between regions are contained to a level of ATC and in no case exceed the TTC between the regions. All the regional entities of Eastern Region and / or neighbouring region(s) will adhere to their levels of net interchanges as advised by ERLDC whenever such breach in TTC level among the regions takes place to ensure the grid security irrespective of frequency and schedule. Assessment of Total Transfer Capability (TTC), Transmission Reliability Margin (TRM) and Available Transfer Capability (ATC) for import and export of power in Eastern Region as required for reliable system operation and for facilitating non-discriminatory open access in transmission shall be carried out by ERLDC in coordination with National Load Despatch Centre and other RLDCs. The ‘Detailed Procedure for Relieving Congestion in Real Time Operation’ as approved by the CERC vide order dated 22.04.2013 may be referred for further details. The assessed TTC, TRM and ATC shall be posted on ERLDC/NLDC website. 29 | P a g e ERLDC: POSOCO The detailed procedure for assessment of TTC, monitoring and invoking congestion conditions in real-time, application of Congestion Charge and Congestion Charge accounting and settlement shall be as per the regulation / procedure issued / approved by CERC 7.1.2.2. Generation Rescheduling ERLDC may revise the interchange schedule as allowed by IEGC regulation 6.4.12, 6.5.5, and 6.5.16. Further details may be seen in the chapter on scheduling. 7.1.2.3. Curtailment of Scheduled Transactions The transactions already scheduled may be curtailed by ERLDC in the event of transmission constraints; congestion in the grid, or in the interest of grid security. In line with regulations 6.4.12, 6.5.28, 6.5.30 and 6.5.31 of IEGC the transactions shall generally be curtailed in the following sequence for deviation from schedule a. Short term bilateral transactions b. Short term collective transactions c. Medium term transactions d. Long-term transactions Amongst the customers of a particular category, curtailment shall be carried out on pro rata basis. ERLDC would curtail a transaction at the periphery of the Regional entities. SLDC (s) shall further incorporate the inter-se curtailment of intra State entities to implement the curtailment. 7.1.2.4. Procedure for Relieving Congestion Congestion Management shall be as per the detailed procedure for relieving congestion in real time operationas approved by CERC vide its order dated 22.04.2013. It is important to note that the congestion charge could be applied both upstream and downstream of the congested corridor irrespective of the frequency. Whenever actual flow on inter/ intra regional link/ corridor exceeds Available Transfer Capability and security criteria are violated for continuously two time blocks, the National Load Despatch Centre may issue a warning notice. In case SLDC observes congestion within the Intra State grid it shall take appropriate action and inform the respective RLDC which in turn shall inform the NLDC. The notice for congestion shall be communicated to all the Regional entities telephonically or through fax/voice message/ e-mail and through postings on website and making the same available on the common screen at NLDC/ RLDCs/ SLDCs. The various formats may be referred in the detailed procedure for relieving congestion in real time operation under regulation 4 (2) of the Central Electricity Regulatory Commission (Measures to relieve congestion in real time operation) Regulations, 2009. In addition to above, Nodal Agency(NLDC) may issue instruction for Regulation Up / Regulation Down to any RRAS provider, through concerned RLDC, in line with the Central Electricity Regulatory Commission (Ancillary Services Operations) Regulations 2015, in case of likelihood or occurrence of violation of n-1 criteria for any of the transmission corridor or violation of ATC of any flow gate. 7.1.2.5. Defence Mechanism Despite utmost caution exercised during operational planning and implementing all the above steps to improve the network security and reliability, the possibility of a contingent situation cannot be totally ruled out. It calls for suitable defence mechanism to be available in the system to take care of such contingencies. Following are the minimum schemes which should be operational in Eastern Region to ensure safe and secure grid operation. i) Automatic Under Frequency Load Shedding Scheme. 30 | P a g e ERLDC: POSOCO In line with clause 5.2(n) of IEGC, all regional entities shall provide Automatic Under Frequency Load Shedding in their respective system to arrest frequency decline that could result in a collapse / disintegration of the grid as per the scheme formulated by ERPC forum and shall ensure its effective application and functionality at all times to prevent cascade tripping of generating units in case of any contingency. ERLDC shall inform ERPC Secretariat about instances when the desired load relief is not obtained through these relays in real time operation. ERPC Secretariat shall carry out periodic inspection of U/F relays and maintain proper records of the inspection. It is extremely important that there should be no overlapping between the areas covered by under frequency load shedding and that included in the manual load shedding plan as part of demand control. The approved Automatic Under Frequency Load Shedding Scheme at Annexure XV ii) Special Protection scheme Such schemes are required to take care of some special contingencies and operate under specific contingency conditions. Power Demand Over (PDO) ride at Gazuwaka and Talcher The Power Demand Override at HVDC stations control systems provide the features when power flow through HVDC System gets automatically changed to pre-set value when declared contingencies such as tripping/overloading of elements or tripping of generators take place. The HVDC back to back station at Gazuwaka having a transfer capacity of 1000 MW( 500 MW per pole block) is utilised for transfer of power from Eastern Region to Southern region. The station is connected to Jeypore 400kv substation of CTU in Eastern Region through D/C twin moose line. Jeypore substation is in turn connected to Indravati (PowerGrid) and Bolangir (PowerGrid) through S/C 400kV lines. Jeypore has further connectivity to 220kV system of OPTCL via 2x 315MVA ICTs. However under heavy power transfer to Gazuwaka(SR) from Jeypore tripping of any of the element as mentioned above might give rise to a contingent condition leading to cascade tripping of one or more elements within south Orissa network. In order to circumvent this contingency condition following special protection system of power demand override has been implemented at Gazuwaka HVDC station Similarly PDO at Talcher and Kolar is also designed to a preset value under certain contingencies. These PDOs are described at Annexure XVI Special protection system at HVDC Talcher( SPS 450 and SPS 1000) Talcher Super thermal power station having a capacity of 3000MW( 6x500 MW) is located in Orissa of Eastern Region. The station was commissioned with 2x500MW capacity and subsequently its second stage was commissioned and station capacity was augmented to 3000MW with commissioning of its further 4x 500MW machines. The station is the largest capacity station in the region. However, the capacity of the entire stage II ( 4x500 MW) was allocated to the beneficiaries of southern region. Subsequently, 10% of the capacity was allocated to the Orissa, in Eastern region. For evacuation of Talcher STPS –II generation to Southern Region, +/- 500kV HVDC bipole transmission system was commissioned right upto the load centre of Southern Region at Kolar. The HVDC substation at Talcher has two pole blocks 1000MW capacity each( subsequently augmented to 1250MW ). The very basic design of the evacuation system of Talcher stage II to SR poses a major threat to Eastern Region and subsequently to the New Grid as any sudden forced outage of one or both the poles would mean that Eastern Grid has to initially absorb a jerk of load throw off to the tune of 1800-2000MW . The surplus power would get wheeled through Talcher-Rourkella 400kV D/C 765 kV Angul – Jharsuguda S/C and 400 kV Rengali –Baripada-Kolaghat S/C. During monsoon as such these corridors remain heavily loaded and such contingency of pole block at Talcher 31 | P a g e ERLDC: POSOCO would lead to a definite cascade tripping leading to isolation /possible collapse of Orissa system including TSTPP station. In order to avoid such contingency two automatic special protection schemes were envisaged and have been implemented at Talcher Super Thermal power station. The 1st scheme as commonly known as SPS 450 was first implemented and subsequently a further improvised 2nd scheme was devised as known as SPS 1000 scheme. Both the schemes and their modalities of arming and disarming is described below: SPS 450: This scheme was originally implemented with a view that Eastern and Western Region would absorb a jerk of 450 MW therefore rest of the generation as available at Talcher stage II generation must be shed in order avoid a cascade tripping of the network. However, during monsoon, from Eastern Regional point of view at times absorbing even 450MW under N-1 contingency criteria of Talcher-Rourkella 400kV D/C Line becomes critical when major generation at Talcher stage II must be shed in order to avoid further criticality of the Grid. Further under any critical outage condition in the rest of the New Grid outage of HVDC bipole might pose a serious threat when it might necessitate arming of SPS -450 scheme with due coordination with NLDC. The Scheme is described below SPS 1000: Post formation of the NEW Grid this scheme was subsequently envisaged in order to minimise shedding of generation at Talcher STPP. The basic philosophy of this scheme is to absorb 1000MW in place of 450 MW as the Grid size increased. However, as one of the prerequisites for arming this scheme Eastern Regional operator has to ensure that sufficient evacuation margin( approx 1000 MW) is available at the AC evacuation system of TSTPP. The scheme is described below: Both SPS 450 and SPS 1000 schemes are described at Annexure XVII Modification in Talcher-Kolar SPS in ER Region due to Synchronisation of SR grid with NEW grid (Additional 600MW Gen Reduction): Background In Southern Region, there is a provision for load shedding in three groups depending on the power loss on HVDC (Trip Signal 1 for 800 MW load shedding, Trip Signal 2 for 700 MW additional load shedding, Trip signal 3 for 500 MW additional load shedding considering extended operation of HVDC in the 2000-2500 MW range). So a total of 2000 MW shedding is envisaged in Southern Region. In the NEW grid side of Talcher-Kolar HVDC bipole, there is automatic reduction/tripping of generation at Talcher Stage-II of NTPC. Two schemes are available at Talcher Stage-II; SPS 450 and SPS 1000 where the number indicates the quantum of power injected into the NEW grid after tripping of Talcher-Kolar HVDC pole or bipole. In SPS 450, three units are tripped at Talcher Stage-II while in SPS 1000, a maximum of one unit is tripped and the balance reduction in generation achieved through fast automatic reduction of generation. In normal operation, SPS 1000 is armed and in some exceptional cases such as an outage of elements in the NEW grid, SPS 450 is activated. There are instances when a single pole trips on line fault and the other pole goes to ground return. In such cases, the healthy pole retries thrice for going to metallic return and in case it fails, it goes in ground return mode where there is a restriction of 150 MW. There have been instances when the Talcher-Kolar SPS fails to operate leading to high frequency in the NEW grid and low frequency in the Southern Grid. Post 765 kV SholapurRaichur in operation, the impact of any failure of Talcher-Kolar SPS would lead to wheeling of additional power to Southern Region through the NEW grid creating insecure conditions. In fact, even injection of 1000 MW into NEW grid and inadequate load shedding in Southern Region can 32 | P a g e ERLDC: POSOCO lead to insecure conditions as the entire power would be wheeled through 765 kV SholapurRaichur. So, additional safeguards are required. Triggering the SPS and SPS action In case of single pole or bipole outage or blocking of Talcher-Kolar HVDC sensed at Talcher HVDC terminal, a trip signal is extended to nearby generators such as Sterlite, GMR, JITPL ensuring minimum communication so that the objective of restricting injection to NEW grid is achieved. The reduction in generation to be achieved through these stations is 600 MW. This would be in addition to SPS 1000 already in operation at Talcher-II. SPS 1000 will be functional as it is with additional relief of 600 MW in the event of Talcher- Kolar pole tripping to ensure grid security. Presently after commissioning of JITPL additional 600 MW quantum of generation reduction is shared in following ratio: - Sterlite- 200 MW, GMR-200 MW and JITPL- 200 MW. Special protection system at SEL (Sterlite Energy Limited) SEL have a total installed capacity of 2400 MW ( 4 x 600 MW) is located in Odisha. Out of these four units second unit (Unit-2) is dedicated to Odisha and is connected at separate 400 kV Bus (400 kV OPTCL bus) which also have 2 x 315 MVA 400/220 KV ICT installed. The 220 kV side of this SEL bus is connected with 220 kV VAL (Vedanta Aluminium limited) through 220 kV SELVAL D/C. The remaining three unit at SEL (Unit 1, 3 & 4) is connected to other 400 kV Bus at SEL (400 kV PGCIL bus) which further have two outgoing lines connected to it, one to Rourkela and one to Raigarh. In turn these two lines i.e 400 kV SEL-Raigarh S/C and 400 kV SEL-Rourkela S/C is used to evacuate power from SEL. SPS at SEL continuously monitor flow of all 400 kV lines and it gets actuated whenever flow of any line touches 650 MW. In case flow of any line exceeds 650 MW, generation reduction at SEL took place to bring the line loading under limit. 33 | P a g e ERLDC: POSOCO CASE 1 (400kV Buses are Decoupled) a) Contigency:-Tripping of 400kV SELROURKELA (PGCIL LiLO-1) Effect:‐ Over Loading of 400kV SEL‐Rourkela(beyond 650 MW)‐LIL0‐2 CILMS Action Depending up on flow of 400kV SEL‐ Rourkela if Loading is greater than 650 MW but Grid Export Violation Value less than 30% of Priority one Generator MW(say Gen1) i) CILMS Action :‐ Tripping of Priority one Generator HPLP (among Unit 1,3 and 4) if Grid Export Violation Value is greater than 30% of Priority one Generator MW(say Gen1) but less than sum of 30% of Priority one Gen MW and 30% Prioriy two Gen MW(if Prio2 Gen not available in the network then prio3 Gen will concider) ii) CILMS Action :‐ Tripping of Priority one Generator HPLP and Prio2 Generator HPLP (if Prio2 Gen not available in the network then prio3 Gen will concider among Unit 1,3 and 4) iii) if Grid Export Violation Value is greater than 30% of sum of all available Generators MW in the network but less than Priority one Gen MW (say Gen1) CILMS Action :‐ Tripping of Priority one Generator (among Unit 1,3 and 4) if Grid Export Violation Value is greater than Priority one Generator MW(say Gen1) but less than sum Priority one Gen MW and 30% Prioriy two Gen MW(if Prio2 Gen not available in the network then prio3 Gen will concider) iV) CILMS Action :‐ Tripping of Priority one Generator and Prio2 Generator HPLP (if Prio2 Gen not available in the network then prio3 Gen will concider among Unit 1,3 and 4) CASE 1 (400kV Buses are Decoupled) b) Contigency:-Tripping of 400kV SELRAIGARH (PGCIL LiLO-1) Effect:‐ Over Loading of 400kV SEL‐Raigarh(beyond 650 MW)‐LILO‐2 CILMS Action Depending up on flow of 400kV SEL‐ Raigarh if Loading is greater than 650 MW but Grid Export Violation Value less than 30% of Priority one Generator MW(say Gen1) i) CILMS Action :‐ Tripping of Priority one Generator HPLP (among Unit 1,3 and 4) if Grid Export Violation Value is greater than 30% of Priority one Generator MW(say Gen1) but less than sum of 30% of Priority one Gen MW and 30% Prioriy two Gen MW(if Prio2 Gen not available in the network then prio3 Gen will concider) ii) CILMS Action :‐ Tripping of Priority one Generator HPLP and Prio2 Generator HPLP (if Prio2 Gen not available in the network then prio3 Gen will concider among Unit 1,3 and 4) iii) if Grid Export Violation Value is greater than 30% of sum of all available Generators MW in the network but less than Priority one Gen MW (say Gen1) CILMS Action :‐ Tripping of Priority one Generator (among Unit 1,3 and 4) if Grid Export Violation Value is greater than Priority one Generator MW(say Gen1) but less than sum Priority one Gen MW and 30% Prioriy two Gen MW(if Prio2 Gen not available in the network then prio3 Gen will concider) iV) CILMS Action :‐ Tripping of Priority one Generator and Prio2 Generator HPLP (if Prio2 Gen not available in the network then prio3 Gen will concider among Unit 1,3 and 4) 1 2 * In GS Display Two separate Export setpoint is given for PGCIL GRID PGCIL Grid Export Setpoint (if Both the PGCIL Grid Lines are Connected) PGCIL Single Grid Export Setpoint (if only one PGCIL Grid Line connected) 34 | P a g e ERLDC: POSOCO SPS for power transfer to Bangladesh Bheramara back-to-back HVDC station with a capacity of 500 MW was commissioned in October 2013 in Bangladesh. Bheramara is connected to Behrampur in West Bengal, India through a 400 kV D/C line. 400 kV Farakka-Jeerat was LILOed at Behrampur to facilitate power transfer to Bangladesh. Keeping in mind low voltage problems at Jeerat and system security, the following SPS was devised and put into operation: S. No. Triggering Criteria for SPS SPS actions (signal shall be generated to do following) Signal to be sent Bheramara (Yes/No) 1 Voltage at 400kV Behrampur going below 390kV To trip 80 MVAR Bus reactor at 400kV Behrampur. No, Local action at Behrampur. 2 Voltage at 400kV Behrampur going below 380kV, the SPS shall generate a signal. To ramp down HVDC set-point to 350 MW (with Appropriate Filter switching to maintain Bheramara Voltage) Yes 3 If the frequency goes below 49.5 Hz. To ramp down HVDC set-point to 350 MW (with Appropriate Filter switching to maintain Bheramara Voltage) Yes 4 If the 400kV FarakkaBehrampur line flow goes above 780 MW (Flow may touch 800 MVA). To ramp down HVDC set-point to 350 MW (with Appropriate Filter switching to maintain Bheramara Voltage) yes 5 Tripping of 400kV Sagardighi-Baharampur D/C as well as FSTPSBaharampur S/C (sensed by opening of CB contacts at Baharampur) To ramp down HVDC set-point to 350 MW (with Appropriate Filter switching to maintain Bheramara Voltage) yes iii) Islanding Scheme To avoid total black out of the grid during system disturbances and for early normalisation, the procedure for islanding of systems and major generating stations with associated loads need to be developed constituent wise/system wise. The islanding schemes as in operation in Eastern Region is shown at Annexure XVIII 7.1.2.6. Switching Diagram The switching diagrams of all generating stations (100 MW and above), 400kV, important 220kV and 132kV substations especially those involved in the evacuation of generation shall be made available to ERLDC system operator at SCADA Desk. The selection of such diagrams is described at Chapter 8. The same shall be updated from time to time. 35 | P a g e ERLDC: POSOCO 7.1.2.7. Operational Areas of Importance The following areas needs careful implementation by the concerned constituents / stations:i) In case of a 2 main & transfer bus system at any sub-station, it must be ensured that the segregation of feeders on the different buses is uniform. It would help in minimizing the effect on the system in case of a bus fault. ii) In 400kV substations having one and half breaker scheme, it must be ensured that each feeder remains connected to both the buses so that any bus fault does not result in inadvertent outage of feeders. In case any element, say a line or an ICT or a bus reactor, is expected to remain out for a prolonged period at such substation, the main and tie breakers of such elements should be closed after opening the line side isolator. This should be done after taking all suitable precautions to avert inadvertent tripping. iii) The substation operators must ensure the above condition even when any lightly loaded line is opened to control over voltage. Such opening of lines is generally superimposed over other line outages on account of faults created by adverse weather conditions resulting in reduced security of the system. iv) Single pole auto reclose facility on 400kV lines should always be in service. Approval of ERLDC would be required for taking this facility out of service. Likewise, in case any transfer breaker at any 400kV substations having two main and transfer bus scheme is engaged, the same would be informed to ERLDC. v) In order to damp out the low frequency oscillations in the system, the power system stabilizers on the generating units would be tuned as per the programme drawn at ERPC forum. in consultation with the constituents. vi) All regional entities would endeavor to operate the connected generation and reactive power management devices such as Capacitors, Reactors, Synchronous Condensers, Fixed Series Capacitors (FSCs), Static Var Compensators (SVCs) etc in a manner which enables stable voltage behavior at various points of the grid under different operating conditions. vii) All regional entities would also maintain in good operating conditions of all control measures such as defence mechanism, SPS, U/F & U/V load shedding, AVRs, PSS, FGMO, Operating reserves, emergency back-up power supplies etc., and ensure that the operational security standards are maintained for reliable and secured operation of the interconnected system. viii) In line with sections 5.2(f) of the IEGC, the generating units should ensure free governor operation. 7.1.2.8. i) ii) Recording Instruments, Voice and Communication Facilities The recording instruments such data acquisition system, disturbance recorder event logger, fault locator, time synchronization equipment voice recorder and any other such equipment in each generating station / sub-station / control centre / SLDCs / ERLDC shall be kept in good working condition in order to record the events and sequence. All such places shall have a common time reference whose authenticity shall be ensured by periodic verification and validation procedure to be developed and monitored by ERPC Secretariat. Each regional entity shall provide adequate and reliable communication facility internally and with other constituents / RLDC to ensure exchange of data / information necessary to maintain reliability and security of the grid. All the agencies shall provide systems to telemeter power system parameters such as power flow, voltage and status of switches/transformer taps etc., in line with interface requirements and other guidelines made available to RLDC / SLDCs atleast before the date of commercial operation of the generating stations or substation/line being connected to the ISTS. 36 | P a g e ERLDC: POSOCO iii) iv) v) In line with Central Electricity Authority (Technical Standards for Connectivity to Grid) Regulations 2007, the requester and user shall provide necessary facilities for voice and data communication and transfer of online operational data such as voltage, frequency, line flows and status of breaker and isolator position and other parameters as prescribed by the appropriate Load Despatch Centre and agree to maintain the communication system in good condition. In line with Central Electricity Authority (Technical Standards for Connectivity to Grid) Regulations 2007, every generating station and substation connected to the grid at 220kV or above shall be provided with disturbance recording (DR) and event logging facilities. All such equipment shall be provided with time synchronization facility for common time reference. For a high degree of service reliability under normal and emergency operation, at least one main telecommunication channel with an alternate backup channel shall be provided 7.1.2.9. Monitoring of System States (Grid Health) As a corollary to the provisions laid down in the IEGC chapter on Operating Code for Regional Grids, ERLDC has the responsibility of monitoring the state of the regional grid at all times. The state of the grid has been classified as either NORMAL or ALERT or EMERGENCY, depending on whether certain security criteria are violated or not, as stated below. The display system in control room has been accordingly modified to alert the operator, in case the state of the grid passes to either to ALERT mode or EMERGENCY mode. The Boolean conditions for various modes are as follows: NORMAL mode – (50.05 Hz Grid frequency 49.9 Hz) AND (No Flowgate limit, as specified by operator violated) ALERT mode – Actual flow through Flowgate-1 Limit specified by operator OR Actual flow through Flowgate-2 Limit specified by operator OR Grid Frequency 49.9 Hz & > 49.7 Hz OR Grid Frequency > 50.2 Hz EMERGENCY mode – (Resultant output of ALERT mode) AND (Grid Frequency 49.7 Hz) 7.2. Periodic auditing of protection system With a view to ensuring security of the integrated grid at all times, the Task Force on “Power System Analysis Under Contingencies” in its report recommended periodic auditing of the protection system of every region. Accordingly, auditing of all sub-stations / power stations of ER grid is to be carried out every year. For this purpose, one or two teams comprising representatives from ERPC Secretariat, POWERGRID, ERLDC and an STU (other than the one being audited) would be constituted by PCC and the team would visit the substations to be audited as per a schedule chalked out by PCC. All substations / power stations of the region that are of 220kV and above, would be covered within the scope of the audit. For the purpose of audit, the team would follow a checklist which has been finalised in ERPC forum. The same is given in Annexure. The checklist by and large encompasses all the points as mentioned in the report of the Task Force on “Power System Analysis Under Contingencies”. 37 | P a g e ERLDC: POSOCO On completion of audit, the teams would submit their observations and recommendations on the corrective actions to be taken, if any, by the concerned STU/ GENCO or CTU. If there is any scope for improving the existing protection infrastructure, the audit team may also recommend the same. Action plan for implementing the recommendations of the protection audit would be prepared in RPC forum and the same would be regularly monitored/ reviewed in monthly PCC meetings. 38 | P a g e ERLDC: POSOCO Chapter 8 8. Scheduling and Despatch Procedure 8.0. Introduction The broad principles and guidelines to be followed for scheduling and dispatch of power in the regional ISTS and the demarcation of responsibilities for this purpose are in accordance with Part 6 of the IEGC. 8.1. Scope This procedure is applicable to ERLDC and other RLDCs, all the thermal and hydro ISGSs on which beneficiary constituents have shares, the beneficiary constituents of Eastern Region and any regional entity. For the purpose of implementation of the schedules for import of power from Hydro stations in Bhutan, this procedure shall also be applicable to the hydro stations of Bhutan 8.2. Objective This chapter deals with the procedures to be adopted for scheduling of the inter-State generating stations (ISGS) and net exchange of regional entities on a daily basis with the modality of the flow of information among the ISGS/RLDCs/entities of the Region. The procedure for submission of capability declaration by each ISGS and submission of exchange schedule by each beneficiary is intended to enable RLDCs to prepare the dispatch schedule for each ISGS and exchange schedule for each beneficiary. It also provides methodology of issuing real time dispatch/drawal instructions and rescheduling, if required, to ISGS and beneficiaries. 8.3. Description of the procedure The Regional grids shall be operated as power pools (with decentralized scheduling and dispatch), in which the States shall have operational autonomy, and SLDCs shall have the total responsibility for (i) scheduling /dispatching their own generation (including generation of their embedded licensees), (ii) regulating the demand of their customers, (iii) scheduling their drawal from the ISGS (within their share in the respective plant’s expected capability), (iv) arranging any bilateral interchanges, and (v) regulating their net drawal from the regional grid. The system of each State shall be treated and operated as a notional control area. The algebraic summation of scheduled drawal from ISGS , longterm access , medium term and short-term open access arrangements shall provide the drawal schedule of each State, and this shall be determined in advance on daily basis. The regional entities shall regulate their generation and / or consumers’ loads so as to maintain their actual drawal from the regional grid close to the above schedule. The regional entities, through their SLDCs shall always endeavour to restrict their net drawal from the grid within their respective schedules. The introduction of the scheduling and despatch mechanism as mandated in IEGC, has further evolved the framework for developing other power markets such as Short term open access transactions and collective transactions that can fit in with the scheduling and despatch procedures as mandated in IEGC. Further CERC has also issued regulation on Short Term and and Collective transactions and procedure for short term and collective transactions have been duly issued by CTU and approved by CERC. Therefore procedure as issued by CTU on Short term and Collective may be referred separately as a part of this procedure. In order to understand the procedure and bring in more clarity the scheduling and despatch procedure has been prepared in the form of flow chart as described below: The entire activities are broadly divided into three parts namely (i) Day ahead scheduling (ii) Revision of schedules (iii) Implementation of Final schedules 39 | P a g e ERLDC: POSOCO All the relevant formats are enclosed at Annexure XIX Under fuel shortage conditions, thermal ISGSs may face constraints in adhering to the usual scheduling procedure. They may propose to deliver a higher MW during peak-load hours by saving fuel during off-peak hours, in pursuance to Clause 21(4) of the CERC Terms and Conditions of Tariff 2009-14. The broad guidelines to be followed for scheduling ISGSs under such conditions are as follows: Fuel shortage would be declared by the generating stations on a day ahead basis only and status cannot be changed during the day of operation even if fuel supply status changes, except in case of unit tripping. The concerned plant shall declare its energy capability (MWh), maximum ex-bus generation (MW) and minimum possible ex-bus generation (MW) that can be maintained. Utilities may requisition based on their requirements either as average MW in all time blocks or different MW in different time blocks upto the entitled maximum MW remaining within the total energy entitlement for the day. The default would be average MW during all blocks for those beneficiaries whose time-block wise requisition is not received by RLDC. Peak hours shall be of minimum three hours duration as decided on a regional basis through Operational Coordination sub Committee (OCC) meetings of the RPC. In between the month changes could also be done by RLDC with advance declaration of two days. The OCC can also decide peak hours as more than 3 hrs based on regional load curves either in one continuous spell or two spells for covering morning and evening peak hours. [e.g. one and half hour continuous or 1 hour and 2 hour continuous in each spell]. DC for the day in such an event shall be taken to be equal to the maximum peak-hour expower plant MW schedule specified by the concerned Load Despatch Centre for that day. Procedure for revising ISGS schedule downwards on account of surrendering of share by beneficiaries 8.4. As already mentioned in this chapter, the beneficiaries of an ISGS have full autonomy in deciding their respective requisitions from the ISGS. Thus, in the event of low demand as well as high availability from own generating stations, a beneficiary may either not requisition its full share or even prefer to forgo its full share from the ISGS. Such surrendering by multiple beneficiaries of a thermal ISGS for a particular time period , may cause the despatch schedule of the station to become less than the minimum level of generation technically achievable by the thermal units. Under such circumstances ERLDC will moderate the requisitions of the under-requisitioning beneficiaries in a manner so that unrealistic backing down or shutting down of thermal unit can be avoided. The general philosophy to be adopted is as follows: 8.4.1. Before issuance of revision 0 schedule (at 17:00 Hrs) for the next day If the generation schedule on certain time blocks determined by summing the requisitions of its beneficiaries is found to be less than the minimum level of generation technically achievable by station, the Central Generating Stations (CGS) or Inter State Generating Stations (ISGS) have the option to go for reserve shut down, as per Regulation 6.3B of the IEGC. Such ISGS / CGS shall be entitled to compensation for additional fuel cost towards operating below normative plant availability factor & for multiple start / stop operations, as per provisions laid down in the IEGC. 40 | P a g e ERLDC: POSOCO 8.4.2. Before issuance of revision 1 schedule (at 23:00 hrs) for the next day (a) If the dispatch schedule of the station on certain time blocks is already below the declared capability and further surrendering of share by any beneficiary leads to a schedule that is below the minimum level of generation technically achievable by the station, then the revision in requisition will be accommodated as per provisions of Regulation 6.3B of IEGC. (b) In case of surrendering of share by multiple beneficiaries received between 17:00 hrs to 22:30hrs, pro-rata approach will be adopted. 8.4.3. On the day of operation: Surrendering of share will be considered on first-come-first-serve basis. At any stage, if the dispatch schedule is already at the minimum level of generation technically achievable by the station, and there is further request for surrendering of share,. the Central Generating Stations (CGS) or Inter State Generating Stations (ISGS) have the option to go for reserve shut down, as per Regulation 6.3B of the IEGC. 8.4.4. Status of requisition Requisition for revision received at ERLDC will remain valid till the revision of corresponding schedule is carried out and published. Thereafter validity of the same requisition will expire and no reference of any earlier requisition can be drawn at a later time/date. 8.4.5. Revision of schedule for upward revision of entitlement As per present practice agreed by all constituents, in case of upward revision of entitlement, full entitlement will be scheduled to those constituents who have already requisitioned full entitlement previously. In case there is already less requisition by any constituent from ISGS/s for some block, no revision of schedule will be carried out for upward revision of entitlement for those blocks for that constituent provided minimum level of generation technically achievable by the station criteria is satisfied. If minimum level of generation technically achievable by the station criteria is/are not satisfied, then ERLDC shall increase requisition of that constituent to the extent to give minimum level of generation technically achievable by the station schedule of that ISGS. However, for those blocks where full entitlement is requisitioned the same constituents, ERLDC will schedule full entitlement for that constituent. 8.4.6. Revision of schedule for downward revision of entitlement In case of downward revision of entitlement, revision of schedule will be carried out subject to restricted entitlement. No revision will be carried out for that constituent, whose requisition is already below entitlement previously minimum level of generation technically achievable by the station criteria is/are satisfied and requisition is less than revised entitlement. If minimum level of generation technically achievable by the station criteria is/are not satisfied, then ERLDC shall increase requisition of that constituent to the extent to give minimum level of generation schedule technically achievable by the that ISGS. In case of subsequent upward revision of entitlement, same methodology as followed in case of upward revision of entitlement will be followed. For those constituents, who have given less requisition from any ISGS earlier and due to subsequent downward revision of entitlement from same ISGS which is less than the requisition(specially when unit trips), schedule from that ISGS will be restricted to entitlement for that constituent and validity of earlier requisition of that constituent will expire. In case of subsequent upward revision of entitlement from same ISGS (specially when unit returns), ERLDC will schedule full entitlement from that ISGS to the same constituent. 41 | P a g e ERLDC: POSOCO 8.4.7. Scheduling of LTA and MTOA: 1. Constituent/Generator would only furnish to ERLDC the mutually agreed schedules by 17:00 Hrs for the next day. Endorsement of the concerned SLDC/RLDC (when one of party is from outside region) will be required. 2. ERLDC would incorporate the schedules and release the schedule for next day by 18:00 hrs. 3. SLDCs/Generators can inform of any mutually agreed changes duly endorsed by concerned SLDC/RLDC (when one of party is from outside region) by 22:00 hrs of previous day to ERLDC. 4. Schedules for next day to be frozen by 23:00 hrs 5. Revision of the schedule during course of the day would be permitted, depending upon intimation of the revised mutually agreed schedules duly endorsed by concerned SLDC/RLDC (when one of party is from outside region) to ERLDC. The concerned SLDCs/RLDCs (when one of party is from outside region) may also give standing instructions to ERLDC in advance to accommodate all day ahead requisition/revision on the day of operation, on behalf of constituents under their jurisdiction so that schedule furnished by other constituent/s/generator/s will be construed as mutually agreed schedule and will be revised accordingly. 6. In case of tripping of unit of Generating station/s having LTA, schedule will be revised with intimation to concerned SLDCs/RLDCs. The revised schedules shall become effective from the 4th time block, counting the time block in which the forced outage is declared and revision sought in MW quantum from the generator to be the first one. 7. Revised schedules for other revision shall become effective from the 4th time block, counting the time block in which revised mutually agreed schedule duly endorsed by concerned SLDC/RLDC(when one of party is from outside region)has been received by ERLDC to be the first one. 8.4.8. Scheduling of power to Bangladesh Scheduling of power transfer to Bangladesh will be mainly coordinated between NLDC India and NLDC Bangladesh. On the basis of ISGS availability and percentage share allocation NLDC will prepare Bangladesh entitlement. Final schedule will be prepared considering ISGS allocation, approved STOA and available margin. ERLDC will only implement the approved schedule by NLDC. 42 | P a g e ERLDC: POSOCO Procedure, priority, timeline etc. for scheduling for all types of transactions shall be guided by IEGC and other regulations of CERC amended time to time 8.4.9. Revision of schedules on Unit tripping: As per Cl 6.5.19 and 6.5.19A of IEGC, generators are to give the requisition for revision of schedule on outage of a unit. The relevant clause is quoted below: “Notwithstanding anything contained in Regulation 6.5(18), in case of forced outage of a unit for a Short Term bilateral transaction, where a generator of capacity of 100 MW and above is seller, the generator shall immediately intimate the same along with the requisition for revision of schedule and estimated time of restoration of the unit, to SLDC/RLDC as the case may be. With the objective of not affecting the existing contracts, the revision of schedule shall be with the consent of the buyer till 31.07.2010. Thereafter, consent of the buyer shall not be a pre-requisite for such revision of schedule. The schedule of the generator and the buyer shall be revised, accordingly. The revised schedules shall become effective from the 4th time block, counting the time block in which the forced outage is declared to be the first one. The RLDC shall inform the revised schedule to the seller and the buyer. The original schedule shall become effective from the estimated time of restoration of the unit. However the transmission charges as per original schedule shall continue to be paid for two days” Also as per Cl 6.5.19A, curtailment of ST/MT/LT transactions are to be done on pro-rata basis. The relevant clause is given below: “In case of revision of schedule of a generating unit, the schedules of all transactions under the long-term access, medium-term open access and short-term open access (except collective transactions through power exchange), shall be reduced on pro-rata basis” Accordingly, the generators/traders/sellers should intimate the curtailed figures for each transaction/contract depicting the figures block wise. The details of methodology of pro-rata curtailment indicating DC (old) and DC (new) should be clearly depicted in the requisition. Also at the end, all the entities should confirm the following: “Curtailments have been done on pro-rata basis as per Cl 6.5.19 and 6.5.19A of IEGC without preference to any transaction/contract”. 8.4.10. Availing of URS power by beneficiaries: As per CERC order Dtd.11/01/10 on providing flexibility in revision of daily schedule in case of bilateral transactions in order to facilitate utilization of un-requisitioned surplus (URS) Power to NTPC stations, CERC has stated the following: “We direct that all the generating stations, governed by the Tariff Regulations of the Commission be allowed to change schedule for the unrequisitioned quantum of power from one beneficiary(s) to another beneficiary(s) of the same power station on the requisition by these beneficiaries through the provision provided in the IEGC, i.e. within six time blocks or as per the provisions of the IEGC as amended from time to time. In case the original beneficiary requests back for its share of power, then its schedule and schedule of beneficiary who had availed URS power would be revised in the six time blocks again, or as specified in the IEGC as amended from time to time. These schedule revisions would be treated as re-allocation of power on temporary basis and would not be taken as open access transactions” To facilitate transaction of such URS, the beneficiary desiring the URS power shall send the URS requisition file to the desired ISGS and subsequently the desired ISGS shall endorsed the URS requisition of the beneficiary and should send the file to ERLDC ISGS source-wise for implementation in the daily schedules. In case the beneficiary is inter regional, then after receipt of the ISGS endorsed file ERLDC shall implement the URS file subject to margin available in the desired Inter regional Path. 43 | P a g e ERLDC: POSOCO 8.4.11. Down Scheduling of Reserve Regulation Ancillary Services Regulation Up and The ‘Ancillary Operation Service’ Procedure is issued in compliance to Regulation 14of the Central Electricity Regulatory Commission (Ancillary Services Operations) Regulations 2015, herein after referred to as the “AS Regulations”. The objective of AS Regulations is to help in restoring the frequency level to the nominal level and to relieve the congestion in the transmission network. All Generating Stations that are Regional Entities and whose tariff for the full capacity is determined or adopted by the Central Electricity Regulatory Commission (CERC) shall provide the Reserves Regulation Ancillary Services (RRAS Provider). National Load Despatch Center (NLDC), as the Nodal Agency, shall be responsible for implementation of Ancillary Services at inter-state level through the Regional Load Despatch Center (RLDCs). The Nodal Agency shall prepare merit order stack of all RRAS Providers based on the variable cost of generation as the data provided by the RRAs provider to respective RPCs and NLDC. The merit order stack shall be sorted from the lowest variable cost to the highest variable cost for the purpose of implementation of the “Up Regulation” of RRAS and shall be sorted from the highest variable cost to the lowest variable cost for the purpose of implementation of the “Down Regulation” of RRAS. NLDC shall Trigger RRAS Regulation Up and Regulation Down as per the system condition/ criteria mentioned in the procedure and send the file to respective RLDC for implementation. RLDC after implementation of RRAS file within the time line as mentioned in procedure, upload the schedule in its website and intimate the RRAS provider through mail or over phone. NLDC/RLDC may direct the selected RRAS Provider(s) (through RLDC) to withdraw their services after the circumstances leading to triggering of RRAS no longer exist and in case of other reasons like unit tripping, withdrawal of under requisition by the beneficiary etc. The time-frame for implementation and withdrawal of service shall be determined as per the Detailed Procedure. A virtual regional entity called “Virtual Ancillary Entity (VAE)” is created by each RLDC for only scheduling purpose. The schedule under Ancillary for the VAE shall be deemed delivered. For Regulation Up Service, power shall be scheduled from the RRAS Provider to the respective VAE by the RLDC and for Regulation Down Service, power shall be scheduled from the respective VAE to the RRAS Provider. The schedule of the RRAS Providers will become effective earliest from the time block starting 15 minutes after issue of the dispatch instruction by the NLDC or from any time block as mentioned in NLDC RRAS file. The schedule of the RRAS Provider shall be at ex-bus periphery. The injection loss (for Regulation-UP service) and the withdrawal loss (for Regulation-DOWN service) is accounted for in kind in the schedule of the respective VAE. In case of downward DC revision due to unit tripping in the station of the RRAS provider, the RRAS power shall be curtailed first, followed by STOA, MTOA and LTA transactions. RRAS curtailment shall be effective from the second time block considering the time block in which the intimation is received as the first time block. In case of transmission line tripping/congestion in evacuation of power from the RRAS provider generating station, the schedules of the respective RRAS Provider generating station 44 | P a g e ERLDC: POSOCO shall be revised by the quantum scheduled by the Nodal Agency under RRAS followed by STOA, MTOA and LTA transactions as per requirement. Once the URS power from a RRAS provider has been scheduled under RRAS, then, this can be recalled only by the original beneficiary in accordance with the CERC Ancillary Services Operations Regulations 2015.In case any beneficiary other than the original beneficiary requests for URS power from a generating station which is a RRAS provider, such request will not be considered by RLDCs if the same URS power has already been scheduled under RRAS 45 | P a g e ERLDC: POSOCO Name of the Activity: SCHEDULING FOR DAY AHEAD START Receive from each ISGS Capacity Availability in Form - A format at 09:00hrs ISGS Ex-pp Declare Capacity Availability for the following day No Is all applicable DCs Received ? Yes % Weekly Loss & Share Allocation % Prepare ISGS Entitlement of all constituents in 15min time blocks for the following day - Form - B Send Form - B to all the beneficiary constituents at 10:00hrs (R0) & then Subsequent revisions. Yes Is there any change in ISGS DC? DC_ Rev No Receive STOA Data from OA Dept. Check and configure the Advance Approved STOAs Receive requisition from each constituent in Form C format at 15:00hrs No ISGS & STOA (Advance Appd) requisitions of Constituents Are Requisitions of all constituents received? Yes Cont..2 46 | P a g e ERLDC: POSOCO From 1 Receive Data from NLDC at 15:00hrs PX Transaction Wheeling Diversiion Inter Regional Trx Preparation of Constituent's Drawal Schedule & ISGS Despatch Schedule Req_ Rev Not OK OK Check for Tr Constraint, Tech Min & Ramping Send Drawal Schedule to SLDCs & Despatch Schedule to ISGS -(Form - D) for the following day at 17:00hrs Yes Is there any URS Broadcast the URS Details to All the Constituents & Upload to RLDC Website No Receive Data from Grid Mgmt Check / configure the Day Ahead Approved STOAs Req_ Rev Requisition Change Is there any change in ISGS DC or Constituent’s Requisition? DC_Rev DC Change No Preparation of Constituent's Drawal Schedule & ISGS Despatch Schedule Send final Drawal Schedule to SLDCs & Despatch Schedule to ISGS -(Form - D) for the following day at 23:00hrs Is there any URS Power? END 47 | P a g e ERLDC: POSOCO Activity: REVISION OF CURRENT DAY SCHEDULE START No Is there any Change in DC of ISGS? RR Yes Receive the revised of ISGS Capacity Availability in Form A format Receive Revised Declaration of Available Capacity of ISGS Yes No Prepare ISGS Entitlement of all constituents in 15min time blocks w.e.f 6th time block Form - B Is it due to forced outage of Unit? Send From - B to all the beneficiary constituents Send From - B to all the beneficiary constituents Receive Revised Requisition from the Beneficiary Constituents Receive requisition from constituent in Form - C format Prepare ISGS Entitlement of all constituents in 15min time blocks w.e.f 4th time block Form - B Preparation of Constituent's Drawal Schedule & ISGS Despatch Schedule Not OK OK Send Drawal Schedule to SLDCs & Despatch Schedule to ISGS. (Form - D)& upload to web Check for Tr Constraint, Tech Min & Ramping Yes Is there any URS Power? Broadcast the URS Details to All the Constituents and Upload to RLDC website END 48 | P a g e ERLDC: POSOCO Activity: Procedure flow chart for current day schedule revision…contd RR Yes Is it NEW Approval of Same Day STOA? No Yes Is there any System Constraint? No END No Is SLDC Changed its Requisition? Yes Receive the revised Requisition of the Beneficiary Constituent in Form - C format Receive Revised Requisition of Beneficiary Constituent Preparation of Constituent's Drawal Schedule & ISGS Despatch Schedule w.e.f 6th time block or latter as approved / requisitioned Preparation of Constituent's Drawal Schedule & ISGS Despatch Schedule w.e.f 4th time block Send Drawal Schedule to SLDCs & Despatch Schedule to ISGS -(Form - D) Yes Check for Tr Constraint, Tech Min & Ramping Yes Check for Tr Constraint, Tech Min & Ramping No No Is there any URS Power? No Yes Broadcast the URS Details to All the constituents & Upload to RLDC website END 49 | P a g e ERLDC: POSOCO Activity: IMPLEMENTED SCHEDULE START Regional Weekly Loss % State System Loss % Are Loss % Values entered correctly? Correct the values as applicable for the particular day No Yes Are Loss % Values entered correctly? Share Allocation % No Correct the values as applicable for the particular day Yes STOA Details (Advance Approved & Day Ahead Approvals) No Are STOAs Configured correctly? Correct the values as applicable for the particular day Yes Details of Grid Incidents and Grid Disturbance if any. No Was the Schedule Revision done correctly? Correct the values as per Declaration in line to IEGC provisions Yes Details of Transmission Constraints, if any. No Was the curtailment done correctly? Incorporate the curtailment with correct values as per IEGC guidelines / provisions Yes Details of Revisions in Declared Capacity of ISGS & Requirements of Constituents Was all the Revisions scheduled correctly? No Check for the Constituent's Drawal Schedule & ISGS Despatch Schedule & co-ordinate for rectification of errors if any. Yes Cont..2 50 | P a g e ERLDC: POSOCO From 1 Inter Regional Link Schedules (STOA & Wheeling / Diversion Details) Check for matching of the Inter Regional Schedules for each link. Are the Inter Regional Link Schedules are matching with other Region? No Co-ordinate with respective RLDCs & eliminate the discrepancy. Yes Communicate to respective RLDC Release the Final Implemented Schedule and Upload in to Web. Receive from SLDC / ISGS / Traders / RLDCs Is there any dispute on discrepancy of the Schedule, with in 5 days? Go to Start Yes No Release weekly schedules to commercial dept for Energy Accounting END 51 | P a g e ERLDC: POSOCO Chapter 9 9. SCADA System Operation 9.1. Introduction For over all development of Load Despatch & Communication facilities in Control Centers, a Unified Load Despatch Scheme (ULDC) in ER has been commissioned in September, 2005. The scheme envisaged installation and commissioning of Remote Terminal Units with dedicated communication system comprising of Fibre Optic and PLCC system, installation and commissioning of Auxiliary Power Supply system such as UPS, DG set. Regional Load despech Center Established at Kolkata whereas State Load Despatch Centres (SLDCs) were established at Howrah (West Bengal), Maithon (DVC), Patna (Bihar), Ranchi (Jharkhand), Bhubaneswar (Odisha) and Sikkim (Sikkim) along with Sub-LDCs were also established. ULDC scheme operates in a hierarchal structure consisting of State of Art equipment’s and advanced EMS-SCADA functions. 9.2. Energy Management System Energy Management system (EMS) modules implemented in the different control centers (RLDC/ SLDCs) consists of various applications covering wide spectrum of functions like Pre-dispatch, Real time dispatch and Post-dispatch functions. The Energy Management System (EMS) tools such as state estimation, contingent analysis, optimum power flow, load forecasting, resources scheduling and commitment has provided system operators greater flexibility in taking appropriate and judicious decisions during the course of operation. To supplement further, other tools such as State Estimator (SE), Network Topology Processor (NPT) and Contingency analysis (CA) 9.3. Communication System A strong Communication Backbone network is the key to the smooth functioning of the ULDC Scheme. Keeping this in view; a dedicated communication has also been established under ULDC scheme consisting of Fibre-Optic & Power Line Carrier. Communication (for the end link data flow). in order to provide reliability and redundancy in data communication channel, an alternate physical route between ERLDC & SLDCs has been established. 9.4. SCADA Features Under this scheme more than 40000 numbers of Analog measurands (consisting of MW, MVAR, AMP, KV, FREQ, OLTC tap position) and Status Indication points (consisting of ISO, CB, SOE) have been wired up covering more than 460 nodes across the Eastern Region. Data from these nodes are updated every 10-15 seconds for analog measured and status point indication with the change of state. 9.5. Operational Requirements 9.5.1. Validation/Correctness of Data The entire EMS functions and real time monitoring of the regional grid depends upon the availability, reliability and validity of the tele-metered data. It is therefore, utmost essential that the various control centers viz. RLDC / SLDCs / SubLDCs take responsibility towards correctness/ validation of the data on a regular basis so that the facilities created in this scheme is optimally utilized to benefit the grid operation. 9.5.2. Availability of Speech and Data Communication System: In the event of commissioning of a new Generating station / sub-station / transmission element etc., it is essential that reliable and efficient speech & data communication systems are provided by the concerned agency to facilitate data flow up to ERLDC / SLDC. as the case 52 | P a g e ERLDC: POSOCO may be prior to commence the commercial operation. In this connection, Clause 4.6.2 of Indian Electricity Grid Code is relevant and the same is reproduced below. Quote “Reliable and efficient speech and data communication systems shall be provided to facilitate necessary communication and data exchange, and supervision/control of the grid by the RLDC, under normal and abnormal conditions. All Users, STUs and CTU shall provide Systems to telemeter power system parameter such as flow, voltage and status of switches/ transformer taps etc. in line with interface requirements and other guideline made available by RLDC. The associated communication system to facilitate data flow up to appropriate data collection point on CTU’s system, shall also be established by the concerned User or STU as specified by CTU in the Connection Agreement. All Users / STUs in coordination with CTU shall provide the required facilities at their respective ends as specified in the Connection Agreement.” Unquote 9.5.3. Availability of RTUs Remote Terminal Units (RTUs) constitute an important element of the SCADA system for transfer of analog measurands and status indications continuously from various nodes to the control centers. Hence, it is essential that RTUs installed in the system and reporting to the different control centers are monitored and maintained in a proper way to ensure continuity of data to the control centers for the operational purpose. Failure of any RTU may cause stoppage of data to the control centers and thereby may cause operational problem. As such, RTU needs utmost attention and any problem encountered in RTU causing failure of data to the control centers is required to be attended at the earliest preferably within 24 hours so that information from the defective RTU is restored to the respective control centers to avoid any operational problem. 9.5.4. Availability of Dedicated Communication System In order to transfer the real time data from RTUs to Sub-LDCs / SLDCs / SRLDC communication back bone network consisting of Fibre Optic and PLCC end links etc. are provided and the same need to be maintained properly. Further in case of any failure of the link viz. fibre cut between two locations causing complete failure of upstream data, failure of supply to the repeater station etc. an immediate action is initiated by the concerned agency to restore the system data as quickly as possible preferably within 24 hours to avoid any operational problem. 9.5.5. Upkeep / Maintenance of Control Centers Efforts should be made by SRLDC / SLDCs / Sub-LDCs to ensure that proper environmental conditions are maintained in all the control centers for proper functioning of the equipments and in the event of failure of any auxiliary systems such as Air Conditioning, UPS etc., immediate action is initiated by the concerned to restore the system at the earliest. 53 | P a g e ERLDC: POSOCO Chapter 10 10. Metering and Settlement System 10.0 Introduction The settlement system is an important part in implementation of Availability Based Tariff (ABT) . The system involves metering, data collection and processing, energy accounting and raising of bills of the constituents. This chapter indicates the roles and responsibilities of the different regional entities in making the settlement system operative in most efficient manner. 10.1 Metering and Data Collection 10.1.1 As per Chapter-6 clause 6.4.21 of IEGC, the CTU shall install Special Energy Meters on all inter connections between the regional entities and other identified points for recording of actual net MWh inter-changes, average frequency on 15-minute time block and MVARh drawls under low/high voltage conditions. 10.1.2 The type of meters to be installed, metering scheme, metering capability, testing and calibration requirements and scheme for collection and dissemination of meter data shall be as per Annexure-2 of IEGC. 10.1.3 All concerned entities having SEMs installed in their premises shall fully cooperate and extend necessary assistance by taking weekly meter reading and transmitting them to ERLDC in time. 10.1.4 All concerned entities having SEMs shall also carry out necessary time adjustments in the meter as per the procedure already in vogue/advice of 10.1.5 In the event of any reported problem of SEMs as by ERLDC during processing in the matter shall be reported to concerned / to the owner of the meter for necessary replacement /repair. 10.2 Automated Meter Reading (AMR) The intent of AMR scheme is to automate the task of data collection from each meter/location periodically and storing the same in a database. Data from the database is be used by application software such as ABT energy accounting software and further processing. GPRS based energy meter data collection is beneficial for both the constituents and Load despatcher. AMR system solve the problem of manual meter data downloading from the remote locations resulting in timely data receipt by Regional Load Despatch Centre as well as submission of processed data to Regional Power Committee. In Eastern Region, SEM data from some remote locations was not being received due to DCD error and other system complicacies which are normalised after implementation of AMR system and ERLDC started receiving data on regular basis. Total 655 nos of SEM out of 875 nos are connected with DCU in Eastern Region and all DCUs are reporting to Central Data Collection System (CDCS) at ERLDC. 10.3 Data Processing 10.3.1 As mentioned in section 6.4.21, all the energy meter data would reach ERLDC by every Tuesday afternoon via email. The CTU/STU, ISGSs and regional entities shall be responsible for sending of data of sending of data to ERLDC. ERLDC would carry out data validation and in case of any problem, request any entity to send the data again. Each entity would therefore have necessary backup of data at their local PC level. 10.3.2 The computation of the net injection of each ISGS and actual net drawl of each beneficiary shall be carried out in line with clause 6.4.22 of IEGC based on the above meter readings received at ERLDC. The preparation and issue of REA to the constituents shall be done by ERPC Secretariat on the basis of meter data and implemented schedule forwarded by ERLDC. 54 | P a g e ERLDC: POSOCO 10.3.3 Data related to the reactive energy exchange between two STU systems and between STU and ISTS points would also be forwarded by ERLDC for preparation of reactive energy accounts and communication to all constituent and ERLDC by ERPC Secretariat. 10.3.4 The final schedule implemented by ERLDC shall be open to all regional entities for checking / verification for a period of five days and mistakes/omissions ,if any ,would be rectified. 10.3.1 Energy Accounting ERPC Secretariat would process the information provided by ERLDC and other utilities to determine the following energy accounts: 10.3.1.1 Monthly Regional Energy Account for the purpose of billing a) Capacity charges payable by each beneficiary to each ISGS. b) Energy charges payable by each beneficiary to each ISGS c) ISGS energy scheduled for each regional beneficiaries. In case of utilities outside Eastern regions are having shares on ISGSs, ERLDC shall be furnishing consolidated schedule drawal at the concerned regional boundary/ies only. 10.3.1.2 ` Weekly Deviation Account Weekly Deviation charges shall be settled as per deviation calculation for each 15 minute block. The deviation charges payable/receivable shall be calculated with respect to deviation Pool. The Pool Account shall be maintained by ERLDC. The deviation account as prepared by ERPC Secretariat shall have the following components a) Deviation charges payable by beneficiaries/ISGSs/IPPs to Pool b) Deviation charges receivable by the beneficiaries/ISGSs/IPPs from the pool c) Additional Deviation charges payable by beneficiaries/ISGSs/IPPs to Pool d) Pool balance amount due to capping of deviation rate for Thermal ISGSs. Since the hydro stations within Bhutan System is not covered under deviation settlement mechanism, the accounting for drawal from these stations shall be as per the Monthly energy account as per the agreed principles. However, deviations of injections from these stations shall be accounted for and duly apportioning the deviations amongst its beneficiaries. 10.3.1.3 Weekly VARh Account The VARh account as prepared by ERPC Secretariat shall have two distinct components. a) VARh charges payable/receivable for VARh exchange between STU systems b) VARh charges payable by Beneficiaries for low VARh drawal or High VARh injection between STU and ISTS points. The VARh account for low VARh drawal and High VARh injection between STU ans ISTSs shall be maintained by ERLDC. Any payment to be made from VARh account shall be discussed beforehand in ERPC forum. 10.3.1.4 Congestion Charge Account The Congestion Charge account is prepared by ERPC secretariat. There is a congestion imposed on real time Grid Operation, Congestion Charge shall be applicable to Regional entities as per the CERC (Measures to relieve congestion in real time operation) Regulations and orders on rate of congestion charge as applicable from time to time. Congestion charge would be levied for over drawal or under-injection in the importing control area and, Congestion charge would also be levied for under drawal or over-injection in the exporting control area. 55 | P a g e ERLDC: POSOCO 10.3.2 Pool Account Operation In line with Annexure-I of IEGC, from the date of issue of weekly deviation account and Reactive Energy Charge Account by ERPC Secretariat, within 10-days, the concerned regional entity shall pay on priority the indicated amount into regional deviation, Reactive Energy and Congestion charges accounts operated by ERLDC. The agencies that have to receive the money from pool accounts would then be paid within 2 working days. These pool accounts are to be reconciled once in periodic intervals (i.e quarterly) and reconciliation statement is uploaded at ERLDC Website. 56 | P a g e ERLDC: POSOCO Annexure: I Generation capacities in Eastern Region 57 | P a g e ERLDC: POSOCO Annexure: II List of Generating Units and their Capacities (As on 30.06.16) CAPACITY DETAILS BSPGCL BSEB SYSTEM & BSPHCL STATION THERMAL INS CAP EFF CAP UNITS TOTAL UNITS BARAUNI 2x110 220 2x105 210 MUZAFFARPUR 2x110 220 2x110 220 TOTAL HYDRO 440 KOSI DEHRI ( BHPC ) OTHERS TOTAL 430 4x5 20 4x5 20 7x1.65 11.6 7x1.65 11.6 13.3 13.3 13.3 13.3 TOTAL HYDRO GRAND TOTAL ALL FIGURES IN M W THERMAL+HYDRO 24.9 24.9 464.9 454.9 JUUNL JSEB SYSTEM & TVNL STATION INS CAP UNITS THERMAL TVNL PATRATU TENUGHAT 4x50+2x100+ 4x110 2x210 TOTAL HYDRO UNITS 4x40+2x90+ 2x105+2x110 420 2x210 1260 SUBERNREKHA 2x65 130 2x65 2X5 10 2X5 THERMAL+HYDRO TOTAL 770 420 1190 SIKIDIRI TOTAL HYDRO GRAND TOTAL EFF CAP TOTAL 840 130 10 140 140 1400 1330 D V C SYSTEM STATION THERMAL INS CAP UNITS TOTAL EFF CAP UNITS TOTAL BOKARO'B' WARIA TPS CTPS 'A' CTPS 'B' MEZIA MEZIA 'B' DSTPS DTPS KODERMA TPS RTPS 3x210 1x140+1x210 3x140 2x250 4X210+2x250 2x500 2x500 1X140+1X210 2x500 2X600 630 350 420 500 1340 1000 1000 350 1000 1200 7790 3x210 1x140+1x210 3x130 2x250 4X210+2x250 2x500 2x500 1X140+1X210 2x500 2X600 630 350 390 500 1340 1000 1000 350 1000 1200 7760 MAITHON PANCHET TILAYA 2X20+1x23.2 2x40 2x2 63.2 80 4 147.2 7937.2 2X20+1x23.2 2x40 2x2 63.2 80 4 147.2 7907.2 TOTAL GAS TURBINE HYDRO TOTAL GRAND TOTAL TH+ HY + GT 58 | P a g e ERLDC: POSOCO CAPACITY DETAILS OPGC & OHPC STATION THERMAL INS CAP UNITS TALCHER (NTPC) STAGE-I STAGE-II BURLA CHIPLIMA BALIMELA RENGALI U.KOLAB U.INDRAVATI MACHKUND TOTAL HYDRO OPGC GRAND TOTAL IB VALLEY THERMAL+HYDRO TOTAL 4x60 2x110 250 220 470 4x60 2x110 240 220 460 2x49.5+3x37.5 +2x32 3x24 2X75+6x60 5x50 4x80 4x150 3X17+ 3X21.5 275.5 2x49.5+3x37.5 +2x32 3x24 2X75+6x60 5x50 4x80 4x150 3X17+ 3X21.5 275.5 TOTAL HYDRO(OHPC) TOTAL ALL FIGURES IN M W EFF CAP UNITS 2x210 72 510 250 320 600 57.37 2084.9 420 2974.9 2x210 72 510 250 320 600 57.37 2084.87 420 2964.87 WEST BENGAL SYSTEM STATION INS CAP UNITS TOTAL EFF CAP UNITS TOTAL THERMAL WBPDCL BANDEL SANTALDIH KOLAGHAT BAKRESWAR SAGARDIGHI DPL DPPS 4x82.5+1x210 2X250 6x210 5x210 2 x 300 3x75+1x110+1X300+ 1X250 TOTAL HYDRO (WBSEDCL) 540 500 1260 1050 600 885 4x60+1x210 2X250 6x210 5x210 2 x 300 1x70+2x75+1x110+1X 300 + 1X250 4835 JALDHAKA-I JALDHAKA-II MASSANJORE RAMAM TISTA TLDP MICRO HYDEL PPSP 4x9 2x4 2x2 4x12.5 9X7.5 4X33 TITAGARH N.COSSIPORE SOUTHERN BUDGE-BUDGE 450 500 1260 1050 600 880 4740 36 8 4 50 67.5 132 7.51 900 1205.0 4x9 2x4 2x2 4x12.5 9X7.5 4X33 4x60 2x30+2x50 2x67.5 3X250 240 160 135 750 1285 4x60 100 2x67.5 3X250 240 100 135 750 1225 2X300 600 2X300 600 4X225 TOTAL HYDRO 4X225 36 8 4 50 67.5 132 6.19 900 1203.7 GAS TURBINE TOTAL G.T. CESC THERMAL TOTAL Haldia Energy Ltd ((Thermal)) Haldia TPS GRAND TOTAL THERMAL+HY+GT 7925 7769 59 | P a g e ERLDC: POSOCO CAPACITY DETAILS SIKKIM SYSTEM SYSTEM SIKKIM STATION INS CAP UNITS HYDRO DIESEL TOTAL TOTAL 32.89 5 37.89 ALL FIGURES IN M W EFF CAP UNITS TOTAL 32.89 5 37.89 CENTRAL SECTOR SYSTEM THERMAL STATION FARAKKA STG-I & II FARAKKA STG-III KAHALGAON STG-I KAHALGAON STG-II NTPC HYDRO: NHPC BHUTAN (DGPC) : HYDRO CHPC KHPC BHPC DHPC THPC INS CAP UNITS 3x200+2x500 1x500 TOTAL 1600 500 EFF CAP UNITS 3x200+2x500 1x500 TOTAL 1600 500 4X210 3x500 840 1500 4X210 3x500 840 1500 TALCHAR STG-I TALCHAR STG-II * BARH STG-II NABINAGAR TOTAL NTPC 2X500 4X500 2X660 1 X 250 1000 2000 1320 250 9010 2X500 4X500 2X660 1 X 250 1000 2000 1320 250 9010 RANGIT TEESTA V TOTAL NHPC 3 x 20 3 x 170 60 510 570 3 x 20 3 x 170 60 510 570 4x84 4 x 15 2 X 20 +2 X12 2X63 6 x 170 336 60 64 126 1020 1606 4x84 4 x 15 2 X 20 +2 X12 2X63 6 x 170 336 60 64 126 1020 1606 CHUKHA CHPC KURICHU HEP BASOCHHU HEP DAGACHHU HEP TALA HEP TOTAL IPP/MPP SYSTEM THERMAL VEDANTA APNRL GMR TATA JINDAL IND BHARAT HYDRO GATI DANS GROUP STATION INS CAP UNITS TOTAL EFF CAP UNITS TOTAL STERLITE* ADHUNIK GKEL* MPL JITPL IBEUL SUB-TOTAL 4x600 2 X270 3X350 2x525 2x600 2 X350 2400 540 1050 1050 1200 700 6940 4x600 2 X270 3X350 2x525 2x600 2 X350 2400 540 1050 1050 1200 700 6940 CHUJACHEN JORETHANG HEP SUB-TOTAL 2X55 2 X 48 110 96 206 7146 206 2X55 2 X 48 110 96 206 7146 Total * One unit each of Sterlite and GKEL is dedicated to Odisha EASTERN REGION SYSTEM STATION INS CAP EFF CAP TOTAL TOTAL 33050 32775 THERMAL 5 5 DIESEL 6021 6022 E.REGION HYDRO 0 0 GT 38801 TOTAL 39077 Talcher Stage-II ( I.C 2000 MW) is dedicated to SR. Only 10% share is allocated to GRIDCO. 60 | P a g e ERLDC: POSOCO Annexure :III Captive Power Stations in Eastern Region and Their Capacities CAPTIVE POWER STATIONS IN EASTERN REGION AS ON 30.05.2016 POWER SATION SYSTEM ODISHA BIHAR JHARKHAND W.BENGAL COAL INDIA LTD REGION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 1 2 3 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 2 3 4 VENDANTA (JHARSUGUDA) NALCO (ANGUL) JINDAL STEEL & POWER LTD., ANGUL BHUSAN STEEL & STRIPS (M'MUNDALI) BHUSAN STEEL, JHARSUGUDA HPCL(HINDALCO), HIRAKUD JINDAL STAINLESS LTD., DUBURI IMFA (CHOUDWAR) RSP(ROURKELA) IFFCO (PARADEEP) NBVL (MERAMUNDALI) VEDANTA (LANJIGARH) ARATI STEEL (GHANTIKHAL, CUTTACK) ACTION ISPAT & POWER PVT. LTD. VISA STEEL LTD. (NEW DUBURI) KMCL(NINL), Duburi OCL INDIA LTD., RAJGANGPUR M/S FACOR POWER LIMITED SMC POWER GEN. LTD. SREE GANESH SHYAM DRI( PANDOL, SAMBALPUR) ACC, BARGARH MAITHON ISPAT NIGAM LTD., JAIPUR RD. TATA SPONGEIRON( JODA ) MSP METALLICS LTD. ORISSA SPONGE IRON & STEEL LTD EMAMI PAPER MILLS LTD. RSPL (KATAPALLI) ARYAN ISPAT & POWER PVT. LTD. PATTANAIK STEEL (KEONJHAR) MAHAVIR FERRO ALLOYS PVT. LTD. DINABANDHU / YAZDANI STEEL & POWER SEVEN STAR STEELS LTD. NARBHERAM POWER & STEEL PVT. LTD. TOTAL FCI USHA MARTIN BCCL REHLA TOTAL JOJOBERA BSL TISCO (EXCL. DG SETS) BIHAR CAUSTIC & CHICAL LTD USHA MARTIN LTD., JAMSHEDPUR USHA MARTIN LTD., RANCHI ABCIL, GARHWA TOTAL DSP TATA POWER HALDIA HALDIA REFINERY (IOC ) HALDIA PETROCHEMICALS LTD. IISCO CRESCENT POWER BEL PCBL, DURGAPUR RAM SWARUP LOHIA UDYOG RENUKA SUGAR DPSCO ELECTRO STEEL GREEN POWER. HIMADRI CHEMICAL CORPORATE ISPAT ALLOY AMRITA BIO-ENERGY & IND. LTD. KPL (BIOMASS) SIIPL (SOLAR) KESORAM REYON KAMARHATI BIOGAS LTD TOTAL ECL BCCL CCL NEC TOTAL TOTAL INSTALLED CAPACITY (MW) 9X135 10 X120 4X135 1X33+1X77+2X150 1X40+1X60+2X130+2X8 3 X 100+1X67.5 2X125+1X13 2X54+1X30+2X60 4X25+2X60 2 X 55 1X30+1X65 3 X 30 1X40+1X50 1X25+1X12+1X43 3X25 2X19.25+1X24 2X27 1x45 1X8+1X25 1X32 1X30 1X30 1X30 1X18.5+1X7.5 1X25 1X24 1X15+1X5 1X20 1X18 1X15 1X12 1X10 1X8 1X8 80 25 1X30 2X120 + 67.5 2X55+3X60+1X12 1X67.5+3X30+1X25 1X12.5+1X20 35X1+30X2+25X1+15X1 10X2 30X2 2X60+4X5 (2X45+1X30) 2X10+2X20 ( 2X20) (1x40) ( 1X30) ( 1X15) (4x3) (1x12) (1X10) 10 ( 1X6) TOTAL (MW) 1215 1200 540 410 376 367.5 263 258 220 110 95 90 90 80 75 62.5 54 45 33 32 30 30 30 26 25 24 20 20 18 15 12 10 8 8 5892.00 80 25 30 135 307.5 302 215 30 135 20 60 1070 140 120 84.5 75.5 60 40 40 30 20 15 14.2 12 12 10 10 6 5 6 6 706.2 20 49.6 70.3 1 140.9 7944 61 | P a g e ERLDC: POSOCO Annexure: IV Deviation rate at different frequencies 62 | P a g e ERLDC: POSOCO Annexure: V Format message for violation of IEGC EASTERN REGIONAL LOAD DESPATCH CENTRE POWER SYSTEM OPERATION CORPORATION LIMITED 14, GOLF CLUB ROAD, TOLLYGUNJ, KOLKATA-700033 Tel.: 033-24235265/5875, FAX: 033-24235809/5704, www.erldc.org Message No Non‐Compliance Message Type Emergency Date Alert From:‐Shift‐In‐Charge, ERLDC, Kolkata To WBSEB OPTCL DVC JSEB Copy To Sub : Violation of Indian Electricity Grid Code Type of Violation Category of IEGC Clause Violation Frequency Violation Voltage Violation 5.2(m) Loading Violation Zero Crossing Violation Deviation Violation 5.2(s) 6.4.12 6.6.3 6.6.6 6.4.12 6.4.6 Special Events Regional Entity EMERGENCY Drawal / Injection Schedule (MW) Time (HH:MM) BSPHCL Details 5.4.2(a) 5.4.2(b) 6.4.6 6.4.7 6.4.10 6.4.12 Actual Drawal / Injection (MW) Actual Deviation (MW) Area Control Error (MW) Desired Drawl/ Injection (MW) You are requested to take immediate action to strictly adhere to desired drawl/generation as mentioned above and take immediate actions to remove the violation for reliable and secure system operation. Non‐compliance of the RLDC direction would be a threat to grid security and shall be treated as violation of CERC Regulations / CEA Grid Standards / Electricity Act, 2003. The same would be reported to CERC as per Cl.1.5 of IEGC, 2010 and amendments thereof. Shift-In-Charge Eastern Regional Load Despatch Centre 63 | P a g e ERLDC: POSOCO Annexure: VI List of 765/400kV & 400/220kV ICTs and their tap Positions ICT TAP POSITION TAP POSITION OF 765/400 kV & 400/220 kV ICTS IN EASTERN REGION AS ON 30.06.16 SUBSTATION CAPACITY TAP GAYA 765/400 kV SASARAM 765/400 kV NEW RANCHI 765/400 kV ANGUL JHARSUGUDA BINAGURI NEW PURNEA MUZAFFARPUR MALDA SASARAM 400/220kV BIHARSHARIF BIDHANNAGAR PATNA FARAKKA STPS MAITHON RANCHI JAMSHEDPUR PARULIA BAKRESWAR ARAMBAGH JEERAT KHARAGPUR SUBHASGRAM KOLAGHAT BARIPADA RENGALI ROURKELA TALCHER STPS MERAMUNDALI N. DUBURI U. INDRAVATI HEP JEYPORE MENDASAL BOLANGIR CHAIBASA KEONJHAR RANGPO GAYA 400/220 kV 3x1500 1x1500 2x1500 2X1500 2X1500 2X315 2X315 2X315 2X315 2X315 3X315 1X315 2X315 1X315 2X315 2X315 2X315 2X315 2X315 4X315 4X315 2X315 4X315+ 1X 500 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 5X315 1X315 + 1x500 12 14 12 12 12 10 11 12 12 12 12 9B 11 11 9B 9B 15 9 11 13 11 7 9 12 9 12 10 13 10 9 9B 14 6, 9 9B 9B 9B 9 12 FOR 765/400 kV TAP 1:807/400, 12:765/400, 23: 723/400 FOR 400/220 KV ICT TAP 1: 440/220, 9:400/220, 17:360/220 64 | P a g e ERLDC: POSOCO Annexure: VII Reactive Compensation Details LENGTH Sl No LINE/SUB-STN REACTORS CAPACITY IN MVAR ( KM ) LINE 1 2 BEHRAMPUR-JEERAT SAGARDIGHI-SUBASHGRAM 200 256.3 3 4 5 6 7 8 9 11 12 14 15 16 FARAKKA-PARULIA-I BIDHANAGAR-PARULIA I LAKHISARAI-B'SHARIFF-I LAKHISARAI-B'SHARIFF-II K'GAON-MAITHON-I K'GAON-MAITHON-II ROURKELLA-CHAIBASA-I ROURKELA-TALCHER I ROURKELA-TALCHER II ROURKELA- JAMSHEDPUR-II KEONJHAR-BARIPADA BARIPADA-MENDASAL-II 150 11 89 89 172 172 120 175 175 17 18 19 BAKRESWAR-ARAMBAGH BAKRESWAR-JEERAT RENGALI-INDRAVATI 132 162 356 20 21 22 23 24 25 26 27 28 29 32 B'SHARIFF-TENUGHAT MALDA-PURNEA -I MALDA-PURNEA -II BINAGURI-BONGAIGAON-I BINAGURI-BONGAIGAON-II BINAGURI-BONGAIGAON-III BINAGURI-BONGAIGAON-IV BINAGURI-TALA-I BINAGURI-TALA-II BINAGURI-TALA-IV PURNEA-MUZAFFARPUR-I 180 167 167 216 216 224 224 115 115 98 240 33 PURNEA-MUZAFFARPUR-II 240 34 35 36 37 38 ROURKELA-JHARSUGUDA- I ROURKELA-STERLITE-I MERAMUNDALI-ANGUL-I ANGUL-BOLANGIR BOLANGIR-JEYPORE 142 113 20.8 199 288 39 40 41 42 43 44 45 46 47 48 B'SHARIFF-PUSAULI -I PUSAULI-ALLAHABAD PUSAULI-SARNATH MUZAFFARPUR-GRKPR-I MUZAFFARPUR-GRKPR-II B'SHARIFF-BALIA -I B'SHARIFF-BALIA -II PATNA-BALIA-III PATNA-BALIA-IV RANCHI-SIPAT-I 195 271 49 RANCHI-SIPAT-II 405 50 51 52 JEYPORE-GAJUWAKA-I JEYPORE-GAJUWAKA-II MPL-RANCHI -I 220 220 188 53 MPL-RANCHI -II 188 54 55 56 PUSAULI-BIHARSHARIFF-I PUSAULI-BIHARSHARIFF-II 765 kV PUSAULI-FATHEPUR 198 198 356 57 765 kV RANCHI-DHRAMJAYGARH I 303 58 765 kV RANCHI-DHRAMJAYGARH II 303 59 60 61 LAKHISARAI-KhSTPP - I LAKHISARAI-KhSTPP - II PATNA - KISHANGUNJ-I 145 145 352 62 PATNA - KISHANGUNJ-II 352 63 MAITHON-GAYA-I 235 64 MAITHON-GAYA-II 235 65 66 67 68 69 70 71 72 73 74 MAITHON-MEJIA-I BANKA-BIHARSARIFF I & II BARIPADA-KEONJHAR BIHARSARIFF-PURNEA I BIHARSARIFF-PURNEA II BIHARSARIFF-VARANASI-I BIHARSARIFF-VARANASI-II PURNEA- BINAGURI-I PURNEA- KISHANGANJ-I 765 KV GAYA- BALIA 83 185 156 232 232 321 321 168 71 120 75 76 77 765 KV GAYA- VARANASI-I 766 KV GAYA- VARANASI-II 765 KV JHARSUGUDA-ANGUL I 272 272 273 78 765 KV JHARSUGUDA-ANGUL II 273 79 80 764 KV JHARSUGUDA-DHARAMJAYGARH-I 765 KV JHARSUGUDA-DHARAMJAYGARH- II 151 151 TOTAL 156 273 260 260 242 242 185 185 405 REMARKS END 1X50 1X63 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1 X 63 1 X 63 1X63 1X63 1x50 1x50 1x50 1x63 1x63 1X63 1X63 1X80 1X80 1X63 1X63 1X63 1x63 1x63 1x63 1x63 1x63 1X63 1x80 1x50 1x50 1x80 1X50 1X63 1X63 1X63 1X50 1X50 1X50 1X63 1X63 1X80 1X80 1X80 1X80 1X80 1X80 1 X50 1 X50 1 X50 1 X50 1 X63 1 X63 1 X 330 # 1 X 330 # 1 X 240 # 1 X 330 # 1 X 240 # 1 X 330 # 1 X 50 1 X 50 1 X 63 1 X 63 1 X 63 1 X 63 1 X 50 1 X 50 1 X 50 1 X 50 1 X 50 2 X 50 1 X 50 1 X 80 1 X 80 1 X 50 1 X 50 1 X 63 1 X 63 1 X 240 # 1 X 330 # 1 X 240 # 2 X 240 # 1 X 240 # 1 X 240 # 1 X 240 # 1 X 240 # 1 X 330 # 1 X 330 # JEERAT SAGARDIGHI SUBHASGRM FARAKKA PARULIA B'SHARIFF B'SHARIFF MAITHON MAITHON ROURKELA TSTPP TSTPP ROURKELA BARIPADA MENDASAL BARIPADA BAKRESWAR JEERAT RENGALI INDRAVATI TENUGHAT MALDA MALDA BONGAIGAON BONGAIGAON BINAGURI BINAGURI BINAGURI BINAGURI BINAGURI PURNEA MZFRPR PURNEA MZFRPR ROURKELA ROURKELA MERAMUNDALI BOLANGIR BOLANGIR JEYPORE BIHARSARIFF PUSAULI PUSAULI MUZAFFARPUR MUZAFFARPUR BALIA BALIA BALIA BALIA RANCHI SIPAT RANCHI SIPAT GAJUWAKA GAJUWAKA MPL RANCHI MPL RANCHI PUSAULI PUSAULI PUSAULI FATHEPUR RANCHI DHARAMJAYGARH RANCHI DHARAMJAYGARH LAKHISARAI LAKHISARAI PATNA KISHANGANJ PATNA KISHANGANJ GAYA MAITHON GAYA MAITHON MAITHON BANKA BARIPADA BIHARSARIFF BIHARSARIFF BIHARSARIFF BIHARSARIFF PURNEA PURNEA GAYA BALIA GAYA GAYA JHARSUGUDA ANGUL JHARSUGUDA ANGUL DHARAMJAYGARH DHARAMJAYGARH SWITCHABLE SWITCHABLE NOW AT 220 KV IN NER IN NER SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE IN NR IN NR IN NR IN NR IN WR IN WR IN SR (SWITCH) IN SR (SWITCH) 765 kV LINE SWITCHABLE IN NR 766 kV LINE SWITCHABLE IN WR (SWITCHABLE) 767 kV LINE SWITCHABLE IN WR (SWITCHABLE) SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE IN WR (SWITCHABLE) IN WR (SWITCHABLE) 9549 65 | P a g e ERLDC: POSOCO Sl No LINE/SUB-STN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 765 KV ANGUL 765 kV GAYA 765 KV JHARSUGUDA 765 kV PUSAULI 765 kV RANCHI NEW ANGUL ARAMBAGH BAKRESWAR BANKA BARH BEHRAMARA BEHRAMPORE BIDHANNAGAR BIHARSHARIFF BINAGURI BOLANGIR CHAIBASA DUBURI DURGAPUR FARAKKA GAYA INDRAVATI JAMSHEDPUR JEERAT JEYPORE JHARSUGUDA JITPL KAHALGAON KEONJHAR KHARAGPUR KISHANGANJ KODERMA LAKHISARAI MAITHON MAITHON RIGHT BANK MUZAFFARPUR NEW MELLI PANDIABALLI PATNA PURNEA PUSAULI RAGHUNATHPUR RANCHI RANCHI NEW RANGPO RENGALI ROURKELA REACTORS CAPACITY IN MVAR LENGTH ( KM ) REMARKS BUS TOTAL # three single phase units, whose combined capacity is indicated 2 x 330 # 2 x 240 # 2 X 240 # 1 x 330 # 2X240 # 3X125 1X50 1X50 1X80 1X80 2X63 1X80 1X50 1X50+1X80+1X125 2X125 1X80 1X80 1X80 1X50 2X50 2 X125 1X125 2X50 1X50 31.5* + 1X125 +1 x 63 2X125 2X50 2X50 1X80 1 X80 1 X 125 2X50 1 X 80 1X50 2 X 50 2X125 1X63 1X80+1X63 1X80+2x125 2X125 2 X 125 2X50 1X80+1x125 2x125 2 X 80 31.5* 1X50+1X125 765 kV 765 kV 765 kV 765 kV 765 kV BANGLADESH * T ertiary winding of 400/220/33 kV ICT 125 * T ertiary winding of 400/220/33 kV ICT 7983 * 31.5 MVAR reactor is connected to 33 kV tertiary winding 66 | P a g e ERLDC: POSOCO Annexure: VIII Format for message to be issued by ERLDC for Real Time Outage clearance पावर िस टम ऑपरे शन िनगम िलिमटे ड पव ू ीर् क्षेत्रीय भार प्रेषण कद्र कोलकाता - 700033 APP NO PHONE: FAX: संदेश संख्या: ERLDC/Ft-02/ DATE: T.O.O : प्रेषक : पाली प्रभारी प्रबंधक , पव ू ीर् क्षेत्रीय भार प्रेषण कद्र , कोलकाता सेवा मे : SCE/CPCC/ER-II/KOLKATA प्रित: 1 2 3 4 SCE/SLDC/SIKKIM/GANGTOK SCE/JLHEP SUB: SHUTDOWN CLEARANCE REF YOUR MSG NO. : MAIL DATE: T.O.O : The following shutdown may be availed ELEMENT NAME FROM DATE HOURS TO DATE TYPE NATURE HOURS PURPOSE: CONDITIONS : NOTE: पाली प्रभारी प्रबंधक 1. Before aviling the shutdown, final switching off clearance must be taken from ERLDC. 2. Before requesting for the switching off/in code from ERLDC, it must be ensured that PTW has been taken/return ,all men and materials were removed from site and all necessary safety precautions were taken. 3. The S/D is to be returned within scheduled period. 4. ERLDC may defer/postpone the shutdown if the system condition does not permit opening of the element/s. 67 | P a g e ERLDC: POSOCO Annexure: IX New transmission element charging and issue of certificate of successful trial run operation 68 | P a g e ERLDC: POSOCO 69 | P a g e ERLDC: POSOCO 70 | P a g e ERLDC: POSOCO 71 | P a g e ERLDC: POSOCO 72 | P a g e ERLDC: POSOCO 73 | P a g e ERLDC: POSOCO 74 | P a g e ERLDC: POSOCO 75 | P a g e ERLDC: POSOCO 76 | P a g e ERLDC: POSOCO 77 | P a g e ERLDC: POSOCO 78 | P a g e ERLDC: POSOCO Annexure :X Format for Weekly Reports EASTERN REGIONAL LOAD DESPATCH CENTRE P OW ER SYSTEM OP ERATION CORP ORATION LIM ITED WEEKLY REPORT (As per IEGC Clause No.5.5) DATE: Year: 2016-2017 / Week No: Period: From To A) FREQUENCY PROFILE: DATE MAXIMUM Freq (Hz) Time MINIMUM Freq (Hz) Time Average Frequency Freq. Dev Index (% of Time) MIN VDI (% of Tim e) Frequency Range (% of time) <49.9 49.9 - 50.05 >50.05 B) VOLTAGE (kV) : DATE MAX MIN VDI (% of Tim e) MAX MAX MIN VDI (% of Tim e) C) MAJOR GENERATORS TRIPPED / DESYNCHRONIZED / RE-SYNCHRONIZED DURING THE WEEK S.No Station Agency Unit No. Capacity Outage Date Time Restoration Date Time Reasons 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 79 | P a g e ERLDC: POSOCO D) % OF TIME N-1 CRITERIA WAS VIOLATED IN THE INTER - REGIONAL CORRIDORS SL INTER - REGIONAL CORRIDOR NO Weekly Average 1 2 E) % OF TIME ATC WAS VIOLATED AT THE INTER - REGIONAL CORRIDORS EXPORT ATC SL INTER - REGIONAL CORRIDOR NO 1 2 3 4 F) IMPORT ATC NR SR NER WR % OF TIME ANGULAR DIFFERENCE BETWEEN IMPORTANT BUSES WAS BEYOND PERMISSIBLE LIMITS (30 DEGREE) SL PAIR OF BUSES NO 00/01 01/01 02/01 03/01 04/01 05/01 06/01 Weekly Average G) IMPORTANT TRANSMISSION ELEMENTS TRIPPED / RESTORED DURING THE WEEK : OUTAGE RESTORATION SL LINE/ICT NO Date Time Date Time 1 2 3 4 5 6 7 8 REASON/REMARKS H) FOLLOWING ELEMENTS ARE UNDER BREAKDOWN (MORE THAN 03 MONTHS):SL NO Transmission Element / ICT Outage From Date OWNER Reasons for Outage 1 I) GRID DISTURBANCES / INCIDENTS (if any): NIL Violation Category Voltage Frequency Constituents 1 2 3 4 5 6 00/01 01/01 02/01 03/01 04/01 05/01 06/01 00/01 01/01 02/01 03/01 04/01 Loading 05/01 06/01 00/01 01/01 02/01 03/01 04/01 05/01 06/01 BSPHCL JUVNL DVC ODISHA WBSETCL SIKKIM TOTAL Total J) MESSAGES ISSUED BY ERLDC, REGARDING VIOLATION CATEGORY, WHEN FREQUENCY WAS BEYOND THE BAND OF 49.9-50.05 HZ: 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 K) SPECIAL MENTION: (U.K. VERMA) GM, ERLDC 80 | P a g e ERLDC: POSOCO Annexure :XI Format for Quarterly Reports POWER SYSTEM OPERATION CORPORATION EASTERN REGIONAL LOAD DESPATCH CENTRE QUARTERLY REPORT (AS PER IEGC CLAUSE 6.5.2 a) Quarter No. (1,2,3or 4) Period from: Month’yy to Month’yy Brief report on Regional Power System / Performance of the grid is given below: 1. POWER SUPPLY POSITION a) Peak Demand Met and Unrestricted Demand (MW) MONTH Month-yy Month-yy Month-yy STATE BSEB JSEB DVC OPTCL WBSETCL REGION BSEB JSEB DVC OPTCL WBSETCL REGION BSEB JSEB DVC OPTCL WBSETCL REGION PK DMD MET PK REQ SHORTGE % b) Energy Met and Requirement (MU) MONTH Month-yy STATE ENERGY REQ ENERGY AVAILABILITY OWN SCHD UI SOURCE DRWL ENERGY MET SHORTGE % BSEB JSEB DVC OPTCL WBSETCL REGION 81 | P a g e ERLDC: POSOCO MONTH Month-yy Month-yy STATE ENERGY REQ ENERGY AVAILABILITY OWN SCHD UI SOURCE DRWL ENERGY MET SHORTGE % BSEB JSEB DVC OPTCL WBSETCL REGION BSEB JSEB DVC OPTCL WBSETCL REGION 2. REPORT ON SYSTEM CONSTRAINT ON REGIONAL GRID The details of the system constraint in Eastern Region is given in Annexure-I. 3. QUALITY OF SERVICE a) Frequency Profile (% time) % of time of the month frequency remained Month Month’yy Month’yy Month’yy <49.9 49.9-50.05 >50.05 IEGC band 49.9-50.05 Following curves are enclosed: Annexure II - Frequency duration curve for Month’yy Annexure III - Frequency duration curve for Month’yy Annexure IV - Frequency duration curve for Month’yy b) Voltage Profile All figures in KV JEERAT BINAGURI BIHARSHARIFF MONTH MAX MIN MAX MIN MAX Month’yy Month’yy Month’yy MIN DURGAPUR PATNA MAX MIN MAX MIN 82 | P a g e ERLDC: POSOCO Month-yy JSEB DVC OPTCL WBSETCL REGION 7. GENERATION OF CENTRAL SECTOR THERMAL POWER STATIONS AND THEIR DECLARED CAPACITY PLANT Month-yy GEN(MU) AVG DC (%) Month-yy GEN(MU) AVG DC (%) Month-yy GEN(MU) AVG DC (%) FSTPP KhSTPP-I KhSTPP-II TSTPP Event-Reporting (Clause 6.9.6): 8. GRID INCIDENCES IN ER SYSTEM 83 | P a g e ERLDC: POSOCO Annexure :XII (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) (x) Format for written report for event reporting (vide IEGC Clause 5.3.1) Time and date of event Location Plant and/or Equipment directly involved Description and cause of event Antecedent conditions Demand and/or Generation (in MW) interrupted and duration of interruption All Relevant system data including copies of records of all recording instruments including Disturbance Recorder, Event Logger, DAS etc. Sequence of trippings with time. Details of Relay Flags. Remedial measure 84 | P a g e ERLDC: POSOCO Annexure:XII(a) FormatforReportingSystemDisturbances (Detailed Report by the Constituents, as finalised by Protection Coordination Committee) OCCURRENCE REPORT (1) Date & Time of Occurrence : (2) Name of the Sub Station / Generating Station : (3) Details of Occurrence : At the time of occurrence the disposition of the feeders was as below Bus B Bus A BUS COUPLER BREAKER STATUS (WHETHER “ON” / “OFF”) For one and half breaker scheme Feeder I Feeder II Tie-breaker (On/Off ) Diameter 1 Diameter 2 Diameter 3 (4) Sequence of Trippings : Event Time (hh mm ss ) 85 | P a g e ERLDC: POSOCO (5) Relay Indication for Faulted Line/Transformer/Bus : (A) Relay Indication Name of Bay / Line Sl. No. Relay Indication Local End Relay type / Make And Indications Remote End Relay type / Make And Indications 1. 2. 3. 4. (6) Location and nature of Fault : (7) PLCC counter readings : Before Local end After Remote end Before After CH I CH II (8) (9) Analysis:- Restoration:Sl.No. From To Duration 86 | P a g e ERLDC: POSOCO Remedial Measures / Lesson Learnt Enclosure:1. Schematic Diagram showing position of (ON/OFF) breakers, Isolators and Relay Indications. 2. DR Charts. 3. Event Logger outputs. 87 | P a g e ERLDC: POSOCO Annexure :XIII Categorisation of Grid Incidences/Disturbances Annexure XIV (a) Sl No Date Name of Element/Elements Annexure XIV (b) Sl No Date Name of Element/Elements Voltage Level Tripped 220kV 400kV Categorisation of Grid Incidents Voltage Level 220kV 400kV Frequency(Hz) Before After Rescheduling Required ?(Y/N) Category of Incidence (1/2) Remarks if any Categorisation of Grid Disturbance Frequency(Hz) Antecedant Generation Before After Generation(MW) Lost (MW) % age Loss of Gen Antecedant Load(MW) Lost %age Load(MW) Load Loss Category (1/2/3/4/5) Remarks 88 | P a g e ERLDC: POSOCO Annexure :XIV List of Important Elements Tie Lines (as on 30.06.2016) SL.NO TIE-LINE OWNED BY CONNECTED SYSTEMS LENGTH COND. END-2 (KM) (TYPE) (KV) CKTS. POWERGRID(NR) POWERGRID(NR) POWERGRID(NR) POWERGRID(WR) POWERGRID(WR) 272 237 356 303 149 QUAD BERSIMIS QUAD BERSIMIS QUAD BERSIMIS QUAD BERSIMIS HEXA-ZEBRA 765 765 765 765 765 D/C S/C S/C D/C D/C 261 195 QUAD-MOOSE QUAD-MOOSE 400 400 242 321 QUAD-MOOSE TW.MOOSE 400 400 D/C Q/C D/C D/C END-1 VOLTS NO.OF A) 765 KV LINES 1 2 3 4 5 GAYA-VARANASI GAYA-BALIA PUSAULI-FATEHPUR RANCHI(NEW)-DHARAMJAYGARH JHARSUGUDA-DHRAMJAYGARH 6 7 8 9 MUZZFARPUR-GOROKHPUR PATNA-BALIA 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 BARH-GOROKHPUR SASARAM -SARNATH SASARAM-NAVINAGAR SASARAM -ALLAHABAD BINAGURI-BONGAIGAON BINAGURI-BONGAIGAON BINAGURI-TALA I & II BINAGURI-TALA IV BINAGURI-MALBASE TEESTA-RANGPO IBEUL-RAIGARH SEL-RAIGARH JHRASUGUDA-IBEUL JHRASUGUDA-RAIGARH ROURKELA-RAIGARH ROURKELA-SEL RANCHI -SIPAT BEHRAMPUR-BEHRAMARA FARAKKA-BEHRAMPUR FARAKKA-SAGARDIGHI FARAKKA - MALDA FARAKKA - PARULIA 32 33 34 35 36 37 38 39 40 41 42 43 44 45 KAHALGAON -BANKA MAITHON - KAHALGAON SAGARDIGHI-BEHRAMPUR SAGARDIGHI-SUBHASGRAM SAGARDIGHI-PARULIA BEHRAMPUR-JEERAT JEERAT-SUBHASGRAM SUBHASGRAM(PG)-HALDIA PARULIA-BIDHANAGAR KHARAGPUR-BARIPADA JAMSHEDPUR-MEJIA-B MAITHON - MEJIA B MAITHON - MEJIA B DSTPS - JAMSHEDPUR 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 KODERMA-BIHARSARIFF GAYA-KODERMA MAITHON-MAITHON RIGHT BANK RANCHI-MAITHON RIGHT BANK RANCHI-RAGUNATHPUR RAGUNATHPUR-MAITHON JAMSEDPUR-AHUNIK JAMSHEDPUR-TISCO BARIPADA-TISCO JEYPORE-GAZUWAKA ANGUL-MERAMANDALI-I ANGUL-MERAMANDALI-II SEL- MEERAMANDALI INDRAVATI-INDRAVATI TSTPP-MERAMUNDALI GMR-MERAMUNDALI MEERAMUNDALI- NEW DUBURI BARIPADA-MENDASAL BARIPADA-NEW DUBURI MENDHASAL-NEW DUBURI JITPL-ANGUL TSTPP - RENGALI POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID(ER) POWERGRID(ER) POWERGRID(ER) POWERGRID(ER) POWERGRID(ER) B) 400 KV LINES BIHARSHARIFF-BALIA BIHARSHARIFF-VARANASI POWERLINKS POWERGRID POWERGRID POWERGRID POWERGRID(ER) POWERGRID(ER) POWERGRID(NR) POWERGRID(NR) POWERGRID(ER) POWERGRID(NR) POWERGRID(ER) POWERGRID(NR) POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID & IBEUL POWERGRID & SEL POWERGRID & IBEUL POWERGRID POWERGRID POWERGRID & SEL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID(ER) POWERGRID(ER) POWERGRID POWERGRID(ER) POWERGRID(ER) POWERGRID(ER) POWERGRID POWERGRID POWERGRID NHPC IBEUL SEL POWERGRID POWERGRID(ER) POWERGRID(ER) POWERGRID POWERGRID(ER) POWERGRID NTPC NTPC NTPC POWERGRID(NR) POWERGRID(NR) NTPC POWERGRID(NR) POWERGRID(NER) POWERGRID(NER) THEP THEP THEP POWERGRID POWERGRID POWERGRID(WR) IBEUL POWERGRID(WR) POWERGRID(WR) SEL POWERGRID(WR) BANGLADESH POWERGRID WBPDCL POWERGRID 353 76 81 271 217 220 115* 98* 121* 11 91 147 64 110 212 113 405 71* 73 67 40 QUAD-MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE QUAD-MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE HTLS 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 POWERGRID NTPC POWERGRID 150 TW. MOOSE 400 D/C S/C D/C S/C D/C D/C D/C S/C S/C D/C S/C S/C S/C S/C S/C S/C D/C D/C S/C S/C D/C S/C POWERGRID POWERGRID POWERGRID POWERGRID WBSETCL POWERGRID POWERGRID HEL WBSETCL WBSETCL & OPTCL POWERGRID POWERGRID POWERGRID POWERGRID NTPC POWERGRID WBPDCL WBPDCL WBPDCL POWERGRID WBSETCL POWERGRID POWERGRID WBSETCL POWERGRID POWERGRID POWERGRID NTPC POWERGRID POWERGRID POWERGRID(ER) WBSETCL POWERGRID HEL WBSETCL POWERGRID(ER) DVC DVC 48 172 26 246 171 200 80 90 11 98 168 84 TW. MOOSE TW. MOOSE (HTLS) TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW. MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE 400 400 400 400 400 400 400 400 400 400 400 400 D/C D/C D/C S/C D/C S/C S/C D/C D/C S/C S/C D/C POWERGRID DVC DVC POWERGRID 97 156 TW. MOOSE TW. MOOSE 400 400 S/C D/C DVC POWERGRID POWERGRID POWERGRID POWERGRID DVC POWERGRID DVC POWERGRID POWERGRID(ER) POWERGRID POWERGRID SEL POWERGRID(ER) NTPC GMR OPTCL POWERGRID(ER) POWERGRID(ER) POWERGRID(ER) JINDAL NTPC POWERGRID DVC MPL MPL DVC POWERGRID APNRL POWERGRID DVC POWERGRID(SR) OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL POWERGRID OPTCL OPTCL OPTCL POWERGRID POWERGRID 111 82 31 188 169.17 52.9 0.3 39 116 220 25 18 220 3 51 8 90 273 190 115 85 24 QUAD-MOOSE QUAD-MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE QUAD-MOOSE TW. MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW.MOOSE TW. MOOSE 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 D/C D/C D/C D/C S/C S/C D/C S/C S/C D/C S/C S/C D/C S/C S/C S/C D/C S/C S/C S/C D/C D/C POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID APNRL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERLINKS OPTCL POWERGRID GMR POWERGRID OPTCL POWERGRID OPTCL JINDAL POWERGRID 89 | P a g e ERLDC: POSOCO Annexure XIV … contd Tie lines cont… 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 PATNA-SIPARA DEHRI--PUSUALI PUSUALI-SAHUPURI ARRAH-KHAGAUL PATNA-KHAGUAL SASARAM- NEW SASARAM NEW SASARAM- ARRAH BODHGAYA-GAYA(PG) DEHRI-GAYA(PG) MUZZFARPUR-KANTI MUZZAFFARPUR-HAZIPUR-I & II N.PURNEA - MADHEPURA N.PURNEA - PURNEA BALIMELA-U.SILLERU JINDAL-JAMSHEDPUR JODA-RAMCHANDRAPUR BUDHIPADAR-KORBA II & III BUDHIPADAR-RAIGARH I TSTPP-MERAMUNDALI TSTPP-RENGALI HPS BISRA(PG)-TARKERA(OPTCL) JEYPORE(PG)-JAYNAGAR(OPTCL) TSTPP-TALCHER FARAKKA-LALMATIA RENGALI-RENGALI BARIPADA-BALASORE MAITHON(PG)-K'SWARI(DVC) MAITHON- DUMKA CHANDIL-SANTALDIH RANCHI-HATIA CHANDIL-RANCHI TENUGHAT-BIHARSHARIF JAMSHEDPUR-RAMCHANDRAPUR MAITHON(PG)-DHANBAD(DVC) PARULIA(PG)-PARULIA(DVC) WARIA-BIDHANNAGAR DHALKHOLA(PG)-DHALKHOLA(WB) EM-SUBHASGRAM I &II SUBH'GRM(PG) - NEWTOWN SUBH'GRM(PG) - SUBH'GRM (WB) SUBH'GRM(PG) - EMSS(CESC) SUBH'GRM(PG) - BANTALA BINAGURI-NJP NJP- KISHANGANJ BIRPARA- CHUKHA BIRPARA-MALBASE BIRPARA-SALAKATI RANGPO- JLHEP NEW MELLI- JLHEP BSPHCL BSPHCL BSPHCL & UPPCL POWERGRID BSPHCL POWERGRID POWERGRID BSPHCL & PG BSPHCL & PG POWERLINKS BSPTCL POWERGRID POWERGRID OPTCL & APTRANSCO OPTCL & DVC OPTCL & JUSNL OPTCL & CSEB POWERGRID OPTCL OPTCL OPTCL OPTCL OPTCL ECL OPTCL OPTCL DVC POWERGRID WBSETCL & JUSNL JUSNL JUSNL BSPHCL & JUSNL POWERGRID DVC DVC DVC & WBSETCL POWERGRID CESC WBSETCL WBSETCL CESC WBSETCL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID DANS DANS POWEGRID BSPHCL POWERGRID POWERGRID POWERGRID POWERGRID BSPHCL BSPHCL BSPHCL POWERGRID POWERGRID POWERGRID POWERGRID OPTCL OPTCL OPTCL OPTCL OPTCL NTPC NTPC POWERGRID POWERGRID NTPC NTPC POWERGRID POWERGRID POWERGRID POWERGRID JUSNL POWERGRID JUSNL JUSNL POWERGRID POWERGRID POWERGRID DVC POWERGRID CESC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID WBSETCL POWERGRID POWERGRID POWERGRID(ER) POWERGRID POWERGRID 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 MUZZAFARPUR- DHALKEBAR BARHI - B'SHARIFF BARHI-RAJGIR DEOGHAR-SULTANGANJ KAHALGAON-KAHALGAON ARRAH-ARRAH DUMRAON-ARRAH PURNEA(PG)-PURNEA(BS) PURNEA(PG)-KISANGANJ DEHRI--PUSUALI KARMANASA--PUSUALI KARMANASA-SAHUPURI KARMANASA-CHANDAULI SONENAGAR - RIHAND MAITHON-JAMTARA KHARAGPUR-KHARAGPUR KOLAGHAT-KOLAGHAT MACHKUND-VIZAG JODA-KENDPOSI BARIPADA-RAIRANGPUR BARIPADA-BARIPADA GARWA-SONENAGAR LALMATIA-SABOUR POWERGRID BSPHCL & DVC BSPHCL & DVC BSPTCL & JUSNL POWERGRID POWERGRID POWERGRID BSPHCL BSPHCL POWERGRID POWERGRID BSPHCL & UPPCL BSPHCL & UPPCL BSPHCL & UPPCL DVC & JUSNL DVC DVC OPTCL & APTRANSCO OPTCL & JUSNL OPTCL OPTCL BSPHCL & JUSNL BSPHCL & JUSNL POWERGRID DVC DVC JUSNL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL DVC DVC DVC OPTCL OPTCL POWERGRID POWERGRID JUSNL JUSNL 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 CHANDIL-MANIQUE PATRATU-PATRATU GARWA-RIHAND RANGIT-RAMMAM KAHALGAON-SABOUR KAHALGAON-LALMATIA BIRPARA-BIRPARA MALDA-MALDA NJP-NBU RANGIT - MELLI ARHA-JAGDISHPUR RANGIT-RANGPO RANGIT-KURSEONG RANGIT-SAGBARI CHUJACHEN-MELLI BANKA-SABOUR BANKA-BANKA JUSNL & DVC JUSNL & DVC JUSNL & UPPCL POWERGRID POWERGRID POWERGRID WBSETCL WBSETCL WBSETCL SIKKIM BSPHCL POWERGRID POWERGRID SIKKIM POWERGRID & GATI BSPTCL BSPTCL JUSNL JUSNL JUSNL NHPC NTPC NTPC POWERGRID POWERGRID POWERGRID NHPC POWERGRID NHPC NHPC NHPC CHUJACHEN POWERGRID POWERGRID POWERGRID 158 159 NJP-MELLI BSPHCL POWERGRID UPPCL BSPHCL BSPHCL BSPHCL POWERGRID POWERGRID POWERGRID BSPHCL BSPTCL BSPTCL BSPTCL APTRASCO DVC JUSNL CHATTISGARH CHATTISGARH OPTCL OPTCL OPTCL OPTCL OPTCL NTPC OPTCL OPTCL DVC JUSNL WBSETCL JUSNL POWERGRID BSPHCL JUSNL DVC DVC WBSETCL WBSETCL POWERGRID WBSETCL WBSETCL CESC WBSETCL WBSETCL POWERGRID POWERGRID POWERGRID POWERGRID(NER) DANS DANS 0.5 64 72 50 25 0.2 112 96 16 22 56 100 2 24 130 127 180 81 40 40 15 6 30 79 1 77 7 73 105 34 42 182 0.5 28 1 17 3 24 26 0.5 23.2 19 0.2 108 38 40 160 10 21 ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA MOOSE ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA TW.MOOSE ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA & CABLE ZEBRA ZEBRA MOOSE MOOSE ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 D/C S/C S/C D/C S/C S/C S/C D/C D/C D/C D/C D/C D/C S/C S/C S/C D/C S/C D/C S/C D/C D/C S/C S/C D/C D/C D/C D/C S/C D/C S/C S/C D/C D/C D/C D/C S/C D/C S/C D/C D/C S/C S/C D/C D/C S/C D/C S/C S/C NEPAL BSPHCL BSPHCL BSPHCL NTPC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID UPPCL UPPCL UPPCL JUSNL WBSETCL WBSETCL APTRANSCO JUSNL OPTCL OPTCL BSPHCL BSPHCL 129 170 125 93 2 3 61 1 70 63 29 27 25 139 100 1 1 160 48 70 11 104 72 ZEBRA LARK LARK PANTHER PANTHER PANTHER PANTHER LARK PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER LARK PANTHER PANTHER PANTHER PANTHER PANTHER 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 S/C S/C S/C S/C S/C S/C S/C T/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C S/C DVC DVC UPPCL WBSETCL BSPHCL JUSNL WBSETCL WBSETCL WBSETCL SIKKIM BSPHCL POWERGRID WBSETCL SIKKIM SIKKIM BSPTCL BSPTCL 1 3 30 27 37 34 1 6 8 32.5 30 54 61 25 66.3 45 11 PANTHER LARK PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER PANTHER+ ZEBRA PANTHER PANTHER 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 132 D/C S/C S/C S/C S/C S/C D/C D/C D/C D/C S/C S/C S/C S/C S/C S/C S/C C) 132 KV LINES RANGPO-CHUJACHEN 161 RANGPO- MELLI NJP-MELLI LAKHISARAI - JAMAUI 162 163 RANGIT - RABANGLA KALINGPONG-MELLI 160 132 S/C POWERGRID POWERGRID SIKKIM 90 PANTHER 132 POWERGRID POWERGRID BSPHCL GATI INFRA POWERGRID POWERGRID POWERGRID CHUJACHEN SIKKIM BSPHCL GATI INFRA 17 90 25 20 PANTHER PANTHER PANTHER ZEBRA 132 132 132 S/C S/C D/C POWERGRID WBSETCL & SIKKIM NHPC WBSETCL SIKKIM SIKKIM 25 15 LARK DOG 66 66 S/C D/C S/C 90 | P a g e ERLDC: POSOCO Other Important Lines S.NO LINE OWNED BY CONNECTED SYSTEMS LENGTH COND. VOLTS NO.OF END-2 (KM) (TYPE) (KV) CKTS. POWERGRID 272 Qd. BERSIMIS 765 D/C 184 89 145 231 277 217 94 196 168 71 98 240 130 195 95 95 99 167 99 100 156 72 356 171 143 82 120 130 162 130 210 185 75 80 98 177 153 200 72.5 141 77 143 110 TW. MOOSE TW. MOOSE TW. MOOSE QD. MOOSE Qd. BERSIMIS QUAD-MOOSE QUAD-MOOSE QUAD-MOOSE QUAD-MOOSE QUAD-MOOSE QUAD-MOOSE QUAD-MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE TW. MOOSE QUAD-MOOSE TW. MOOSE TW.MOOSE 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 400 D/C D/C D/C D/C D/C D/C Q/C D/C D/C D/C D/C D/C D/C D/C D/C D/C D/C D/C S/C S/C S/C S/C S/C D/C D/C D/C D/C S/C S/C S/C D/C D/C S/C S/C S/C S/C S/C D/C D/C S/C Q/C D/C D/C 40 85 75 152 68 101 112 92 21 34 63 63 44 150 1 20 41 42 55 18 70 31 16 16 55 53 51 30 6 10 90 95 61 25 120 30 101 102 34 136 6 93 20 134 135 65 68.7 176 64 ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA SINGLE CORE XLPE ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA TW. MOOSE ZEBRA ZEBRA ZEBRA ZEBRA TW. MOOSE ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA ZEBRA 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 220 D/C D/C D/C D/C D/C S/C S/C S/C D/C D/C S/C S/C D/C D/C S/C D/C S/C D/C T/C S/C S/C D/C D/C D/C D/C S/C D/C S/C D/C D/C D/C D/C D/C Q/C D/C S/C S/C S/C S/C S/C D/C T/C S/C D/C S/C S/C S/C D/C D/C END-1 A) 765 KV LINES 1 ANGUL-JHARSUGUDA POWERGRID POWERGRID B) 400 KV LINES 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 BANKA-BIHARSARIFF LAKHISARAI-BIHARSARIFF KAHALGAON -LAKHISARAI BIHARSHARIFF-PURNEA MAITHON-GAYA KAHALGAON -BARH BARH -PATNA PATNA- KISHANGANJ PURNEA - BINAGURI I & II PURNEA-KISHANGANJ BINAGURI-KISHANGANJ PURNEA - MUZAFFARPUR BIHARSHARIFF-MUZAFFARPUR BIHARSHARIFF- PUSAULI FARAKKA - KAHALGAON I & II FARAKKA-KAHALGAON III & IV BOKARO-KODERMA MALDA - PURNEA MERAMUNDALI - MENDASAL RENGALI-KEONJHAR KEONJHAR- BARIPADA JEYPORE - INDRAVATI INDRAVATI - RENGALI TSTPP - ROURKELA ROURKELA- JHARSIGUDA JAMSHEDPUR - CHAIBASA CHAIBASA- ROURKELA KTPS - JEERAT BAKRESWAR - JEERAT BAKRESWAR - ARAMBAGH PPSP - ARAMBAGH PPSP - BIDHANAGAR KTPS - ARAMBAGH KTPS-KHARGPUR KTPS-KHARGPUR PARULIA - JAMSHEDPUR MAITHON - JAMSHEDPUR MAITHON - RANCHI DSTPS-RAGHUNATHPUR I & II JAMSHEDPUR-BARIPADA RANCHI-RANCHI NEW RANCHI-ROURKELA-I&II BINAGURI-RANGPO POWERGRID POWERGRID POWERGRID ENICL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERLINKS POWERGRID POWERGRID POWERGRID POWERGRID DVC POWERGRID OPTCL OPTCL OPTCL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID WBSETCL WBSETCL WBSETCL WBSEDCL WBSEDCL WBSETCL WBSETCL WBSETCL POWERGRID POWERGRID POWERGRID DVC POWERGRID POWERGRID POWERGRID POWERGRID 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 BIHARSHARIFF-FATUAH BIHARSHARIFF-BODHAGYA BIHARSHARIFF-BEGUSARAI MTPS-BEGUSARAI MTPS-DARBHANGA MTPS-GOPALGANJ SASARAM-ARRAH FATUAH-MTPS WARIA-PARULIA WARIA-MEJIA CTPS A-DHANBAD CTPS B-DHANBAD DHANBAD-GIRIDIH BOKARO-JAMSHEDPUR KASBA-EMBYPASS KASBA-SUBHASGRAM(WB) BOKARO-CTPS BOKARO-CTPS B KALYANESHWARI-MEJIA KALYANESHWARI-BURNPUR BURNPUR-MEJIA MEJIA-MUCHIPARA MEJIA-BARJORA PARULIA-MUCHIPARA BOKARO-RAMGARH PTPS -TENUGHAT PATRATU-HATIA CHANDIL-RAMCHANDRAPUR JEYANAGAR-U.KOLAB MERAMANDALI-NALCO MERAMUNDALI - BIDANASI MERAMUNDALI - DUBURI(OLD) KATAPALLI-BUDHIPADAR IBTPS - BUDHIPADAR TARKERA-BUDHIPADAR TARKERA-CHANDIPOSH TARKERA-BARKOT RENGALI-CHANDIPOSH RENGALI-BARKOT U. KOLAB-THERUVALI U. KOLAB-JAYANAGAR BALIMELA-JEYNAGAR TALCHER-MERAMUNDALI MERAMUNDALI - BHANJNAGAR MENDHASAL -BHANJNAGAR MENDHASAL - NAYAGARH NAYAGARH - BHANJNAGAR THERUVALLI - BHANJNAGAR THERUVALLI - LAXMIPUR BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL POWERGRID BSPHCL DVC DVC DVC DVC DVC DVC CESC WBSETCL DVC DVC DVC DVC DVC DVC DVC DVC DVC JUSNL JUSNL JUSNL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL POWERGRID POWERGRID NTPC POWERGRID POWERGRID NTPC NTPC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID NTPC NTPC DVC POWERGRID OPTCL POWERGRID POWERGRID POWERGRID POWERGRID NTPC POWERGRID POWERGRID POWERGRID WBPDCL WBPDCL WBPDCL WBPDCL WBPDCL WBPDCL WBPDCL WBPDCL POWERGRID POWERGRID POWERGRID DVC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID NTPC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID NTPC NTPC DVC POWERGRID OPTCL OPTCL POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID WBSETCL WBSETCL WBSETCL WBSETCL WBSETCL WBSETCL WBSETCL WBSETCL POWERGRID POWERGRID POWERGRID DVC POWERGRID POWERGRID POWERGRID POWERGRID C) 220 KV LINES BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL POWERGRID BSPHCL DVC DVC DVC DVC DVC DVC WBSETCL WBSETCL DVC DVC DVC DVC DVC DVC DVC DVC DVC JUSNL JUSNL JUSNL OPTCL NTPC OPTCL OPTCL OPTCL OPGC OPTCL OPTCL OPTCL OPTCL OPTCL OHPC OHPC OHPC NTPC OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL BSPHCL POWERGRID BSPHCL DVC DVC DVC DVC DVC DVC CESC WBSETCL DVC DVC DVC DVC DVC DVC DVC DVC DVC TVNL JUSNL JUSNL OHPC NALCO OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL OPTCL 91 | P a g e ERLDC: POSOCO Annexure XIV …. contd List of important Transformers LOCATION VOLTAGE RATIO CAPACITY (MVA) OWNERSHIP A) 765/400 KV ICTS GAYA RANCHI NEW SASARAM ANGUL JHARSUGUDA 765/400 765/400 765/400 765/400 765/400 3X1500 2X1500 2X1500 4X1500 2X1500 POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID B) 400/220 KV & 400/132 KV ICTS JAMSHEDPUR FARAKKA PARULIA MALDA BIHARSHARIF JEYPORE RENGALI MAITHON ROURKELA RANGPO CHAIBASA NEW DUBURI RANCHI TSTPP BINAGURI BARIPADA INDRAVATI HPS KEONJHAR BOLANGIR ARAMBAGH BIDHANNAGAR KOLAGHAT TPS BAKRESWAR TPS SAGARDIGHI TPS PATNA MERAMUNDALI MENDHASAL KODERMA TPS JEERAT KHARAGPUR BOKARO-A TPS KISHANGANJ TISCO BANKA LAKHISARAI BARH-II STPS KAHALGAON GAYA SASARAM NEW PURNEA MUZAFFARPUR SUBHASGRAM 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/220 400/132 400/132 400/132 400/132 400/132 400/220 400/220 400/220 400/220 400/220 2X315 1X315 2X315 2X315 3X315 2X315 2X315 2X315 2X315 5X315 2X315 2X 315 2X315 2X315 2X315 2X315 2X315 2X315 2X315 4X315 2X315 2X315 2X315 1X315 2X315 2X315 2X315 2X315 4X315 2X315 2X315 1X 500 2X315 2X200 2 x 200 2X200 2X200 1X315 + 1X500 1 X 500 + 1X315 1 X 500 + 1X315 2X315 + 1 X 500 4X315+1X500 POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID NTPC POWERGRID POWERGRID POWERGRID(1) + OHPC(1) POWERGRID POWERGRID WBSETCL WBSETCL WBPDCL WBPDCL WBPDCL POWERGRID OPTCL OPTCL DVC WBSETCL WBSETCL DVC POWERGRID DVC POWERGRID POWERGRID NTPC NTPC POWERGRID POWERGRID POWERGRID POWERGRID POWERGRID(2+1) + CESC(2) 92 | P a g e ERLDC: POSOCO Annexure XIV (contd) List of Reactors and Harmonic Filters LENGTH Sl No LINE/SUB-STN REACTORS CAPACITY IN MVAR ( KM ) LINE 1 2 BEHRAMPUR-JEERAT SAGARDIGHI-SUBASHGRAM 200 256.3 3 4 5 6 7 8 9 11 12 14 15 16 FARAKKA-PARULIA-I BIDHANAGAR-PARULIA I LAKHISARAI-B'SHARIFF-I LAKHISARAI-B'SHARIFF-II K'GAON-MAITHON-I K'GAON-MAITHON-II ROURKELLA-CHAIBASA-I ROURKELA-TALCHER I ROURKELA-TALCHER II ROURKELA- JAMSHEDPUR-II KEONJHAR-BARIPADA BARIPADA-MENDASAL-II 150 11 89 89 172 172 120 175 175 17 18 19 BAKRESWAR-ARAMBAGH BAKRESWAR-JEERAT RENGALI-INDRAVATI 132 162 356 20 21 22 23 24 25 26 27 28 29 32 B'SHARIFF-TENUGHAT MALDA-PURNEA -I MALDA-PURNEA -II BINAGURI-BONGAIGAON-I BINAGURI-BONGAIGAON-II BINAGURI-BONGAIGAON-III BINAGURI-BONGAIGAON-IV BINAGURI-TALA-I BINAGURI-TALA-II BINAGURI-TALA-IV PURNEA-MUZAFFARPUR-I 180 167 167 216 216 224 224 115 115 98 240 33 PURNEA-MUZAFFARPUR-II 240 34 35 36 37 38 ROURKELA-JHARSUGUDA- I ROURKELA-STERLITE-I MERAMUNDALI-ANGUL-I ANGUL-BOLANGIR BOLANGIR-JEYPORE 142 113 20.8 199 288 39 40 41 42 43 44 45 46 47 48 B'SHARIFF-PUSAULI -I PUSAULI-ALLAHABAD PUSAULI-SARNATH MUZAFFARPUR-GRKPR-I MUZAFFARPUR-GRKPR-II B'SHARIFF-BALIA -I B'SHARIFF-BALIA -II PATNA-BALIA-III PATNA-BALIA-IV RANCHI-SIPAT-I 195 271 260 260 242 242 185 185 405 49 RANCHI-SIPAT-II 405 50 51 52 JEYPORE-GAJUWAKA-I JEYPORE-GAJUWAKA-II MPL-RANCHI -I 220 220 188 156 273 53 MPL-RANCHI -II 188 54 55 56 PUSAULI-BIHARSHARIFF-I PUSAULI-BIHARSHARIFF-II 765 kV PUSAULI-FATHEPUR 198 198 356 57 765 kV RANCHI-DHRAMJAYGARH I 303 58 765 kV RANCHI-DHRAMJAYGARH II 303 59 60 61 LAKHISARAI-KhSTPP - I LAKHISARAI-KhSTPP - II PATNA - KISHANGUNJ-I 145 145 352 62 PATNA - KISHANGUNJ-II 352 63 MAITHON-GAYA-I 235 64 MAITHON-GAYA-II 235 65 66 67 68 69 70 71 72 73 74 MAITHON-MEJIA-I BANKA-BIHARSARIFF I & II BARIPADA-KEONJHAR BIHARSARIFF-PURNEA I BIHARSARIFF-PURNEA II BIHARSARIFF-VARANASI-I BIHARSARIFF-VARANASI-II PURNEA- BINAGURI-I PURNEA- KISHANGANJ-I 765 KV GAYA- BALIA 83 185 156 232 232 321 321 168 71 120 75 76 77 765 KV GAYA- VARANASI-I 766 KV GAYA- VARANASI-II 765 KV JHARSUGUDA-ANGUL I 272 272 273 78 765 KV JHARSUGUDA-ANGUL II 273 79 80 764 KV JHARSUGUDA-DHARAMJAYGARH-I 765 KV JHARSUGUDA-DHARAMJAYGARH- II 151 151 TOTAL REMARKS END 1X50 1X63 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1X50 1 X 63 1 X 63 1X63 1X63 1x50 1x50 1x50 1x63 1x63 1X63 1X63 1X80 1X80 1X63 1X63 1X63 1x63 1x63 1x63 1x63 1x63 1X63 1x80 1x50 1x50 1x80 1X50 1X63 1X63 1X63 1X50 1X50 1X50 1X63 1X63 1X80 1X80 1X80 1X80 1X80 1X80 1 X50 1 X50 1 X50 1 X50 1 X63 1 X63 1 X 330 # 1 X 330 # 1 X 240 # 1 X 330 # 1 X 240 # 1 X 330 # 1 X 50 1 X 50 1 X 63 1 X 63 1 X 63 1 X 63 1 X 50 1 X 50 1 X 50 1 X 50 1 X 50 2 X 50 1 X 50 1 X 80 1 X 80 1 X 50 1 X 50 1 X 63 1 X 63 1 X 240 # 1 X 330 # 1 X 240 # 2 X 240 # 1 X 240 # 1 X 240 # 1 X 240 # 1 X 240 # 1 X 330 # 1 X 330 # JEERAT SAGARDIGHI SUBHASGRM FARAKKA PARULIA B'SHARIFF B'SHARIFF MAITHON MAITHON ROURKELA TSTPP TSTPP ROURKELA BARIPADA MENDASAL BARIPADA BAKRESWAR JEERAT RENGALI INDRAVATI TENUGHAT MALDA MALDA BONGAIGAON BONGAIGAON BINAGURI BINAGURI BINAGURI BINAGURI BINAGURI PURNEA MZFRPR PURNEA MZFRPR ROURKELA ROURKELA MERAMUNDALI BOLANGIR BOLANGIR JEYPORE BIHARSARIFF PUSAULI PUSAULI MUZAFFARPUR MUZAFFARPUR BALIA BALIA BALIA BALIA RANCHI SIPAT RANCHI SIPAT GAJUWAKA GAJUWAKA MPL RANCHI MPL RANCHI PUSAULI PUSAULI PUSAULI FATHEPUR RANCHI DHARAMJAYGARH RANCHI DHARAMJAYGARH LAKHISARAI LAKHISARAI PATNA KISHANGANJ PATNA KISHANGANJ GAYA MAITHON GAYA MAITHON MAITHON BANKA BARIPADA BIHARSARIFF BIHARSARIFF BIHARSARIFF BIHARSARIFF PURNEA PURNEA GAYA BALIA GAYA GAYA JHARSUGUDA ANGUL JHARSUGUDA ANGUL DHARAMJAYGARH DHARAMJAYGARH SWITCHABLE SWITCHABLE NOW AT 220 KV IN NER IN NER SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE IN NR IN NR IN NR IN NR IN WR IN WR IN SR (SWITCH) IN SR (SWITCH) 765 kV LINE SWITCHABLE IN NR 766 kV LINE SWITCHABLE IN WR (SWITCHABLE) 767 kV LINE SWITCHABLE IN WR (SWITCHABLE) SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE SWITCHABLE IN WR (SWITCHABLE) IN WR (SWITCHABLE) 9549 93 | P a g e ERLDC: POSOCO Annexure XIV.. contd Sl No LINE/SUB-STN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 765 KV ANGUL 765 kV GAYA 765 KV JHARSUGUDA 765 kV PUSAULI 765 kV RANCHI NEW ANGUL ARAMBAGH BAKRESWAR BANKA BARH BEHRAMARA BEHRAMPORE BIDHANNAGAR BIHARSHARIFF BINAGURI BOLANGIR CHAIBASA DUBURI DURGAPUR FARAKKA GAYA INDRAVATI JAMSHEDPUR JEERAT JEYPORE JHARSUGUDA JITPL KAHALGAON KEONJHAR KHARAGPUR KISHANGANJ KODERMA LAKHISARAI MAITHON MAITHON RIGHT BANK MUZAFFARPUR NEW MELLI PANDIABALLI PATNA PURNEA PUSAULI RAGHUNATHPUR RANCHI RANCHI NEW RANGPO RENGALI ROURKELA LENGTH ( KM ) REACTORS CAPACITY IN MVAR REMARKS BUS 2 x 330 # 2 x 240 # 2 X 240 # 1 x 330 # 2X240 # 3X125 1X50 1X50 1X80 1X80 2X63 1X80 1X50 1X50+1X80+1X125 2X125 1X80 1X80 1X80 1X50 2X50 2 X125 1X125 2X50 1X50 31.5* + 1X125 +1 x 63 2X125 2X50 2X50 1X80 1 X80 1 X 125 2X50 1 X 80 1X50 2 X 50 2X125 1X63 1X80+1X63 1X80+2x125 2X125 2 X 125 2X50 1X80+1x125 2x125 2 X 80 31.5* 1X50+1X125 TOTAL # three single phase units, whose combined capacity is indicated 765 kV 765 kV 765 kV 765 kV 765 kV BANGLADESH * T ertiary winding of 400/220/33 kV ICT 125 * T ertiary winding of 400/220/33 kV ICT 7983 * 31.5 MVAR reactor is connected to 33 kV tertiary winding SERIES COMPENSATION ELEMENTS & HVDC CONVERTERS 1 2 3 4 5 5 FSC + TCSC AT PURNEA END OF 400KV PURNEA - MUZAFFARPUR I & II FSC AT JEYPORE END OF 400KV BOLANGIR-JEYPORE LINE FSC AT JEYPORE END OF 400KV JEYPORE - GAJUWAKA I& II FSC AT RENGALI END OF 400KV RENGALI - INDRAVATI LINE FSC AT RANCHI END OF 400 KV RANCHI-SIPAT I & II 500MW HVDC BACK-TO-BACK CONVERTER AT SASARAM Filters at Gazuwaka East 106 MVAR Doubled Damped Filter 106 MVAR 3rd Harmonic/Doubled Damped Filter 50 MVAR Bus Reactor Filters at Talcher Doubled Damped filter 120 MVAR (Switchable) 97 MVAR 66 MVAR Shunt Capacitor 72.6 MVAR Shunt Capacitor Filters at Pusauli 112 MVAR at North Bus 112 MVAR at East Bus Filters at Bheremara 91 MVAR at 400 kV Side 91 MVAR at 230 kV Side Number 1 2 2 Number 6 3 1 2 Number 4 4 Number 4 4 94 | P a g e ERLDC: POSOCO List of Important Generators Control Area Station Type Owner Farakka Farakka STPS Stage I & II Farakka STPS Stage III Kahalgaon STPS Stage I Kahalgaon STPS Stage II Talcher STPS Stage I Talcher STPS Stage II ISGS Thermal ISGS Thermal ISGS Thermal ISGS Thermal ISGS Thermal ISGS Thermal ISGS Thermal ISGS Hydro ISGS Hydro ISGS Hydro ISGS Hydro ISGS Hydro ISGS Hydro ISGS Hydro Thermal Hydro Thermal Thermal Thermal Thermal Thermal Thermal Thermal Thermal Thermal Thermal Thermal Thermal Hydro Hydro Thermal Thermal Thermal Thermal Thermal Hydro Hydro Hydro Hydro Thermal Thermal Thermal Thermal Thermal Thermal Hydro Hydro NTPC NTPC NTPC NTPC NTPC NTPC NTPC NHPC NHPC DGPC(Bhutan) DGPC(Bhutan) DGPC(Bhutan) DGPC(Bhutan) DGPC & TATA TVNL(JSEB) JSEB DVC DVC DVC DVC DVC DVC DVC WBPDCL WBPDCL WBPDCL WBPDCL WBPDCL NHPC WBSEDCL DPL DPL HEL CESC OPGC OHPC OHPC OHPC OHPC MPL APNRL SEL GMR-Infra' JINDAL IBEUL DANS GATI Kahalgaon Talcher Stg I Talcher Stg II Barh Teesta -V Rangit Bhutan Bhutan Bhutan Bhutan Bhutan Teesta Rangit Tala Chukha BHPC Kurichu Dagachu Tenughat Jharkhand Subarnarekha Waria Mejia CTPS B Mejia-B DVC Koderma TPS Bokaro"B" DSTPS Kolaghat Sagardighi Bakreswar Santaldih Bandel TLDP West Bengal PPSP DPL DPL HALDIA Budge-Budge IB Balimela U-Kolab Orissa U-Indravati Rengali MPL ADHUNIK Sterlite* GMR* IPP JITPL INDBHARAT JLHEP CHJACHEN * one unit of Sterlite and GMR is dedicated to Odisha Capacity(MW) 3x200+2x500 1x500 4x210 3x500 2x500 4x500 2X660 3x170 3x20 6x170 4x84 20X2+2X12 4x15 2x63 2x210 2X65 (U#4) 210 4X210+2X250 2 X 250 2 X 500 2 x 500 3x210 2 X 500 6x210 2x300 5x210 2 X 250 U#5 (210) 4x33 4X225 (U#7) 300 (U#8) 250 2X300 3X250 2x210 6x60+2x75 4x80 4x150 4x50 2 x 525 2X270 4X600 3x350 2x600 2X350 2X48 2 X 55 95 | P a g e ERLDC: POSOCO Annexure :XV Automatic UFR load shedding Schemes and Feeder Disconnection to control overloading 96 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of Bihar UFR relay 97 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of Jharkhand UFR relay 98 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of DVC UFR relay 99 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of Odisha UFR relay 100 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of West Bengal UFR relay 101 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Feeder wise detail of CESC UFR relay Settings of Under frequency relays CESC system Stage 132/33kV G/S/S CHAKMIR 49.2Hz NCGS DUMDUM 49.0Hz BBGS MAJERHAT 48.8Hz JADAVPORE KRS PRS NCGS 48.6Hz LILUAH 33kV Feeder Stage‐I 55 MVA TRF ‐ 1 & 2 KAMARHATI TRF ‐ 1 KUTIGHAT TRF ‐ 3 TOTAL Stage‐II NEW DUMDUM TRF ‐ 1 NEW DUMDUM TRF ‐ 2 SOUTH DUMDUM TRF ‐ 1 DUMDUM TRF ‐ 3 BAURIA 1 & 3 FORESHORE RD D/S( 6 KV FEEDER) SALIMAR D/S ( 6 KV FEEDER) TOTAL Stage‐III DIAMOND CITY WEST D/S THAKURPUKUR TRF ‐ 1 THAKURPUKUR TRF ‐ 2// BEHELA(N) TRF ‐ 1 SOUTHCITY D/S TRF ‐ 2 TOLLYGUNJE(N) D/S TRF ‐ 1/ SOUTH CITY TRF ‐ 1 BALLYGUNJE D/S 6 KV TRF ‐ 1 PRINCEP ST D/S (6 KV FEEDER) KUTIGHAT TRF ‐ 1 KUTIGHAT TRF ‐ 2 KUTIGHAT TRF ‐ 4 TOTAL Stage‐IV 132 KV LILUAH ‐ CESC(BRS) 1,2 &3 AT WBSETCL LILUAH S/S TOTAL Max Load in MW SUMMER WINTER 47 29 8 6 10 8 65 43 15 14 15 12 18 9 7 90 11 9 8 7 12 5 3 55 13 10 7 4 24 13 14 8 23 8 16 6 6 6 125 15 5 10 4 4 4 75 120 70 120 70 102 | P a g e ERLDC: POSOCO Annexure: XV (Cont…) Priority wise Feeders/ICTs identified to be disconnected in case of over drawal Bihar Priority 1 2 3 Feeders/ICTs 400/220 kV 315 MVA ICT at Biharsariff 132 kV Arrah (PG)- Arrah (BSPHCL) 132 kV Purnea(PG)-Purnea(BSPHCL) Point of Disconnection 400 kV Biharsariff PG 132 kV Arrah PG 132 kV Purnea PG Feeders/ICTs One 400/220 kV 315 MVA ICT Jamsedpur 220 kV Ranchi(PG)-Chandil(JUVNL) Point of Disconnection 400 kV Jamsedpur Jharkhand Priority 1 2 220 kV Ranchi-PG DVC Priority 1 2 3 Feeders/ICTs 220 kV Maithon (PG)-Kalyaneswari (DVC) 220 kV Parulia (PG)-Parulia (DVC) 220 kV Maithon (PG)-Dhanbad (DVC) Point of Disconnection 220 kV Maithon-PG 220 kV Parulia PG 220 kV Maithon-PG Feeders/ICTs 220 kV Rengali(PG)-Rengali(OPTCL) 220/132 kV Baripada 160 MVA ICT 220 kV Baripada(PG)-Balsore (Odisha) Point of Disconnection 220 kV Rengali-PG 220 kV Baripada-PG 220 kV Baripada-PG Feeders/ICTs 220 kV Dalkohla (PG)-Dalkohla(WB) 132 kV Malda (PG)-Malda(WB) 220 kV Subhasgram(PG)Subhashgram(WB) Point of Disconnection 220 kV Dalkohla-PG 132 kV Malda-PG 220 kV Subhasgram PG Odisha Priority 1 2 3 West Bengal Priority 1 2 3 103 | P a g e ERLDC: POSOCO Annexure :XVI Power Demand Override PDOs at Talcher Sl No 1 2 3 4 5 6 7 Number of Connected generators /AC lines 6 5 4 3 2 1 0 DC Power Limit in MW No Limit No Limit No Limit 1500 MW 1000 MW 500 MW Controlled Shut down /ESOF PDOs at Kolar Sl No 1 2 3 4 5 6 7 Number of Connected generators /AC lines 6 5 4 3 2 1 0 DC Power Limit in MW No Limit 2000 MW 1500 MW 1000 MW 500 MW Controlled Shut down Controlled Shut Down/ ESOF PDO (Run Back) at HVDC Gajuwaka Totally 16 PDO’s can be programmed at HVDC Gajuwaka .Presently only 4 PDO’s have been used and they are detailed below PDO’s at HVDC Gajuwaka Poles SL NO Type of PDO Contingency DC Powerlimit 1 PDO-2 East Bus AC U/V Relay set at Vs – 87.5 V or 318 kV ( on 400 kV side on any phase- phase) 500 MW 2 PDO-4 500 MW 3 PDO-5 4 PDO-6 Tripping of Jeypore –Indravati 400kV S/C Jeypore-meramundali 400kV S/C One ckt of Jeypore-Gazuwaka 400kV D/C Both 400/220kV Jeypore ICTs Jeypore-Jeynagar 220kV D/C East Bus frequency at 49.0 Hz and below. Rate of fall of frequency df/dt – 0.3 Hz./sec Overload Trip contact of Gajuwaka S/s ICT on southern side 150 MW 250MW 104 | P a g e ERLDC: POSOCO Annexure : XVII Special Protection schemes at Talcher and Kolar SPS 450 Under this mode of SPS the power injection to N-E-W grid is limited to 450 MW. The actual generation by the generators is considered for building the logic. Logic for single pole tripping: This logic is based on the assumption that during the tripping of one pole of HVDC the other available pole will automatically ramp up to 1250 MW. The logic is built using power relays and the logic adopted is detailed below. One pole trips AND Total Power injected by generators is more than 1700 MW THEN Tripp one of the selected unit (Presently unit six selected) instantly Logic for Bipole tripping Presently this logic is built using power relays and the logic adopted is detailed below. If Both Poles trip AND Power injected by Generators is more than 1100 MW THEN Trip two nos of selected units( presently unit six and three are selected) IF The total power injected by the generators is still more than 550 MW for more than 250 milliseconds THEN Trip Unit 4 SPS 1000 Under this mode of SPS the power injection to N-E-W grid is limited to 1000 MW. The actual injection to the HVDC system (by measuring the flow on four a/c lines between TSTPS and Talcher HVDC station) is considered for building the logic. Under SPS 1000 scheme no generation shedding is required for a single pole tripping. For contingencies of both pole tripping and for single pole tripping with the HVDC system going to ground return mode, generation shedding will be done. Extent of generation shedding depends on the actual power flow through the HVDC link and to limit the actual injection to N-E-W grid to 1000 MW 105 | P a g e ERLDC: POSOCO 106 | P a g e ERLDC: POSOCO HVDC INTER TRIP SCHEME (SPS 1000) Sl number Condition Unit 6 Trip 1 IF THE HVDC POWER FLOW IS MORE THAN 1600 MW & BOTH POLE BLOCKED Unit 5 Unload by 150 MW Unit 4 Unload by 150 MW IF THE HVDC POWER FLOW IS BETWEEN 1450 MW TO 1600 MW & BOTH POLE BLOCKED Unit 6 Trip Unit 5 Unload by 150 MW Unit 4 No effect IF THE HVDC POWER FLOW IS MORE THAN 1600 MW & ONE POLE BLOCKED WITH REMAINING POLE ON GROUND RETURN MODE Unit 6 Trip Unit 5 Unload by 150 MW Unit 4 No effect IF THE HVDC POWER FLOW IS BETWEEN 1300 MW TO 1450 MW & BOTH POLE BLOCKED Unit 6 Unit 5 Unload by 150 MW Unload by 150 MW Unit 4 Unload by 150 MW Unit 6 Unload by 150 MW Unit 5 Unload by 150 MW Unit 4 Unload by 150 MW Unit 6 Unit 5 Unit 4 Unload by 150 MW No effect Unload by 150 MW Unit 6 Unload by 150 MW Unit 5 No effect Unit 4 Unload by 150 MW Unit 6 Unload by 150 MW 8 IF THE HVDC POWER FLOW IS BETWEEN 1000 MW TO 1150 MW & BOTH POLE BLOCKED Unit 5 Unit 4 No effect No effect Unit 6 Unload by 150 MW 9 IF THE HVDC POWER FLOW IS MORE BETWEEN 1000 MW TO 1150 MW & ONE POLE BLOCKED WITH REMAINING POLE ON Unit 5 No effect Unit 4 No effect 2 3 4 5 IF THE HVDC POWER FLOW IS MORE BETWEEN 1450 MW TO 1600 MW & ONE POLE BLOCKED WITH REMAINING POLE ON GROUND RETURN MODE 6 IF THE HVDC POWER FLOW IS BETWEEN 1150 MW TO 1300 MW & BOTH POLE BLOCKED 7 IF THE HVDC POWER FLOW IS MORE BETWEEN 1300 MW TO 1450 MW & ONE POLE BLOCKED WITH REMAINING POLE ON GROUND RETURN MODE Action 107 | P a g e ERLDC: POSOCO Annexure :XVIII Islanding schemes in ER Station/System Islanding scheme Criteria CHPC (Bhutan) One machine (84 MW) alongwith Thimpu Load gets islande with opening of bus coupler breaker The entire system gets islanded at Kasba ( the synchronising point) Low Frequency( 47.0Hz) CESC NALCO(CPP in Orissa system) ICCL(CPP within Orissa system) RSP (CPP in Orissa system) Bhushan Power & Steel (CPP in Orissa system) Arya ISPAT and power Ltd. (CPP in Orissa system) Main –I bus connects all lines connecting OPTCL Network Main –II bus connects plant load and generators Bus coupler breaker opens to isolate plant with generators from rest of the system The plant gets connected to OPTCL network at 132kV. The 132/33 kV Transformer gets isolated from 132kV system CP2 has 2 units 60MW each generating at 11kV and connected to 132 bus through 132/33 transformer CP1 has 3 units, 45 MW each, generating at 6.6 kV and connected to 33 kV bus through 33/6/6kV Transformer Scheme I : All units gets islanded by opening of 132kV lines Scheme II: One unit may reamin with Grid and get islanded by opening of 132kV and 33kV Bus coupler CBs 130MW TG#1 & TG#2 will get islanding status in Governor, AVR and Siprotect Relays through PLC Logic. For this all status of breaker in MRSS (220kV Main breaker# 1,220kV Main breaker#2, and Bus coupler) and 220kV cable feeder #1 at 130MW power plant wired up to PLC in 130MW Whenever the 18 MW TG set is running in synchronization condition with OPTCL Grid following relays have been nvisaged for islanding purpose of 18 MW TG set: 1)MICOM-P341, Areva make 2)6RW 6000, Siemens make MICOM-P341 shall sense any rate of changed of frequency and the variation of voltages between Grid supply and Low frequency (47.8 Hz) Or High frequency (52.5 Hz) Low Freq( 47.4 Hz) Low Freq ( 47.5 Hz) Low frequency(Both the schemes operate at 47.6 Hz) Under frequency 47.5 Hz for 2.5 Sec Over Frequency 52.6 Hz for 2.5 Sec 108 | P a g e ERLDC: POSOCO generation. Accordingly, it shall give trip command to Grid incomer breaker. Instead of above, the electrical quantities like U/V, O/V, U/F, O/F are measured by MICOM-P341 as well as 6RW 6000 and give trip command to Grid incomer breaker Maithon Ispat Limited (CPP in Orissa system) In the scheme, Micom P 341 Relay, Areva Make, operates during Grid Disturbance and it gives Trips command to SMS TIE 2 breaker and 220 kV incomer breaker and consequently incomer breaker gives trip command to 20/25 and 28/35 MVA transformer 220 kV incomer breaker and 11 kV ALONE Breaker through interlocks Whenever there is a disturbance in the system, the relay calculates the current & voltage parameters and evaluates the type of fault. Then the relay gives the alarm/ trip command. When a trip command actuates by the relay, it operates the master trip relay and subsequently trips the corresponding 132KV Grid incomer breaker. This results in clearing the fault and isolating the TG set from feeding the fault current. Also there is a provision for tripping of downstream 33KV Grid Hindalco(CPP in The power system of CGP of Hindalco Orissa system) Industries Ltd is connected to grid at 132 kV level through two number of Alco feeders from Burla Power House to their 132 kV main receiving substation. They have got grid islanding scheme in order to survive during grid disturbance. The disturbance in the grid is sensed by the Numerical Relay Micom P 341 through following four criteria and it opens the grid connecting breakers in their main receiving substation. IMFA (CPP in Orissa Islanding of 108 MW captive Power Plant system) is done by sensing frequency IFFCO (CPP in Orissa system) IBTPS Under frequency 48.0 Hz for 0 Sec Over Frequency 52.0 Hz for 1.0 Sec Under frequency 48.0 Hz Over Frequency 51.5 Hz Under frequency 48.0 Hz Rate of fall of frequency 0.8Hz/Sec Islanding of IBTPS is done using LADR (Load Accessed Directional Relay) technique. From every feeder, lock out tripping pulse is extended to LADR relay at BC panel. Continuously the dI/dt on the system due to the available of target loads and enerators are monitored by the relay and as per the 109 | P a g e ERLDC: POSOCO VAL (CPP in Orissa system) allowable load limit, this relay sends command for shedding. Different proposed islanding scheme:Islanding Scheme:Bus-1:- IB (1,3), AT1&2, Korba-2, Bhusan-(1,2), SPS Bus-2:- IB (2,4), Vedanta(1,2), Korba3,Katapali (1,2) Tarkera(1,2), Raigarh VAL is a captive power plant having generation of 9 x 135 MW and connected to the grid at 220 kV level via 220 kV VAL-Budhipadar D/C line. It has a facility to island itself from grid in case of any sever disturbance in grid Under frequency 48.5Hz Rate of fall of frequency 1.2 Hz/Sec 0.2 Sec delay. Under frequency 48.0 Hz 0.5 Sec delay. 110 | P a g e ERLDC: POSOCO Annexure :XIX Scheduling Formats ( Broad guidelines for the Formats) Form A: 1. DC Declaration by ISGS Thermal Time Block 1 2 3 . . . . . 96 1. 2. 3. 4. For Date: Station 1 Ex(PP) DC MW Station 2 Ex(PP) DC MW Station N Ex(PP)DC MW Technical Minimum Limit (MW) upto which station can be backed down without restoring to oil support Ramp up Rate MW/min or steps of load raising in avg MW Ramp Down Rate MW/min steps of load lowering in Avg MW Remarks : Unit under Maintenance/Overhauling/Other constarints Form A for ISGS Hydro C A P A C IT Y D E C L A R A T IO N (E X -B U S ) TO : S C E , E R L D C , K O L K ATA F R O M : S H IF T IN C H A R G E … … … … … . P O W E R S T A T IO IN D E C L A R E D C A P A C IT Y (E X - B U S ) O F … … ... P O W E R S T A T IO N M SG. NO. REV . N o. (A ) D E C L A R E D C A P A B IL IT Y (i) FO R D ATE D ATE O F IS S U E U N IT N o s . C a p a b ility a t 0 0 :0 0 H rs . o f n e x t d a y T IM E C A P A B IL IT Y E xB U S (M W ) T IM E (h h :m m ) 1 0 :0 0 T O 2 4 :0 0 2 0 :0 0 T O 2 4 :0 0 0 :0 0 T O 2 4 :0 0 3 (ii) U n its to g o u n d e r p la n n e d s h u td o w n day d u rin g n e xt N IL U n its lik e ly to re tu rn fro m p la n n e d s h u td o w n d u rin g (iii) n e xt d a y N IL T IM E D U R A T IO N (iv ) D e c la re d c a p a b ility b a s e d o n A -(i), (ii) & (v ) (iii) a b o v e FROM TO 0 0 :0 0 2 4 :0 0 :0 0 D E C L A R E D C A P A B IL IT Y O F E X B U S (M W ) SU G G ES TE D SC HED ULE F ro m (h h :m m ) 0 0 :0 0 To (h h :m m ) D C E x-b u s (M W ) 2 4 :0 0 E x- B us M W H N H P C D AT A F O R TH E D AT E (v i) D C (E ) (M W H ) ( v ii) ( v iii) ( ix ) (B ) ( i) ( ii) ( iii) _ ( iv ) REV NO MSG NO A c tu a l E x- b u s (A ) (M W H ) A d ju s te d p ro p o s e d to b e m a d e in s c h e d u le (A -E ) (M W H ) D e c la re d C a p a c ity ( T h e m a x im u m M W a v a ila b le fo r 3 h rs . o r m o re D u rin g p e a k in g ) MW M a xim u m a v a ila b le c a p a c ity o f E x- b u s u n d e r n o rm a l v o lta g e a n d fre q u e n c y MW % C a p a c ity In d e x [(v ii) / (v iii)*1 0 0 ] R E S E R V O IR L E V E L A N D IN F L O W S S T A T U S R e s e rv o ir le v e l (C u rre n t) m tr. A v e ra g e In flo w s o n p re v io u s d a y C um ecs C um ecs A n tic ip a te d a v e ra g e in flo w s fo r th e n e x t d a y O v e rlo a d C a p a c ity (v ) T im e d u ra tio n fo r w h ic h m a x im u m g e n e ra tio n c a n b e s u s ta in e d a t a s tre tc h (D e p e n d in g U p o n A n tic ip a te d in flo w ) ( v i) M in im u m 'm u s t ru n ' g e n e ra tio n (if a n y ) a lo n g w ith tim e p e rio d G e n e ra tio n (M W ) T IM E (h h :m m ) ( v ii) A n y o th e r c o n s tra in ts R E M A R K S :- S H IF T IN C H A R G E 111 | P a g e ERLDC: POSOCO Form B Statement of Entitlement for beneficiaries Constituent : Time Block Stn 1 For Date Ex(PP) DC Declared by ISGSs Stn 2 . . Stn N Stn 1 Ex(PP) Entitlement from Stn 2 . . Stn N 1 2 3 Time Block DC 96 Fig : in MW Form C: Statement of Requisitions from Beneficiaries Time Block Stn 1 For Date: Ex(PP) Requisitions from ISGSs Stn 2 . . Stn N Utility 1 Bilaterals & PXs Utility 2 . . Stn N 1 2 3 96 Figure in MW Form D : Format for Schedule of drawl by Constituents Stn 1 EX-PP Tm Pt. Blk Stn 2 EX-PP . EX-PP . EX-PP Stn N EX-PP LOSS For Date DEBIT FOR ISGS WHEEL BILAT TOTAL IEX TOT. PXI TOT. NET DRAWAL SCHD. 1 2 . . . . . . 96 112 | P a g e ERLDC: POSOCO Format for Schedule of Ex PP Generation TmPt. Blk For Date: AVL SCHD AVL SCHD AVL SCHD AVL SCHD AVL SCHD StN1 Stn1 Stn2 Stn2 . . . . StnN StnN (Ex-PP) (Ex-PP) . . . . ( Ex-PP) (Ex-PP) ( Ex-Bhu) (Ex-Bhu) UnReq UnReq SurplusStn1 SurplusStnN (Ex-PP) (Ex-PP) 1 2 96 113 | P a g e ERLDC: POSOCO Annexure: XX Meter Locations BHUTAN METER LOCATIONS IN C. SECTOR INTER-CONNECTED SYSTEM B’SARIFF (M) B BI-01,BI-02,BI-67 BODHGAYA (S) BI-15,BI-16 MADHEPURA (S) BI-05,BI-06 PURNEA (S) BI-03,BI-04,BI-51 KISHANGANJ (S) BI-20 KHAGUAL (S) BI-13,BI-14 ARAH (S) H BI-11 DUMRAO (S) BI-12 J’PUR (S) BI-19 BANKA (S) BI-58 NEW PUSAULI (S) BI-32 NEW PUSAULI (S) BI-33 C SABOUR (S) BI-59 L SABOUR (S) BI-07 K’GAON (S) BI-10 DEHRI (S) S P BI-62 MOHANIA(S) BI-49 KUDRA (S) BI-50 HAJIPUR (S) BI-52,BI-53 KANTI (S) BI-68,BI-69 KHAGAUL(S) BI-22 FATUAH (S) BI-23 SIPARA (S) BI-24,BI-25 DEHRI (S) BI-17,BI-18 LAKHISARAI (S) BI-30, BI-31 JAMUI (S) BI-26, BI-27 SULTANGANJ(S) BI-28,BI-29 B’ D E S H N E P A L BHERAMARA (S) T/C D/C T/C D/C (M) GAYA EP-13,EP-14 (M) PURNEA EP-83,EP-84 (M) PURNEA ER-62,ER-63,ER-48 (M) PURNEA ER-49 (M) ARAH EM-72,EM-73 (M) ARAH ER-09 (M) ARAH ER-10 (M) ARAH EP-27 (M) BANKA EP-52 (M) ARAH ER-94 (M) PUSAULI ER-14 (M) BANKA EP-53 (M) K’GAON D/C D/C D/C D/C D/C D/C D/C KH-13 (M) K’GAON KH-19 (M) PUSAULI ER 55 (M) PUSAULI ER-79 (M) PUSAULI ER-78 (M) MZ’PUR ER-56,ER-57 (M) MZ’PUR EM 31,EM-32 (M) PATNA EM-65 (M) PATNA EM-64 (M) PATNA EP-46,EP-47 (M) GAYA EP-15,EP-16 (M) LAKHISARAI EN-51,EN-52 (M) LAKHISARAI EN-89,EN-90 (M) BANKA EN-83,EN-84 (M) B’PORE EP-93 EP-95 DHALKEBAR EP-95 NE-84 NE-88 (C) (S) B’SARIFF ER-01,ER-02,ER-03 D/C GALEGPHU/ MOTUNGA MUZ’PUR ES-09 C. S E C T O R E R / I P P NE-83 (M) NE-87 BINAGURI (M) Q/C ER-37,ER-21, EN-06, EN-07 BIRPARA (M) ER-42,ER-43 (S) B’GAON NE-85,NE-86, NE-89, NE-90 D/C (S) SALAKATI NE-81,NE-82 N E R B’SHARIFF(E) (M) (S) SASARAM (N) ER 82, ER-83 BRBCL (M) EP-23,EP-24 PUSAULI ICT ER-94,ER-97 PUSAULI (M) ER-56 GAYA(M) EP-19,ES-26 MUZ’PUR (M) EM-25, EM-26 B’SF (M) EM-21, EM-22 PATNA (M) (S) SAHUPURI D/C NR-03 (S) VARANASI NR-19,NR-20 (S) GORKH’PUR D/C NR-11, NR-12 (S) BALIA D/C NR-13, NR-14 (S) BALIA EM-53, EM-57 EP-42, EP-43 BIHARSHARIFF(M) D/C EP-03, EP-04 BARH (M) D/C BH -18,EM-20 (S) VARANASI NR-22, NR-23 (S) GORKH’PUR NR-09, NR-10 (S) D’GARH EN-42,EN-41 CS-02, CS-03 EP-66,EP-68 STERLITE (M) ST-09,ST-14 RANCHI (M) EM-47,EM-48 N. RANCHI (M) EN-10 EN-99 GAJUWAKA (M) ER-84 ER-85 D/C D/C D/C D/C R NR-01, NR-02 NR-15,NR-16 SUNDERGAR (M) SUNDERGAR (M) N (S)RAIGARH CS-57,CS-62 (S)RAIGARH CS-58,CS-63 W R (S) SIPAT CS-60,CS-61 (S) D’GARH CS-01 CS-04 (S) GAJUWAKA DC-03 DC-04 S R 765 kV 400 KV 220 KV 132 KV (M) ---- MAIN (S) ---- STANDBY 114 | P a g e ERLDC: POSOCO METER LOCATIONS IN C. SECTOR INTER-CONNECTED SYSTEM TARKERA (S) G R I D C O D/C (M) ROURKELA OR-01,OR-02 KATAPALI(M) ER-23,ER-24 (S) BOLANGIR OR-17 SADEIPALI(M) ES-22 (S) BOLANGIR OR-18 M’MUNDALI (M) OR-08,OR-14 M’MUNDALI (S) D/C D/C ES-23 (S) ANGUL EP-71,EN-32 (M) TALCHER TL-11,TL-12 (S) BARIPADA OR-09,OR-10 M’SHAL (M) OR-20 RENGALI (S) OR-11 RENGALI(S) D/C OR-03,OR-04 J’NAGAR(S) D/C (M) EM-88 TALCHER (M) TL-10 RENGALI ER-30,ER-31 (M)JEYPORE ER-34,ER-35 (M)I’VATI OR-05,OR-06 I’VATI(S) OR-13 BALASORE (S) D/C ER-86 (M) BARIPADA OR-60,OR-63 BARIPADA (S) ER-20,EM-58 (M) BARIPADA OR-61 ER-98 (M) BARIPADA R’RANGPUR(S) (M) ER-99 TALCHER (M) TL-09 TALCHER OR-62 TTPS (S) OR-12 M’MUNDALI (S) TL-09 (S) BARIPADA OR-07 DUBURI (M) EM-89 OR-22 S I K K I M (S) RANGIT RAVANGLA(M) RG-07 SM-01 (S)SILIGURI MELLI (M) ER-57 SM-02 (M)RANGIT SAGBARI EM-03,EM-05 GANGTOK ICT R’CHANDRAPUR (M) JS -01,JS-02 D/C D/C DUMKA (S) JS -09,JS-10 J S E B RG-10 D/C CHAIBASA (S) JS -11,JS-12 LALMATIA (S) D/C (S)JAM’PUR ER-17,ER-18 (M) MAITHON EN -87,EN-88 (M)CHAIBASA EN -97,EN-98 (M) K’GAON KH-14 (M) FARAKKA JS-03 LALMATIA (S) JS-04 HATIA (S) JS-06,JS-07 CHANDIL (S) EM-03,EM-05 D/C FK-14 (M) RANCHI EN-96,EM-44 (M) RANCHI JS-05 EM-45 400 KV 220 KV 132 KV (M) ---- MAIN (S) ----- STANDBY C. S E C T O R E R / I P P DALKHOLA (M) EP-55,EM-96 BIRPARA (M) ER-44,EM-75 SILIGURI (M) ER-52,ER-53 S’GRAM (M) EP-72,EP-73 B’PORE (S) EN-68,EN-69 FARAKKA (S) FK-16 DURGAPUR (S) EM-91,EM-20 MALDA(M) ER-58,ER-59 S’GRAM(M) EN-16,EN-17 DURGAPUR (S) ER-68,ER-08 S’GRAM (S) EM-74 S’GRAM (M) D/C D/C D/C D/C (M) S’DIGHI D/C WB-25,WB-27 (M) S’DIGHI WB-12 (M) S’DIGHI WB-14,WB-21 (S) MALDA D/C WB-05,WB-06 HALDIA D/C D/C D/C EM-18,EM-19 S’GRAM (S) EM-17 SILIGURI(M) W B (M) B’NAGAR WB-19,WB-20 (M) S’DIGHI WB-13 S’GRAM (M) JEERAT WB-09 (S) K’SEONG S E WB-58 ER-54 RANGIT(M) RG-04 B’GURI (M) (S) DALKHOLA WB-18,WB-16 (S) BIRPARA WB-01,WB-02 (S) NBU WB-03,WB-04 EM BYPASS (S) K’SEONG D/C ER-19,ER-45 CHAIBASA (S) ES-30,ES-29 RANGIT (M) WB-57 J’GURI (M)KOLAGHAT/K’PUR B WB-30,WB-29 (S) R’MAM WB-11 (M) JEERAT WB-08 (M) KHARAGPUR RG-06 B’PORE (S) EP-89 BARIPADA (S) ER-27 S’GRAM (M) WB-17 N.TOWN, BANTALA EN-61,EN-62 GAYA (S) D/C EN-48,EN-70 (M) KODERMA DV-40,DV-42 B’SHARIFF(S) D/C EP-25,EP-26 MAITHON (S) T/C (M) KODERMA DV-20,DV-21 (M) MEJIA EM-97,EM-98,ER-15 MAITHON (M) D/C DV-04,DV-24,DV-25 (S) DHANBAD ER-11,ER-12 MAITHON (M) D/C DV-18,DV-19 (S) K’SWARI EM-80,EM-81 JMS’PUR (S) D/C DV-08,DV-09 (M) DSTPS EP-20,EP-21 DURGAPUR (M) EM-05,ER-06 BARIPADA (S) EM-86 JAMSHEDPUR (S) EM-86 MAITHON (S) DV-10,DV-06 (S) PARULIA DV-01 V C (M) TISCO DV-34 (M) TISCO DV-35 EP-22 (M) RTPS DV-36 RANCHI (S) (M) RTPS EM-41 D DV-38 115 | P a g e ERLDC: POSOCO METER LOCATIONS IN BSPHCL INTER-CONNECTED SYSTEM D/C (M) GAYA EP-13,EP-14 T/C (S) B’SARIFF BODHGAYA (S ) BI-15,BI-16 B’SARIFF (M) BI-01,BI-02,BI-67 ER-01, ER-02,ER-03 NEW PUSAULI (S) (M)ARAH ER-94 BI-32 NEW PUSAULI (S) TENUGHAT J S E (S) (M) JS 62 (S) LALMATIA (M) KAHALGAON JS 63 JAPLA BI-09 (S) (M) SONENAGAR (M) SULTANGANJ W B D V DEOGARH (S) JS 65 KISHANGANJ BI-21 WB 52 (M) BARHI (S) DV 51 (M) NR 07 BI 66 CHANDAULI (S) (M) NR 06 SAHUPURI BI 56 H KARMNASA BI 63 (S) (M) NR 05 400 KV 220 KV 132 KV (M) ---- MAIN (S) ---- STAND BY D/C LAKHISARAI (S) (M) LAKHISARAI EN-51,EN-52 BI-30,BI-31 MADHEPURA(S) BI-05,BI-06 PURNEA (S) BI-03,BI-04,BI-51 KISHANGANJ(S) BI-20 D/C (M) PURNEA T/C (M) PURNEA EP-83,EP-84 ER-62,ER-63,ER-48 (M) PURNEA ER 49 ARAH (S) BI 11 DUMRAO (S) BI 12 KHAGAUL (S) D/C JAGDPUR (S) ARAH EP 27 (M) BANKA EP 52 EP 53 (M) K’GAON KH 13 (M) K’GAON C KARMNASA BI 64 L D/C (M) LAKHISARAI EN-89, EN-90 (S) MUZ’PUR EM-31,EM-32 KHAGAUL (S) BI-22 FATUAH (S) (S) (M) MUZ’PUR EP-56,EP-57 D/C BI-26, BI-27 KANTI (M) BI-68,BI-69 BI-23 SIPARA S E C T O R KH 19 PUSAULI ER 79 (M) PUSAULI ER-55 (M) PUSAULI ER-78 BI-50 JAMUI (S) ARAH ER 09 (M) ARAH ER 10 (M) ARAH EM-72,EM-73 (M) BI-19 BANKA (S) BI 58 SABOUR(S) BI 59 SABOUR (S) BI 07 K’GAON (S) BI-10 MOHANIA BI 49 DEHRI (S) HAJIPUR (S) BI-52,BI-53 C E N T R A L (M) BI-62 KUDRA (S) (M) SONENAGAR RIHAND (S) N R BI 48 RAJGIR BI 55 BSF C P NALANDA (M) ER-14 BI-33 BI-13,BI-14 BI 61 DALKHOLA BARHI S BI 60 JS 64 B B’SF BI 57 B (M)PUSAULI (M) PATNA EM 65 (M) PATNA D/C EP-46,EP-47 BI-24,BI-25 SULTANGANJ (S) BI-24,BI-25 DEHRI (S) BI-17,BI-18 EM 64 (M) PATNA D/C (M) BANKA D/C (M) GAYA BI-24,BI-25 EP-15,EP-16 116 | P a g e ERLDC: POSOCO METER LOCATIONS IN JUVNL INTER-CONNECTED SYSTEM B’SF B S E B WB SEB D V C G R I D C O N R (M) TENUGHAT (S) BI 57 JS 62 K’GAON (S) BI 60 SULTANGANJ (S) BI 61 WB 53 JS 63 (M) JAPLA JS 64 (M) DEOGARH JS 65 (M) CHANDIL (M)JAMTARA DV 56 PATRATU DV 53 JS 66 (M) PATRATU JS 54 JS-53 JODA (S) OR 52 RIHAND (S) NR 08 R’CHANDRAPUR (M) JS 02 DUMKA (S) JS 09,JS-10 U V JS 40 JODA (S) OR 53 GOELKERA (S) ER 17 (S) JAM’PUR ER 18 D/C (M) MAITHON EN-87EN 88 CHAIBASA (S) D/C (M) CHAIBASA(S) JS-11,JS-12 EN-97,EN-98 LALMATIA (S) (M) JS 57 MAITHON(S) MANIQUE DV 55 (S) JAM’PUR JS 01 (M) LALMATIA BI-09 SONENAGAR (S) SANTALDIH (S) J R’CHANDRAPUR (M) K’GAON KH 14 JS 03 LALMATIA (S) (M) FARAKKA JS 04 FK 14 (M) CHANDIL C E N T R A L S E C T O R JS 56 (M) RAMCHANDRAPUR JS 51 (M) ROURKELA OR-51 N (M) KENDPOSI D/C JS 05 (M) GARWA L (M) RANCHI EN-96,EM 44 CHANDIL (S) JS 52 JS 58 HATIA (S) JS-06,JS 07 (M) RANCHI EM 45 400 KV 220 KV 132 KV (M) ---- Main (S) ----- Stand by 117 | P a g e ERLDC: POSOCO METER LOCATIONS IN DVC INTER-CONNECTED SYSTEM KODERMA (M) B S E B (S) MAITHON EP-50,EP-51 DV-40,DV-42 RAJGIR (S) (M) BARHI RTPS (M) DV 51 BI 55 (S) MAITHON EP 22 DV-36 NALANDA(S) BI 56 (S) BARIPADA TISCO (M) DV-34 EM 86 (S) JAMSHEDPUR DV 35 D W B S KOLAGHAT (S) WB 54 (S) MAITHON DV-24,DV-25,DV-05 EM 97,EM-98,EM-76 (M) KOLAGHAT DV 61 BIDHANNAGAR WB 51 EP 44 T/C MEJIA (M) (S) (M) WARIA DV 60 V PARULIA DV 01 (S) (M) Durgapur D/C ER 05 ER 06 DV 64 E C B (S) JAMSHEDPUR MEJIA (M) EM 76 (S) RANCHI DV 05 RTPS (M) EM 41 DV 38 DHANBAD (S) (M) MAITHON ER 11,ER-12 DV-18,DV-19 KALYANESWARI(S) DV 08,DV-09 G R I D C O J S E B (M) MAITHON EM 80,EM-81 KODERMA (M) JINDAL (S) (M) JAMSHEDPUR DV 57 OR 54 (S) GAYA EN-48,EN-70 DV-40,DV-42 KODERMA (S) (M) BSF DSTPS(ANDAL)_ (M) (S) (M) PATRATU DV 53 JS 40 CHANDIL (S) JS 56 JAMTARA JS 66 (S) (S) JAMSHEDPUR DV 06 EP 20 DV 10 EP 21 RAGHUNATHPUR(M) DV 36 DV 38 S E C T O R EP 25,EP-26 DV 20,DV-21 PATRATU JS 54 C E N T R A L (S) MAITHON EP 22 EP 78 (S) RANCHI (M) MANIQUE DV 55 (M) MAITHON DV 56 400 KV 220 KV 132 KV (M) ---- Main (S) ----- Stand by 118 | P a g e ERLDC: POSOCO METER LOCATIONS IN GRIDCO INTER-CONNECTED SYSTEM RAMCHANDRAPUR J S E B D V C (S) (M) JODA JS 51 OR 53 KENDPOSI (S) (M) JODA OR 52 JS 52 GOELKERA (S) (M) ROURKELA JS 53 OR 51 JAMSHEDPUR(S) (M) JINDAL DV 57 G R I OR 54 D/C (M) ROURKELA TARKERA (S) ER-23,ER-24 OR-01,OR-02 (M) BOLANGIR KATAPALLI(S) OR 17 ES 22 (M) BOLANGIR SADEIPALLI(S) ES 23 OR 18 (S) ANGUL MERAMUNDALI (M) D/C OR-14,OR-08 EP-71,EN-32 MERAMUNDALI(S) OR-09,OR-10 (S) BARIPADA OR-20 DUBURI (M) EM-88 (S) BARIPADA OR-22 EM-89 MERAMUNDALI(M) OR-07 RAIGARH (S) CS 56 KORBA (M) BUDHIPADAR OR 56 (S) (M)BUDHIPADAR (S) (M)BUDHIPADAR OR 57 CS 54 S R (S) TSTPP TL-18 D C R (M) TSTPP TL-11,TL-12 MENDASAL (M) RENGALI PH OR-11 W D/C KORBA CS 55 U. SILERU (M) OR 59 (S) BALIMELA DC-05 400 KV 220 KV 132 KV (M) ---- MAIN (S) ---- STAND BY OR 15 O (S) TALCHER TPS (S) OR-12 RENGALI (S) OR-03,OR-04 (M) TSTPP TL-10 (M) TSTPP TL-09 S E C T O R (M) RENGALI ER-30,ER-31 JAYANAGAR (S) OR-05,OR-06 (M) JEYPORE INDRAVATI (S) OR-13 (M) INDRAVATI BALASORE(S) OR-60,OR-63 (M)BARIPADA BARIPADA (S) OR 61 R’RANGPUR(S) OR 62 (M)BARIPADA (S) (M)BARIPADA BALASORE C E N T R A L ER-34,ER-35 ER-86 ER-20,EM-58 ER 98 (M)BARIPADA ER 99 EM 66 119 | P a g e ERLDC: POSOCO METER LOCATIONS IN WBSETCL INTER-CONNECTED SYSTEM (M) DALKHOLA DALKHOLA(S) WB-16,WB-18 S I K K I M J S E B B S E B MELLI (S) SM 51 V C 66 kv W WB 59 B BIRPARA (S) WB-01,WB-02 (M) BIRPARA ER-44,EM-75 (M) S’GRAM EN-16,EN-17 (M) NJP HALDIA NBU(S) WB-04,WB-03 EM BY PASS(S) ER-52,ER-53 (M) S’ GRAM EP-72,EP-73 S’ GRAM EN 62 S’ GRAM EN 61 (S) FARAKKA NEW TOWN BANTALA CHANDIL(S) JS 57 (M) SANTALDIH WB 53 S KISHANGANJ(S) BI 21 (M) DALKHOLA B KOLAGHAT WARIA(S) (M) BIDHANNAGAR DV 64 WARIA (S) DV 60 WB 54 (M) BIDHANNAGAR WB 51 FK 16 (M) MALDA ER-58,ER-59 (S) B’RAMPORE ER-68,ER-69 SAGARDIGHI (M) WB-25,WB-27 B’NAGAR (S) (M) DURGAPUR ER 07 WB-07 WB 52 DV 61 SAGARDIGHI (M) WB-12 MALDA (S) WB-05,WB-06 E KOLAGHAT(M) D (M) KALINGPONG EM-96,EP-55 EP 89 (S) BARIPADA KHARAGPUR(M) WB 17 ER 27 RAMAM (M) WB-11 NEW JALPAIGURI(S) (S) RANGIT RG 06 (M)BINAGURI ER-45,ER 19 KURSEONG(M) WB-57 KURSEONG (M) WB-58 JEERAT (M) WB-09 S’GRAM(S) D/C (S) RANGIT RG 04 (S) SILIGURI ER 54 (S) SUBHASGRAM EM 17 (M) SUBHASGRAM EM 18,EM-19 (S) CHAIBASA ES 29 WB 29 KOLAGHAT(M) WB 30 SAGARDIGHI(M) WB-13 SAGARDIGHI(S) WB-14,WB-21 MAIN STAND BY S E C T O R (S) B’RAMPORE JEERAT (M) WB-08 KHARAGPUR(M) 400 KV 220 KV 132 KV (M) ----(S) ----- C E N T R A L BIDHANAGAR(S) WB-19,WB-20 (S) (S) CHAIBASA ES 30 SUBHASGRAM EM 74 (M)DURGAPUR EM-91,EM-20 (M) DURGAPUR ER-08,ER-68 120 | P a g e ERLDC: POSOCO METER LOCATIONS IN SIKKIM INTER-CONNECTED SYSTEM C H E P S CHUZACHEN MELLI CZ-05 SM 03 I 66 kV SM 01 RG 07 RAVANGLA (M) (S) RANGIT GYALSHING SAGBARI SM 07 W B S E B K KALIMPONG(S) WB-59 66 kv (M) MELLI I SM 05 (S) MELLI (M) RG 10 (S) NJP SM 02 ER 57 EM 04 EM 06 M (M) RANGIT 132 kV SM 04 SM-51 K 400 KV 220 KV 132 KV (M) ---- MAIN (S) ----- STAND BY MELLI SM 06 C E N T R A L EM 03 132/66 S E C T O R EM 05 GANGTOK 121 | P a g e ERLDC: POSOCO METER LOCATIONS IN CENTRAL SECTOR TRANSMISSION SYSTEM PART-I MELLI GYALSHING CU06 CU 07 CU05 RG 01 RG02 RG03 RANGIT CHUKHA CU 08 TALA SAGBARI SINGHIGAON TH-01 TH-02 TH-04 RG-10 CU 03 CU 01 CU02 RG 04 RG-11 RG06 RG 07 RAMAM EM02 RG08 EM01 EM 03 EM 04 RAVANGLA TS01 TS01 TS03 TEESTA MALBASE BIRPARA EM-67 ER 41 ER 47 ER 39 ER 40 ER 22 EM-11 EM-12 EM-13 EM-14 K’ SEONG ER76 ER-57 KISHENGANJ ES-16 ES-17 ER-50 ER-51 ER 53 ER52 ES-18 ES-19 ER-46 NJP (WBSEB) GORAKHPUR BONGAIGAON BINAGURI ER-47 SILIGURI ER-54 NE 85 NE 86 ER 23 BINAGURI JL-03 JLHEP SALAKATI ER 42 ER 43 ER 37 EM 7 EM 8 EM 10 EM 9 EM-68 EN-85 EN-86 JL-05 EM 75 ER 46 MELLI TS-05 TS-06 N. MELLI BT33 BT40 BIR(W) ER 44 CZ-02 CZ-01 CZ-07 SM03 RANGPO BT34 BT35 EM 06 GATI CZ-05 BT36 BT 39 EM 05 CZ-03 66 kV BT38 BT37 GANGTOK ES-11 ES-12 NBU EM25 EM26 MUZAFFARPUR EM23 EM27 EM24 EM28 PURNEA EM29 EM30 Madhepura ER 65 ER 63 KANTI(B) HAJIPUR Dhalkebar(Nepal) EP-92 ER-88 ER 09 / 4153A EP-85 EP-86 ES-09 ER 62 411A ER 64 ER 49 DALKHOLA PUR(B) BALIA K’GANJ EM-96 EP-55 WB-16 WB-18 WB-52 SASARAM (N) ALLAHABAD MALDA(W) VARANASI ER 78 KARMANASA EP-23 EP-24 ER 56 PUSAULI NEW BANKA ER 10 J’Pur ARRAH EP-74 EP-75 BI 13 BI 14 KHAGAUL DUMRAO Sipara L’SARAI EN-47 EN-27 EN-89 EN-90 EN-26 EN-46 EN-51 EN-52 BANKA KH-31 KH-32 KH 35 KH 36 EM 56 EM 55 EM 57 ER 88 EM 53 KG 03 KG 02 KG 01 ER 01 VARANASI B’SHARIFF(BSEB) LAKHISARAI KH-11 KH-12 KH 01 KH 02 KH 03 KH04 EM 54 TENUGHAT KAHALGAON KH 07 KH 08 KH 15 KH 14 GORAKHPUR(NR) BH-18,BH-20 BH-04 BH-05 BH-03 BH-02 MAITHON KH 17 KH 18 KH 05 KH 06 SABOUR BH-06 BH-07 BH-08 BH-10 KAHALGAON(B) KH 16 KH 19 KH 13 PATNA BALIA NR 02 MALDA BIHARSHARIFF ER 02 KH 10 KH 09 FATUA ER 59 ER 58 ER 60 EP-25 EP-26 EP-04 JAMUI ER 03 KODERMA (DVC) ER 61 EM-21 EM-22 EN-01 EN-02 ER-89 ER-90 ARAH ER 94 ER 9 GAYA ER-82 ER-83 N’Nagar ER 14 ER 13 ER 55 DEHRI EP-19 ES-26 SASARAM (E) ER 79 SAHUPURI NR 01 DALKHOLA(WB) F’PUR KUDRA ES-20 ES-21 LALMATIA BS 09 FARAKKA BARH 122 | P a g e ERLDC: POSOCO PART-II LALMATIA(JSEB) KAHALGAON HATIA MPL RB CHANDIL MALDA FK14 SIPAT EN-96 EM 44 EM 45 RANCHI EM 46 EN-03 EN-05 EN-08 EN-09 FK 01 FK 02 ER16 TIE TRA FK 06 FK 07 FK 18 FK-30 FK 05 B’ PORE ER 07 ER 68 EP-05 EP-06 ER70 ER69 FK 03 FK 04 FARAKKA FK 16 SAGARDIGHI EN-87 EM-85 EN-88 EM-84 MAITHON EM 97 EM-98 FK15 DUMKA EM 41 RTPS(DVC) EM-82 EM-83 FK 13 FK 10 FK 11 K’GAON EM 42 FK17 FK 08 FK 09 EM 43 DURGAPUR ER 66 ER 11 ER 12 EM 80 EM 81 BHERAMARA BANGLADESH B’NAGAR(WB) ER 67 MEJIA DHANBAD (DVC) NEW RANCHI K’SWARI (DVC) KODERMA (DVC) DSTPP (ANDAL) ER 06 ER 05 WB-14 PARULIA WB 08 EP-20 EP-21 EN-10 EN-99 JEERAT JAMSHEDPUR D’jaygarh(WR) EN-56 EN-56 ER 08 ER18 HALDIA ER 17 AP-03 AP-04 BS 05 BS 06 CHAIBASA APNRL AP-02 AP-01 BANTALA EM 17 KOLAGHAT RC PUR KHARAGPUR ER 71 ER 72 ROURKELA DUBURI (GR) S’GRAM(W) EM ER-80 ER 23 BYPASS ER 27 BARIPADA ER 81 EM 93 ER 24 EM 16 EM 18 SUBHASGRAM CHBA ER 25 WB 09 EM 15 WB 10/476A ER 26 SAGARDIGHI MEDHASHAL(GR) EM 69 TATA TISCO S’GARH NEW TOWN BALASORE(GR) TARKERA RAIGARH RENGALI(G) ST 09 ST 14 STERLITE ER 30 ER 31 ER 73 ER 74 BARIPADA(GR) RAIRANGPUR(GR KEONJHAR IBEUL ST 13 ST 10 RAIGARH(WR) STG-II TL05 TL06 TL07 TL 02 TL 13 TL 01 TL 11 TL 12 TL 10 TTPS TL 09 TALCHER STPP JEYPORE ER 36 ER 85 ER75 ER 84 400 KV 220 KV 132 KV MERAMUNDALI OR 08 OR 14 OR-07 ER77 ER 34 TL 04 ER 86 INDRAVATI PG RENGALI PS TL-14 TL-15 TL08 TL 28 TL 03 INDRAVATI PG BALASORE(GR) RENGALI ER29 469A D’jaygarh(WR) ER 28 ER 35 GAJUWAKA(S) DC-3 SR JD-02 DC-4 GAJUWAKA(E) SR JINDAL JD-05,JD-03 GM-09,GM-11 JEYNAGAR KATAPALLI SADEIPALLI BOLANGIR ANGUL EN-78 EM-95 GM-10 S’GARH 123 | P a g e ERLDC: POSOCO Annexure :XXI Grid Maps 124 | P a g e ERLDC: POSOCO 125 | P a g e ERLDC: POSOCO 126 | P a g e ERLDC: POSOCO 127 | P a g e ERLDC: POSOCO 128 | P a g e ERLDC: POSOCO 129 | P a g e ERLDC: POSOCO 130 | P a g e ERLDC: POSOCO 131 | P a g e ERLDC: POSOCO 132 | P a g e ERLDC: POSOCO Annexure :XXII Message for violation of TTC/Flow Gate/System Constraint. Eastern Regional Load Despatch Centre POWER SYSTEM OPERATION CORPORATION 14 Golf Club Road, Tollygunge, Kolkata 700033 Tel.: 033-24235435, FAX: 033-24235809 web:www.erldc.org FAX MESSAGE Reference: ERLDC/OPRN/SYSCON/_____ FROM: SCE , ERLDC, KOLKATA TO: SCE : (concerned LDC / ISGS) Date :_________ TOO :______ Copy To: Sub: Immediate action for measures detailed below on violation of TTC/Flow Gate/System constraint. At present the Deviation of your control area/ISGS is as follows: Regional entity / Schedule Actual Overdrawal/Overgeneration(+)/ Region Underdrawal/Undergeneration(-) The following TTC limits are getting violated at present: The following flow gate alarms have come: Name of Flow Gate Name Actual The following lines are presently critically overloaded: Name of the line Limit Power Flow (MW) <Action to be taken> Remark: SHIFT CHARGE ENGINEER ERLDC/KOLKATA 133 | P a g e ERLDC: POSOCO Annexure :XXIII :- Format for Applying and Withdrawing congestion 134 | P a g e ERLDC: POSOCO 135 | P a g e ERLDC: POSOCO 136 | P a g e ERLDC: POSOCO Document Management Information: Document Name Document ID Rev No. Classification Operating Procedures for Eastern Region ERLDC/OP/2015-16/Rev 11 11 Date 31st July 2015 Public Document Modification History Revision No 00 01 Date of Revision 31.10.2008 08.12.2008 Remarks 02 31.10.09 03 29.10.10 04 31.12.10 1) All the annexures updated. 05 31.03.2011 1) All the annexures updated. 06 20.05.2011 1) All the annexures updated. 07 29.05.2012 08 28.06.2013 09 26.07.2013 10 31.7.2014 11 31.07.2015 1) Chapter 6 flow gates are reviewed. 2) Chapter 7 scheduling and despatched procedure revised. 3) All the annexures are updated 1) Chapter 2 Frequency control is reviewed 2) Chapter 3 Voltage control is reviewed 3) Chapter 5 Switching coordination is introduced 4) Chapter 7 flow gate are reviewed 5) Chapter on Water supply system at ERLDC is deleted, 6) All annexures are revised 1)Chapter 4 outage planning is reviewed 2) Annexure- I, II, III, VII & XV is updated as per information received from WBSLDC 1) Frequency Band Updated 2) Annexures Updated 3) Flow gate reviewed 1) Annexures Updated Annexure XXIV ( schedule of Regional Transmission Assets) added at Page 118120 1) Chapters 1 to 7 and 9 revised in line with the draft IEGC (under consideration by CERC for implementation w.e.f 01.01.2010). All annexures updated & Annex- XXV (Message format for violation of TTC) added 2) Chapter 10 for Water Supply system included 1) Chapters 1 ,2,3 and 6 revised in line with new IEGC (implemented from 03.05.2010) 2) Chapters 7 and 8 are revised. 137 | P a g e ERLDC: POSOCO 2) Flow gate reviewed 12 04.07.2016 1. Chapter 2,3,4,5,6,7,8,9,10 Updated 2. Annexures Updated 138 | P a g e