Hybrid Power Plants: Securing Returns in off-grid Energy Investments Siemens Hybrid Power Solutions Unrestricted © Siemens AG 2016 All rights reserved. Decentralized Energy Solutions Agenda Off-grid Energy Investments: Definitions and Market Success factors in off-grid Energy Projects Conclusions Unrestricted © Siemens AG 2016 All rights reserved. Page 2 Siemens Hybrid Power Solutions Boes EM DES SGS Off-grid Investments: Definitions and Markets What is an off-grid energy investment? What markets of off-grid energy investments exist? For this session: energy is defined as electrical power Off-grid power systems are found as: Investment into: • Projects with no access to an integrated large scale power grid • Single or limited number of power generation plants • Isolated microgrid or minigrid power distribution • Special cases: systems with weak grid connection • Utility projects for remote islanded grids • Utility projects for community grid • Utility projects for geographical islands • Industry projects in different sectors: e.g. mining, oil processing, etc. © 2016 - Mathias Becker For this session: off-grid energy investment is defined as a hybrid power plant with integration of renewable sources Unrestricted © Siemens AG 2016 All rights reserved. Page 3 Siemens Hybrid Power Solutions Boes EM DES SGS Market development for off-grid energy investments Challenges in the off-grid investment market Changes in Technology Generation Costs Fuel costs Weak / inexistent grids Emission restrictions Hybrid Power Plants Renewable Systems Fuel today Logistic costs time Unrestricted © Siemens AG 2016 All rights reserved. Page 4 Siemens Hybrid Power Solutions Boes EM DES SGS Essence in Off-grid Energy Investments for all involved Parties: Equalized Risk Distribution Utility Investor Know-how End User / Beneficiary IPP Technology Finance Owner Full Ownership Service Partial Ownership Licensing Leasing Model Unrestricted © Siemens AG 2016 All rights reserved. Page 5 Siemens Hybrid Power Solutions IPP = Independent Power Producer Boes EM DES SGS 1 Project Development 2 Technology 3 Financing 4 Execution 5 Social Economical Setting Successful off-grid Investment Success factors in Off-grid Energy Investments Unrestricted © Siemens AG 2016 All rights reserved. Page 6 Siemens Hybrid Power Solutions Boes EM DES SGS Success Factor 1: Project Development Forming a sound project setup with fully committed parties Important elements of Project Development are (selection): • Offtake • Design according to demand • Location • Renewable resource exploration & definition • Interconnection to distribution of the Microgrid • Supply of fuel and other relevant consumables, incl. fresh water • Community interaction and licensing • Technology supply • Logistics • Labor & training In Off-grid Investments everything is about reliability of supply there is no grid to safeguard operation! Unrestricted © Siemens AG 2016 All rights reserved. Page 7 Siemens Hybrid Power Solutions Boes EM DES SGS Success Factor 2: Technology Technology Risk Minimization Selection of knowledgeable & experienced technology provider: • Knowledge in power system design • Knowledge in plant control design • Knowledge in special requirements of hybrid power plants • Experienced in execution of complex projects • Experienced in operation of complex projects • Financially strong to accompany the owner reliably throughout the lifetime of the project • etc. Uniqueness of each Off-grid investment needs special attention and tailor made design! Unrestricted © Siemens AG 2016 All rights reserved. Page 8 Siemens Hybrid Power Solutions Boes EM DES SGS What’s different in a Hybrid Plant? Wind Plant Industrial Load PV plant Storage Residential Load Control Center Diesel generators MW Load 00:00 06:00 12:00 18:00 24:00 Time Unrestricted © Siemens AG 2016 All rights reserved. Page 9 Siemens Hybrid Power Solutions Boes EM DES SGS What’s different in a Hybrid Plant? Wind Plant Industrial Load PV plant Storage Residential Load Control Center MW Diesel generators Diesel Gensets Load PV Power 00:00 06:00 12:00 18:00 24:00 Time Unrestricted © Siemens AG 2016 All rights reserved. Page 10 Siemens Hybrid Power Solutions Boes EM DES SGS What’s different in a Hybrid Plant? Wind Plant Industrial Load PV plant Storage Residential Load Control Center MW Diesel generators Diesel Gensets Load PV Power 00:00 06:00 12:00 18:00 24:00 Time Unrestricted © Siemens AG 2016 All rights reserved. Page 11 Siemens Hybrid Power Solutions Boes EM DES SGS Technical challenges within a Hybrid Plant project MON Hours Minutes Seconds Milliseconds Unrestricted © Siemens AG 2016 All rights reserved. Page 12 Siemens Hybrid Power Solutions Boes EM DES SGS Success Factor 3: Financing New Challenges in Financing New market with much higher risk adversity from financing institutions than in established power markets, e.g. thermal plants: • Little knowledge in financing market about Off-grid Investments • Small size of Off-grid Investments • Small number of implemented projects • Many projects realized under a pilot investment character, with support from government of development funds, hence only little financing market feedback • Perception of technology as embryonic in the financing market Gain trust in the financing community through transparency by early involvement! Unrestricted © Siemens AG 2016 All rights reserved. Page 13 Siemens Hybrid Power Solutions Boes EM DES SGS Success Factor 4: Implementation Mastering all Phases of Project Lifetime Focused interpretation: Implementation is the execution phase of the construction and erection of an Off-grid Investment Important aspects to consider in Off-grid Investments: • Complex projects with high level of interaction and interfaces • Single point of contact on any project implementation aspect • Guarantees encompassing the overall plant and its function and not only components, leaving the implementation risk with the owner • Single responsibility to meet the requirements of all components and the overall integrated plant • Single responsibility to meet the implementation schedule • Comprehensive support beyond construction phase Best suited approach for Off-grid Investments: Turnkey implementation! Unrestricted © Siemens AG 2016 All rights reserved. Page 14 Siemens Hybrid Power Solutions Boes EM DES SGS Success Factor 5: Social Economical Setting Sustainable Embedding of the Project • Support the government to introduce high penetration hybrid power technology: adaption of mindset • Support to the government to define suitable technical, commercial and legal framework • Open and transparent communication with affected or benefitted community • Support of local capacity building • Usage of labor of the region to implement the project • Usage of local staff for operation • Accompany the customer in commercial operation: careful and supportive aftersales services © 2016 - Mathias Becker A comprehensive project approach beyond pure business is needed! Unrestricted © Siemens AG 2016 All rights reserved. Page 15 Siemens Hybrid Power Solutions Boes EM DES SGS Conclusions: To secure returns in Off-grid Investments it is mandatory … 1. … to care for a sound and strong project setup 2. … to have a strong involvement with local Community and the Beneficiaries of the project 3. … to contract with a Turnkey Supplier with experience in Off-grid Investments / Hybrid Plants Unrestricted © Siemens AG 2016 All rights reserved. Page 16 Siemens Hybrid Power Solutions Boes EM DES SGS Published by and Copyright 2016: Siemens AG Energy Management Distributed Energy Systems Freyeslebenstrasse 1 91058 Erlangen, Germany Tel.: + 49 9131 / 18 – 83 3 56 To obtain further information, please contact: andreas.boes@siemens.com This document contains forward-looking statements and information – that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens’ control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated. Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their respective owners. Subject to change without prior notice. The information in this document contains general descriptions of the technical options available which do not always have to be present in individual cases. The required features should therefore be specified in each individual case at the time of closing the contract. Smart Generation Solutions EM DES AL:N ECCN:N Unrestricted © Siemens AG 2016 All rights reserved. Page 17 Siemens Hybrid Power Solutions Boes EM DES SGS