Hartford Civic Arena Roof Collapse Group 16 Overview: • Introduction. • Structural design. • Causes of collapse. • Conclusions. • Sources. Introduction. • Collapse occurred 18th of January 1978 • Large snowstorm. • The roof collapsed while Arena was not in use. • No fatalities or injuries. Structural design: • Fraoli, Blum & Yesselman, Engineers were employed to design arena. • The engineers used an innovative design. • It was based on space frame design. • Spanning 91.44m x 109.72m. • 25.29m above floor level. • The predicted deflection = 330.2mm at midpoint and 150mm at edges. Structural design: • Differed from standard space frame design: • Cross-shaped built up sections used. • Top horizontal bars intersected at different points to diagonal bars rather than at the same point. • Short posts on the nodes supported the roofing panels. • Four columns were 13.71m inside roof edges. • The space frame was not pre-chambered. Structural design: Diagrams; Causes of collapse: Three contributary factors • Structural design. • Construction. • Project Management. Structural design: • Cross-shaped members. • Intersection of top horizontal and diagonal bars, not connected at the same point. • Inaccurate computer analysis, torsional buckling not considered. • Top layer’s interior and exterior compression members overloaded. • Very little redundancy. • No independent recheck of structural design. Project management; • No overall project manager responsible for the entire project. • No qualified structural engineer employed to perform inspections of structure during construction. Overall, no hierarchy of responsibility • Construction: • Connections were not fabricated or assembled to design specifications. • Excessive deflections noted on ground assembly. • After frame was complete, deflection was measured to be twice that predicted by computer analysis (660.4mm). • No responsibility taken by contractor towards the performance of the project. Conclusions: • Employ Project Manager to take responsibility for entire project. • Employ Qualified Structural Engineer to investigate and report structural deficiencies. • Recheck design calculations and analysis, when unexpected deformations occur. • Investigate any possible structural deficiencies. • Include as large amount of redundancy as is feasible. • Independently check design calculations. Sources: • Hartford Civic Arena Roof Collapse. Rachel Martin. • Probability-Based Load Criteria for Structural Design. Bruce R. Ellingwood. • Failure Case Studies in Civil Engineering Education. Rachel Martin.