Presentation Group 16 2006.ppt

advertisement
Hartford civic centre
arena roof collapse
Presentation






Introduction
Organisation of the team
Roof design
Indications of failure
Reasons for failure
Conclusions
Location

Connecticut, USA
The arena

Built in 1975

Sports and convention complex

Large capacity
Team behind the structure






Well known architect – Vincent Kling
Engineers – Fraoli, Blum & Yesselman (FBY)
Construction – Bethlehem Steel Company
Inspection – Gulick Henderson
Many sub-contractors
Coordinated by a construction manager
Roof structure – an overview

FBY proposed a unique design

Space frame measuring 91m x 110m

Save $500,000 but…required complex analysis
Roof structure - pyramidal truss


Top & bottom square grids
Diagonals connecting them
Roof structure - bracing


Top horizontal bars
Main diagonals
Roof structure – 3 unusual features
1) Top horizontal bars – “cross” cross-section
2) Horizontal bars and diagonal bars intersected at
different points → bending stresses
Roof structure – 3 unusual features
3) Roof supported by 4 large pylon legs inside
edges of frame
Prior to failure

During assembly – excessive deflection at nodes

Members of the public & politicians concerned

In position – deflection at centre twice expected
Failure occurs


Heavy snowfall
Timing – good fortune
Investigation into the collapse


Actual loads on roof at failure < total load
assumed in design
Along frame edges, buckling of top bars not
prevented
Investigation into the collapse


Actual loads on roof at failure < total load
assumed in design
Along frame edges, buckling of top bars not
prevented
Computer analysis of failure

Tells us what happened after first bar buckled
→ “progressive collapse”

Need for redundancy

5000 members in roof – 50 more would have
prevented buckling
Other contributing factors proposed:



Torsional buckling
Differences between design and as-built
Violations of American Institute of Steel
Construction (AISC) code
Conclusions





Sound engineering judgement and ethics
Make use of redundancy
Computer analysis has limitations – buckling not
considered
Peer review
Responsibility
Final outcome


Out of court settlement six years later
Not made clear who had responsibility for
structural integrity of project
Group 16




Antoine Gaudin
Brendan McCabe
Eoghan MacTighearnáin
Andrew Lochaden
Download