Hartford Civic Arena Roof Collapse Group 16: Group 16 consists of four students: Antoine Gaudin, Andrew Lochaden, Brendan McCabe and Eoghan MacTighearnáin. Introduction: The Hartford Civic Centre Arena is a sports arena with a seating capacity of ten thousand. It is situated in the city of Hartford, Connecticut in the north east of the USA. Early in the morning of the 18th of January 1978, just 3 years after its completion, its space truss roof collapsed under loading resulting from a heavy snowfall. Fortunately, there were no injuries or fatalities. Space Frame Roof Design: In 1970, Vincent Kling was commissioned to be the architect for the Hartford Civic Centre. He hired Fraoli, Blum, and Yesselman, Engineers shortly afterwards. An innovative space frame roof design was proposed. The 91m x 110m roof consisted of two grids composed of horizontal steel bars (9m for the top bars, 6.4m for the intermediate) separated by 9m diagonal members connecting the nodes of the upper and lower grids. The members in the top grid were also braced diagonally at Figure 1: Elevation of space frame roof their midpoints. The resulting space frame looked like a series of linked pyramidal trusses as below. Refer to figures one and two. Figure 2: pyramid module This innovative space roof design had three particularly unusual features: 1) the truss members had a “cross” cross-sectional configuration, which did not give good resistance to buckling. The cross shaped section provided a much smaller radius of gyration than either a Universal Beam or Tube Shaped Beam. 2) The top horizontal members and the diagonal members intersected at different points instead of at the same point making the roof particularly vulnerable to buckling. 3) Instead of the roof being supported by boundary columns or walls, it sat on four pylon legs. Refer to figures one and two. Because of these changes from normal practice, computer analysis was used to check the safety of the building design. 2006 Hartford Arena Roof Collapse – Group 16 1/3 Indications of failure: In order to save money, the structure was assembled on the ground. While it was still on the ground, the engineers were notified that excessive deflections had been found at some of the nodes. Once the roof was put into position the deflections were measured and found to be twice that which was predicted by the computer analysis. Again, the engineers were notified but they claimed that such derivations from the theoretical deflections were to be expected. When a subcontractor was attempting to fit the steel frame supports for fascia panels on the outside of the truss, difficulties were encountered due to excessive deflections. Approximately a year after the building was constructed, a citizen contacted the engineers to express concern about the large deflection he’d noticed. He was assured that the building was safe. Reasons for roof failure: After the building had collapsed it was determined that the load due to the self weight of the roof had been underestimated by 20%. However, the sum of the dead and live loads was less than the total assumed in the design. The midpoint braces for the rods in the top layer had not been installed. The exterior rods were only braced every 30-feet, rather than the 15-feet intervals specified, and the interior rods were insufficiently braced at their midpoints. Along the frame edges, the diagonals and top bars were in the same inclined plane; hence buckling out of this plane wasn’t prevented. The top bars were free to bend outward in a direction perpendicular to that plane. Figure 3: Buckling of top horizontal chord The diagram to the left illustrates some of the differences between the original design and the design as was implemented on site, for the east-west edges of the roof. As can be seen, the difference caused a huge reduction in the allowable forces for the structure. The diagonal members were attached some distance below the horizontal members. The flexibility of the connection reduced the effectiveness of the bracing by introducing a spring brace instead of the hard brace that had been assumed. Figure 4: Designed versus as-built connections 2006 Hartford Arena Roof Collapse – Group 16 2/3 The most overstressed members in the top layer buckled under the snow load, leading to the bucking of other members and the collapse. There were some other faults with the design, including: The slenderness ratio of some members violated American Institute of Steel Construction (AISC) guidelines, as did members with bolt holes greater than 85% of cross-sectional area. Some of the diagonal members were misplaced Analysis of the failure: A study was made of the progressive failure of the roof. A computer model of the roof structure, with correct buckling lengths and stiffnesses of all bars, was “loaded” in steps, searching for the value of the load at which the first bar would buckle. This load was conservatively evaluated to be 13% below the total load actually on the roof on the day of failure. Loading of the model was increased further to examine what happened after the first bar buckled. When a member of a frame buckles, it transfers its load to adjacent bars. Most of the time, the adjacent bars cannot carry the extra load and then also buckle. The failure of additional bars transfers their load progressively to new bars until the roof cannot carry any greater load and begins to collapse. Progressive collapse can start as the result of even a minor deficiency unless redundancy is introduced as structural insurance. The addition of less than fifty bars to brace the top outer horizontal bars to a frame consisting of almost five thousand bars would have made the Hartford roof safe by preventing bar buckling. Conclusion: The engineers for the Hartford Arena depended on computer analysis to assess the safety of their cost cutting design. The roof design was extremely susceptible to buckling which was a mode of failure not considered by that particular computer analysis and, therefore, left undiscovered. Construction costs were reduced but the analysis of the innovative design was not meticulous enough. The Hartford Arena contract was divided into five subcontracts coordinated by a construction manager. Not only did this fragmentation allow mistakes to slip through the cracks, it also left confusion over who was responsible for the project as a whole. Even though the architect recommended that a qualified structural engineer be hired to oversee the construction, the construction manager refused saying that it was a waste of money and that he would inspect the project himself. After the collapse he disclaimed all responsibility on the grounds that a design error had caused the collapse. As a result of the construction manager's refusal to hire a structural engineer for the purpose of inspection, no one realized the structural implications of the bowing structures. This collapse illustrates the importance of having a structural engineer, especially the designer, perform the field inspection. The excessive deflections apparent during construction were brought to the engineer's attention multiple times. The engineer, confident in his design and the computer analysis that confirmed it, ignored these warnings and did not take the time to recheck his work. For projects of this scale, a peer review of the design is usually required. However, the authorities did not require it for this particular project. In all likeliness, a peer review would have revealed the design flaws responsible for the collapse of the roof. If all or some of the lessons learned from such engineering disasters are understood and taken on board by all engineers, then such failures may be avoided. Most importantly, the risk of injury or death to members of the public who use these structures may be dramatically reduced. References: Levy, Matthys and Salvadori, Mario (1992), Why Buildings Fall Down: How Structures Fail. W. W. Norton, New York, NY Martin, Hartford Civic Center Arena Roof Collapse, http://www.eng.uab.edu/cee/faculty/ndelatte/case_studies_project/Hartford%20Civic%20Center/h artford.htm 2006 Hartford Arena Roof Collapse – Group 16 3/3