Facilities Services Weekly Update Meeting

6/26/2015

8:00 a.m.

1.

Current Projects a.

Vangstad i.

Basement flooded the other night due the rain- still looking into a way to repair

this issue ii.

Updated the budget and Ron will be meeting with the contractor to figure out

how we can finish the project. iii.

Found more asbestos to remove. b.

Student Center Upper Lounge i.

Pat talked to the architect yesterday to finalize some of the project details.

Should be sending out plans today to get it out to bid next week. c.

Flood Wall i.

Today they will be starting to install the storm sewer pipe going east of the pump station. Hoping for good weather so Strata can dig the storm sewer going

west. The footings a walls will go east first and then west. (90’ per pour) ii.

Still need to move the dedication tree- needs to be done this week. Will be going

in at the Library Mall. d.

Climate Control Upgrade i.

No updates. e.

McCoy/Snoey Basketball Court i.

Will need to bids on the asphalt- would like to complete next month.

1.

Met with Lynn Johnson yesterday. f.

Back Alley i.

On hold. g.

Hill slide Waterfall i.

On hold. h.

McFarland 1 st floor Water-proofing i.

Received 2 bids- will need to figure out a timeline.

1.

Wick has the lowest bid. i.

President’s House Retaining Wall i.

Ron has received two bids and we will be going with the lowest bid. Will repair

75 feet.

1.

Wick/Bradco will be doing the project. j.

Field House Addition i.

Plans were sent to Ron this morning. Bids will go out next week (21 day bid). ii.

They will need to relocate some coaches for accreditation. k.

Graichen Gym Floor i.

Lettered and striped the floor yesterday. Will be in tonight and Monday to put

the rest of the sealer on it. l.

Wellness Center i.

All the black dirt is stripped off and they are ready to dig for the foundation. ii.

Had to locate our fiber yesterday and mark it since it will be exposed for the rest

of the project.

m.

Heat Plant i.

Still working on buyouts. n.

Circle Hall i.

Will be here mid-July to put up the awning. o.

Comm. Arts- 4 th floor McFarland i.

This project is DONE and will be moved from the agenda. p.

SEGS Office Remodel i.

Sheetrock is up in the new offices and skim-coating is done. ii.

Ceilings are up in 3 of the offices. iii.

NOVA will still need to come to rework the sprinkler lines. q.

Housing i.

Mythaler & President’s House Sewer Line

1.

Still working on a timeline. ii.

Guest suites in McCoy & Robertson

1.

Will need to be completed by the end of the summer. Have all materials- just need to get the work done. iii.

Robertson/Mythaler Fire Alarm Upgrade

1.

Bid opening was Monday. Will be going with Enterprise Electric- still

$2200 over budget. Ron will be meeting with Stephanie to discuss options to get both projects complete.

2.

Also working with Simplex to see if there are any breaks they can give us to keep us on budget.

3.

Looking to sign contracts early next week.

2.

Future Projects a.

Fine Arts Building i.

No updates.

3.

Events a.

New student orientation on Friday b.

Theatre sale on Saturday

4.

Safety a.

Discounts have been submitted. b.

Will be sending out the training for accessing the training modules next week.

5.

FAMIS a.

Timecard Corrections (app) i.

Will be sending out training ppt to department.

6.

Building Services a.

Still working on doing the major building cleanings b.

There is still water comping into Rhoades when it rains (STEM Office and Penthouse

door)

7.

Maintenance a.

No updates.

8.

Power House a.

Try to get Wrigley’s out to fix the steam leak in Snoey.

9.

Other a.

Security Cameras

i.

Will be moving forward with the new system, Avigilon. b.

Department Openings i.

Power House position

1.

No applications.