CASEY ARBORWAY PROJECT Welcome Public Meeting March 29, 2012 Today’s Agenda 1. Selected Alternative 2. Casey Project Design Schedule 3. 25% Design Phase • Key Design Elements • Schedule 4. Continued Community Participation Process The Alternative Selected For Design …. At Grade …. Welcome to the Casey Arborway Project The Basis for Decision • Extensive Community Involvement (5 public meetings and 12 working group meetings in 9 months) • Removing visual barriers to connect neighborhoods • Restoring the Emerald Necklace and connecting open space areas The Basis for Decision • Advanced bike and pedestrian connections (north/south and east/west) • Improved bus operations in and around the area • Measures of Evaluation • Cost Estimates – design, construction and lifecycle The Public Agency Process The Partnership Continues – MassDOT – highway & transit – DCR – owner of surface roadway and signals – City of Boston – owner of adjacent roadways, parks and maintains signals The Community Partnership: WAGDAG Next Phase: Design • Maintain guiding principles, goals and objectives • Integral to developing designs and addressing operational issues • Continue to balance mobility needs with livability opportunities • Continue to challenge the design team to incorporate new ideas based on local concerns Community Concerns • Construction Management – Logistics, traffic management, protection of neighborhoods, commuters, business and transit • Strategies to protect neighborhoods from cut through traffic Community Concerns - Continued • MBTA bus trips travel time – during and post construction • Coordination with small businesses before and during demolition and construction • Arborway Yard and the ABP program Casey Arborway Project Design & Construction Schedule Accelerated Bridge Program Opportunity Project Schedule 25% Design Submission by September 2012 75% Design Submission by March 2013 Final Design July 2013 Construction Completion Advertise October 2013 October 2016 PLANNING STUDY 2011 25% DESIGN 2012 TO FINAL DESIGN 2013 DEMOLITION AND CONSTRUCTION 2014 2015 Community Involvement Throughout Project Select Alternative 25% To Final Design Review Construction Staging & Traffic Management Planning and Phasing Construction Management Meetings 2016 Design Phase For the Casey Arborway Project Key Elements & Schedule Design Process • Planning Stage - COMPLETED • 25% Design – Identifies design parameters: – Horizontal and vertical alignments – Signal phasing – Urban design and landscaping – File the environmental notification form (ENF) • 75% Design – Includes additional design detail (plans/specifications) based on 25% review • Plans, Specifications and Estimates (PSE) – Finalizes all construction-related documents Key Design Elements • Open space and landscaping • Signalization details and roadway configuration • Pedestrian and bicycle connections • Parking & pick-up/drop-off (including school buses) • Non-peak design variations Key Design Elements - Continued • Upper busway/Washington Street • Shea Square and Morton Street • Construction staging and traffic management • Sustainable design Casey Arborway Project – 2012-2013 Community Participation – DRAFT Design Schedule 2012 25% Design Begins File ENF* Submit Receive All 25% Design Comments MAR APR MAY JUN WAG DAG DAG DAG JUL AUG SEP OCT NOV DEC DAG PUB MTG WAG = Working Advisory Group 25% DESIGN PUBLIC HEARING MEPA SITE MTG MEPA = Massachusetts Environmental Policy Act DAG = Design Advisory Group 2013 Submit PS&E** Design Submit Receive All 75% Design Comments JAN FEB MAR APR MAY JUN DAG DAG 75% DESIGN PUBLIC MEETING *ENF=Environmental Notification Form DAG Advertise JUL AUG SEP OCT PS&E** DESIGN PUBLIC MEETING **PS&E=Plans, Specifications, and Estimates Continued Community Participation Process For 25% Design WAGDAG Design Advisory Group Technical Focus Proposed DAG Meetings 25% Design Phase - Meeting Topics • Construction Management • Logistics and plans • Traffic plans and management for all modes, • Cut through traffic, business access • Livability • Urban Design – gateways • Landscaping and open space • Mobility • Roadway and intersection design, signalization, medians and non-peak hour designs D E S I G N M E E T I N G S Casey Arborway Project – 2012 Community Participation - DRAFT Schedule 25% Design Begins Submit 25% Receive All Design for 25% Design Comments Review File ENF MAR APR MAY JUN JUL WAG1 DAG DAG 1 DAG 2 DAG 3 DAG4 Public Meeting AUG MEPA Site Meeting Meeting Topics DAG1 Design: (Shea Circle & Asticou Rd/Washington St) DAG2 Design Charrette: (SWCP, MBTA Plaza & Franklin Park) DAG3 Design: Traffic (roadway cross sections & operations) DAG4 Construction and Traffic Management SEP OCT 25% Design Public Hearing Casey Arborway Project Discussion