Office of Financial Management Washington State Major Project Agency Number

advertisement
Office of Financial Management
Washington State Major Project
Status Report for December 2014
Agency Number: 699
Agency: State Board for Community &
Technical Colleges
Project Number: 20082703
Project Title: Communication & Technology Building
Bill Reference:
Project Description:
Construction of an Advanced Technology Center instructional building at Bates, Central
Tacoma (Mohler) Campus. The project will provide educational program space for
Digital Media, Engineering and Information Technologies programs. Student Services,
open collaboration space, computer lab, STEM classroom and library services will also
be provided in the new facility.
The College’s primary goals of this project are as follows:
Address the student needs at our Central Tacoma (Mohler) Campus by:
• Providing classrooms and laboratory’s for Communications (Digital Media),
Information Technologies and Engineering program courses to enhance the
educational process for career training students seeking technical degrees
• Collocating department programs from multiple campuses to one campus in the
same building
• Providing space for essential academic support services such as a library,
computer labs, general education classrooms and similar support functions
• Accomplishing Master Plan objectives
• Providing space for Student Services/Support functions
Project Total Cost:
Phase
Predesign
Design
Design (carry over)
Design (carry over)
Art
Construction*
Construction Contingency Pool
Other (Approp/Non
Approp)
Total
Biennium
2007-09
2009-11
2011-13
2013-15
2013-15
2013-15
2013-15
Appropriation
I51 BH7G
J16 BH9H
J16 BH9H
J16 BH9H
S02 5ART
S02 L324
S99 L390
Amount
$
173,000
$ 1,755,000
$
327,345
$
66,864
$
92,835
$ 23,718,257
$
711,000
$26,447,000
* MACC = $18,567,000 (base bid amount). Additional costs will include consultant
services, equipment, art and other project related costs.
Schedule:
Budget Schedule
(as currently funded)
Predesign
Jul 2007 – Jul 2008
Programming Revisions Jul - Nov 2009
Schematic Design
Dec - Mar 2010
Design Development
April - Sept 2010
Construction Documents Oct 2010 – Mar 2013
Bidding
Construction
Close Out
Move In
May - June 2013
June – Aug 2014
Aug – Sept 2014
September 2014
Actual/Forecast
Jul 2007 – Jul 2008
Aug - Nov 2009
Dec - Mar 2010
April - Oct 2010
Oct 2010 - June 2011;
July 2013 - Jan 2014
Jan – Feb 2014
May 2014 – Sept 2015
Sept 2015
Sept 2015
Variance
(wks)
0
0
0
4
44
35
57
52
52
Project Status and discussion of Critical Path:
The project was awarded an NTP on May 06, 2014. Work is approximately 79% into the
construction schedule with no impacts to the critical path. The construction contract is
485 days with Substantial Completion scheduled for September 2015.
Contract Award History
Pre-Design (07-09)
A/E Agreement
Sub-total
$ 173,000
$ 173,000
Design (09-11)
A/E Agreement
Amendments
Sub-total
$ 1,300,506
$ 708,106
$ 2,008,612
Construction (13-15)
A/E Consulting:
A/E Agreement
Amendments
Pending Changes
Sub-total
Total
Current Design
Contingency
(09-11) Agreement
$ 709,579
$
30,000
$ 739,579
$ 2,923,191
Construction Contract (excl. tax):
Bid Award Amount $18,567,000
Change Orders
$ 364,390
Pending Changes
$ 418,886
Sub-total
$19,350,276
Total
$19,350,276
$
Current Construction
Contingency
$
4,376
145,074
Potential for Project Cost Overruns/Claims
Potential risk for project overruns/claims could be encountered through construction
change orders if they were to exceed the budgeted construction contingency.
Discussion of Project Quality
A constructability review of the project took place in March of 2011. The complete set of
drawings has been coordinated by all A/E disciplines to address all of the constructability
comments. Corrections were incorporated into drawings and specifications. The project
was created and documented through use of Building Information Modeling (BIM). This
not only records 2d drawings and specifications but includes 3d scaled models of the
building including architectural, structural, mechanical, electrical and plumbing building
elements. The General Contractor ran clash detection and constructability assessments of
the Building Information Model. Construction coordination was addressed early and
efficiently using this process. The project is currently 80% complete through the
construction schedule. Quality has been maintained and improved as construction has
progressed. Sustainability design goals for the project target achievement of a Silver LEED
sustainability rating. Current project assessment, scores the project within the low end of
the Gold certification level.
Project Photographs:
South end of instructional support wing.
Interior brick installed.
Driveway, parking and sidewalk work.
Follow this link to access an interactive self-guided tour of the facility design and links
to additional presentation and animation work related to the Public Art for the project:
http://www.bates.ctc.edu/ATC
Drawings and Renderings:
Site Plan
First Floor Plan
Second Floor Plan
View from South East
View from North East
Download