Office of Financial Management Washington State Major Project Status Report for December 2014 Agency Number: 699 Agency: State Board for Community & Technical Colleges Project Number: 20082703 Project Title: Communication & Technology Building Bill Reference: Project Description: Construction of an Advanced Technology Center instructional building at Bates, Central Tacoma (Mohler) Campus. The project will provide educational program space for Digital Media, Engineering and Information Technologies programs. Student Services, open collaboration space, computer lab, STEM classroom and library services will also be provided in the new facility. The College’s primary goals of this project are as follows: Address the student needs at our Central Tacoma (Mohler) Campus by: • Providing classrooms and laboratory’s for Communications (Digital Media), Information Technologies and Engineering program courses to enhance the educational process for career training students seeking technical degrees • Collocating department programs from multiple campuses to one campus in the same building • Providing space for essential academic support services such as a library, computer labs, general education classrooms and similar support functions • Accomplishing Master Plan objectives • Providing space for Student Services/Support functions Project Total Cost: Phase Predesign Design Design (carry over) Design (carry over) Art Construction* Construction Contingency Pool Other (Approp/Non Approp) Total Biennium 2007-09 2009-11 2011-13 2013-15 2013-15 2013-15 2013-15 Appropriation I51 BH7G J16 BH9H J16 BH9H J16 BH9H S02 5ART S02 L324 S99 L390 Amount $ 173,000 $ 1,755,000 $ 327,345 $ 66,864 $ 92,835 $ 23,718,257 $ 711,000 $26,447,000 * MACC = $18,567,000 (base bid amount). Additional costs will include consultant services, equipment, art and other project related costs. Schedule: Budget Schedule (as currently funded) Predesign Jul 2007 – Jul 2008 Programming Revisions Jul - Nov 2009 Schematic Design Dec - Mar 2010 Design Development April - Sept 2010 Construction Documents Oct 2010 – Mar 2013 Bidding Construction Close Out Move In May - June 2013 June – Aug 2014 Aug – Sept 2014 September 2014 Actual/Forecast Jul 2007 – Jul 2008 Aug - Nov 2009 Dec - Mar 2010 April - Oct 2010 Oct 2010 - June 2011; July 2013 - Jan 2014 Jan – Feb 2014 May 2014 – Sept 2015 Sept 2015 Sept 2015 Variance (wks) 0 0 0 4 44 35 57 52 52 Project Status and discussion of Critical Path: The project was awarded an NTP on May 06, 2014. Work is approximately 79% into the construction schedule with no impacts to the critical path. The construction contract is 485 days with Substantial Completion scheduled for September 2015. Contract Award History Pre-Design (07-09) A/E Agreement Sub-total $ 173,000 $ 173,000 Design (09-11) A/E Agreement Amendments Sub-total $ 1,300,506 $ 708,106 $ 2,008,612 Construction (13-15) A/E Consulting: A/E Agreement Amendments Pending Changes Sub-total Total Current Design Contingency (09-11) Agreement $ 709,579 $ 30,000 $ 739,579 $ 2,923,191 Construction Contract (excl. tax): Bid Award Amount $18,567,000 Change Orders $ 364,390 Pending Changes $ 418,886 Sub-total $19,350,276 Total $19,350,276 $ Current Construction Contingency $ 4,376 145,074 Potential for Project Cost Overruns/Claims Potential risk for project overruns/claims could be encountered through construction change orders if they were to exceed the budgeted construction contingency. Discussion of Project Quality A constructability review of the project took place in March of 2011. The complete set of drawings has been coordinated by all A/E disciplines to address all of the constructability comments. Corrections were incorporated into drawings and specifications. The project was created and documented through use of Building Information Modeling (BIM). This not only records 2d drawings and specifications but includes 3d scaled models of the building including architectural, structural, mechanical, electrical and plumbing building elements. The General Contractor ran clash detection and constructability assessments of the Building Information Model. Construction coordination was addressed early and efficiently using this process. The project is currently 80% complete through the construction schedule. Quality has been maintained and improved as construction has progressed. Sustainability design goals for the project target achievement of a Silver LEED sustainability rating. Current project assessment, scores the project within the low end of the Gold certification level. Project Photographs: South end of instructional support wing. Interior brick installed. Driveway, parking and sidewalk work. Follow this link to access an interactive self-guided tour of the facility design and links to additional presentation and animation work related to the Public Art for the project: http://www.bates.ctc.edu/ATC Drawings and Renderings: Site Plan First Floor Plan Second Floor Plan View from South East View from North East