Office of Financial Management Washington State Major Project Status Report December 15, 2007 Agency Number: 699 Agency: Olympic College Project Number: 04-1-951 & 04-1-202 School/Campus Bremerton Campus Project Title: Science and Technology Center Bill Reference(s): 26-03-800 (5) (a) & 26-03X-807 Contact Name, phone number, email: Bill Wilkie 360-475-7835 bwilkie@oc.ctc.edu Barbara Martin 360-475-7501 bmartin@oc.ctc.edu Project Description This project replaces the existing Math/Science Building as proposed in the Pre-Design analysis. The new building will provide state-of-the-art teaching laboratories for Biology, Chemistry, General Science, Geology and Physics. Also included are computer classroom/labs and general-purpose classrooms to be jointly used by Science, Math and English, with a portion of these spaces planned for future conversion to six additional science labs. Technical support spaces, administration and faculty offices are also included in the project. Square feet: Predesign: 55,000 gsf; SD: 59,000 gsf; CD: 57,598 gsf Scope Changes : The replacement of pumps in the central boiler plant, at a cost of $117,389 is the largest addition to the construction contract scope to date. Provision of power to the fixed furniture in seven classrooms was added by Change Order during construction at a cost of $30,775. There are no additional Change Orders expected. We are in the final phases of purchasing equipment for the building. We are also in the final phases of completing the demolition of the building this project replaced along with the related projects. Project Total Cost: Phase Predesign Design Construction * Other (Approp/NonApprop) Total * MACC 12/15/07 Biennium 2002-2004 2004-2006 2006-2008 Appropriation G50 G50 G50 G42, G49 Amount $123,821 $918,862 $15,164,000 $22,953,000 Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule 05/02 07/03 04/05 07/05 04/06 11/06 01/07 Actual/Forecast 05/02 09/03 12/1/05 1/5/06 9/06 3/30/07 10/16/07 Variance (wks) 0 +9 weeks +30 weeks +22 weeks +21 weeks +20 weeks +40 weeks Project Status and discussion of Critical Path for Construction An early bid package for relocation of an existing utilidor was bid in August, 2005, and completed in September, 2005. The Bid Award Amount for the Utilador Package was $194,640, Change Orders were $11,221 and the package was completed for $205,861. The balance of the work was bid on December 1, 2005, with the Notice to Proceed issued on January 5, 2006. The Bid Award Amount for the main package was $14,021,498. Change Orders to date total $1,110,200, including the added scope work of replacing pumps in the central boiler plant at a cost of $117,389. Pending Changes totaling $7,507 have been identified at this time. Minor additional costs are anticipated as work toward final completion is performed. Substantial Completion was achieved on 3/30/07. The contractor received a contract extension of 24 days, consistent with this substantial completion date. Final acceptance was reached on October 16th 2007, and we have completed the first full Quarter of classes in the new building. The Construction Contract figures below are the totals for the two bid packages. Contract Award History A/E Agreement Original Agreement $ Amendments $ Pending Changes(CA) $ Total $ Current Design 12/15/07 98,500.00 1,719,326.20 0.00 1,817,826.20 Construction Contract (excl. sales tax) Bid Award Amount $14,216,138 Change Orders $ 1,121,421 Pending Changes $ 7,507 Total $15,345,066 Current Construction Contingency $ .00 Contingency $ Potential for Project Cost Overruns/Claims Change Orders and Pending Changes currently total 7.97% of the bid amount. The three largest change items to date are the additional scope of replacing pumps in the central boiler plant (+$117,389), payment for lighting controls work the subcontractor claimed was not included in its bid ($72,243), and the replacement and improvement of storm drainage piping in the public right-of-way that was incorrectly shown on the existing City of Bremerton drawings (+$69,356). Extended overhead costs of $31,806, related to the 24 day extension of time received by the contractor, mentioned above, are also included. Discussion of Project Quality The project is designed to meet the qualitative expectations and standards identified at the beginning of the design process for overall image, functionality, durability and long-term operational performance. Value Engineering and Constructability reviews during the Construction Documents phase were used to confirm that the systems, materials and detailing decisions remained consistent with these guiding principles for the building. No changes to project quality have been made during the construction phase. Project Photographs Building Entry facing the Library 12/15/07 Southwest Corner of Building from the Mall Northwest Corner of the Building from the Campus Entry 12/15/07 Courtyard Facade of North Wing 12/15/07