Joining forces for the fast production of a power transformer Four and a half months from order receipt to delivery Due to the failure of a transformer in a Manhattan sub­ station, a U.S. customer needed a replacement for a 130-MVA, 134/69-kV unit. Thanks to its efficient process­ es, the Siemens transformer production network is an especially flexible and responsive partner to its customers in these types of emergencies. So in this case, too, imme­ diate assistance was provided. The customer ordered a transformer model that has been in production in Nuremberg for a number of years. The new replacement had to be manufactured in just five months. Although the usual throughput time for a power transformer is nine to twelve months, Siemens was able to meet this goal. A highly motivated team, efficient engi­ neering and production, flexible solutions, a number of process changes, and particularly close communication with the customer all contributed to successful comple­ tion of the project in just four and a half months. Since an already existing design that had undergone multiple practical tests was used, it was possible to save a great deal of time during the project planning and engi­ neering phase. An elaborate purchasing strategy enabled further crucial time savings by: • transporting the monitoring equipment to the end customer directly from the supplier • dividing the scope of supply for steel parts among several suppliers • adding the transformer tank and cooling system to the supplier scope of production Siemens AG Energy Management Division Transformers Katzwanger Strasse 150 90461 Nuremberg, Germany Contact Martin Modes martin.modes@siemens.com • performing the cooling system acceptance process directly on the sub-supplier’s premises Following the electrical test that was recently passed, the transformer and accessories will now be transported by truck and barge to Zeebrugge in Belgium, and from there they will be shipped by sea to New York. The last leg of the journey will be particularly interesting. After being loaded onto a barge, the transformer will be hoisted by mobile crane over a highway and into its installation site. The highway will be closed overnight to all traffic during the night while this work is carried out. Publisher and Copyright 2015: Siemens AG Energy Management Division Freyeslebenstrasse 1 91058 Erlangen, Germany siemens.com/transformers