On-site transformer repairs in the Middle East The Siemens transformer service unit, which is part of Transformer Lifecycle Management® (TLM), once again put its performance to the test while repairing a transformer for a Middle East petrochemical company. The 64-MVA 220/20-kV transformer was repaired on the customer’s premises, avoiding the need for time-consuming and expensive transport to the manufacturer’s factory in Germany. Following the diagnosis of a defective winding on the affected transformer, the customer ordered three new sets of windings from Siemens and then placed the order to install and recommission the transformer on-site. Time was an important concern, beginning with the contract award, because the failure of the feeding transformer in an industrial plant brings production to a standstill and incurs high follow-on costs. The customer therefore scheduled a maximum of 36 calendar days from the time the transformer was taken out of service until it was brought back on line. TLM Nuremberg worked with Siemens Middle East to evaluate the options for on-site repair, and the closest repair factory was brought on board through a collaboration agreement. The concept that Siemens TLM ultimately submitted won over the customer on all points. The winding sets were to be supplied from the transformer factory in Dresden, while the installation and commissioning work would be performed by local staff and TLM employees from Nuremberg. TLM Nuremberg assumed overall responsibility for the project. Thanks to the excellent planning and extensive expertise of the employees involved, the dedication of the supervisors from Germany, and the great teamwork of the local Siemens personnel, all of the work was completed with impressive speed. The entire repair, from disassembling Inserting the repaired active part into the transformer housing the transformer to acceptance by the customer, was completed in just 24 days; the entire retrofit, from taking the transformer out of service to bringing it back on line, took 34 calendar days. As a result, the planned project duration, which was extraordinarily short to begin with, was reduced by two days. The customer was delighted with the quality as well as the remarkable speed of the repair. siemens.com/transformers Markus Biller, who heads TLM in Nuremberg, also praised his team’s impressive performance. “Our people fulfilled the order at top speed, literally working day and night. The fact that we have received additional orders confirms this success. A repair of this scope makes the transformer ready and able to perform for the next 30 years.” After final acceptance: The transformer is ready for another 30 years of operation Siemens AG Energy Management Division Transformers Katzwanger Strasse 150 90461 Nuremberg, Germany Contact Frank Küffner frank.kueffner@siemens.com Publisher and Copyright 2015: Siemens AG Energy Management Division Freyeslebenstrasse 1 91058 Erlangen, Germany siemens.com/transformers