Siemens transformer factory in Brazil at full power The Siemens factory in Jundiaí concludes a large-scale project and enhances its export business with orders from the U.S. siemens.com/energy/transformers The Siemens transformer factory in Jundiaí in the Brazilian federal state of São Paulo supplied the last of a total of 64 transformers for the extensive Jirau Hydroelectric – Rio Madeira Project to its customer Energia Sustentável do Brasil (ESBR) on time. The project, which has been in progress since 2009, comprised 14 340 MVA–525kV step-up transformers, 27 auxiliary oil-immersed transformers, plus 24 auxiliary dry-type transformers. One of the key challenges was the transport of the step-up transformers to Porto Velho in the northern Brazilian Amazon region. All of the transformers were shipped disassembled. Accessories and oil were transported on highways, while the tank – the heaviest part of the transformer, weighing some 180 tons – was transported in five steps by truck, ship, and barge. »In order to transport the transformers, several moves were required, and each was considered a risky operation. This meant more planning effort. It took up to 150 days to transport a transformer, though, as ship, barge, and road permits had to be available at the same time in order to ensure that all moves went hand in hand,« explains Project Manager Ana Priscilla P. Siqueira, who adds: »Despite the adversities, the transformers were supplied on time, according to the customer’s needs.« The challenge: shipment of a 180-ton transformer tank Answers for energy. Ten transformers for New Jersey, Ohio, and Pennsylvania In the meantime, the Siemens transformer factory in Jundiaí has also manufactured and delivered an 870-MVA three-phase autotransformer to First Energy, one of the largest investor-owned utilities in the United States. The transformer, earmarked to enhance the existing 500 kV network in the states of New Jersey, Ohio, and Pennsyl­ vania, was produced in the record time of only 150 days. The delivery of the transformer underlines the close relationship between Siemens and First Energy, which has already been continued with a new order for the engineering, production, testing, and logistics activities for three more transformers. All of the units are being designed and produced in Jundiaí in close cooperation with the Siemens Global Technology Center (GTC). The cooperation between the Siemens transformer factory network and the GTC ensures delivery of the most stateof-the-art and cost-efficient technologies. »The investment proves Siemens’ – and especially the Jundiaí plant’s – capacity for producing and exporting technology. Over the last three years, almost 50 percent of the large power transformers exported from Brazil to the United States were produced at our Jundiaí plant,« say engineers Fabiana Pileggi and Felipe Estácio from Siemens Brazil. Ready for operation: the first of ten transformers for U.S. customer First Energy