Managing Projects Chapter Objectives Be able to: Explain the difference between routine business activities and projects. Describe the five major phases of a project. Construct a Gantt chart and interpret the results. Construct a project network diagram and calculate the earliest and latest start and finish times for all activities. Identify the critical activities and paths in a network. Crash a project. © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 2 Project Management: Why Do It? Building Mega Refineries in Record Time (India, 2006): • Demand for gasoline is increasing in USA • No new refineries in USA • Need to process heavy crude • Current capacity is not enough © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 3 Reliance Industries, Ltd: • Mobilized initial workforce of 20,000, will grow to 150,000 to complete project by December 2008 • Built residential complex for 2500 families to attract skilled workers needed and an irrigated 2000-acre farm nearby • Expansion will add capacity of 582,000 barrels a day • Each welder will have six helpers to keep him supplied with necessary materials © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 4 What Is a Project? A series of related tasks directed toward some major output or goal Often driven by a completion deadline © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 5 Project Phases I • Concept Phase – Broad definition and feasibility analysis – Budget estimates within 30% • Project definition Phase – Tentative schedules, budgets, organization – Budget estimates refined within 5% to 10% © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 6 Project Phases II • Planning phase – Detailed tasks, timing, budgets and resources – Milestones – Project management tools • Performance phase – Execution and control • Postcompletion phase – “Wrap-up” – Reassignment of project resources © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 7 Statement of Work (SOW) A written description of the project objectives to be achieved, with • a brief statement of the work to be done • a proposed schedule specifying the start and completion dates • budget and completion steps (milestones) • written reports to be supplied. © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 8 Breaking Down the Work • • • • Allows independent operation Improves manageability Decentralizes authority Enables monitoring and measurement • Provides assessment of required resources © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 9 Work Breakdown Structure (WBS) Level 1 Program 2 Project 3 Task (group or organization) 4 Subtask 5 Work Assignment (organizational unit) © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 10 Work Breakdown Structure Example Level 1 Custom Home Builder 2 Custom Home 3 Foundation (group or organization) 4 Concrete work 5 Set-up forms (organizational unit) © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 11 Tools for Project Control: Gantt Charts ID Task Name 1 2 3 4 5 Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 6 Activity 6 Start 4/4/2005 4/5/2005 4/7/2005 4/8/2005 4/13/2005 Finish Duration Apr 2005 4 5 6 7 8 9 10 11 12 13 14 15 16 17 4/6/2005 3d 4/8/2005 3d 4/11/2005 2d 4/15/2005 5d 4/14/2005 1d 4h 4/15/2005 4/18/2005 1d ...But there is no detailed information about interrelationships © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 12 Tools for Project Control: Network Diagrams • • • • Network techniques Consider precedence relationships Capture interdependency of activities Determine critical path(s) – Sequence(s) of activities that determines overall duration of the project © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 13 Critical Path Method (CPM) Consider the following consulting project: Activity Designation Immediate Predecessor(s) Duration (weeks) Assess customer’s needs A None 2 Write and submit proposal B A 1 Obtain approval C B 1 Develop service vision and goals D C 2 Train employees E C 4 Quality improvement pilot groups F D, E 5 Write assessment report G F 1 Develop a network diagram and determine the duration of the critical path(s) and slack times for all activities © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 14 This activity-on-node (AON) diagram shows the precedence relationships ... D, 2 START A, 2 B, 1 C, 1 F, 5 G, 1 FINISH E, 4 . . .as well as the length of each activity. Do you see the two paths through the network? © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 15 Some Definitions • Earliest Start Time (ES) = Latest EF for all immediate predecessors • Earliest Finish Time (EF) = ES + activity’s duration • Latest Start Time (LS) = LF – activity’s duration • Latest Finish Time (LF) = Earliest LS for all immediate successors • Slack = amount of allowable delay in an activity = Equal to LS – ES or LF – EF for an activity © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 16 Insights • A ‘hit’ to a critical activity will make project late • Rational time estimates needed • Slack activities can start later • Difference between effort-driven and timedriven activities • Useful to have ‘Start’ and ‘Finish’ boxes on network diagram, particularly when there are two or more independent activities at the beginning and/or end of a project. © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 17 Some Assumptions • Project activities can be identified as entities. (There is a clear beginning and ending point for each activity.) • Project activity sequence relationships can be specified and networked • Project control should focus on the critical path (activities with no slack) © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 18 In First Example ... • Network-based scheduling techniques to: Show precedence Determine project duration Identify critical paths and activities • Setting EF = LF for last activity implies that current length of project is OK © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 19 However, there are often ... • Deadlines for finishing projects – (Olympic stadium, dormitories, etc.) • Penalty or overhead costs if project is late • Competitive pressures – Competitors, slowing demand (Reliance Industries, Ltd.) © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 20 Ways to Shorten (Crash) a Project • BORROW resources from noncritical activities (ones with greatest slack) • Add MORE resources • Work MORE hours • Spend MORE $$$$ © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 21 Idea behind “CRASHING” Duration of individual effortdriven activities can be shortened, but at a cost Example: Following project must be completed by Week 26 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 22 Project Data Activity Duration Predecessors Crashable Weeks A 6 None None B 11 A 4 $700 C 14 A 3 $2,000 D 2 A None E 4 B 1 $2,000 F 5 B 1 $1,000 G 6 C 1 $1,000 H 7 C 2 $2,000 I 3 D None J 4 E None K 4 F, G 2 $1,500 L 3 H, I 1 $2,500 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Crash Cost/Week Chapter 5, Slide 23 Network Diagram for Project E 17 21 E L 22 26 6 17 L 10 21 S S E, 4 E 21 25 F L 26 30 F S E 17 22 B, 11 L 21 26 F E 0 6 L 0 6 E 6 20 E 26 30 S F L 6 20 L 26 30 S START S F,5 F J, 4 A, 6 F S C, 14 G, 6 F FINISH K, 4 E 20 26 E 0 0 L 20 26 E 30 30 L 0 0 S L 30 30 S F F S H, 7 D, 2 E 6 8 L 22 24 S F F E 20 27 L 20 27 S L, 3 F E 27 30 L 27 30 S I, 3 E F 8 11 L 24 27 S F © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 24 1. Write Down All Possible Paths and Lengths of Time for Each Path ABEJ ABFK ACGK ACHL ADIL Length 25 26 30 30 14 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 25 2. Identify All Paths to be Shortened Path ABEJ ABFK ACGK ACHL ADIL Length 25 26 30 30 14 Critical Path Critical Path © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 26 3. Find Lowest-Cost Way to Shorten Critical Path(s) Path ABEJ ABFK ACGK ACHL ADIL Length 25 26 30 30 14 To CRASH, either: 1. Shorten C or 2. Shorten {G or K} and {H or L} • Shorten C by 3 weeks Cost = 3×$2,000 = $6,000 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 27 Update Lengths in Table Path ABEJ ABFK ACGK ACHL ADIL Length 25 26 3027 3027 14 Are we done? What are our next cheapest alternatives? © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 28 To Crash Further 1. Shorten C some more, or 2. Shorten {G or K} and {H or L} • Shorten Both G and H by 1 Week: • Cost = $1,000 + $2,000 = $3,000 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 29 Update Lengths in Table Path ABEJ25 ABFK ACGK ACHL ADIL Length 26 302726 302726 14 Total Cost to Crash = $6,000 + $3,000 = $9,000 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 30 If the reduction in overhead per week is $4000 How many more weeks should the company try to crash the project? Observations • Cost of crashing becomes more and more expensive as cheapest options are used up • There is a limit to how far a project can be crashed. • Crashing non-critical activities is pointless © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 32 Controlling Projects CPM used primarily to Plan and Schedule, BUT ... • Things rarely go as planned • The need for additional activities arises • Better time and resource estimates are made as project progresses use of PERT (Program evaluation and review technique) where probabilistic time estimates are used © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 33 Computer-Based Package Advantages • Regular updates • Change analysis, tracking, and exception reports • High level of detail • Scheduling around resource constraints • Text examples using Microsoft Project™ on pages 139-141 © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 34 Project Management Institute (PMI) www.pmi.org • PMI: – Sponsors education and certification – Sponsors conferences, research, user groups – Publishes Guide to the Project Management Body of Knowledge (PMBOK®) • PMBOK® – Part I: Various business processes for projects – Part II: Nine project knowledge areas © 2008 Pearson Prentice Hall --- Introduction to Operations and Supply Chain Management, 2/e --- Bozarth and Handfield, ISBN: 0131791036 Chapter 5, Slide 35 Managing Projects Case Study Viva Roma!