EXECUTIVE SUMMARY of NH-24 Bareilly-Sitapur Status As On 20 Jun 14 Concessionaire: M/S Bareilly Highways Project Ltd. (A JV of M/s ERA Infra Engg. And SIBMOST) & Independent Engineer: M/S Intercontinental Consultants and Technocrats Pvt. Ltd. (ICT) PROJECT IMPLEMENTATION UNIT BAREILLY Project: 4 laning and widening of NH-24 Bareilly-Sitapur REASONS FOR DELAY OF PROJECT NH 24 1. Forest Clearances :- The proposal was submitted to DFO on 03Aug 2009.Final sanctions obtained:(a) District Shahjhanpur was received on 14-12-2011 . (b) District Sitapur 14 Jun 2012. (c) District Bareilly, Khiri and Hardoi on 13 Aug 2012. 2. Processing for Tree felling permissions commenced thereafter. 3. Rate of cutting of trees is slow. Concessionaire was exploited by Ban Nigam to assist in tree felling to achieve pace in cutting of trees .Orders to fell tree were received in Jun and Aug 12.Approximate 1400 trees yet to be felled. 4. Financial Closure Agreement was signed on 22Jun10,however it was complete in May 11 much beyond permissible six months (Clause 24.1.1.) 5. Appointed date Appointed date fixed by authority as 01 Mar 11 on basis of first MPR received from Concessionaire. However the same has been contested and denied till date by Concessionaire. 6. Land Acquisition Dates for 3A Notification for 425 hects (Additional required for four lanes) was 16 -11-09. Similarly the dates for 3D Notification were14-5-10, 18-5-10 , ,255-10, 08-10-10,12-10-10,01-09-11,25-11-11. However till date the 3G awards of 15 hect still pending. Possession for 175hects is pending and mutation for 365 hects is pending. 7. ROB there are four ROBs, however construction work yet to commence. Minimum two years are required. 8. Royalty For earth District administration has been slow and randomly issued clearances. This kept machinery idle at times. 9. Utilty Shifting UPPCL took time to submit estimates and in according permission for supervision charges. 10. Encroachments Civil administration avoids direct involvement in encroachment removal until compelled by courts or higher authorities. 11. Financial Mismanagement This has been one of the major cause, where issues related to over payment of advances, unclear equity by concessionaire and non involvement of Authority by the bankers and Lender Engineer resulted in improper utilsation of loan disbursed by the bankers. This led to abandoning of entire project site ,closure of four camps,general strike by the employees, complete stoppage of work for six months and stoppage of further release of loan installments by the bankers. As well as it led to non maintenance of equity debt ratio. 12. Inflation and Economic Slow Down Over the last three years or so ,there has been steep hike in prices of petroleum products, banning of mining by various Supreme Court Rulings, slow clearances related to tree felling, rise in prices of construction materials etc. The compounding effect of all this led to making ongoing projects economically less viable. 13. State Support Agreement As per Clause 47.3 of CA . UP State Govt was to provide state support Agreement for providing support and services. However the same has not been done till date. 14. Org Set Up and Unprofessional subcontractors of Concessionaire Concessionaire has been employing subcontractors without intimating Authority who are petty and lack skilled manpower for maintaining quality and safety norms. Similarly there have been major changes in staff of concessionaire after strike, this has also caused delay for lack of continuity. National Highways Authority of India -Bareilly Brief Report of Bareilly - Sitapur BOT Project Dated: 20 Jun 14 1 Name of Project Four Laning Of Bareilly- Sitapur Section of NH-24 in the State Of Uttar Pradesh. 2 Contract Length From Km 262.000 to Km 413.200 (Existing Chainage) 3 Contract Section NHDP-PHASE III 4 Employer National Highways Authority Of India 5 Independent Consultant M/s ICT Pvt. Ltd. 6 Name Of Concessionaire M/s Bareilly Highways Project Limited 7 EPC Contractor M/s Era Infra Engineering Limited 8 Lender Engineer M/s Scott Wilson Pvt. Ltd. 9 CA Cost of Project Rs.10460 Million 10 Concession Agreement Date 22nd June 2010 11 Date of Financial Closure 21st May 2011 12 Appointed date 1st March 2011 13 Schedule project completion date 910 days or 30 Months From Appointed Date 14 Concession Period 20 years from Appointed date 15 Construction Period 910 days or 30 Months From Appointed Date i.e. 26th August 2013 16 Performance Security Rs 52.30 (Crores ) 17 Defect Liability Period 120 days after Termination. Based on the Appointed date as on 01st March 2013, the construction period of 910 days is completed on 26th August 2013. The Concessionaire has not been able to achieve the Milestone-I, II, III and scheduled completion date. Concessionaire response related to Shifting of Milestone (if any) is awaited. NHAI has issued the Cure Period Notice on dated 11.11.2013. Concessionaire response related to Termination of Contract Agreement is awaited. Action by Authority on Cure period Notice has been kept in Abeyance for additional 3 Months vide NHAI HQ letter No NHAI/BOT/11019/15/2008/UP/BSNH/24 /48167 dated 22 Jan 14. Draft Termination notice forwarded in May 14.Discussed with MV Kini. Under process. Concessionaire received approximately 59 Crs in phases from bankers May onwards and arrived in Project area with limited manpower 20 May onwards. He has undertaken maintenance and has commenced earth work, casting two slab of bridge at Behgul,DBM work approximately 800m in camp 4 area .Approximately four to five small subcontractor have moved in over last ten days. Programe for the balance work including resource mobilization requirement/procurement not yet submitted by the concessinaire. 2. & material SALIENT FEATURE OF THE PROJECT AS PER CA: 1 Total Length of 4 Lane Road including 28.750 Km of 5 bypasses 157.590 Km. 2 Total Length 2 Lane Service Road (Both Side) 38.100 Km. 3 Right of Way (ROW) Existing–40-45, Proposed–60m both for Non-urban and Urban areas 4 Grade Separator 05 Nos 5 Major Bridges 08 Nos 6 Minor Bridges 14 Nos 7 Vehicular Underpass 18 Nos 8 Pedestrian Underpass 11 Nos 9 ROB 04 Nos 10 Box Culverts 69 Nos 11 Pipe Culverts 90 Nos 12 Truck Lay bye 10 Nos 13 Bus Bays 39 Nos 14 Toll Plaza 02 Nos KM 267 & KM 370 3. PROGRESS: A) FINANCIAL PROGRESS: The Project is completely stand-still even after issue of Cure Period Notice by NHAI. All the site camp offices are completely closed and there is no sign of reviving the Project. Total Project Cost = 1046 Crores Progress up-to 28th February 2014 26.18% i.e. 273.92 Crores Progress during the February month up to 0.00% 28th Feb’ 2014 The work progress is extremely slow at site since July 2013 onwards; Concessionaire has hardly achieved 0.75% progress in last 8 months. B) PHYSICAL PROGRESS: 1. Highways:- Sr.No Linear Progress upto 15.5.2014 Linear Progress after 15.5.2014 till in Km 16.6.2014in Km Item of Work LHS RHS Total Linear on Both Sides LHS RHS Total Linear on Both Sides 1 Subgrade 19 62 81 0.3 0 0.3 2 GSB 13 47.5 60.5 0 0.5 0.5 3 WMM-I 11 36 47 0 0 0 4 WMM-II 7.5 31.5 39 0 0.8 0.8 5 DBM-I 5 27 32 0 0.7 0.7 6 DBM-II 2.98 0 2.98 0 0 0 2. STRUCTURE WORKS Sr.No 1 2 Type of Structure Major Bridge Minor Bridge Physical Progress till 15th May, 2014 Work done during 16th May, 2014 to 15 June 2014 8 7 bridges in progress Only 1 Deck slab(2 lane) done at MJB Bahgul River at 289+021 LHS 14 1No. completed and 12 Nos. in progress Only 1 Deck slab(2 lane) done at MNB Rampura Nalla at Ch 284+806LHS No work Total 3 Grade Separator 5 4 Nos. is in Progress (substructure work at three Grade Separator are completed) 4 ROB 4 Not started yet No work 5 VUP 19 10 Nos. is in Progress No work 6 PUP 11 1No. completed(except finishing) and 4 Nos. in No work progress 7 Box Culvert 70 58Nos. is in Progress No work 8 H.P. Culvert 119 92Nos. is in Progress No work 9 RE Works 2,00,000 sqm 26217 sqm No work Activities of PIU:- 3. Land Acquisition Status:(i) Hectarage by details of land for this project is as under:- Total land required - 925 Hec. Land available - 501.49 Hec. Balance to be acquired - 425 Hec. 3D notified - 425 Hec. 3G (Award ) - 344.483 Hect Govt land where no award needed - 62.110Hect. Total Land Awarded(344.483+62.110) - 406.593Hect % of land available 501.49+406.593=908.083/925 - 98.17% (ii) Status Of Compensation District Bareilly S,jhanpur Chainage 262288Km length Kheri Hardoi sitapur G Total 288-343Km 343-358 &366-377KM 357365.6Km 377.2413.2KM 262-413.6Km 26 Km 55Km 26.2Km 8.0Km 36.0Km 151.200Km Land (Hects) 40.22 115.27 137.353 22.41 110.49 425.65 3G Award & 36.83+2.3 95.6484+1 96.825+23.22 22.41 92.77+17.6 406.593 Govt land (H) 7=40.22 7.78=113.4 =120.045 37=110.49 28 Cost of 13.23 Cr 41.94Cr 22.02Cr 7.48 Cr 20.30Cr 103.76Cr 12.09 Cr 17..48 Cr 14.0 Cr in 7.0 Cr 16.00 Cr 66.57 Cr 4.26Cr 8.72 Cr 41.40Cr Awarded land Amount Deposited By process PIU Amt Distr By 4.08Cr 10.81 Cr 13.52 Cr CALA 4- Tree Cutting: Name of District Bareilly Chainage Km 262.000 to Km 288.000 Shahjahanpur Kheri Hardoi Sitapur G.Total Km 288.000 toKm 343.000 Km 343.000 to Km 358.000 & Km 366.000 to Km 377.200 Km 357.800 to Km 365.600 Km 377.200 to Km 13.200 Km 262.000 to Km 13.200 Length 26.000 55.000 26.200 8.000 36.000 151.200 No. of trees affected (Total = 32,278) 7544 13237 3646 941 6910 32278 Tree Cutting Upto Date 6842 13219 3,170 941 6,708 30880 Balance Trees for cutting 702 18 476 0 202 1398 Note:- The tree cutting work has been completed in about 24 km length in Bareilly, 55 km length in Shahjahanpur district, 22 km length in Kheri, Full 08 km length in Hardoi & 36 km length in Sitapur district. Total – 145 Km. 30880 numbers of trees has been cut against the total of 32,278 to be cut. The balance No of trees to be cut is 1398 nos. 5. STATUS OF MAINTENANCE: The Concessionaire is repairing the potholes with bituminous material. Out of total 151.2 kms length, potholes in 112.7kms are required to be filled as in rest length either two lane DBM-I is available on one side (26.5 kms) or the carriageway has been repaired by Authority in towns in 12 kms length. Out of total 112.7 kms, appx 100 kms length has been repaired till date. In the stretch repaired as above the Concessionaire has left many small potholes. Also the approaches of the diversions have not been repaired. In the month of Dec 2013, the Concessionaire has submitted detailed maintenance work programme according to which they agreed to execute following works: i. Pot hole repair =24555sq. ii. Resurfacing by Overlay = 18.6 Kms iii. Repair of Earthen Shoulder = 126 Kms. However the Concessionaire has taken up only Pot hole repair work. They have not shown any intention to carry out the work of overlay and earthen shoulders. CHAINAGE WISE MAINTENANCE Maintenance completed stretch Maintenance with SDBC Maintenance 2 with SDBC Maintenance 3 with SDBC Maintenance 4 with SDBC Maintenance 5 with SDBC Maintenance 6 with SDBC Total Completed 1 262+000 275+000 13KM Completed 280+000 293+000 13KM Completed 296+000 304+000 8KM Completed 307+000 327+000 20KM Completed 336+000 339+900 3KM Completed 354+000 419+000 65KM Completed 122KM 6. MATERIAL REQUIREMENTS MATERIAL REQUIREMENT AS ON DATED 16THJUNE 2014 Sr. No Material UOM Total Materials Required Material consumed till 16thJune 2014 Balance to be procured 1 2 3 4 Cement Steel Coarse sand Aggregate 10 mm Bags MT MT MT 1604973 9936 112475 763674 787324 3511 28100 195636 817649 6425 84375 568038 5 6 7 8 9 Aggregate 20 mm Aggregate 40 mm Stone Dust GSB Bitumen MT MT MT MT MT 902697 438486 853584 1770117 51884 194341 85491 112570 301868 5399 708356 352995 741014 1468249 46485 7. STATUS OF UTILITY SHIFTING Sl No District UPCCL Division Estimated Amount Work done % of Progress 1 Bareilly Km 262.000 to Km 288.000 Bareilly 23052756 Nil 0% Tilhar 38843672 2 ShahjahanpurKm 288.000 to Km 343.000 Shahjahanpur City 31368064 37228685 34% Shahjahanpur Rural 39638255 3 Lakhimpur KheriKm 343.000 to Km 358.000 & Km 366.000 to Km 377.200 Lakhimpur Kheri 4 HardoiKm 357.800 to Km 365.600 Hardoi 5 SitapurKm 377.200 to Km 413.200 18525126 Over all 3261970.60 18% 5434244 Nil 0% 59230454 30761014 52% 33% Note:- Utility Shifting Revised Estimates Revised Estimates for left over Electric Items were reworked out at PIU in consultation with IE and Concessionaire rep for four Districts namely Bareilly, Hardoi, Khirie and Shahjhanpur. These were submitted to RO for his Approval. Revised Approval received on 31 Mar 14 . Revised Estimates for Sitapur District can only be submitted on assistance from Concessionaire. The delay on account of non shifting of Utility is squarely of Concessionaire. 8. MAIN COMMENTS OF CONCURRENT AUDITOR AND INTERNAL AUDIT Concurrent Auditor report from Apr 13 to Nov 13 as well as Internal Audit carried out in Dec 13 at PIU Bareilly has adversely commented upon both on Physical progress &Financial progress achieved by the Concessionaire . Major amount of Rs 206,33,17,314/ which is almost equivalent to Capital contribution of promoter has been passed on to EPC and still standing intact. Contrary to same Concessionaire has brought project to stand still for want of finances. This is a significant mismatch. Also, there is variation in Physical progress reported by IE ie 26.17% Vs 31.03% adjusted in accounts of Concessionaire. The same is serious breach of Agreement. 9. ROBs Test pile drawing of 318 / Structural drawing of 289 submitted to NR, Railways in July2013. Revised Estimates for three ROBs for approval of supervision charges by Railway Authorities submitted to Rly Auth Moradabad by Concessionaire through PIU letter 12051/7/2013/PIU Bareilly /2904 dt 07 Dec 13. Actual Construction of ROBs would require minimum 2 to 3 yrs. Concessionaire has shown some interest and has liaised with railway authority at Moradabad. Approximately 13 Lakhs supervision charges being deposite by him. CONCESSIONAIRE’s REPORT:- 20 JUN 14