Tower Crane WG FINAL proposal for review to send to NETWORK

advertisement
May 15, 2013
PROPOSED CHANGES TO ONTARIO REGULATION 213/91, CONSTRUCTION PROJECTS, UNDER THE OCCUPATIONAL HEALTH AND SAFETY ACT
FOR IMPROVING TOWER CRANE SAFETY
AS RECOMMENDED BY THE TOWER CRANE REGULATION REVIEW WORKING GROUP
CURRENT REQUIREMENT IN O. REG. 213/91
NO definition of “climbing”
PROPOSED CHANGES RELATED TO TOWER CRANES
NEW DEFINITION
“climbing” means the process in which a tower crane working on or
within a structure that is under construction, as the height of that
structure increases, the tower crane is raised to a new working
height by changing the elevation of the crane superstructure and
includes top-climbing, bottom-climbing, internal climbing and
telescoping.
NO definition of “mobile crane”
NEW DEFINITION
“mobile crane” means a mechanical device or structure that
incorporates a boom that,
(a) Is capable of moving in the vertical and horizontal plane,
(b) Is capable of raising, lowering or moving a load suspended from
the boom by a hook or rope, and
(c) Is mounted on a mobile base or chassis,
RATIONALE/COMMENT RE: PROPOSED CHANGES

A proposed definition of “climbing” is being added and is a
combination of the definitions from the CSA standard Z248-04,
Code for Tower Cranes, and the United States Occupational
Safety and Health Administration (OSHA) Regulations.

The term “extending” a tower crane (terminology currently
used in section 154 of the Construction Regulation) which has
traditionally meant external “top-climbing” of a tower crane, is
being replaced with “climbing” (as defined) to avoid confusion
over the different types of “climbing”.
A proposed definition of “mobile crane” is being added,

consistent with the one in O. Reg. 275/11, Scope of Practice –
Trades in the Construction Sector, under the Ontario College of
Trades and Apprenticeship Act, 2009,
 to clarify when particular requirements apply specifically to
mobile cranes and not to other types of cranes e.g. operator
qualifications specified under the OCTAA.
and includes a telescoping or articulated boom but does not include
equipment that is used exclusively for fire-fighting or by automotive
wreckers and tow trucks to clear wrecks and haul vehicles.
NO definition of “self-erecting tower crane”

NEW DEFINITION
“self-erecting tower crane” means a tower crane that is capable of
being erected without the use of ancillary equipment.
1
A proposed definition of “self-erecting tower crane” is being
added for clarity and comes from the CSA standard Z248-04,
Code for Tower Cranes.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
“tower crane” means a travelling, fixed or climbing mechanical
device or structure that has,
(a) a boom, a jib or both,
(b) a power-driven drum and wire rope to raise, lower or
move material, and
(c) a vertical mast;
PROPOSED CHANGES RELATED TO TOWER CRANES
“tower crane” means a travelling, fixed or climbing mechanical
device or structure that is of the travelling, fixed or climbing type
and that has,
(a) a boom, a jib or both,
(b) a power-driven drum and wire rope to raise, lower or move
material, and
(b) a vertical mast or tower.
11. (1) The following incidents are prescribed for the
purpose of section 53 of the Act:
11. (1) The following incidents are prescribed for the
purpose of section 53 of the Act:
1. A worker falling a vertical distance of three metres or more.
UNCHANGED EXCEPT FOR ADDITION OF ITEM 12.
2. A worker falling and having the fall arrested by a fall arrest
system other than a fall restricting system.
3. A worker becoming unconscious for any reason.
4. Accidental contact by a worker or by a worker’s tool or
equipment with energized electrical equipment, installations
or conductors.
5. Accidental contact by a crane, similar hoisting device,
backhoe, power shovel or other vehicle or equipment or its
load with an energized electrical conductor rated at more
than 750 volts.
6. Structural failure of all or part of falsework designed by, or
required by this Regulation to be designed by, a professional
engineer.
7. Structural failure of a principal supporting member, including a
column, beam, wall or truss, of a structure.
8. Failure of all or part of the structural supports of a scaffold.
9. Structural failure of all or part of an earth- or water-retaining
structure, including a failure of the temporary or permanent
supports for a shaft, tunnel, caisson, cofferdam or trench.
10. Failure of a wall of an excavation or of similar earthwork with
2
RATIONALE/COMMENT RE: PROPOSED CHANGES

Current definition of “tower crane” is revised slightly for clarity.

The term “tower crane” includes a self-erecting tower crane
regardless of its lifting capacity.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
respect to which a professional engineer has given a written
opinion that the stability of the wall is such that no worker will
be endangered by it.
11. Overturning or the structural failure of all or part of a crane or
similar hoisting device.
17. (1) A constructor shall establish for a project written
procedures to be followed in the event of an emergency and shall
ensure that the procedures are followed at the project.
12. Accidental or uncontrolled movement of a load or part of a load
or any failure of rigging suspended from a tower crane.
17. (1) A constructor shall establish for a project written
procedures to be followed in the event of an emergency and shall
ensure that the procedures are followed at the project.
NEW (1.1) If the emergency procedures include the use of a
tower crane to move a worker or workers in a platform, basket,
stretcher or other rescue device suspended from the crane, the
requirements of (NEW) ss.153.1 shall be met.
(2) The constructor shall review the emergency
procedures with the joint health and safety committee or the
health and safety representative for the project, if any.
(2) The constructor shall review the emergency procedures
with the joint health and safety committee or the health and safety
representative for the project, if any.
(3) The constructor shall ensure that the emergency
procedures are posted in a conspicuous place at the project.
(3) The constructor shall ensure that the emergency
procedures are posted in a conspicuous place at the project.
102. No operator shall leave unattended the controls of,
RATIONALE/COMMENT RE: PROPOSED CHANGES
NEW Item 12 – A new incident is added for which a constructor
would have to provide a written report to the Ministry and to a Joint
Health and Safety Committee, health and safety representative or
trade union, if any, within 2 days of the incident, setting out the
circumstances of the occurrence and the steps taken to prevent a
recurrence. There appears to be a recent increased incidence of
suspended loads being dropped by cranes. Such incidents can
have catastrophic results on workers and property. This addition
would provide the Ministry an opportunity to follow up on particular
incidents to determine whether they involved any violations of the
Construction Regulation.
New ss.(1.1) – If a decision is made by the constructor and tower
crane employer that the tower crane on a project could be used if
necessary in the event of an emergency situation to rescue a
worker from an elevated position on the building or structure under
construction, then that must be clearly indicated in the emergency
procedures and appropriate details provided. The constructor and
employer would have to ensure that the tower crane and platform,
basket, stretcher or other rescue device used to rescue a worker
meet the requirements in NEW subsection 153.1.
102. No operator shall leave unattended the controls of,
(a) a front-end loader, backhoe or other excavating machine with
its bucket raised;
(a) a front-end loader, backhoe or other excavating machine
with its bucket raised;
(b) a bulldozer with its blade raised;
(b) a bulldozer with its blade raised;
(c) a fork-lift truck with its forks raised; or
(c) a fork-lift truck with its forks raised; or
(d) a crane or other similar hoisting device with its load raised.
(d) subject to s.164, a crane or other similar hoisting device with
its load raised.
3
A cross reference to section 164 is added. S.64 is being changed
to allow a load to be suspended from an unattended tower crane
only if specified by the crane manufacturer.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
Amended March 2013, came into effect April 8, 2013 to align
with the Ontario College of Trades and Apprenticeship Act,
2009 coming into effect on the same date.
150. (1) Subject to subsection (2), no worker shall operate
a crane or similar hoisting device unless the worker holds a
certificate of qualification issued under the Ontario College of
Trades and Apprenticeship Act, 2009, that is not suspended, or
the worker is an apprentice and is working pursuant to a training
agreement registered under that Act, that is not suspended, in
the trade of,
(a) hoisting engineer — mobile crane operator 1, if the worker is
operating a crane or similar hoisting device capable of
raising, lowering or moving any material that weighs more
than 30,000 pounds;
(b) hoisting engineer — mobile crane operator 1 or hoisting
engineer — mobile crane operator 2, if the worker is
operating a crane or similar hoisting device capable of
raising, lowering or moving only material that weighs more
than 16,000 pounds but no more than 30,000 pounds; or
PROPOSED CHANGES RELATED TO TOWER CRANES
150. (1) Subject to subsections (1.2) and (2), no worker shall
operate a mobile crane or tower crane or similar hoisting device
unless the worker holds a certificate of qualification issued under the
Ontario College of Trades and Apprenticeship Act, 2009, that is not
suspended, or the worker is an apprentice and is working pursuant
to a training agreement registered under that Act, that is not
suspended, in the trade of,
(a) hoisting engineer — mobile crane operator 1, if the worker is
operating a crane or similar hoisting device capable of raising,
lowering or moving any material that weighs more than 30,000
pounds;
RATIONALE/COMMENT RE: PROPOSED CHANGES
Section 150 is revised to clarify that the operator qualifications
specified under the Ontario College of Trades and Apprenticeship
Act, 2009 apply only to operators of mobile cranes and tower
cranes and not to any other types of cranes or hoisting devices.
(b) hoisting engineer — mobile crane operator 1 or hoisting engineer
— mobile crane operator 2, if the worker is operating a crane or
similar hoisting device capable of raising, lowering or moving
only material that weighs more than 16,000 pounds but no more
than 30,000 pounds; or
(c) hoisting engineer — tower crane operator, if the worker is
operating a tower crane.
(c) hoisting engineer — tower crane operator, if the worker is
operating a tower crane.

NEW (1.1) Subject to subsection (1.2), an apprentice operating a
tower crane shall be constantly monitored during the operation
of the crane by a person who:
(i)
meets the requirements of ss.(1)(c),
(ii)
is in direct audio communication with the apprentice,
(iii)
is not engaged in performing other work while
monitoring the apprentice who is operating the crane, and
(iv)
is able to direct the apprentice during the operation
of the crane.
1.1) Subsection (1) does not apply when a worker is using
excavation equipment to place pipes into a trench.
4
In NEW subsection 150(1.1),
o
The monitor would not have to be in constant
visual contact of the apprentice operator since there may
be situations when their views of each other are blocked
by objects/structures on the construction site during the
movement of a load by the crane.
o The term “during the operation of the crane” means while
the apprentice is manipulating the controls of the crane
and the controls are “ON”. The intent is for the monitor to
be able to tell the apprentice to immediately stop the
operation at any point should an unsafe situation develop.
o The reference to “not engaged in performing other work” in
paragraph (iii) would allow the monitor to do work related
to the hoisting operation e.g. guiding a load being moved
or unhooking a load placed by the apprentice.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(1.1) Subsection (1) does not apply when a worker is
using excavation equipment to place pipes into a trench.
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES

Deleting existing subsection (1.1) does not change the current
intent or implementation of the requirement. Subsection (1.1) is
deleted because the Ministry has determined that excavation
equipment used to place pipes into a trench is not a crane or a
hoisting device similar to a crane, and section 150 is being
changed so it would no longer apply to “similar hoisting device”
i.e. it would only apply to mobile and tower cranes.

The NEW subsection (1.2) would make it mandatory for
operators of self-erecting tower cranes to have completed the
MTCU training programs for self-erecting tower cranes
released in 2009. The specific titles and identifying numbers of
the training programs are not included in the Regulation as they
may be updated/changed at any time by MTCU.
New (1.2) An operator of a self-erecting tower crane,
(a) rated more than 40 metre tonnes, shall hold a certificate of
qualification issued under the Ontario College of Trades and
Apprenticeship Act, 2009, that is not suspended in the trade of:
(i)
hoisting engineer — mobile crane operator 1, or
(ii)
hoisting engineer — tower crane operator, and
(b) rated up to and including 40 metre tonnes, shall hold a
certificate of qualification issued under the Ontario College of
Trades and Apprenticeship Act, 2009, that is not suspended in
the trade of:
(i)
hoisting engineer — mobile crane operator 1, or
(ii)
hoisting engineer — mobile crane operator 2, or
(iii)
hoisting engineer — tower crane operator, and
(c) shall have successfully completed the relevant modular training
standard developed and administered by the Ministry of
Training, Colleges and Universities for self-erecting tower crane
operator.
(2) No worker shall operate a crane or similar hoisting device,
other than one described in subsection (1), unless,
(a) the worker has written proof of training indicating that
he or she is trained in the safe operation of the crane
or similar hoisting device; or
(b) the worker is being instructed in the operation of the
crane or similar hoisting device and is accompanied by
a person who meets the requirements of clause (a).
(3) A worker shall carry his or her proof of training while
operating a crane or similar hoisting device.
(2) No worker shall operate a crane, other than one described in
subsection (1), or similar hoisting device unless,
(a) the worker has written proof of training indicating that he or she
is trained in the safe operation of the crane; or
(b) the worker is being instructed in the operation of the crane or
similar hoisting device and is accompanied by a person who
meets the requirements of clause (a).
(3) A worker shall carry his or her proof of training, or qualification
issued under the Ontario College of Trades and Apprenticeship Act,
2009, while operating a crane or similar hoisting device.
5
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
151. (1) No crane or similar hoisting device shall be
subjected to a load greater than its rated load-carrying capacity.
(2) The manufacturer of a crane or similar hoisting device
or a professional engineer shall determine its rated load-carrying
capacity in accordance with,
(a) for a mobile crane, Canadian Standards Association
Standard Z150-1974 Safety Code for Mobile Cranes;
and
(b) for a tower crane, Canadian Standards Association
Standard Z248-1976 Code for Tower Cranes.
(3) Every crane or similar hoisting device shall have
affixed to it a load rating plate,
(a) that the operator can read while at the controls; and
(b) that contains enough information for the operator to
determine the load that can be lifted for each
configuration of the crane.
(4) A luffing boom crane, other than a tower crane, shall
have affixed to it a boom angle indicator that the operator can
read while at the controls.
152. (1) The owner of a crane or similar hoisting device
shall keep a permanent record of all inspections of, tests of,
repairs to, modifications to and maintenance of the crane or
similar hoisting device.
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
151. (1) No crane or similar hoisting device shall be subjected to a
load greater than its rated load-carrying capacity.
(2) The manufacturer of a mobile crane or tower crane or similar
hoisting device or a professional engineer shall determine its rated
load-carrying capacity in accordance with, as appropriate,
a) for a mobile crane, Canadian Standards Association Standard
Z150-1974 Safety Code for Mobile Cranes; and

ss.(151(2) – The revision is necessary since the referenced
CSA standards apply only to mobile cranes and tower cranes
and not to “similar hoisting devices”.
(b) for a tower crane, Canadian Standards Association Standard
Z248-1976 Z248–04, Code for Tower Cranes.
(3) Every crane or similar hoisting device shall have affixed to it a
load rating plate chart,

ss.(3) – The existing term, “load rating plate” is replaced with
the term, “load rating chart” for consistency with the CSA
standard Z248-04, Code for Tower Cranes. This same
editorial change is made throughout the regulation to ensure
consistency and would apply to all cranes. This revision would
not change the existing intent or interpretation of the
requirements.

ss.(4) - Deleting “other than a tower crane” means all luffing
boom cranes, including luffing tower cranes, would need to
have a boom angle indicator. This change reflects the
changing technology of tower cranes since the initial
introduction of this requirement in the Regulation. Industry
experience indicates most new luffing tower cranes have
digital boom angle indicators at the operator’s controls. Older
cranes that do not have boom angle indicators may need to
have them retrofitted in order to comply with this requirement.

Section 152 is revised based on CSA standard Z248-04, Code
for Tower Cranes, Clause 6.2, to provide clarity regarding the
creation and maintenance of the machine history of a crane
and the crane’s log book. Although section 152 applies
generally to any crane and not just to tower cranes, the Tower
(a) affixed to it which the operator can read while at the controls of
the crane;
(b) (NEW) with the operator of the crane if the crane is operated by
remote control; and
(c) that contains enough information for the operator to determine
the load that can be lifted for each configuration of the crane.
(4) A luffing boom crane, other than a tower crane, shall have
affixed to it a boom angle indicator that the operator can read while
at the controls of the crane.
152. (1) The owner of a crane or similar hoisting device shall
keep a permanent written record of all inspections of, tests of,
repairs to, modifications to and maintenance performed on the
crane. or similar hoisting device.
6
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
(1.1) NEW The permanent written record referred to in
subsection (1) shall:
(a) include the names and signatures of the persons who
performed the inspections of, tests of, repairs to, modifications to
and maintenance on the crane and the dates on which these were
performed; and
(b) be considered a permanent part of a crane that is to be
transferred to each subsequent new owner of the crane.
(2) The owner of a crane or similar hoisting device shall
prepare a log book for it for use at a project that shall include the
record referred to in subsection (1) covering the period that is the
greater of,
(a) the immediately preceding twelve months; and
(b) the period the crane or similar hoisting device is on
the project.
(2) (a) The owner of a crane or similar hoisting device shall
prepare a log book for the crane or similar hoisting device while it is
at a project.
(b) The log book shall include the written record referred to in
subsection (1) for the crane covering at least the twelve months
immediately preceding the project.
(2.1) NEW
(a) For the duration of the project, the log book shall
permanently record all inspections of, tests of, repairs to,
modifications to and maintenance performed on the crane or similar
hoisting device; and
(3) The log book shall be kept with the crane or similar
hoisting device.
(b) The log book referred to in clause (a) shall include the
names and signatures of the persons who performed the inspections
of, tests of, repairs to, modifications to and maintenance on the
crane and the dates on which these were performed.
(3) The log book shall be kept with the crane or similar
hoisting device while the crane or similar hoisting device is on the
project and shall be made available to an inspector upon request.
(3.1) NEW The record of all inspections of, tests of, repairs to,
modifications to and maintenance performed on the crane or similar
hoisting device referred to in subsection (2.1) shall be transferred
from the log book to the owner’s permanent written record referred
to in subsection (1).
7
RATIONALE/COMMENT RE: PROPOSED CHANGES
Crane Regulation Review Working Group would like to
recommend that industry consider these proposed
requirements for all cranes and not just tower cranes. The
revisions would not impose new obligations but would simply
clarify in regulation what is routinely currently done in practice
with respect to crane inspection/maintenance records by crane
owners and crane users/operators while a crane is on a
project.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
(4) The owner of a crane or similar hoisting device shall retain
and make available to the constructor on request copies of all log
books and records for the crane or similar hoisting device.
(4) The owner of a crane or similar hoisting device shall retain and
make available on request to the constructor, inspector or other
person involved in the inspections of, tests of, repairs to,
modifications to and maintenance performed on the crane or similar
hoisting device copies of the log book and all written records for the
crane or similar hoisting device referred to in subsection (1).
153. (1) No worker shall use as a workplace a platform,
bucket, basket, load, hook, sling or similar device that is capable
of moving and is supported by a cable attached to the boom of a
crane or similar hoisting device, except in accordance with this
section.
153. (1) Subject to ss. 153.1, no worker shall use as a
workplace a platform, bucket, basket, load, hook, sling or similar
device that is capable of moving and is supported by a cable
attached to the boom of a crane or similar hoisting device, except in
accordance with this section.
(2) A crane may be used to raise, support or lower a
worker only if,
only if,
RATIONALE/COMMENT RE: PROPOSED CHANGES
ss.(4) - New requirement is added for the crane owner to provide,
upon request, copies of all written records related to the tests,
inspections, repairs, modifications and maintenance performed on
a crane to a Ministry inspector or other person involved in any of
the above listed activities e.g. professional engineer inspecting the
crane, mechanic/technician servicing the crane. Currently, the
crane owner only has to provide the information to the constructor
on a project. Professional engineers would need to refer to these
records in order to comply with engineers’ expanded inspection
requirements for tower cranes proposed in sections 158, 159, and
159.1.
Although section 153 applies generally to any crane and not just to
tower cranes, the Tower Crane Regulation Review Working Group
would like to recommend that industry consider this proposed
requirement for all cranes.
(2) A crane may be used to raise, support or lower a worker
(a) conventional access equipment cannot be used;
(a) UNCHANGED;
(b) the platform that the worker is on,
(b) UNCHANGED EXCEPT WHERE NOTED BELOW
(i) is designed by a professional engineer in
accordance with good engineering practice,
(ii) is constructed in accordance with the design
drawings,
(iii) is equipped with more than one means of
suspension or support,
(iii) is equipped with more than one means of suspension or support,
or is attached to the load block of the crane by a secondary means
of suspension,
(iv) is equipped with anchor points for the attachment of
the worker’s fall arrest systems,
8
ss.153(2)(b)(iii) – The revision is proposed by the Ministry, and is
meant to clarify the current requirement, provide more compliance
flexibility and codify in Regulation a common industry practice used
to comply with the requirement.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(v) is equipped with a guardrail in accordance with
section 26.3,
(vi) is suspended from, or supported by, a direct
attachment to the boom of the crane,
(vi) is suspended from the boom or supported by a direct
attachment to the boom of the crane,
ss.153(2)(b)(vi) - The minor revision is proposed by the Ministry,
and is meant to clarify the current requirement and does not
change the current intent of the requirement.
(iv)
Paragraph (2)(c)(iv) - The minor revisions are proposed by the
Ministry, and are meant to clarify the current requirement and do
not change the current intent of the requirement A revised load
rating chart must be specifically prepared for the hoisting of workers
on a platform, incorporating the provision for the crane not to be
loaded in excess of 25% of its maximum rated load, thereby
unambiguously providing the necessary information to an operator
to hoist workers safely. Crane operators would have to be informed
about and would have to use the revised load rating chart
whenever hoisting workers.
(vii) is designed, constructed and maintained so that
the failure of one means of support or suspension
will not cause the collapse of all or part of the
platform, and
(viii) has its maximum rated load capacity legibly and
permanently marked in a conspicuous place on
it; and
(c) the crane,
(i) is equipped with fail-safe mechanisms that will
prevent the boom and the suspended platform from
free falling in the event of a power source or
system failure or the inadvertent release of any
operating controls,
(ii) is not used to hoist material while the platform is
being used to support a worker,
(iii) is not loaded in excess of 25 per cent of its
maximum rated load,
(iv) has a revised load rating chart prepared by a
professional engineer in accordance with good
engineering practice and affixed in a conspicuous
place on the crane,
(v) has, on its hoist line, hooks equipped with selfclosing safety catches at the point where the
platform is suspended, and
(vi) is equipped with an automatic limit switch that
prevents the platform and load from reaching
beyond the highest permissible position specified
by the crane manufacturer.
has a revised load rating chart

prepared by a professional engineer in accordance with
good engineering practice taking into consideration the
load restriction in paragraph (iii), and

that is affixed in a conspicuous place on the crane made
available to the crane operator prior to the commencement
of the hoisting operation,
9
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(3) Any modifications or repairs to the boom of the crane
shall be made in accordance with the instructions of the crane
manufacturer or a professional engineer.
(4) Every worker on the platform shall wear a full body
harness connected independently to anchor points on the
platform and used in conjunction with a lanyard fitted with a
shock absorber.
(5)
The design drawings of the platform shall,
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(3) UNCHANGED;
(4) UNCHANGED;
(5) UNCHANGED;
(a) set out the size and specifications of all components
of the platform, including the type and grade of
materials used for it;
(b) state the maximum live load of the platform;
(c) specify the model and type of crane to be used in
conjunction with the platform; and
(d) include a statement that, in the opinion of the
professional engineer who designed the platform,
the design meets the requirements of clauses (a), (b)
and (c).
(e) Revoked.
(6) Before the platform is used, a competent worker shall
inspect it and verify in writing that it has been constructed in
accordance with the design drawings.
(6) UNCHANGED;
(7) UNCHANGED;
(7) No person shall use the platform until the verification
required under subsection (6) is given.
(8) A professional engineer or a competent worker
designated by the professional engineer shall inspect the crane
to ensure its structural integrity using non-destructive testing
methods approved by the Canadian General Standards Board
before the crane is used to lift persons and then at least once
every 12 months after that.
(8) (a) A professional engineer or a competent worker designated
by the professional engineer shall inspect the crane, except a tower
crane, to ensure its structural integrity using non-destructive testing
methods approved by the Canadian General Standards Board
before the crane is used to lift persons and then at least once every
12 months after that;
(b) (i) (NEW) The inspection of structural components shall include
methods of non-destructive testing recognized by the
CAN/CGSB 48.9712-2006, Non-destructive Testing –
10
ss.153(8) – The current wording in the Regulation incorrectly refers
to the Canadian General Standards Board (CGSB) i.e. the CGSB
does not approve any methods of non-destructive testing (NDT) –
rather, it specifies the qualifications and certification of persons
involved in NDT. The changes are proposed by the Ministry to
correct this historical drafting error and do not change the existing
intent or implementation of the requirement.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
Qualification and Certification of Personnel standard; and
(9) A competent worker shall visually inspect the crane’s
structural elements and the rigging equipment for defects before
each use of the crane.
(10) The employer shall ensure that an adequate means
of communication between the worker on the platform and the
crane operator is established, maintained and used.
(11) Before beginning any hoisting operation under this
section, the constructor shall notify by telephone an inspector in
the office of the Ministry of Labour nearest to the project.
(12) The employer shall ensure that every worker involved
with the hoisting operation receives adequate instructions about
the requirements, restrictions and hazards associated with the
hoisting operation.
(13) The employer shall develop adequate emergency
rescue procedures and communicate these in writing to all
workers involved with the hoisting operation.
(14) The constructor shall keep all design drawings, test
reports, written statements and certification documents required
under this section with the crane at all times during the hoisting
operation.
(15) On request, the constructor shall provide an inspector
with copies of any document described in subsection (14).
(ii) (NEW) the non-destructive testing, and interpretation and
evaluation of testing results, shall be conducted by a person
certified in accordance with CAN/CGSB 48.9712-2006, Nondestructive Testing – Qualification and Certification of
Personnel standard.
(8.1) NEW
(8.1) (a) If the crane is a tower crane, a professional engineer shall
inspect the structural, electrical, mechanical and hydraulic
components and systems of the tower crane and shall test the
crane’s control systems in accordance with the Practice Standard for
Tower Crane Review developed by the Professional Engineers of
Ontario.
(b) (i) The inspection of structural components shall include methods
of non-destructive testing recognized by the CAN/CGSB
48.9712-2006, Non-destructive Testing – Qualification and
Certification of Personnel Standard; and
(ii)
the non-destructive testing, and interpretation and evaluation of
testing results, shall be conducted by a person certified in
accordance with CAN/CGSB 48.9712-2006, Non-destructive
Testing – Qualification and Certification of Personnel standard.
NEW Ss.153(8.1) – If a tower crane is to be used to hoist a worker
on a man basket or platform, an engineer must inspect more than
just the structural components of the crane prior to the crane
hoisting a worker i.e. the engineer must inspect the same items as
noted in revised s.159 in accordance with the Practice Standard for
Tower Crane Review developed by the Professional Engineers of
Ontario (PEO) in consultation with the Tower Crane Regulation
Review Working Group rather than “good engineering practice”.
The Practice Standard is meant to guide professional engineers in
their inspections of tower cranes (see sections 158 and 159 for fully
explanation). A tower crane that complies with the proposed s.158
and s.159 (inspected by an engineer before and after its erection
and at least every 12 months after that) would be considered in
compliance with the inspection requirement in ss.153(8.1).
Ss.(9) – (15) REMAIN UNCHANGED
153.1 (NEW) Where a tower crane is used to move a worker or
workers in an emergency operation, the following requirements shall
be met:
(a) the emergency procedures required under s.17 involving a tower
crane shall be approved by a professional engineer prior to the
tower crane being put into service on a project;
(b) the platform, basket, stretcher or other rescue device shall:
11
The new section 153.1 sets out the requirements when a tower
crane is to be part of a constructor’s emergency procedures for a
project (as required in section 17) and is intended to be used to
hoist workers in some kind of platform, basket, stretcher or rescue
device in the event of emergencies. The proposed requirements in
ss.(d)(e)(f)(h)(i) mirror similar current requirements in ss.153(9) to
(15) ss.(g) has a new inspection requirement. However, the
constructor would NOT have to notify the Ministry prior to an
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
(i) comply with ss.153(2)(b) and (5); OR
(ii) if it is not practicable to comply with ss.153(2)(b),
1. be designed and approved by a professional engineer to
be adequate to move a person or persons in a safe
manner;
2. have design drawings in accordance with ss.153(5);
3. be suspended from, or supported by the boom of the
crane; and
4. in addition to item 3 above, be attached to the load block
of the crane by a secondary means of suspension;
(c) the tower crane shall comply with ss.153(2)(c);
(d) the employer shall develop adequate emergency rescue
procedures and communicate these in writing to all workers to
be involved in an emergency hoisting operation;
(e) the employer shall ensure that every worker involved in the
emergency hoisting operation receives adequate instructions
about the requirements, restrictions and hazards associated with
the operation;
(f) the employer shall ensure that an adequate means of
communication between the worker or workers on the platform,
basket, stretcher or other rescue device and the tower crane
operator is established, maintained and used during an
emergency hoisting operation;
(g) the platform, basket, stretcher or other rescue device shall be
inspected by a competent person at least once a week or more
frequently as determined by the constructor or by the supervisor
appointed by the constructor to ensure the platform, basket,
stretcher or other rescue device is maintained in good condition
and is ready for immediate use during an emergency;
(h) the constructor shall keep all design drawings for the platform,
basket, stretcher or other rescue device, and the written
emergency rescue procedures with the crane at all times during
an emergency hoisting operation; and
12
RATIONALE/COMMENT RE: PROPOSED CHANGES
emergency hoisting operation (as is currently required for nonemergency hoisting operations under ss.153(11).
Although the new section as currently drafted would apply only to
tower cranes, the Tower Crane Regulation Review Working Group
recommends that it apply to any crane that is to be used to hoist
workers in the event of emergencies.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(i) on request, the constructor shall provide an inspector with
copies of design drawings and emergency rescue procedures
described in paragraph (h).
154. (1) A crane or similar hoisting device shall be set up,
assembled, extended and dismantled only by a competent
worker acting in accordance with the written instructions of the
manufacturer and in such a manner as to not endanger any
person or property.
154. (1) A crane or similar hoisting device shall be set up,
assembled, extended climbed and dismantled only by a competent
worker acting in accordance with the written instructions of the
manufacturer and in such a manner as to not endanger any person
or property.
(2) No crane or similar hoisting device shall include
sections that are not designed for it or that are damaged.
(2) No crane or similar hoisting device shall include sections
that are not designed for it or that are damaged.
(3) No crane or similar hoisting device shall include nuts, bolts,
pins or fastenings that are not the size and quality specified by
the manufacturer.
The term “extended” is being replaced with “climbed”. A new
definition of “climbing” is also being added to avoid confusion
regarding the different types of “climbing” that may be
performed on tower cranes e.g. “extending” a tower crane has
traditionally meant only “top climbing” of a tower crane.

A new ss.(4) is being added to specifically address a common
safety concern related to the use of all cranes. Although the
proposed requirement would apply only to tower cranes, the
Tower Crane Regulation Review Working Group recommends
that it apply to any crane.
(3) No crane or similar hoisting device shall include nuts, bolts, pins
or fastenings that are not the size and quality specified by the
manufacturer.
(4) NEW – Every portable or removable counterweight, test block
and ballast used on a tower crane must be accurately weighed and
its weight must be clearly and durably marked on the counterweight,
test block and ballast.
155. Unless otherwise specified by its manufacturer, a
crane or similar hoisting device,

155. UNCHANGED
(a) shall be equipped with a device to indicate whether its
turntable is level; and
(b) shall be operated with its turntable level.
13
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
156. An outrigger or stabilizing device used on a crane or
similar hoisting device,
(a) shall be extended to meet load capacity chart
requirements; and
(b) shall rest on blocking able to support the crane or
similar hoisting device and its maximum load without
failure or without deformation or settlement which
affects its stability.
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
156. An outrigger or stabilizing device used on a crane or similar
hoisting device,
(a) shall be extended to meet load capacity rating chart
requirements; and
(b) shall rest on blocking able to support the crane or similar
hoisting device and its maximum load without failure or without
deformation or settlement which affects its stability.
14

The term “load rating chart” rather than “load capacity chart” is
to be used throughout the Regulation to ensure consistency
with CSA Z248-04, Code for Tower Cranes which uses the
term “load rating chart”.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
TOWER CRANES
156.1
NEW – NOTIFICATION
(1) The constructor shall complete an approved notification form and
file it at the Ministry office located nearest to the project:
(a) At least seven (7) days prior to the tower crane, excluding
any self-erecting tower crane, being placed into service on
the project; and
(b) At least seven (7) days prior to the tower crane, excluding
any self-erecting tower crane, being dismantled.
This new requirement is being added at the Ministry of Labour’s
direction. To facilitate compliance, the Ministry would develop a
notification form (paper and electronic) that a constructor would be
able to mail (by conventional or electronic means), fax or deliver in
person to the ministry office located nearest to the project.
(2) The notification shall specify the:
(a) the address of the project at which the tower crane is to be
operated/used;
(b) name and address of the tower crane owner/supplier
(lessor);
(c) make, model and serial number of the tower crane to be
operated/used; and,
(d) date of erection and dismantling of the tower crane.
(3) The constructor shall keep the completed notification form
posted in a conspicuous place at the project or available at the
project for review by an inspector until the crane is dismantled.
156.2
NEW – DESIGN
After the amendments come into effect (DATE to be specified),
(1) a tower crane that is being put into service in Ontario for the first
time,
(a) shall be designed and manufactured in accordance with the
European standard EN 14439:2006 or EN 14439:2009, Cranes
– Safety – Tower Cranes;
15
New design specifications for tower cranes are being added,
supported by a revised and more rigorous inspection regime and
new verification process by engineers, to ensure tower cranes will
not endanger workers. As internationally manufactured tower
cranes are routinely designed to this European standard,
compliance with this new requirement is not expected to be
onerous with respect to cranes imported into Ontario after the new
requirements come into effect (if approved).
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(b) shall meet the requirements in the document, Electrical
Specification for Tower Cranes, ESA SPEC-00X-13, published
by the Electrical Safety Authority; and,
(c) shall have control equipment incorporating solid state devices, a
programmable logic controller and/or software systems in
operating and control circuit, designed and installed to meet
circuit performance classification that is control reliable meeting
category 3 or better in accordance with,
(i) ISO 13489-1, Safety of Machinery – safety related parts for
control systems, or
(ii) EN 954-1:1996, Safety of machinery – Safety-related part of
control systems – Part 1: General principles for design.
(2) After a SPECIFIED DATE, a tower crane, other than one
described in ss.(1), that is erected on a project,
(a) shall be designed and manufactured in accordance with CSAZ248-04; and,
ss.(2) - There would be an implementation period for owners of
cranes already in Ontario when the new proposed requirements
come into effect, to give owners time to make necessary
modifications to their cranes so they can comply with the design
requirements of CSA Z248-04, Code for Tower Cranes, as well as
the ESA’s Electrical Specification for Tower Cranes and the control
equipment requirements in ss.156.(1)(b) and (c).
(b) shall comply with the requirements in ss.(1)(b) and (c).
QUESTION TO INDUSTRY: How long should this
implementation period be e.g. 2 years? Industry is being
asked to provide feedback to the Provincial LabourManagement Health and Safety Committee on how much time
would be reasonable to give to crane owners to enable them to
bring their existing cranes into compliance with the new
design requirements.
Tower cranes in service on a project when the new proposed
requirements come into effect, would be allowed to continue to
operate. However, once their work is completed and they are
dismantled and removed from a project, they would also have to be
reviewed and brought into compliance with the new design
requirements.
16
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
QUESTION TO INDUSTRY: The regulation of tower cranes in
Europe has historically required more rigorous inspections of
older cranes. Anecdotal evidence indicates that crane owners,
rather than undergoing the expense of these rigorous
inspections, often sell their cranes instead which are
subsequently sometimes brought to Ontario. The Ministry’s
past tower crane blitzes indicated that many older cranes were
not being properly maintained and as a result, exhibited
defects. Industry is being canvassed for feedback whether
there is a need for more thorough inspections for older tower
cranes as well as after a tower crane undergoes a major
alteration.
1. Should tower cranes be required to undergo a more
thorough inspection than the annual inspection regime
specified in the Practice Standard for Tower Crane Review
developed by the Professional Engineers of Ontario after
they reach a certain age and/or after a major alteration
and/or after a serious defect has been identified?
1. What should be included in this more thorough
inspection?
2. What should be the minimum age of a crane before it
would be required to undergo a more thorough inspection
e.g. 10 yrs? 15 yrs?
3. How often should an older crane be required to undergo a
more thorough inspection e.g. every 3 yrs? 5 yrs?
4. What is meant by “a major alteration” and “serious
defect”?
17
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
TOWER CRANES
157. (1) No tower crane shall be erected at a project
except in accordance with this section.
(2) The foundations supporting a tower crane shall be
designed by a professional engineer in accordance with the
crane manufacturer’s specifications and shall be constructed in
accordance with the design.
(3) The shoring and bracing that support a tower crane or
tie it in place shall be designed by a professional engineer in
accordance with the crane manufacturer’s specifications and
shall be installed in accordance with the design.
157. (1) A tower crane, other than a rail-mounted tower crane, shall
be erected at a project in accordance with this section.
(2) The foundation or work surface supporting a tower crane shall be
designed by a professional engineer in accordance with the crane
manufacturer’s specifications and shall be constructed and installed
in accordance with the design drawings.
(3) The shoring and bracing that support a tower crane or tie it in
place,
(a) shall be designed by a professional engineer in accordance with
the crane manufacturer’s specifications and, if no such specifications
exist, in accordance with good engineering practice, and
(b) shall be constructed, installed and dismantled in accordance with
the design drawings.
(4) The structural engineer responsible for the structural
integrity of the building or structure shall review the design
drawings for the foundation, shoring and bracing for a tower
crane before the crane is erected at a project to ensure the
structural integrity of the building or structure.
(5) The structural engineer who reviews the design
drawings shall sign the drawings upon approving them.
(6) The constructor shall keep at the project while a tower
crane is erected a copy of the signed design drawings for its
foundation, shoring and bracing and any written opinion about the
drawings by a structural engineer.
(4) The structural professional engineer responsible for the
structural integrity of the building or structure shall review the design
drawings for the foundation, shoring and bracing for a tower crane
before the crane is erected at a project to ensure the structural
integrity of the building or structure.
(5) The structural professional engineer who reviews the design
drawings referred to in subsection (4) shall sign the drawings upon
approving them.
(6) The constructor shall keep at the project while a tower crane is
erected a copy of the signed design drawings for its foundation,
shoring and bracing and any written opinion about the design
drawings by a structural professional engineer.
18
ss.(1) – Rail-mounted tower cranes are addressed under s.165.
ss.(2) - The deletion of “in accordance with the crane
manufacturer’s specifications” in ss.(2) is necessary since a tower
crane manufacturer’s specifications and instructions do not address
the design and inspection of a crane’s foundation, shoring or
bracing.
ss.(2) – Since many self-erecting tower cranes are not erected on
foundations but on other solid material or bare ground, the term
“work surface” was added to ensure that whatever surface supports
a self-erecting tower crane, it is assessed by an engineer and
“designed” to support the crane in a safe manner.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
158. (1) Before a tower crane is erected at a project, a
professional engineer or a competent worker designated by a
professional engineer shall inspect its structural elements and
components using methods of non-destructive testing approved
by the Canadian General Standards Board to determine their
structural integrity.
PROPOSED CHANGES RELATED TO TOWER CRANES
158. (1) Before a tower crane, except a self-erecting tower crane, is
erected at a project, and before a self-erecting tower crane is
erected for the first time,
NEW
(a)
a professional engineer or a competent worker designated by a
professional engineer shall inspect its structural, electrical,
mechanical and hydraulic components and systems, and its
control systems, in accordance with the Practice Standard for
Tower Crane Review developed by the Professional Engineers
of Ontario, and identify any defects that may affect worker
health and safety,
(b) the inspection of structural components in clause (a) shall
include methods of non-destructive testing recognized by the
CAN/CGSB 48.9712-2006, Non-destructive Testing –
Qualification and Certification of Personnel standard; and
(2) The professional engineer conducting an inspection or
under whose direction an inspection is done shall prepare a
written report of the test results.
(c) the non-destructive testing, and interpretation and evaluation of
testing results, shall be conducted by a person certified in
accordance with CAN/CGSB 48.9712-2006, Non-destructive
Testing – Qualification and Certification of Personnel standard.
.
(2) The professional engineer conducting an inspection or under
whose direction an inspection is done shall prepare a written
report of the inspection and test results including confirmation
that all components are in adequate condition.
(3) NEW – No tower crane shall be used until:
(a) any defects identified in the inspection in subsection (1) that may
affect worker health and safety are corrected or repaired in
accordance with the instructions of the tower crane manufacturer or
a professional engineer,
(b) the tower crane has been inspected by a professional engineer
to confirm that the defects are corrected or repaired and that
the repaired components are in adequate condition; and
19
RATIONALE/COMMENT RE: PROPOSED CHANGES
A stronger inspection regime is being proposed for tower cranes.
Ministry of Labour’s past enforcement experience indicated defects
and unsafe conditions in not only structural elements of tower
cranes but also in their electrical, mechanical (e.g. hoists) and
hydraulic components and systems as well as control systems. For
this reason, the current inspection requirement is being expanded
beyond structural elements of tower cranes.
In addition, Ministry’s past tower crane enforcement campaigns
indicated tower cranes were being inspected by professional
engineers, as required by section 158, in an inconsistent manner
and that engineers’ inspection reports varied greatly. To address
this inconsistency, the Professional Engineers of Ontario (PEO)
developed a Practice Standard for Tower Crane Review, in
consultation with the Tower Crane Regulation Review Working
Group, to guide professional engineers in their inspections of tower
cranes (see attached document). The attached Practice Standard
is still a draft but very close to being completed. The finalized
Practice Standard is not expected to be much different from the
attached draft version. Once finalized by the PEO, the Practice
Standard is expected to be made into a regulation under the
Professional Engineers Act which would replace the current
reference to the Practice Standard in the final proposed
amendments to the Construction Regulation. Professional
engineers would then be required to follow the new regulation
under the Professional Engineers Act when inspecting tower cranes
in compliance with the Construction Regulation.
The phrase, “or a competent worker designated by a professional
engineer” is being removed at the request of the PEO as it is not
consistent with the Professional Engineers Act. The PEO is
expected to clarify shortly (and before the proposed amendments
are finalized by the Ministry) whether an additional phrase should
be added consistent with the Professional Engineers Act which
currently allows a professional engineer to delegate
duties/functions to a designated person who is under the engineer’s
direct supervision.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(c) the professional engineer in clause (b) has prepared a written
report of the corrections and repairs and results of the
inspection in clause (b).
(3) The constructor shall keep the report at the project
while the crane is erected.
159. (1) A professional engineer or a competent worker
designated by a professional engineer shall visually inspect for
defects the structural elements and components of a tower crane,
(4)
The constructor shall keep all reports required under this
section at the project while the crane is erected at the projected and
shall make them available to an inspector upon request.
159. (1) Except for a self-erecting tower crane, a professional
engineer or a competent worker designated by a professional
engineer shall visually inspect the structural, electrical, mechanical
and hydraulic components and systems of a tower crane, and shall
test the control systems of a tower crane, in accordance with the
Practice Standard for Tower Crane Review developed by the
Professional Engineers of Ontario, and identify any defects,
(a) after the crane is erected and before it is used; and
(a) after the crane is erected and before it is used; and
(b) after the inspection under clause (a), at intervals not
greater than twelve months.
(b) after the inspection under clause (a), at intervals not greater than
twelve months.
(1.1)
(NEW):
(a) A professional engineer shall inspect the structural, electrical,
mechanical and hydraulic components and systems of a selferecting tower crane, and shall test the control systems of a
self-erecting tower crane, in accordance with the Practice
Standard for Tower Crane Review developed by the
Professional Engineers of Ontario, and identify any defects,
(i) every 6 months while the crane is in use; or
(ii) after every 12 erections of the crane,
whichever comes first.
20
See explanation for proposed changes in section 158.
NEW subsection (1.1) – Because self-erecting tower cranes are
often erected and dismantled on a frequent basis for use at
different projects e.g. sometimes daily, they are more prone to
being damaged than regular tower cranes and should be inspected
periodically when they are in service to ensure they are maintained
good condition.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(b) (i) The inspection of structural components in clause (a) shall
include methods of non-destructive testing recognized by the
CAN/CGSB 48.9712-2006, Non-destructive Testing –
Qualification and Certification of Personnel standard; and
(ii) the non-destructive testing, and interpretation and evaluation
of testing results, shall be conducted by a person certified in
accordance with CAN/CGSB 48.9712-2006, Non-destructive
Testing – Qualification and Certification of Personnel
standard.
NEW subsection (1.2) – Is consistent with CSA Z248-04, Code for
Tower Cranes, clause 5.9.8.9.
(1.2) NEW A tower crane shall,
(a) be erected plumb to a tolerance of 1:500 unless otherwise
specified by the manufacturer; and
(b) be plumbed while balanced and then held in the plumbed
condition by wedges or other means.
(2) NEW – The professional engineer or a competent worker
designated by a professional engineer conducting an inspection or
under whose direction an inspection is done shall prepare a written
report of the inspection and test results including confirmation that all
components are in adequate condition.
(2) No tower crane shall be used until any defects found
during an inspection are repaired in accordance with the
instructions of the crane’s manufacturer or a professional
engineer.
(3) NEW – No tower crane shall be used until:
(3) A professional engineer or a competent worker
designated by a professional engineer shall inspect a tower crane
that has been repaired to ensure that the defects are corrected.
(b) the tower crane has been inspected by a professional engineer
or a competent worker designated by a professional engineer to
confirm that the defects are corrected or repaired and that the
repaired components are in adequate condition; and
(a) any defects identified in the inspection in subsection (1) that
may affect worker health and safety are corrected or repaired in
accordance with the instructions of the tower crane
manufacturer or a professional engineer;
21
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(4) The professional engineer conducting an inspection or
under whose direction the inspection is done shall prepare a
written report of the test results.
(5) The constructor shall keep the report at a project while
the crane is erected.
PROPOSED CHANGES RELATED TO TOWER CRANES
(c)
the professional engineer in clause (b) has prepared a written
report of the corrections and repairs and results of the
inspection in clause (b).
(4) The constructor shall keep all reports required under this
section at a project while the crane is erected at the project and shall
make them available to an inspector upon request.
159.1 NEW –
(1)(a)(i) The foundation supporting a tower crane shall be inspected
by a professional engineer before the concrete is poured, and
(ii) the work surface, other than a poured concrete foundation,
supporting a tower crane shall be inspected by a professional
engineer before the crane is erected,
to confirm that the foundation or work surface complies with the
foundation design drawings or the design drawings subject to
any deviations as approved by a professional engineer in
subsection 157(2).
(b)
A written report of the inspection prepared by the professional
engineer in clause (a) shall be kept at the project while the
tower crane is at the project and shall be made available to an
inspector upon request.
(c) The tower crane shall not be erected until the concrete
foundation reaches the strength specified in the foundation
design drawings.
(2)(a) The shoring and bracing that support a tower crane or tie it in
place shall be inspected by a professional engineer after the
shoring and bracing or the tie-ins have been installed and
before the crane is put into service for the first time on the
project.
22
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(b) The professional engineer shall prepare a written report of the
inspection in clause (a) including confirmation that the shoring
and bracing or the tie-ins have been installed in accordance
with the design drawings or the design drawings subject to any
deviations approved by a professional engineer in ss.157(3)
and the building or structure has reached sufficient strength to
resist the crane reactions.
(c) The written report prepared in clause (b) shall indicate the
circumstances that would require additional inspections of the
shoring and bracing or tie-ins by a professional engineer after
the initial inspection in clause (a).
(d) A written report of the inspections in clauses (a) and (c) shall be
kept at the project while the tower crane is at the project and
shall be made available to an inspector upon request.
(3)(a)The structural, electrical, mechanical and hydraulic equipment
used in a climbing operation of a tower crane shall be inspected
by a professional engineer in accordance with the Practice
Standard for Tower Crane Review developed by the
Professional Engineers of Ontario,
(i)
prior to the initial climbing operation of the tower crane at
the project, and
(ii)
after the inspection in paragraph (i), at intervals not greater
than 12 months.
(3)(b) The professional engineer conducting an inspection shall
prepare a written report of the inspection in clause (a) and its test
results including confirmation that all components are in adequate
condition.
23
ss.(2)(c) NEW – A new requirement is added that is cross
referenced in ss.(5) regarding the inspection of shoring, bracing
and tie-ins before and after climbing operations. For routine kinds
of climbing operations, a competent worker can perform the
inspection. However, if the climbing operation is unusual/
complicated, it may be appropriate for an engineer to perform the
post-climbing inspection to ensure the shoring, bracing and tie-ins
have been installed correctly and in accordance with the design
drawings. It should be the responsibility of the engineer to
determine when an engineer rather than a competent worker
should perform this inspection and to specifically note it in the
report.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(4)(a) Each major component used for shoring the tower crane shall
be marked by a conspicuous label stating that the component shall
not be removed or repositioned unless authorized by the
professional engineer in ss.(2)(a).
(b) The label in clause (a) shall be in place on the component while
the component is being used at the project.
(5)(a) After the initial inspection by a professional engineer in
ss.(2)(a), the shoring and bracing components and tie-ins installed
for the climbing operation shall be inspected:
(i) by a competent worker before and after each climbing operation
of the crane unless otherwise specified by the professional
engineer in the written report under ss.(2)(c), to ensure the
shoring and bracing components and tie-ins have been installed
in accordance with the design drawings prepared in ss.157(3),
and
(ii) weekly by a competent worker after each climbing operation to
ensure all the installed shoring and bracing components and tie-ins
are in place.
(b) A written report of the inspections in clauses (a)(i) and (ii) shall
be kept at the project while the tower crane is at the project and shall
be made available to an inspector upon request.
(c) The shoring and bracing components and tie-ins shall not be
removed or re-positioned unless authorized by the professional
engineer responsible for the structural integrity of the building or
structure in ss.157(4)(5).
160. (1) A tower crane shall have automatic limit switches
and automatic overload limit devices that prevent,
160. (1) A tower crane shall have, automatic limiting switches and
devices
(a) limiting devices to:
(a) overloading at relative radii;
(b) a load on the crane from reaching beyond the highest
permissible position specified by the manufacturer;
(i) limit trolley travel at both ends of the boom;
24

A more comprehensive list of limiting devices, as per CSA
standard Z248-04, Code for Tower Cranes, Section 4.18,
replaces the current subsection 160(1) for clarity and
consistency.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
and
(c) the trolley from reaching beyond the permissible travel
limit specified by the manufacturer.
PROPOSED CHANGES RELATED TO TOWER CRANES
(ii) stop boom luffing at the lower or upper limits of boom movement;
(iii) stop load block upward motion before two-blocking occurs;
(iv) limit crane travel at both ends of the runway tracks;
(v) limit maximum load lifted in each gear ratio;
(vi) prevent overloading the crane by limiting the lifted load in
accordance with the operating radius;
(vii) limit the maximum load lifted to the allowable line pull; and,
(viii) limit pressures in hydraulic or pneumatic circuits; and
(b) load-weighing devices.
(2) In addition to automatic limit switches and overload limit
devices, a tower crane shall have such other switches and
devices as the manufacturer specifies.
(2) In addition to automatic limit switches and overload limit devices
the limiting devices in clause (1)(a), a tower crane,
(a) shall have such other automatic switches, devices and safety
devices as the crane manufacturer specifies, and
(b) boom hoist shall have a slack rope-limiting device.
161. (1) A competent worker shall perform operational
tests on a tower crane to ensure that its automatic limit switches
and overload limit devices are installed and functioning in
accordance with the manufacturer’s specifications, if any.
(2) Operational tests shall be done,
(a) after the tower crane is erected on the project and
before it is used; and
161. (1) Operational tests on a tower crane shall be
performed to ensure that its automatic limit switches and overload
limit devices limiting and indicating devices are installed and
functioning in accordance with the manufacturer’s specifications, if
any.
(2) Operational tests shall be done,
(a) by a competent worker after the tower crane is erected on the
project and before it is put into service;
25
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(b) at one-week intervals after the test under clause (a)
while the crane is erected on the project.
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(b) (NEW) by a worker who meets the requirements in ss.150(1) or
(1.2) after each climbing operation and before the crane is put
into service; and
(c) by a worker who meets the requirements in ss.150(1) or (1.2) at
one-week intervals after the test under clause (a) while the
crane is erected on the project.
(3) NEW (a) Subject to clause (b), load tests on a tower crane shall
be performed in accordance with CSA Z248-04, Code for Tower
Cranes, section 6.3.3.
(b) Lifting hardware to perform a load test shall be capable of
supporting at least five times the maximum load to which it may
be subjected.
(3) Overload limit devices for a tower crane shall be tested
using test blocks designed for the purpose that have their weight
clearly marked on them.
(4) The test blocks shall be kept on the project while the crane is
erected.
(4) Overload limit devices for a tower crane shall be tested
using test blocks designed for the purpose that have their weight
clearly marked on them.
(5) The test blocks shall be kept on the project while the crane is
erected.
(6) NEW - The professional engineer who inspects the tower crane
under ss.158(1) and ss.159(1) shall be present,
(a) to witness the performance of load tests and operational tests on
the crane, and
(b) to verify, before the crane is put into service, that the limiting and
indicating devices are set and operating properly.
(7) NEW - After each climbing operation is completed and before the
crane is put into service, the crane shall be plumbed while balanced
and then held in the plumbed condition by wedges or other means.
26
NEW ss.161(3)(b) – CSA Z248-04 requires a minimum factor of
safety of 3:1 on yield for lifting hardware. To avoid confusion and to
reinforce and maintain consistency with existing rigging
requirements in the Construction Regulation, ss. 161(3)(b) is being
added which mirrors the existing requirement in ss.172(1)(d) and is
equivalent to a factor of safety of 3:1 on yield that is referenced in
the CSA standard.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
(8) NEW While a tower crane is in service at the project, it shall be
inspected,
(a) daily by the crane operator as follows:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
ensure all wedges in slab openings are in place and are
tight,
ensure all guy lines and all guy line connections, if used, are
adequate,
inspect mast bolts and anchor bolts,
ensure all limit switches (except line pull limit switch), signal
lights, audio and visual indicators and brakes and
functioning properly,
all wire rope cable that winds on a drum or passes over a
sheave that may reasonably be expected to be in use
during the day’s operation of the crane, shall be visually
inspected daily for damage or possible evidence of rope
failure,
inspect grounding connections,
inspect the tracks for loose connections, proper drainage,
subsidence, and bogie wear on travelling cranes, and
inspect rail clamps, if used, daily or each time their
application is made; and
(b) weekly by a competent worker as follows:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
structural pins and keepers,
trolley rollers, tracks, slewing rings and rollers,
gear shaft and belt drives,
sheaves, bushings and pins,
guy ropes, pendant lines, cable clips, thimbles and ferrules,
jib backstops (boom stops),
all rope attachments,
walkways, handrails and ladders,
the locations in the structure where accumulation of water
could result in damage, to ensure that such water is
drained, and
(x) tie-ins to slabs or other bracing systems where used; and
27
RATIONALE/COMMENT RE: PROPOSED CHANGES
NEW ss. 161(8) is added for clarity and consistency and is
consistent with CSA Z248-04, Code for Tower Cranes, section
6.4.4.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(c) the results of the inspections in clauses (a) and (b) shall be
recorded in the log book for the crane as required in ss.152(2.1).
161.1 Worker training/competencies (NEW)
(1) A tower crane shall be erected, dismantled and climbed on a
project by a competent worker under the supervision of a competent
person.
(2) For the erection and dismantling of a tower crane, the competent
person referred to in subsection (1) shall:
(a) have knowledge and experience in all phases of tower crane
erection, dismantling and climbing procedures and be able to
demonstrate proficiency in the procedures;
(b) have received instruction in the erection and dismantling
procedures for the particular tower crane used at the project in
accordance with the specifications of the manufacturer of that
crane;
(c) have knowledge and experience and be able to demonstrate
proficiency in proper rigging procedures and in the rigging used
by the tower crane at the project;
(d) be knowledgeable regarding:
o Fall hazards, and measures and personal protective
equipment to protect workers from the hazards, and
o Hazards to workers that may be caused by adverse
weather conditions;
(e) be familiar with the communications protocols and safety and
emergency procedures on the project;
(f) develop a written document identifying:
o the workers engaged in the erection and dismantling
operations by name and job title and stating their respective
roles and responsibilities,
28
Training requirements/competencies are being added to ensure a
minimum level of knowledge and instruction for workers and
supervisors involved in the erecting, dismantling and climbing of
tower cranes. The Tower Crane Regulation Review Working Group
recommends that ultimately the Chief Prevention Officer of the
Ministry of Labour should develop a training standard related to the
erecting, dismantling and climbing of tower cranes under the
Occupational Health and Safety Act and approve training programs
that meet that standard.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
o
o
site-specific hazards related to the erection and dismantling
of the tower crane at the project, and
the measures and procedures for controlling and protecting
the workers from those hazards;
(g) meet with all the workers assigned to the erection or dismantling
operation and review with them the written document referred to
in clause (f) prior to any work commencing with respect to the
erection or dismantling operation;
(h) understand the roles and responsibilities assigned to each
worker involved in the erection or dismantling operation; and
(i)
keep a copy of the document referred to in clause (f) at the
project while the tower crane is at the project and make it
available to an inspector.
(3) For the erection or dismantling of a tower crane, a competent
worker shall:
(a) have received instruction in the erection or dismantling
procedure for the particular tower crane at the project;
(b) be familiar with the communications protocols and safety and
emergency procedures at the project;
(c) understand the roles and responsibilities assigned to him/her in
the erection or dismantling operation;
(d) be knowledgeable regarding:
o the site-specific fall hazards related to the erection or
dismantling of the tower crane, and
o the measures and personal protective equipment to protect
him/her from those hazards;
(e) have attended a meeting with the competent person
supervising the erection or dismantling operation and the
competent workers assigned to the operation and reviewed the
29
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
written document referred to in ss.(2)(f) with them prior to any
work commencing with respect to the erection or dismantling
operation; and
(f) have knowledge and experience and be able to demonstrate
proficiency in proper rigging procedures and in the rigging used
by the particular tower crane at the job site.
(4) For the climbing of a tower crane, the competent person referred
to in subsection (1) shall:
(a) have knowledge and experience in all phases of tower crane
erection, dismantling and climbing procedures and be able to
demonstrate proficiency in the procedures;
(b) have received instruction in the climbing procedure for the
particular tower crane used at the project in accordance with the
specifications of the manufacturer of that crane;
(c) be knowledgeable regarding:
o fall hazards, and measures and personal protective
equipment to protect workers from the hazards, and
o hazards to workers that may be caused by adverse weather
conditions;
(d) be familiar with the communications protocols and safety and
emergency procedures on the project;
(e) develop a written document identifying:
o
o
o
the workers engaged in the climbing operation by name and
job title and stating their respective roles and responsibilities,
site-specific hazards related to the climbing of the tower
crane at the project,
and the measures and procedures for controlling and
protecting the workers from those hazards;
(f) meet with all the workers assigned to the climbing operation and
30
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
review with them the written document referred to in clause (e)
prior to any work commencing with respect to the climbing
operation;
(g) understand the roles and responsibilities assigned to each
worker involved in the climbing operation; and
(h) keep a copy of the document referred to in clause (e) at the
project while the tower crane is at the project and make it
available to an inspector.
(5) For the climbing of a tower crane,
(a) (i) Only a competent worker appointed by the competent person
referred to in ss.(1) shall participate in a climbing operation, and
(ii) at least one of the workers in the climbing operation shall be
an operator of a tower crane who holds a certificate of
qualification issued under the Ontario College of Trades and
Apprenticeship Act, 2009, that is not suspended;
(b) The competent worker in clause (a) shall,
(i)
have received instruction related specifically to the type of
climbing procedure for the particular tower crane used at
the project;
(ii)
have attended a meeting with the competent person
supervising the climbing operation and the competent
workers assigned to the climbing operation and reviewed
the written document referred to in ss.(4)(d) with them prior
to any work commencing with respect to the climbing
operation;
(iii) be familiar with the job site communications protocols and
safety and emergency procedures;
(iv) understand the roles and responsibilities assigned to
31
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
him/her in the climbing operation;
(v)
162. (1) A tower crane boom shall be able to slew freely
when the crane is unattended except when,
(a) the boom may collide with another crane, a structure
or another object; or
(b) to slew freely would be contrary to the written
procedures of the crane’s manufacturer.
(2) When a tower crane boom is not permitted to slew freely it
shall be secured in accordance with the written procedures of the
crane’s manufacturer.
be knowledgeable regarding:
a. the site-specific fall hazards related to the climbing of
the tower crane, and
b. the measures and personal protective equipment to
protect him/her from those hazards.
162 (1) A tower crane boom shall be able to slew freely when
the crane is unattended except when,
(a) the boom may collide with another crane, a structure or another
object; or
(b) to slew freely would be contrary to the written procedures of the
crane’s manufacturer.
(2) When a tower crane boom is not permitted to slew freely
because of the circumstances in ss.(1)(a) or (b), it shall be secured
in accordance with the written procedures of the crane manufacturer
or by a professional engineer where the crane manufacturer is no
longer available.
(3) NEW – Where the operating zones of two or more tower cranes
overlap, or where it is unavoidable that the operating zones of a
tower crane and other construction equipment overlap:

(a) subject to (b), the tower cranes and equipment shall be
positioned so that all operators have a clear view of the
other tower cranes or equipment operating in the
overlapping areas;
(b) if compliance with clause (a) is not practicable, anticollision devices shall be used on the tower cranes; and
(c) the constructor shall establish written work and
communications procedures to prevent collisions between
tower cranes and other equipment with overlapping work
32

A new requirement, subsection 162(3), is being added based
on CSA standard Z248-04, Code for tower Cranes, clauses
8.10.2 and 8.10.3. It is also consistent with European Union’s
standard, EN 14439:2007 [clause 5.4.2.8] which requires a
tower crane (except self-erecting ones) to be capable of being
equipped with anti-collision devices and leaves the decision of
whether to install such a device to the user, dependant on a
risk analysis when the crane is erected at the project.
The work and communications procedures are to ensure that
all crane operators in the overlapping zones communicate with
one another to coordinate the movement of the tower cranes
so that crane parts, hoist lines and loads do not collide during
operation.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
zones and shall communicate the procedures to all affected
workers.
163. (1) Subject to subsection (2), the operator’s cabin of
a tower crane shall be located on and attached to or positioned
on the crane in accordance with the instructions of the crane’s
manufacturer for the specific model and configuration of the
crane and in such a manner that in the event of a failure of the
boom, the cabin will not be crushed against the mast.
163. (1) After the amendments come into effect, (DATE to be
specified) and subject to subsection (2), the operator’s cabin of a
tower crane,
(a) that is being put into service in Ontario for the first time, shall
meet the design and installation requirements of the European
standard EN 14439:2006 or EN 14439:2009, Cranes – Safety –
Tower Cranes;
(b) other than one described in ss.(1)(a), shall meet the
requirements of CSA Z248-04, Code for Tower Cranes, for the
operator’s cabin;
(c) shall be located on and attached to or positioned on the crane in
accordance with the instructions of the crane manufacturer for
the specific model and configuration of the crane and in such a
manner that in the event of a failure of the boom, the cabin will
not be crushed against the mast.
(2) The operator’s cabin shall not be located on or
attached to the boom unless,
(2) UNCHANGED
(a) the cabin and its attachments have been specifically
designed and fabricated for that purpose by the
original manufacturer of the crane in accordance with
good engineering practice;
(b) the boom of the crane cannot affect or be affected by
the operation of another crane or make contact with
a structure or equipment;
(c) the crane is not overlapped by any part of another
crane;
(d) because of specific site conditions, the location of
the cabin on the boom provides greater visibility for
the operator than does the manufacturer’s standard
33
New requirements re: operator’s cabins are added to align with the
comparable new design requirements for tower cranes in section
156.2.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
cabin location;
(e) the means of access to the cabin or other locations
on the boom is by a catwalk constructed of skid
resistant expanded metal or similar material and
fitted with solidly constructed guardrails and devices
which provide fall protection for the operator;
(f)
the structural, environmental and ergonomic design
of the cabin is equal to or greater than that of the
crane’s manufacturer’s standard cabin design; and
(g) the proposed location and attachment method
provide a structural and mechanical safety factor
equal to or greater than that of a cabin located on
the crane mast or attached to the slewing ring.
(3) If the crane manufacturer specifies the location of the
operator’s cabin to be on the boom of a tower crane, the crane
manufacturer shall provide to the owner of the crane a report for
the specific model and specific configuration of crane on a
project.
(4) The crane manufacturer’s report shall include,
(3) UNCHANGED
(4) UNCHANGED
(a) the crane load restrictions, reductions or
modifications resulting from the effect of the cabin
weight and its offset from the boom centreline;
(b) the crane configuration and operating restrictions
resulting from the effect of the cabin location and
attachment method; and
(c) engineering design drawings that include,
(i) the structural and ergonomic design of the
cabin,
(ii) the location of the cabin on the boom,
(iii) the attachment method including all fittings and
hardware, and
34
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(iv) all means of access.
164. A load block of an unattended tower crane shall be left
empty, at the top position and located at minimum radius.
165. (1) The track bed of a rail-mounted tower crane shall
have a sound and rigid base capable of carrying all loads to
which it is likely to be subjected without deformation or settlement
which affects the stability of the crane.
164.
Unless otherwise specified by the crane manufacturer and
provided the crane is equipped with positive mechanical locks to
prevent any unintended lowering of the boom, jib or both or the load,
a load block of an unattended tower crane shall be left empty, at the
top position and located at minimum a radius specified by the crane
manufacturer.
In some situations identified by a crane manufacturer, luffing boom
cranes may need to have a load on the load block to facilitate
slewing or weathervaning of the crane during off times. As section
64 currently does not permit this, changes are being made
consistent with CSA Z248-04, Code for Tower Cranes, clause 8.7,
to allow a load to be suspended from an unattended tower crane if
specified by the crane manufacturer.
165. (1) The track bed foundation and track, including rails and ties,
of a rail-mounted tower crane shall have a sound and rigid base be
designed by a professional engineer in accordance with the crane
manufacturer’s specifications to be capable of carrying all loads to
which they are likely to be subjected without deformation or
settlement which may affect the stability of the crane.
Section 165 is changed to clarify that rail-mounted tower cranes are
to be addressed like other tower cranes, including having their track
foundations and tracks designed and inspected by professional
engineers in accordance with the Practice Standard for Tower
Cranes developed by the Professional Engineers of Ontario, to
ensure related health and safety hazards are addressed. This is
consistent with changes being made to s.157 addressing
foundations and work surfaces supporting all tower cranes.
(1.1) NEW – The track foundation and track, including rails and ties,
shall be inspected by a professional engineer in accordance
with the Practice Standard for Tower Crane review developed
by the Professional Engineers of Ontario before a crane is
placed on the track to confirm that the track bed and track have
been installed in accordance with the design drawings.
(1.2) NEW – A written report of the inspection shall be kept at the
project while the tower crane is at the project and shall be made
available to an inspector upon request.
(2) The undercarriage of a rail-mounted tower crane shall
35
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
be fitted with rail clamps that can be firmly attached to the rails to
lock the crane in position.
(2) UNCHANGED
(3) A rail-mounted tower crane shall be locked in position
on the rails when not in use.
(3) UNCHANGED
(4) A rail-mounted tower crane shall have rail stops or
bumpers that extend at least as high as the centre of the
undercarriage wheels and that are securely attached to the rail at
both ends.
(4) UNCHANGED
166. (1) No derrick, stiff-leg derrick or similar hoisting
device shall be attached to a building or structure unless this
section is complied with.
166. UNCHANGED
(2) A professional engineer shall prepare design drawings
and specifications for the attachment of a derrick, stiff-leg derrick
or similar hoisting device to a building or structure.
(3)
The design drawings and specifications shall include,
(a) the location of the derrick, stiff-leg derrick or similar
hoisting device on the building or structure;
(b) the location of anchor bolts, guy wires, supports and
shoring for it;
(c) particulars of the weight of the loads and the radius
at which the loads are to be lifted; and
(d) particulars of the loads and forces on the building or
structure imposed by the derrick, stiff-leg derrick or
similar hoisting device.
(4) The constructor shall ensure that the structural
engineer responsible for the structural integrity of a building or
36
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
structure reviews and approves in writing the design drawings
and specifications for a derrick, stiff-leg derrick or similar hoisting
device before it is installed.
(5) A professional engineer shall inspect a derrick, stiff-leg
derrick or similar hoisting device before it is first used on a
building or structure to ensure that it is installed in accordance
with the design drawings and specifications.
(6) The professional engineer conducting the inspection
shall prepare a written report of the inspection.
(7) The constructor shall keep a copy of the design
drawings and specifications for a derrick, stiff-leg derrick or
similar hoisting device and the report prepared under subsection
(6) at a project while the derrick, stiff-leg derrick or similar hoisting
device is on the project.
167. (1) The pilot of a helicopter that is hoisting materials
shall be competent to fly an externally-loaded helicopter.
167. UNCHANGED
(2) The pilot shall be in charge of the hoisting operation
and shall determine the size and weight of loads to be hoisted
and the method by which they are attached to the helicopter.
(3) Ground personnel including signallers for a helicopter
being used to hoist materials shall be competent workers.
(4) The constructor shall take precautions against hazards
caused by helicopter rotor downwash.
168. (1) A cable used by a crane or similar hoisting
device,
168. (1) A cable used by a crane or similar hoisting device,
37
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(a) shall be steel wire rope of the type, size, grade and
construction recommended by the manufacturer of
the crane or similar hoisting device;
(b) shall be compatible with the sheaves and the drum
of the crane or similar hoisting device;
(c) shall be lubricated to prevent corrosion and wear;
(d) shall not be spliced; and
(e) shall have its end connections securely fastened and
shall be kept with at least three full turns on the
drum.
PROPOSED CHANGES RELATED TO TOWER CRANES
(a) shall be steel wire rope of the type, size, grade and construction
recommended by the manufacturer of the crane or similar
hoisting device;
(b) UNCHANGED;
(c) UNCHANGED;
(d)
UNCHANGED;
(e)
UNCHANGED; and
(f)
NEW shall not be used following any contact with electricity.
(1.1) (NEW)
All wire rope installed on a tower crane shall be
provided with a written record that includes the following
information about the rope:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
(2) No cable used by a crane or similar hoisting device,
(a) subject to subsection (3), shall contain six randomlydistributed wires that are broken in one rope lay or
RATIONALE/COMMENT RE: PROPOSED CHANGES
the diameter;
the length;
the tensile strength of single wires and finish;
the wire rope construction, type of lay, and direction of lay;
the number of outer strands;
the type of core;
the nominal or minimum rated breaking strength;
the recommended maximum working load limit;
the type of end fitting or connection and proof-test results
where applicable;
whether the use of a swivel is permitted;
the name of the manufacturer or supplier of the rope; and,
the name of the person or organization issuing the written
record on the wire rope.
(2.1)(NEW)
A written record required under subsection (1) shall
be included in the permanent record required under ss. 152(1) and
in the log book required under section 152 for a tower crane.
(2) UNCHANGED;
38
The NEW clause (f) in ss. 168(1) means the entire wire rope has to
be replaced if it has come into contact with electricity at any
voltage. Industry experience indicates that electrical current can
travel throughout the length of the wire rope and cause internal
damage that is not visible upon inspection but can cause the rope
to fail.
ss.(1.1) NEW - A new requirement for a written record in
subsection 1.1 is being added consistent with CSA standard Z24804, Code for Tower Cranes, Section 4.11.3. Such a written record
would help ensure the appropriate wire rope is used and that it is
used properly on a tower crane. The term “written record” is being
used rather than the term “test certificate” that is used in the CSA
standard as the latter term may infer some kind of “testing” has to
be done on the wire rope to complete the written record.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
three or more wires that are broken in one strand in
a rope lay;
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(a) UNCHANGED;
(b) shall be smaller than its nominal rope diameter by
more than,
(i) one millimetre for a diameter up to and including
nineteen millimetres,
(b) UNCHANGED;
(i) UNCHANGED;
(ii) two millimetres for a diameter greater than
nineteen millimetres up to and including
twenty-nine millimetres, and
(ii) UNCHANGED; and
(iii) UNCHANGED;
(iii) three millimetres for a diameter greater than
twenty-nine millimetres;
(c) shall be worn by more than one-third of the original
diameter of its outside individual wires;
(d) shall show evidence of kinking, bird-caging,
corrosion or other damage resulting in distortion of
the rope structure; or
(e) shall show evidence of possible rope failure including
rope damage caused by contact with electricity.
(c) UNCHANGED;
(d) shall show evidence of possible rope failure which may be an
immediate hazard including kinking, bird-caging, corrosion, core
protrusion or damage, waviness or other damage resulting in
distortion of the rope structure;
(e) shall show evidence of possible rope failure including rope
damage caused by contact with electricity; or

Current clause 168(2)(e) related to rope damage due to
electrical contact is relocated to ss.168(1) as a new clause (f).

Evidence of corrosion is being deleted from clause (2)(d) since
corrosion may not necessarily result in distortion of the rope
structure, and being moved into a new clause (f).

Addition of new cause (2)(e) related to heat damage is
consistent with rope replacement criteria in CSA standard
Z248-04, Code for Tower Cranes, Section 6.5.

Subsection 168(4) is amended by adding a new paragraph (iii)
(e) shall show evidence of heat damage from any cause; or
(f)
(3) No cable that is static or is used for pendants,
(a) shall contain three or more broken wires in one lay or
in a section between end connectors; or
(b) shall have more than one broken wire at an end
connector.
(4) Rotation-resistant wire rope shall not be used for a
cable for boom hoist reeving and pendants.
NEW shall show evidence of corrosion which may be an
immediate hazard
(3) UNCHANGED;
(a) UNCHANGED;
(b) UNCHANGED;
(4) Rotation-resistant wire rope shall not be used
(i) for boom hoist reeving unless specified by the crane
39
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
(5) Rotation-resistant wire rope shall not be used where
an inner wire or strand for a cable is damaged or broken.
PROPOSED CHANGES RELATED TO TOWER CRANES
manufacturer;
(ii) as a pendant; or
(iii) on a tower crane unless the rope has 14 outer strands or more,
or unless the inner core is plastic coated.
(5) Rotation-resistant wire rope shall not be used where an inner
wire or strand for a cable is damaged or broken.
168.1 (NEW)
Swivels shall not be used on boom hoist cable on a tower crane
unless they are allowed,
(a) by the tower crane manufacturer and wire rope manufacturer, or
(b) if the tower crane manufacturer is no longer in business, by a
professional engineer and the wire rope manufacturer.
169. A cable used by a crane or similar hoisting device
shall be capable of supporting at least,
RATIONALE/COMMENT RE: PROPOSED CHANGES
169. UNCHANGED
(a) three and one-half times the maximum load to which it
is likely to be subjected if it is used on a device other
than a tower crane and it winds on a drum or passes
over a sheave;
(b) five times the maximum load to which it is likely to be
subjected if it is used on a tower crane and it winds
on a drum or passes over a sheave;
(c) three times the maximum load to which it is likely to
be subjected if it is a pendant or is not subject to
winding or bending; and
40
re: the use of rotation-resistant wire rope used on tower cranes,
consistent with CSA standard Z248-04, Code for Tower
Cranes, Section 4.11.

Subsection 168(5) is deleted since a damaged inner wire or
strand of a cable cannot be seen by a visual inspection.

The addition of a new requirement regarding swivels is based
on industry experience and the CSA standard Z248-04, Code
for Tower Cranes. However, unlike the CSA standard clause
4.11.2(h), the section requires that the use of swivels must be
allowed by both crane AND wire rope manufacturers. If either
the crane or wire rope manufacturer recommends that swivels
not be used with its respective product, then swivels must not
be used on boom hoist cable. The CSA standard allows the
use of swivels if either the crane OR rope manufacturer permits
swivels to be used.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
(d) ten times the maximum load to which it is likely to be
subjected if the crane or similar hoisting device is
used for supporting persons.
170. (1) All cable used by a crane or similar hoisting
device shall be visually inspected by a competent worker at least
once a week when the crane or similar hoisting device is being
used.
(2) The worker performing an inspection shall record the
condition of the rope or cable inspected in the log book for the
crane or similar hoisting device.
171. (1) A cable used by a crane or similar hoisting
device shall be securely attached,
170. (1) Except for a tower crane and subject to ss.161(8), all cable
used by a crane or similar hoisting device shall be visually inspected
by a competent worker as frequently as recommended by the cable
manufacturer and in any case, at least once a week when the crane
or similar hoisting device is in service.
The changes to ss.170(1) clarify that cable on tower cranes has
a more detailed inspection requirement in ss.161(8) and cable
on all other cranes must be visually inspected at a minimum of
once a week or more frequently than once a week if so
recommended by the cable manufacturer.

The addition of “epoxy resin” in ss. (1)(b) reflects current
technology in end terminations in the industry. The
amendment would not change the intent of the requirement
which applies to cable used by any type of crane, not just tower
cranes.
(2) The worker performing an inspection shall record the condition
of the rope or cable inspected in the log book for the crane or
similar hoisting device.
171. (1) A cable used by a crane or similar hoisting device
shall be securely attached,
(a) by binding and fastening the cable around an oval
thimble in a way that is strong enough to prevent the
cable thimble from separating; or
(a) by binding and fastening the cable around an oval thimble in a
way that is strong enough to prevent the cable thimble from
separating; or
(b) by fastening the cable within either a tapered socket
by means of virgin zinc or a wedge-type socket fitted
with a wire rope clip at the dead end to prevent the
accidental release or loosening of the wedge.
(b) by fastening the cable within either a tapered socket by means
of virgin zinc, epoxy resin or a wedge-type socket fitted with a
wire rope clip at the dead end to prevent the accidental release
or loosening of the wedge.
(2) The dead end cable of a wedge socket assembly on a
hoisting line shall extend between 100 millimetres and 300
millimetres out of the socket.

(2) UNCHANGED;
(3) (a) NEW A wire rope pendant cable on a tower crane shall have
all new wire rope terminations proof tested after installation onto
the wire rope in accordance with the recommendations of the
wire rope or termination manufacturer, but in no case to more
than 50% of the wire rope’s nominal or minimum rated breaking
strength; and,
(b) permanent records of the proof testing in clause (a) shall be kept
for the life of the terminations.
41
NEW ss.171(3) is consistent with CSA Z248-04, Code for Tower
Cranes, section 4.11.2 and reflects the critical nature of
terminations on pendant cables.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
172. (1) A container, sling or similar device for rigging or
hoisting an object, including its fittings and attachments,
PROPOSED CHANGES RELATED TO TOWER CRANES
172. UNCHANGED
(a) shall be suitable for its intended use;
(b) shall be suitable for and capable of supporting the
object being rigged or hoisted;
(c) shall be so arranged as to prevent the object or any
part of the object from slipping or falling;
(d) shall be capable of supporting at least five times the
maximum load to which it may be subjected; and
(e) shall be capable of supporting at least ten times the
load to which it may be subjected if it is to be used to
support a person. O. Reg. 213/91, s. 172 (1).
(2) A sling or similar device made of web-type fabric or
nylon shall be labelled to indicate its load rating capacity.
(3) No sling or similar device for rigging or hoisting made
of web-type fabric or nylon shall be used if it may be cut.
173. (1) Every hoisting hook shall be equipped with a
safety catch.
173. (1) Subject to ss.(2), every hoisting hook shall be
equipped with a safety catch.
(2) No safety catch is required on a hoisting hook used in
placing structural members if the method of placing protects
workers to the same standard as a safety catch does.
(2) UNCHANGED;
(3) A hoisting hook shall have its load rating legibly cast or
stamped on it in a location where the person using the hook can
readily see it.
(4) A hoisting hook shall not be used if it is cracked, has a
throat opening that is greater than as manufactured or is twisted
from the plane of the unbent hook.
(3) UNCHANGED;
(4) UNCHANGED;
42
RATIONALE/COMMENT RE: PROPOSED CHANGES
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
174. A hook block shall have its load rating and weight legibly
cast or stamped on it in a conspicuous location.
PROPOSED CHANGES RELATED TO TOWER CRANES
RATIONALE/COMMENT RE: PROPOSED CHANGES
174. UNCHANGED
175. (1) An overhauling weight used on the cable of a
crane or similar hoisting device,
175. UNCHANGED
(a) shall be prevented from sliding up or down the cable; and
(b) shall be securely attached to the load hook and the cable.
(2) No overhauling weight used on the cable of a crane or
similar hoisting device shall be split.
176. Only an alloy steel chain or a chain manufactured for
the purpose shall be used for hoisting.
176. (1) Only an alloy steel chain or a chain manufactured
for the purpose shall be used for hoisting.
NEW (2) A chain used for hoisting shall be:
(a)
labelled to indicate its load rating capacity;
(b) repaired and re-conditioned in accordance with specifications of
the chain manufacturer;
The Ministry of Labour has identified a historical drafting error –
subsection (2) of s.177 is incorrectly located and needs to be
relocated into s.176. This will not change the current intent of s.176
or s.177. Additional requirements are being added for clarity re:
repairing and re-conditioning of chains and their periodic inspection.
(c) after being repaired or re-conditioned, proof tested in
accordance with specifications of the chain manufacturer; and
(d) visually inspected by a competent worker as frequently as
recommended by the chain manufacturer and in any case, at
least once a week when the chain is in service.
177. (1) No alloy chain shall be annealed or welded.
(2) A chain used for hoisting shall be selected, annealed,
normalized and repaired in accordance with the specifications of
177. (1) No alloy steel chain shall be annealed or welded.
(2) A chain used for hoisting shall be selected, annealed,
normalized and repaired in accordance with the specifications of its
43
The Ministry has identified a historical drafting error; subsection (2)
of s.177 is incorrectly located and needs to be relocated into s.176.
This will not change the current intent of s.176 or s.177.
May 15, 2013
CURRENT REQUIREMENT IN O. REG. 213/91
its manufacturer.
178. A friction-type clamp used in hoisting materials shall
be constructed so that an accidental slackening of the hoisting
cable does not release the clamp.
PROPOSED CHANGES RELATED TO TOWER CRANES
manufacturer.
178. UNCHANGED
185. (1) Electrical equipment, installations, conductors
and insulating materials shall be suitable for their intended use
and shall be installed, maintained, modified and operated so as
not to pose a hazard to a worker.
(2) For greater certainty, the regulations made under
section 113 of the Electricity Act, 1998 apply to electrical
equipment, installations, conductors and insulating materials and
to temporary wiring installations on projects.
44
RATIONALE/COMMENT RE: PROPOSED CHANGES
Download