Chapter 5 Activity-Based Costing and Management McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Learning Objective 1 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Traditional, Volume-Based Product-Costing System • Aerotech produces three complex printed circuit boards referred to as Mode I, Mode II, and Mode III. • The following information is obtained from company records: Production: Units Runs Mode I Mode II Mode III 10,000 1 run of 10,000 units 20,000 4 runs of 5,000 units 4,000 10 runs of 400 units 5-3 Traditional, Volume-Based Product-Costing System Direct materials Direct labor Manufacturing overhead Total $ $ Mode I 50.00 60.00 99.00 209.00 Mode II $ 90.00 80.00 132.00 $ 302.00 Mode III $ 20.00 40.00 66.00 $ 126.00 Additional information includes: Direct materials Direct labor (hr/board) Setup time (hr/run) Machine time (hr/board) $ Mode I 50.00 3 10 1 Mode II $ 90.00 4 10 1.25 Mode III $ 20.00 2 10 2 Manufacturing overhead is determined as follows 5-4 Traditional, Volume-Based Product-Costing System Mode I 10,000 3 30,000 Units produced Direct labor (hr/unit) Total hours Mode II 20,000 4 80,000 Total hours required 118,000 Budgeted manufacturing overhead Budgeted direct-labor hours $3,894,000 118,000 Mode I Direct labor (hr/unit) Overhead rate per hour Overhead per unit Mode III 4,000 2 8,000 $ $ = $33 per hour Mode II 3 33 99 $ $ Mode III 4 33 132 $ $ 2 33 66 5-5 Traditional, Volume-Based Product-Costing System With these product costs, Aerotech established target selling prices (Cost × 125%). Direct materials Direct labor Manufacturing overhead Total Cost per unit Target selling price $ $ $ Mode I Mode II Mode III 50.00 $ 90.00 $ 20.00 60.00 80.00 40.00 99.00 132.00 66.00 209.00 $ 302.00 $ 126.00 Mode I 209.00 261.25 Mode II $ 302.00 377.50 Mode III $ 126.00 157.50 209.00 x 1.25 5-6 Learning Objective 2 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Activity Based Costing System (ABC) ABC systems follow a two-stage procedure to assign overhead costs to products. Stage One Identify significant activities and assign overhead costs to each activity in proportion to resources used. Stage Two Identify cost drivers appropriate to each activity and allocate overhead to the products. 5-8 Learning Objective 3 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Overhead Costs Total budgeted cost = $3,894,000 Activity must be done on each unit produced. Activity Cost Pools Unit Level Batch Level ProductSustaining Level Machinery cost pool $1,212,600 Setup cost pool $3,000 Engineering cost pool $700,000 Activity performed on each batch produced. Activities needed to support an entire product line Identification of Activity Cost Pools Facility Level Facility cost pool $507,400 Activity required in order for the production process to occur. 5-10 Unit Level Batch Level ProductSustaining Level Machinery cost pool $1,212,600 Setup cost pool $3,000 Engineering cost pool $700,000 Facility Level Facility cost pool $507,400 Receiving/Inspection cost pool $200,000 Material-Handling cost pool $600,000 Quality-Assurance cost pool $421,000 Packaging/Shipping cost pool $250,000 5-11 Learning Objectives 3&4 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. STAGE ONE Various overhead costs related to machinery Activity cost pool Maintenance Lubrication Depreciation Electricity Computer Support Calibration Machinery Cost Pool Total budgeted cost = $1,212,600 5-13 STAGE TWO Calculate the pool rate Cost Assignment Budgeted Machinery Costs = $1,212,600 Budgeted Machine Hours 43,000 = $28.20/hour Mode I: $28.20 per hr. 1 hr. per unit $28.20 per unit Mode II: $28.20 per hr. 1.25 hr. per unit $35.25 per unit Mode III: $28.20 per hr. 2 hr. per unit $56.40 per unit 5-14 STAGE ONE Calculation of total setup cost Activity cost pool Total budgeted setup cost $20 per hour 10 hr. per setup $200 cost per setup 15 production runs $ 3,000 Total Setup Cost Pool Total budgeted cost = $3,000 5-15 STAGE TWO Calculate the pool rate Cost Assignment Budgeted Setup Costs Planned Production Runs Mode I: (1 Run) $200 per run 10,000 units per run = $.02 per unit = $3,000 15 runs = $200 per run Mode II: (4 Runs) $200 per run 5,000 units per run = $.04 per unit Mode III: (10 Runs) $200 per run 400 units per run = $.50 per unit 5-16 STAGE ONE Various overhead costs related to engineering Activity cost pool Engineering salaries Engineering software Engineering supplies Depreciation Engineering Cost Pool Total budgeted cost = $700,000 5-17 STAGE TWO Allocate based on engineering transactions Cost Assignment Engineering Cost Pool Total budgeted cost = $700,000 Mode I: 25% × $700,000 10,000 units = $17.50 per unit Mode II: 45% × $700,000 20,000 units = $15.75 per unit Mode III: 30% × $700,000 4,000 units = $52.50 per unit 5-18 STAGE ONE Various overhead costs related to general operations Activity cost pool Plant depr. Property taxes Plant mgmt. Insurance Plant maint. Security Facility Cost Pool Total budgeted cost = $507,400 5-19 STAGE TWO Calculate the pool rate Cost Assignment Budgeted Facilities Cost = $507,400 Budgeted Direct-Labor Hours 118,000 = $4.30/hour Mode I: $4.30 per hr. × 3 hr. per unit $12.90 per unit Mode II: $4.30 per hr. × 4 hr. per unit $17.20 per unit Mode III: $4.30 per hr. × 2 hr. per unit $8.60 per unit 5-20 Other Overhead Costs Receiving and Inspection Cost Pool Board Overhead Mode I $ 200,000 Mode II 200,000 Mode III 200,000 × × × × % 6% 24% 70% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 1.20 = 2.40 = 35.00 Material-Handling Cost Pool Board Overhead Mode I $ 600,000 Mode II 600,000 Mode III 600,000 × × × × % 7% 30% 63% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 4.20 = 9.00 = 94.50 Quality-Assurance Cost Pool Board Overhead Mode I $ 421,000 Mode II 421,000 Mode III 421,000 × × × × % 20% 40% 40% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 8.42 = 8.42 = 42.10 Packaging and Shipping Cost Pool Board Overhead Mode I $ 250,000 Mode II 250,000 Mode III 250,000 × × × × % 4% 30% 66% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 1.00 = 3.75 = 41.25 5-21 Other Overhead Costs Receiving and Inspection Cost Pool Board Overhead Mode I $ 200,000 Mode II 200,000 Mode III 200,000 × × × × % 6% 24% 70% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 1.20 = 2.40 = 35.00 Material-Handling Cost Pool Board Overhead Mode I $ 600,000 Mode II 600,000 Mode III 600,000 $14.82 × × × × % 7% 30% 63% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 4.20 = 9.00 = 94.50 Quality-Assurance Cost Pool Board Overhead Mode I $ 421,000 Mode II 421,000 Mode III 421,000 × × × × % 20% 40% 40% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 8.42 = 8.42 = 42.10 Packaging and Shipping Cost Pool Board Overhead Mode I $ 250,000 Mode II 250,000 Mode III 250,000 × × × × % 4% 30% 66% ÷ ÷ ÷ ÷ Units 10,000 20,000 4,000 = Cost/Unit = $ 1.00 = 3.75 = 41.25 5-22 Product Cost from ABC These are the new product costs when Aerotech uses ABC. Mode I Direct materials $ 50.00 Direct labor 60.00 Machinery 28.20 Setup 0.02 Engineering 17.50 Facilities 12.90 Other 14.82 Total $ 183.44 Mode II $ 90.00 80.00 35.25 0.04 15.75 17.20 23.57 $ 261.81 Mode III $ 20.00 40.00 56.40 0.50 52.50 8.60 212.85 $ 390.85 5-23 Learning Objective 5 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Distorted Product Costs Both original and ABC target selling prices are based on (Cost × 125%). Traditional costing ABC costing Original target selling price ABC target selling price Mode I $ 209.00 183.44 Mode II $ 302.00 261.81 Mode III $ 126.00 390.85 261.25 229.30 377.50 327.26 157.50 488.56 The selling price of Mode I and II are reduced and the selling price for Mode III is increased. [$209.00 × 1.25] [$183.44 × 1.25] 5-25 Distorted Product Costs Can you identify any problems Aerotech is likely to face as a result of this distortion? Mode I Traditional costing $ 209.00 ABC costing 183.44 Cost distortion per unit 25.56 Units produced 10,000 Total cost distortion 255,600 Mode II $ 302.00 261.81 40.19 20,000 803,800 Mode III $ 126.00 390.85 (264.85) 4,000 (1,059,400) Traditional costing understates the cost of complex, low volume products. 5-26 Two Key Points A large proportion of nonunit-level activities A unit-level cost driver, such as direct labor, machine hours, or throughput, will not be able to assign the costs of non-unit-level activities accurately. Product diversity When the consumption ratios differ widely between activities, no single cost driver will accurately assign the resulting overhead costs. 5-27 Learning Objective 6 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Cost Drivers A characteristic of an event or activity that results in the incurrence of costs. In selecting a cost driver, we must consider . . . Degree of Correlation Behavioral Effects Cost of Measurement 5-29 Learning Objective 7 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. COLLECTING ABC DATA INTERVIEWS AND PAPER TRAILS - The information for ABC systems initially comes from interviews with employees in the support departments and a review of each department’s records. STORYBOARDING - A procedure used to develop a detailed process flow chart, which visually represents activities and the relationships among activities. MULTIDISCIPLINARY ABC PROJECT TEAMS – To gather information from all facets of an organizations operations, it is essential to involve personnel from a variety of functional areas. A typical ABC project team includes ACCOUNTING, FINANCE, PRODUCTION, OPERATIONS, ENGINEERS, MARKETING etc. 5-31 Learning Objective 8 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Activity-Based Management The use of ABC costing information to help management make decisions 5-33 Activity-Based Management Activity-based costing establishes relationships between overhead costs and activities so that we can better allocate overhead costs. Activity-based management focuses on managing activities to reduce costs. 5-34 Two-Dimensional ABC and ActivityBased Management Activities 5-35 Two-Dimensional ABC and ActivityBased Management Cost Assignment View Resource costs Activities Cost Objects 5-36 Two-Dimensional ABC and ActivityBased Management Cost Assignment View Resource costs Process View Activity Analysis Root Causes Activity Triggers Activity Evaluation Activities Performance Measures Cost Objects 5-37 Elimination of Non-Value-Added Costs Activities Nonvalueadded activities Unnecessary Necessar y Reduce or Eliminate Continually Evaluate and Improve 5-38 Using ABM to Eliminate Non-ValueAdded Activities and Costs 1. Identify Activities. 2. Identify Non-Value-Added Activities. 3. Understand Activity Linkages, Root Causes, and Triggers. Specify parts Select vendor Receive parts Produce goods Inspect finished goods Rework defective products 4. Establish Performance Measures. 5. Report Non-Value-Added Costs. 5-39 Using ABM to Eliminate Non-ValueAdded Activities and Costs Process time Inspection time Move time Storage time Waiting time 5-40 Learning Objective 9 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Customer Profitability Analysis Customer profitability analysis uses activity-based costing to determine the activities, costs, and profit associated with serving particular customers. 5-42 Customer Profitability Analysis Required special packaging. Orders small quantities. Demand fast service. Often changes orders. Orders frequently. A costly customer 5-43 Customer Profitability Analysis Customer-Related Activities Order processing Sales contacts (phone calls, faxes, etc.) Sales visits Shipment processing Billing and collection Design/engineering change orders Special packaging Special handling Cost Driver Base Purchase orders Contacts Visits Shipments Invoices Design changes Units packaged Units handled Cost Drive Rate $ 150 100 1,000 200 160 4,000 40 60 A company may use these customer related costs to help determine the profitability of each customer. 5-44 Customer Profitability Analysis Cumulative Operating Income as a % of Total Operating Income Customer Profitability 125.0% 100.0% 75.0% 50.0% 25.0% 75% of actual operating income 50% of actual operating income 25% of actual operating income 0.0% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 5-45 Learning Objective 10 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Activity-Based Management in the Service Industry Customer Profitability Analysis Activity Analysis 5-47 Learning Objective 11 McGraw-Hill/Irwin Copyright © 2009 by The McGraw-Hill Companies, Inc. All rights reserved. Just-in-Time Inventory and Production Management No materials are purchased and no products are manufactured until they are needed. The primary goal of a JIT production system is to reduce or eliminate inventories at every stage of production. 5-49 Key Features of the JIT Approach Smooth, uniform production rate Pull method of production Purchase is small lot sizes Quick, inexpensive setups High quality materials Effective preventive maintenance Teamwork Multiskilled workers 5-50 JIT Purchasing Long-term contracts with suppliers. Only a few suppliers. Parts delivered in small lots. Grouped payments to vendor. Minimal inspection of materials. 5-51 End of Chapter 5 This is my kind of cost pool! 5-52