Aquatics Renovation – 2-08-16 Weekly Construction Update

advertisement
Measure L Bond Program
SLOCCCD
CONSTRUCTION UPDATE
UPDATES & ACTIVITIES THAT MAY IMPACT
CAMPUS OPERATION
Week of February 8, 2016
San Luis Obispo – Main Pool
Renovation
Work this week: Starting block plates were installed and
concrete was replaced below the diving boards. Diving
boards have been reinstalled and the pool is in the process
of being filled. The Cuesta College Facilities team is
completing some facility repairs.
Access:
Noise:
Parking:
Utilities:
Odors:
Dust:
No access into the gated pool
area
Minor equipment noise
Minor impact
None
Minor impact
None
Download