Measure L Bond Program SLOCCCD CONSTRUCTION UPDATE UPDATES & ACTIVITIES THAT MAY IMPACT CAMPUS OPERATION Week of February 8, 2016 San Luis Obispo – Main Pool Renovation Work this week: Starting block plates were installed and concrete was replaced below the diving boards. Diving boards have been reinstalled and the pool is in the process of being filled. The Cuesta College Facilities team is completing some facility repairs. Access: Noise: Parking: Utilities: Odors: Dust: No access into the gated pool area Minor equipment noise Minor impact None Minor impact None