UNIVERSITY OF BRADFORD BRADFORD METHOD RISK LOG Project name Integrating Thin client Systems for Secure E-Assessment Version 6 15 June 2009 Sara Eyre Author: Project Manager: Project Sponsor/Chair: Revision date Oct 2007 May 2008 Sep 2008 Dec 2008 Feb 2009 June 2009 Distribution Previous revision date Peter Hartley Summary of Changes Changes marked Version 1 in project plan Version 2 updated to UOB format Version 3 updated prior to project board meeting Version 4 updated prior to project board meeting Version 5 updated prior to project board meeting Version 6 updated prior to submission of final report Turquoise Pink Yellow Green Grey This document has been distributed to: Name JISC Project board JISC programme manager Project board and project teams Project board and project teams Project Board and project teams JISC, project board and teams Title Date of Issue Version 28/5/08 2 22/8/08 10/12/08 25/2/09 15 June 2009 3 4 5 6 ITS4SEA Score (PxS) Failure to recruit suitable staff Delays in new staff appointments Loss of project manager 1 4 4 1 4 4 2 4 8 Key institutional Contacts and Project Director – competing priorities leading to lack of input and support Project plan unrealistic 3 5 15 3 4 6 Failure to develop suitable size space for large cluster 4 7 Insufficient student numbers take assessments using thin client technology 8 Some students are unable to use the technology 2 3 4 5 Action to Prevent/Manage Risk Person responsible Severity (1-5) 1 Risk Probability (1-5) Risk id JISC Institutional Exemplar Actions taken Date identified Date last reviewed Use existing staff and recruit backfill posts at a lower level. Reconsider project milestones SE Both staff in post 1/11/07 27/5/08 SE Project on track 1/11/07 27/5/08 Delegate role to CAA support staff in LSS Schedule regular meetings, maintain regular communication by email PH Project nearly completed Regular team meetings being held Project nearly completed 1/11/07 25/2/09 1/11/07 27/5/08 25/2/09 12 Quarterly review and update against progress with feedback from implementations teams SE 1/11/07 15/6/09 4 16 Use trial cluster for word processed exams for disabled students and for formative assessments. SE 1/11/07 22/8/08 4 4 16 Use trial cluster for any small groups taking online exams but results will be less conclusive. SE 1/11/07 10/12/08 25/2/09 3 2 6 Alternative, equivalent assessment method required SW Project completed. Unrealistic objectives highlighted in final report Space allocated but see risk 16. Timescales for development currently unknown. Work underway Two large classes scheduled for jan 09 exams Two exams ran sucessfully Sun Rays installed in cubicles for individuals 1/11/07 15/6/09 SE Page 1 ITS4SEA Score (PxS) Action to Prevent/Manage Risk Person responsible Severity (1-5) Risk Probability (1-5) Risk id JISC Institutional Exemplar 9 Servers running thin clients fail during exam 2 5 10 Provide back up servers. Try deliberately failing server and devise switchover processes. SE 10 Servers are inadequately sized to manage load of large exam classes 2 5 10 Need to run formative assessment with full class starting simultaneously in advance of summative assessment and measure server load. SE 11 SunRay terminals unreliable 3 3 9 Student moves to alternative seat. Need to test smart card swapping will save all past data entered in exam before SunRay failure. SE 12 Supplier fails to continue support of SunRay technology 1 5 5 Use standard PCs as thin clients to windows terminal server. SE Actions taken Additional servers to support thin clients installed No failures encountered URGENT – test needed before Xmas Server sizing still unclear Exam processes overcame issues. Still not 100% resolved for teaching Some Sun Rays in Hub have failed – needs chasing with Sun Two failures during exams; session transferred to other Sun Ray Request for matching grant made and quotation for 120 received Development plans announced at Sun education conference Date identified Date last reviewed 1/11/07 15/6/09 1/11/07 15/6/09 1/11/07 15/6/09 1/11/07 27/5/08 25/2/09 Page 2 ITS4SEA Score (PxS) Action to Prevent/Manage Risk Person responsible Severity (1-5) 13 Risk Probability (1-5) Risk id JISC Institutional Exemplar Actions taken Date identified Date last reviewed Smart cards which work with SunRay technology and current access control system are not manufactured. Lack of academic engagement with the technology 1 3 3 Consider whether to issue two cards or use Sunrays with username and password authentication only. SE Several potential suppliers identified 1/11/07 27/5/08 3 3 9 Continue with OMR exams. Employ staff to design online assessments from academics’ exam questions. PH 1/11/07 25/2/09 15 Student fails course and blames the technology 2 5 10 PH 1/11/07 15/6/09 16 Change in needs of examination office 3 4 12 JD Exam Admin design implemented 1/11/07 15/6/09 17 WASP module from SITS fails to deliver systems required in exams office 3 5 15 For project trials, only consider formative assessments and first year summative exams as the results of these do not pass into subsequent years for degree classification. Processes should be agreed as part of Pathfinder project but software to be used has already been changed Integrate processes using existing Syllabus Plus software Great enthusiasm for the technology from Management lecturer Sudden rush of enthusiasm for CAA Still a potential for this to happen JH WASP testing underway. WASP abandoned. See risk 23 1/11/07 22/8/08 18 Transfer of marks after assessment cannot be done securely into SITS software 3 4 12 Investigate alternative mechanisms or continue existing practices JD Manual transfers already successful Manual transfer continuing due to data inconsistencies 1/11/07 15/6/09 14 Page 3 ITS4SEA Score (PxS) Action to Prevent/Manage Risk Person responsible Severity (1-5) Risk Probability (1-5) Risk id JISC Institutional Exemplar Actions taken Date identified Date last reviewed 19 Space allocated for cluster is not large enough for 120 positions 4 4 16 Try to negotiate larger proportion of space available SE Initial layout produced fits 69 Layout houses 99 student positions 27/5/08 27/5/08 20 Questionmark Perception software is unreliable 4 5 20 Report faults to supplier. Apply all software patches JD Advise authors to follow rules and recommendations for CAA No failures 2/6/08 15/06/09 21 WASP exams scheduling software is unreliable 5 5 25 After 6 months testing decided to abandon implementation RG Software abandoned 2/6/08 22/8/08 22 Full scale trial of CAA cluster cannot be run before real exam 5 4 20 SE URGENT – test needed Exams ran OK Jan09 9/6/08 10/12/08 25/2/09 23 After abandoning WASP, new system cannot be completed in timeframe of project 4 5 20 Cluster development timed to complete before last week of term. May need to get volunteers in vacation to fully load system More regular project team meetings SE/ RG 5/8/08 15/6/09 24 Software on lecturers PC allows invigilator to change student responses 2 5 10 Need to control configuration of NetSupport School AW 1/9/08 15/6/09 25 Conflicting priorities on developers time 5 4 20 More frequent project team meetings SE/ CT Prioritised list of work developed. Budgets organized to allow continued development after formal project end. Software under development in association with supplier Timetable developed for ExamAdmin 1/9/08 15/6/09 Page 4 ITS4SEA Score (PxS) Action to Prevent/Manage Risk Person responsible Severity (1-5) Risk Probability (1-5) Risk id JISC Institutional Exemplar 26 Funding for development of Sun Ray cluster insufficient 4 5 20 Additional E-strategy funding being requested. Finances for build still not agreed SE/ PH 27 CAA expert post only funded until June 2009 5 5 25 Funding to continue post for further 12 months requested to support increased uptake of CAA SE/ PH 28 What level of risk is acceptable for failure of IT systems during online exams 5 5 25 Failover QmP servers, failover VDI and Sun Ray servers. Or paper based assessment methods or reschedule exams JD/ JR Actions taken Date identified Date last reviewed £100K identified as potentially available. E-strategy request refused Being handled outside project E-strategy finance manager contacted Extended until June 2010 18/9/08 10/12/08 25/2/09 15/12/08 15/6/09 Raise at project board 17/2/09 15/6/09 Page 5