Summer IT Project Update Tech Talk September 11, 2007 Wireless Networking Wireless network access available campus-wide Over 220 access points Work still underway in Fine Arts Center, Allen Center, Sparks Center, Center Hall, small houses, some outdoor spaces Improved guest access and high-security options will be available later this fall Usage stats: week | month Computer Lab Upgrades New computers installed in Library computer lab, Baxter 214 New high-speed printers installed in Library computer lab, Library reference area, and both Armory labs Academic Projects Physics mobile computer lab (15 Macbook laptops) replaced Installed Stata (statistical software package) in computer labs LabView for Physics Present Indiana summer projects Creating group work area on 1st floor of Lilly Library (in progress) Classroom Upgrades New projectors installed in 16 classrooms New computers installed in 18 classrooms Supercarts installed in 33 classrooms (work ongoing) New projection systems in Detchon 220, Library 3rd floor seminar room (coming soon) Summer Tech School 21 classes offered Approximately 150 attendees 72 people completed online evaluation form 95.8% rated workshop “excellent” or “good” 90.1% would definitely recommend the workshop to another person Media Center Created dual-boot iMac Lab Apple TV, with instructional videos Editing stations have Apple monitors, providing better color-matching Implemented new student worker training program Enhanced podcasts coming soon to podcasts page Online Services New home page (debuts later today) Fraternity web pages Real-time online honor roll Video virtual tour (coming soon) Sports site enhancements | livestats Networking Projects Network upgrades for College Hall, Delta Tau Delta Traffic shaping methodology changed Upgrading Blackboard server hardware (in progress) Beginning process to connect Wabash to iLight state-wide network Phone system upgraded – new features available this fall Tape backup system Installation in progress Two LTO-3 Ultrium 960 drives 48 media slots 800GB storage capacity per tape 38.4TB total storage capacity Maximum transfer rate 1.1TB/hour Storage Area Network Installation in progress Provides 12 terabytes of data storage Allows for server virtualization, which reduces hardware costs and improves redundancy Data snapshots reduce backup and recovery time Administrative Computing Upgrade to Colleague R18 Migrated to Datatel’s New User Interface Licensed Activities and Events module for advancement office Computer Installations 235 new computers installed New web-based installation schedule process Off-lease laptop computers sold through lottery system (300 entries for 65 computers) To reduce equipment costs, most monitors were retained Equipment Disposal Recycled 22,525 pounds of broken and obsolete equipment with Recycle Force (Indy) Planning community recycle day this fall Windows Vista/Office 2007 Support Vista and Office 2007 supported for student use Campus computers will be upgraded in summer 2008 Vista remote access instructions will be posted to web site soon See knowledge base for information on reading Office 2007 files in Office 2003 Miscellaneous Added 12 Canon G7 digital cameras to checkout pool Added 2 Canon ZR850 digital video cameras to checkout pool Migrated to new version of Exact Target (bulk email program) Implementing web-based printing solution that will allow printing to campus printers without special computer setup