Construction Progress Schedule April 2016 Written by Steve Collins West Campus Reroofing - Completed Greyhound Stadium – Field Drainage, Base Coarse to be installed on the Field this month (Completed). Turf to be installed on Field this month. Concrete flatwork to be continued this month on concourse and visitors side. Press box and Elevator Roof underway, Concession Room roofs mostly complete. Press box Sound and Thermal Insulation. North and South Concessions Overhead Coiling Windows to be installed. North and South Concessions Doors and Door Hardware to be installed. North and South Concessions Tape, Texture and Paint to be done. Locker Rooms and Visitors Toilets, Thermal and Sound Insulation, Sheetrock, and Exterior Finish systems to be done this month. Golden Library –Shelving completed in CUB Ground Zero and ASAB Office for Temporary Library Housing in preparation for Library Renovations starting next summer. Library relocation shelving also started in Building 625. Preparations underway in Bernalillo Hall to house Library Offices.