Construction Progress Schedule April 2016
Written by Steve Collins
West Campus Reroofing - Completed
Greyhound Stadium – Field Drainage, Base Coarse to be installed on the Field this
month (Completed). Turf to be installed on Field this month. Concrete flatwork to
be continued this month on concourse and visitors side. Press box and Elevator
Roof underway, Concession Room roofs mostly complete. Press box Sound and
Thermal Insulation. North and South Concessions Overhead Coiling Windows to
be installed. North and South Concessions Doors and Door Hardware to be
installed. North and South Concessions Tape, Texture and Paint to be done.
Locker Rooms and Visitors Toilets, Thermal and Sound Insulation, Sheetrock, and
Exterior Finish systems to be done this month.
Golden Library –Shelving completed in CUB Ground Zero and ASAB Office for
Temporary Library Housing in preparation for Library Renovations starting next
summer. Library relocation shelving also started in Building 625. Preparations
underway in Bernalillo Hall to house Library Offices.