Start up and Commissioning of Pipelines Presentation by D. S. Nanaware, Chief Project Manager, IOCL, Noida IiPM, Gurgaon 10th July 2009 Contents Methodology for Pre-commissioning of new pipelines Objectives Task Forces Responsibility of Project/Construction Group Responsibility of O& M Group Responsibility of Fire & Safety Group Documentation Commissioning Handing/Taking Over Case Study 10th July 2009 IiPM, Gurgaon 2 Methodology for Pre-commissioning of New Pipelines 10th July 2009 IiPM, Gurgaon 3 Objectives Preparation of pre-commissioning and commissioning plan Safe commissioning of pipeline system Safe and smooth commissioning Proper handing over & taking over of pipeline system Preparation of check list for all pending activities Liquidation of check list points in a time bound manner 10th July 2009 operation IiPM, Gurgaon of pipeline after 4 Task Forces For efficient startup/commissioning specialized task-force can be formed including specialists from: Projects/Construction Group Operations & Maintenance Group Fire & Safety Group 10th July 2009 IiPM, Gurgaon 5 Responsibility of Projects/Construction Group The group will ensure: Mechanical completion of pipeline system Hydro-testing and pigging of entire pipeline Inertization of pipeline Ensuring readiness of pipeline system for commissioning Handing over of pipeline system (including spares, tools, equipment etc) for operation Handing over of relevant documents and certificates to O&M group 10th July 2009 IiPM, Gurgaon 6 Responsibility of O&M Group The O&M group will ensure: Verification and taking over of all contract, project and operation related documents before pre commissioning activities All checks for ensuring system integrity and functionality Verification of all statutory permissions Verification of relevant inspection reports and certificates etc. Verification of vender’s documents for material supply 10th July 2009 IiPM, Gurgaon 7 Responsibility of O&M Representative (contd..) Verification of agreements and MOUs with product suppliers and consumers Preparation of check list with target completion dates for all contracts works and material POs Enlisting of all construction surplus materials, and equipment with all relevant inspection, test certificates and other documents Ensure preparation of check list for balance jobs Verification and taking over the project DFR, concept note and project approvals etc 10th July 2009 IiPM, Gurgaon 8 Responsibility of Fire & Safety Representative Verification of Fire network and equipments as per relevant OISD standards Check the adequacy of first aid fire fighting appliance as OISD Std. 117 Ensuring placement of fire fighting equipments/instruments as per OISD Std. 117 Check the compliance of safety audits, OISD audits and Pre-commissioning audits Check the integrity of fire fighting system before start up and commissioning 10th July 2009 IiPM, Gurgaon 9 Documentation The O&M Documentation In-charge shall take over and ensure proper distribution of documents related to: A. Statutory clearances/Permissions Factory License as per factory act 1948 State Pollution Control Board and Ministry of Environment & Forests (MoEF) clearances State & Central Electricity Authority Permissions (wherever required) Clearance for frequency in case of Radio set, WalkyTalky/VHF /UHF Clearance from CCOE 10th July 2009 IiPM, Gurgaon 10 Documentation A. Statutory clearances/Permissions (contd..) Permissions/Agreements executed for Railways, Road (NH & SH), Canal, OFC and any other crossings Authorization for hazardous waste rule (Management & handling - 1989) B. Revenue and RoU related documents Detailed RoU Survey Reports with Survey Numbers Tree & Crop compensation details and documents Land acquisition documents, ROU Cadastral Map Field management books (FMBs) List of disputes / pending complains with detail status 10th July 2009 IiPM, Gurgaon 11 Documentation C. Construction Related Documents Mechanical Completion Certificate Hydro testing acceptance certificates Equipments Commissioning Certificate with commissioning history Work order copies and Contracts Construction QA/QC records, Procedures and inspection records Radiography films and records MOUs and agreements with product suppliers and consumers (Copies) 10th July 2009 IiPM, Gurgaon 12 Documentation C. Construction Related Documents (contd..) Agreements with contractors, venders, material / Equipment suppliers All taxes and duties statements SAT (Site acceptance Test) of all instruments including certificates and loop testing certificates Process Flow Diagram As-build drawings such as plot plan, cable route drawing, earthing and P&ID etc. 10th July 2009 IiPM, Gurgaon 13 Commissioning of New Pipelines 10th July 2009 IiPM, Gurgaon 14 Objective of Commissioning Commissioning is to bring the constructed / installed system to deliver the desired function. Pipeline commissioning means introducing crude/ product/Gas in the pipeline from originating station, filling the entire length and then start delivering to the planned receipt system. In case of crude pipeline, there may be intermediate storage stations for operational requirement but ultimate supply is to be made to a refinery In case of product pipeline/Gas pipeline, there may be several intermediate delivery stations before terminal/dispatch station. 10th July 2009 IiPM, Gurgaon 15 Pre-commissioning Preparation of commissioning manual A document describing the procedure to be followed for commissioning is to be prepared by experienced persons The purpose of making the document is to set forth the objectives of commissioning of pipeline system and to establish guidelines for safe commissioning in order to achieve the required goals. Pre-commissioning check list A check list is prepared, which covers the technical, safety as well as statutory requirement before the pipeline and associated facilities is declared ready for commissioning. 10th July 2009 IiPM, Gurgaon 16 Pre-commissioning (contd..) Constituting a pre-commissioning team: A committee of experienced engineers is constituted to audit the construction as per pre-commissioning check list and report to the management regarding readiness of the system or any shortcomings to be complied before commissioning. Procurement of consumable/tools/pigs etc: As mentioned in the Commissioning Manual, required consumables, tools, pigs, spares and safety equipments are to be made available prior to commissioning. Availability of product/ crude: As per line fill calculation, the availability of crude oil or the product, as the case may be, is to be ensured at originating / pumping station in coordination with Refinery and Marketing. 10th July 2009 IiPM, Gurgaon 17 Commissioning Pipeline sections are generally commissioned in phased manner / in totality based on the situation and preparedness. After hydro-testing and caliper pigging it is expected that the sections are in a fairly clean condition. 10th July 2009 IiPM, Gurgaon 18 Commissioning action plan Constituting a commissioning team: A committee of experienced engineers is constituted to perform the objective of commissioning. Scrutiny of audited pre-commissioning check list: The committee to ensure the compliance of any shortcomings reported in the pre-commissioning check list. Identification and deployment of manpower at new stations Deployment of security personnel at stations Arrangement of water and disposal plan 10th July 2009 IiPM, Gurgaon 19 Commissioning steps Pressurization of pipeline section with compressed air up to 3-5 Kg/sq cm. Injection of about 500 to 1000 KL water into the section from launching barrel end Launching of cleaning (bi-di) pig after introduction of water in the line Maintaining 5-10 kg/sq.Cm back pressure at other end by venting the air Introducing about 1000 to 3000 KL of water behind the cleaning pig Launching batching (bi-di) pig 10th July 2009 IiPM, Gurgaon 20 Commissioning steps (contd..) Introducing HSD / Crude in the line and maintaining 5 to 10 Kg/sq.cm back pressure at other end. Draining dirty water to storm water drain / pre-fixed drain outlet at the receiving end Receiving cleaning pig Again draining dirty water to storm water drain Receiving batching pig Lining up marketing HSD receipt tank /Refinery or Pipeline crude receipt tank Flow to be diverted to HSD / Crude receipt tank as soon as oil traces are observed. Temporary facility for water draining to be dismantled & permanent blinding put 10th July 2009 IiPM, Gurgaon 21 Commissioning steps (contd..) Since, before pumping water, line is filled with air at a predetermined pressure, so monitoring and air draining facility is kept ready at receiving end to maintain back pressure of air at 5 to 10 Kg/sq.cm Pumping into an empty line will cause excessive flow rate & current in the motors resulting in frequent tripping. May result in increase of interface length. As the pig reaches at receiving end, it is taken out. The muck & dirt quantity is collected and after analysis it is disposed off. Handing over the system to operating group 10th July 2009 IiPM, Gurgaon 22 Commissioning steps (contd..) Specific check points/procedure for Gas Pipelines LPG Pipelines ATF Pipelines 10th July 2009 IiPM, Gurgaon 23 Handing/Taking Over HANDING / TAKING OVER FORMAT NAME OF PROJECT : ______________________ LOCATION : ______________________ PROJECT IDENTIFICATION : ______________________ PROJECT COST : ______________________ PMC : ______________________ CONTRACTOR : ______________________ DATE OF COMMISSIONING : ______________________ 10th July 2009 IiPM, Gurgaon 24 Handing/Taking Over I. 1. DETAILS OF FACILITIES TO BE HANDED OVER _____ INCH DIA. P/L FROM _______ TO ______ (ALONGWITH OFC) HAVING DESIGNED CAPACITY OF ______ MMT/MMSCMD AT PRESSURE _________KG/CM 2. ORIGINAL/DISPATCH TERMINAL/ STATION AT : ______________________ 3. RECEIVING TERMINAL AT : ______________________ 4. SV/IP STATIONS ALONG PIPELINE AT : ______________________ 5. ANY OTHER FACILITIES (IF APPLICABLE) : ______________________ 6. HDD (IF ANY) DETAIL 10th July 2009 : _____________________ IiPM, Gurgaon 25 Handing/Taking Over II. IMPORTANT PARAMETERS AND DATES 1. MECHANICAL COMPLETION DATE OF MAIN LINE WORKS: __________ 2. PIGGING (FOAM, GAUGE, CLEANING PIG & EGP) : __________ 3. HYDRO — TEST & DESIGN PRESSURE OF MAIN LINE : __________ 4. MECHANICAL COMPLETION DATE OF RECEIVING : __________ & ORIGINATING TERMINALS 5. INSTRUMENTATION COMPLETION DATE : __________ OF TERMINAL STATION 6. COMMUNICATION SYSTEM COMPLETION DATE : __________ 7. SCADA AND TELEMETRY COMMISSIONING DATE : __________ 8. DATE FOR PRODUCT/GAS CHARGING IN THE SYSTEM : __________ 9. FINAL DATE OF COMMISSIONING : __________ 10th July 2009 IiPM, Gurgaon 26 Handing/Taking Over III. STATUS OF SYSTEMS / FACILITIES TO BE RECORDED BEFORE TAKING OVER (A) Pipeline & CP 1. Status of ROU, CP test points and Markers OK/ Not OK 2. Checking of mainline & by—pass line valves & Actuator OK / Not OK 3. Physical Status of SV/IP, receiving & Pump stations OK / Not OK 4. Performance test of SVs/IP station Done / Not Done 5. Checking of casing shorting at crossings. Done / Not Done 6. Status of Temporary CP Removed./ Not Rmd 7. Status of captive power system Comm / Not comm. with battery bank (wherever applicable) 8. if pipeline is not charged, is it dried & filled with inert gas 10th July 2009 IiPM, Gurgaon Yes / No 27 Handing/Taking Over (B) COMMUNICATION & SCADA 1. Status of communication system Comm / Not comm. 2. OFC Checking Done/Not Done 3. Status of SCADA and telemetry system Comm / Not comm. (If applicable) 4. Communication between the RTU OK/ Not OK at maintenance bases 5. Communication between the flow OK/ Not OK computers to RTU/SCADA for Master Control Centre 10th July 2009 IiPM, Gurgaon 28 Handing/Taking Over (C) INSTRUMENTATION & METERING 1. Status of metering systems (If applicable) Yes/NO 2. Checking of Instrumentation Panel (If Applicable) Comm/Not comm. 3. Status of Chromatographs (If applicable) Done / Not Done 4. Status of Instruments at SVs/RRs/IPs comm/Not comm. 5. Remote operation of Valves at SVs & Terminals. OK/NOTOK 6. Status of UPS Comm. /Not comm. (D) ELECTRICAL SYSTEM 1. Checking of Electrical Panel & battery backup (If Applicable) Comm/Not comm 2. Electricity at terminals/distribution stations from S.E. Board OK/NOTOK 3. Earthings system Comm/Not comm. 3. Lighting Comm/Not comm. 4. Lightening Protection System OK/NOTOK 10th July 2009 IiPM, Gurgaon 29 Handing/Taking Over (E) FIRE & SAFETY 1. Status of Fire fighting Systems OK / Not OK 2. Status of fire detection system at SVs/RRs/lPs & Terminals Comm/Not comm. 3. Status of on line extinguishing system at SVs/RRs/lPs Comm./Not comm. 4. Safety audit by Fire & Safety personal from O&M Done/ Not Done (F) GENERAL 1. Status Control Buildings Construction Comp./Not Comp. 2. Status of basic amenities for security guards at the Done / Not Done permanent establishment (Security rest room, water, lighting arrangement) 3. Preparation of final checklist before taking over 10th July 2009 IiPM, Gurgaon Done / Not Done 30 Handing/Taking Over (G) DOCUMENTATION 1. Listing & handing over of all procedures, reports, Done / Not Done certificates, vender manuals, drawings and related documents which are to be handed over as per Contractual obligation with the venders 2. Listing & handing over of “As builds”, Alignment Done / Not Done sheet, hydro test report, Pigging report, pipeline route map, pipe book, crossing details (Hard copy & soft copy) 3. Revenue records & records for permanent land acquisition Done! Not Done 4. Certificates related to Metering system Done I Not Done (H) SPARES 1. Commissioning spares Handed over/not handed over 2. Two years spares Handed over/not handed over 10th July 2009 IiPM, Gurgaon 31 Case Study: Commissioning of SSPL Name of Pipeline : Sidhpur- Sanganer Pipeline Length : 517 km Pipe Size & Thickness: 18’ OD x 0.250” WT Pipe Grade : API 5L-X65 Capacity : 3.4 MMTPA (5.7 Max) MAOP : 92 Kg/cm2 Line fill : 79840 Kl 10th July 2009 Sidhpur - Kot : 28500 Kl Kot - Baghsuri : 30500 Kl Baghsuri - Sanganer : 20840 Kl IiPM, Gurgaon 32 Thank You 10th July 2009 IiPM, Gurgaon 33