John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
THEMIS
Mission Integration Working Group (MIWG) #7
Ground Operations Working Group (GOWG) #5
Delta - Ground Operations Review (GOR)
November 29, 2006
KARS Park, KSC, Florida
Hosts: Garrett Skrobot, NASA Mission Manager (MM)
William Van Dyke, NASA Launch Site Integration Manager (LSIM)
Agenda
November 29, 2006
Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
MISSION INTEGRATION WORKING GROUP (MIWG) #7
•
THEMIS Project Status
–
•
•
•
P. Harvey/UCB
Payload Schedule Update (Astrotech and Launch Site Schedules)
Delta Program Status
–
LV Hardware Status
–
Program Issues
Mission Integration Status
–
Integration Schedule
–
Requirements Verification Matrix
–
SCN Review
–
Release of ICD Rev A
–
Action Item Review
L. Loucks/Boeing
L. Loucks/Boeing
D. Tran/Boeing
Launch Site Integration Status
–
Side by Side Testing/Ladder Mods/SSS Installation
V. Segall/Boeing
–
Fueling & Procedure Status
C. Davis/NASA
–
Range Status on Required Deliverables & Procedures
J. Wethern/45SW
Agenda
November 29, 2006
Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
MISSION INTEGRATION WORKING GROUP (MIWG) #7 - Continued
•
Analysis Results
L. Loucks/Boeing
DTO Update
–
Thermal
–
RF Link Analysis
–
Controls/ACS Gas Budget Update
•
Mobile Telemetry Coverage
L. Loucks/Boeing
•
Launch Management Update
KSC
•
Mission Success Overview
KSC
•
Review Spacecraft Mandatory / Required Launch Criteria
KSC
Agenda
November 29, 2006
Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
GROUND OPERATIONS WORKING GROUP (GOWG) #5/ Delta GOR
•
Astrotech Readiness/Issues
G. Gleeson/ASO FL
•
THEMIS Badging & Training Plan
K. Kerr/Analex KSC
•
Launch Site Safety Status/Readiness
C. Loftin/NASA Safety
•
Telemetry and Communications Status/Readiness
M. Lougheed/NASA KSC
•
Spacecraft Procedure Status/Review
R. Sterling/UCB
•
Launch Site Readiness Poll (Go/No Go)
–
THEMIS Project
P. Harvey
–
NASA KSC Public Affairs
G. Diller
–
Boeing Delta Mission Integration
V. Segall
–
Astrotech Mission Management
G. Gleeson
–
NASA LS Telemetry & Communicaitons
M. Lougheed
–
NASA KSC Safety
C. Loftin
–
NASA MM
G. Skrobot
–
NASA LS Launch Site Integration
W. Van Dyke
–
NASA LS Launch Site Integration Branch
F. Stone
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
THEMIS PAYLOAD STATUS
Peter R. Harvey
Project Manager
University of California - Berkeley
Payload Status
John F. Kennedy Space Center
•
PCA Assembly and Test
LAUNCH SERVICES PROGRAM
Payload Status
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Acoustics
& Shock
Vibration
Thermal Vacuum
Spin Balance
FM2/FM3 Thermal
Storage Vacuum
ASO/PAD Schedule 1
John F. Kennedy Space Center
DATE
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
ASO
(F5)
Unpack Probe Unpack Probe Unpack Probe
Unpack Probe Unpack Probe
and EGSE
and EGSE
and EGSE
(ASO1)
(ASO1)
(ASO1)
(ASO1)
(ASO1)
11-Dec
EGSE1 Setup, EGSE2 Setup, EGSE3 Setup,
Install Bolt
Thermal
Thermal
Cutters
Closeouts
Closeouts
Install Bolt
Cutters
Install Bolt
Cutters
Thermal
Closeouts
Thermal
Closeouts
ASO
(PC and PCA)
PC Unpack
(ASO2)
12-Dec
Thermal
Closeouts
Install Bolt
Cutters
Install Bolt
Cutters
13-Dec
RCS MEOP &
LEAK
LPT, S/A Test
14-Dec
RCS MEOP &
LPT, S/A Test
LEAK
15-Dec
RCS MEOP &
LPT, S/A Test
LEAK
16-Dec
PC-VCO TEST
PAD
ASO/PAD Schedule 2
John F. Kennedy Space Center
DATE
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
RCS MEOP &
LEAK
ASO
(F5)
ASO
(PC and PCA)
LPT, S/A Test
INSTALL SEP
HARNESS
PAD
18-Dec
LPT, S/A Test
RCS MEOP & INSTALL SMD
LEAK
LINES
19-Dec
Probe
Transport to
ASO2
Probe
Transport to
ASO2
Probe
Transport to
ASO2
Probe
Transport to
ASO2
Probe
Transport to
ASO2
20-Dec
21-Dec
Weigh, Move Weigh, Move Weigh, Move Weigh, Move Weigh, Move
to Stands
to Stands
to Stands
to Stands
to Stands
22-Dec
Note: RCS MEOP & Leak are performed after hours
ASO/PAD Schedule 3
John F. Kennedy Space Center
DATE
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
ASO
(F5)
SLACK
1-Jan
SLACK
2-Jan
3-Jan
4-Jan
5-Jan
6-Jan
7-Jan
8-Jan
ASO
(PC and PCA)
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe
Fueling
Probe RCS
Electrical
Verifications
Probe RCS
Electrical
Verifications
Probe RCS
Electrical
Verifications
Probe RCS
Electrical
Verifications
Probe RCS
Electrical
Verifications
Wet Weigh,
Probe to PC,
Attach Pyro
Wet Weigh,
Probe to PC,
Attach Pyro
Wet Weigh,
Probe to PC,
Attach Pyro
Wet Weigh,
Probe to PC,
Attach Pyro
Wet Weigh,
Probe to PC,
Attach Pyro
Bag PCA
9-Jan
10-Jan
PCA FNL
11-Jan
PCA FNL
12-Jan
SLACK
PAD
ASO/PAD Schedule 4
John F. Kennedy Space Center
DATE
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
ASO
(F5)
ASO
(PC and PCA)
PAD
Spin Balance
and Weigh
15-Jan
16-Jan
17-Jan
18-Jan
19-Jan
20-Jan
21-Jan
22-Jan
PCA FNL
SLACK
SLACK
SLACK
SLACK
SLACK
SLACK
SLACK
23-Jan
24-Jan
SLACK
25-Jan
SLACK
26-Jan
Mate to 3rd
Stage
PCA EGSE TO
BLKHSE
PCA COMM
CHECK
PCA COMM
CHECK
ASO/PAD Schedule 5
John F. Kennedy Space Center
DATE
29-Jan
30-Jan
31-Jan
1-Feb
2-Feb
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
ASO
(F5)
ASO
(PC and PCA)
PAD
S/C
Clampband
3rd Stage and
S/C Can Up
Encapsulation
Transport to
Pad
T-10 S/C
Functional &
RF Test
3-Feb
4-Feb
5-Feb
6-Feb
7-Feb
8-Feb
9-Feb
T-9 S/C
Launch
Rehearsal
T-8 Power On
Stray Voltage
T-7 Power Off
Stray Voltage
T-6 Remove
Bag, Fairing
Installation
T-5 Fairing
Finaling
ASO/PAD Schedule 6
John F. Kennedy Space Center
DATE
LAUNCH SERVICES PROGRAM
ASO
(F1)
ASO
(F2)
ASO
(F3)
ASO
(F4)
ASO
(F5)
ASO
(PC and PCA)
PAD
T-4 FRR, Prop
Load Prep
12-Feb
13-Feb
T-3 Second
Stage
Fueling,
Ordnance
14-Feb
T-2 Launch
Readiness
Review
T-1 Launch
Countdown
Start
**Launch **
15-Feb
Pack-UP
16-Feb
17-Feb
18-Feb
19-Feb
SHIP
ASO/PAD Manpower
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Manpower
 27 Max while at ASO
 31 Max while at PAD
35
30
25
20
15
10
5
2/19/07
2/12/07
2/5/07
1/29/07
1/22/07
1/15/07
1/8/07
1/1/07
12/25/06
12/18/06
12/11/06
0
Summary
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Summary Status
 Probes and Probe Carrier are Flight Ready
 Plans and Procedures for ASO/PAD in Good Shape
 Shipment Contracted Two Trucks w/ Lead Car Ready
Issues Potentially Impeding Launch Processing
 None
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Side by Side Testing / Ladder Mods /
SSS Installations
V. Segall / Boeing KSC
Cape Status
John F. Kennedy Space Center
•
LAUNCH SERVICES PROGRAM
Access Ladder
– Ladder modified, proof loaded, available for use
•
Side-by-Side Testing
– Procedure written and reviewed; ready for use
– Date (15 Dec) coordinated
– Logistics of delivery (14 Dec) discussed
» Fork lift identified and available
» Mission Integration will facilitate access for non-badged people
» Actual delivery schedule discussion planned for post Astrotech THEMIS delivery
Cape Status
John F. Kennedy Space Center
•
LAUNCH SERVICES PROGRAM
SSS Installation
– Installation will be at Astrotech
» Task is a payload support function; not a liability issue
» Procedure (DCI) is written and in the review process
» Date is under review: THEMIS requests the week of 18 Dec, but Boeing may not be
ready until after the 3rd of Jan. See schedule
•
•
Later date needs real time coordination in parallel with THEMIS fueling activities in the HPF
The SSS installation is planned for a separate bay so that mechanical operations will be deconflicted
THEMIS Upperstage Processing
THE DELTA PROGRAM
John F.NOVEMBER
Kennedy Space Center
20
27
Level 6 Schedule
2006
4
DECEMBER
18
11
25
Date 22 November 2006
Rev: 27 now
2007
JANUARY
1
8
LAUNCH SERVICES
PROGRAM
15
LPD Pulls G200, G201, G202, G203
Motor Dome Clean Check - (FACD) - (DCI: TBD)
Equipment Transfer & Data Station Preps & Quals - (G200 T1)
PAF Receiving & Mech Preps in Airlock - (G200 T1)
PAF Elec Equipment Installation - (G200 T2)
PAF Telemetry Preps - (G200 T3)
Motor Offload & Leak Check/Transfer - (G202 T1)
PAF Telemetry Test - (G200 T3)
Spintable Mechanical and Electrical Preps - (G201 T1)
Motor Bracket & Standoff Installation - (G203 T1)
PAF NCS Checks - (G200 T4)
PAF NCS N2H4 Load Preps - (G200 T5)
PAF NCS Test Securing - (G200 T4)
Spacecraft Probe Carrier - Available
PAF NCS N2H4 Load - (G200 T5)
PAF/Spacecraft SBS Test Preps - (G200 T3) - (DCI: 1)
NCS Vehicle N2H4 Load Securing - (G200 T5)
PAF Mate Preps - (G203 T1)
Receive and Inspect SSS Ordnance
PAF Mate to Motor - (G203 T1)
PAF/Spacecraft SBS Test - (G200 T3) - (DCI: 1)
PAF/Spacecraft SBS Test Securing - (G200 T3) - (DCI: 1)
Wire Harness Routing & Inst'l - (G203 T1)
PAF/Motor Rec'v & Ord Inst'l - (G203 T2)
Spintable Ordnance Inst'l - (G207 T1)
SSS Ordnance Installation
TM Antenna Build - (G203 T1)
Yo Weight Inst'l - (G203 T1)
22-NOV-06
15:35
[Delta Schedules - Publish]/CII_THEMIS_US_now
Page 1 of
2
THEMIS Upperstage Processing
THE DELTA PROGRAM
Level 6 Schedule
Date 22 November 2006
Rev: 27 now
2007
JANUARY
FEBRUARY
John F. Kennedy Space Center
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31LAUNCH
1 2 SERVICES
3 4 5PROGRAM
6 7 8
TM Antenna Inst'l - (G203 T2)
9
10 11
NCS & ETA Blanket Inst'l - (G203 T2)
Motor Buildup Securing - (G203 T1)
Motor Weigh - (G203 T3)
Spin Balance Preps/Adapter Balance - (G204 T1)
Transfer Motor to DPF & Align SBM - (G204 T2)
Balance PAM - (G204 T2)
Preps for Motor Mate - (G205 T1)
Clampband Inst'l - (G205 T2)
Motor Transfer to NPF/ Mate to Spintable - (G205 T1)
Clampband Finaling - (G205 T2)
Composite Electrical Preps - (G206 T1)
Third Stage Ignition S&A/Delivery/Installation - (G205 T2)
Composite Electrical Testing - (G206 T1)
Composite Electrical Test Securing - (G206 T1)
Spintable Ordnance Finaling - (G207 T1)
Transport Canister Preps - (G209 T3)
Third Stage/Spacecraft Mate Preps - (G208 T2)
Spacecraft Weigh Preps (Astrotech) - (G208 T1)
Third Stage Close-out - (G207 T1)
Transfer Third Stage to Astrotech - (G208 T3)
Spacecraft Weigh - (G208 T1)
Spacecraft Mate/Clampband Inst'l/Tensioning - (G208 T2)
Spacecraft Clampband Finaling - (G208 T2)
Spacecraft Finaling - (Spacecraft Ops)
Engineering Walkdown - (G209 T1)
Third Stage & Spacecraft Can-up & Transport Preps - (G209 T1)
Third Stage & Spacecraft Transport to Pad - (G209 T1)
22-NOV-06
15:35
[Delta Schedules - Publish]/CII_THEMIS_US_now
Page 2 of
2
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
KSC Fueling Team Status for THEMIS
Presented to: THEMIS Pre-Ship GOR
By: Chuck Davis
Fueling Team Lead, TA-E3
November 29, 2006
KSC
KSC Fueling Team Status
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• Procedures:
– THEMIS-specific deviations to OMI’s E5534 & E5502 are complete &
under final review prior to obtaining signatures
– OMI E5535 off-load procedure & pre-planned THEMIS-specific
deviations will be available if required
•
•
•
•
ICD “Appx. C” is complete
MSPSP - Fueling GSE portion is complete
All GSE will be in-calibration at the time of use
Schedule:
– Mobilize to Astrotech and set up GSE week of Dec 11
– Connect to spacecraft ~ Jan 3
– Prop load Jan 4
• Prop Loading Team is GO for THEMIS shipment
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Range Status on Required
Deliverables & Procedures
J. Wethern/45SW
Range & Deliverables Status
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• MSPSP RELEASED & APPROVED
• All required deliverables are up to date
• PC handling procedure & Side by Side test are in review
– All hazardous procedures in the NPF require Range Safety approval
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Astrotech Readiness / Issues
Gerard Gleeson / ASO FL
Mission Specific Items
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• Item 1005 Phone installation in Control Room – to be performed after arrival, units available
• Item 1030 Training and Badging - to be performed after arrival
• Item 1101 SCAPE Suits – to be delivered as required prior to loading operations
• Item 1180 Training for Cranes and Forklifts - to be performed after arrival
• Item 4000 LAN configuration – to be completed on arrival – infrastructure is ready
• Item 4110 IONet configuration – to be completed on arrival – infrastructure is ready
• Item 4500 Voice Stations - to be installed after arrival, units available
• Documentation
• UCB Procedures received and reviewed, Comments sent to UCB
• No major issues associated with Themis processing at Astrotech
• Deliverables
• All deliverables on site and ready for use, certificates presented in Data package as required
Astrotech is ready to receive THEMIS
ASO Occupancy
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
2006 Projected Occupancy Plan
ASO
Revision date: 11-20-06
Month
Start of Week Monday
January
2
9
16
Atlas
February
23 30
6
13
M arch
20 27
6
13
20
Delta
April
27
3
10
17
M ay
24
1
8
15
ASO
June
22 29
5
12
July
19 26
3
10
17
August
24
31
Main Conf. Room
7
14
21 28
Sept ember
4
11
18
Oct ober
25
2
9
16
23 30
November
6
13
20 27
December
4
11
18
January
25
1
8
15
February
22
ST P - AV5 4 BC/DL
CONT INGENCY
A High Bay
A Control Room
Astra-AV4
A Office
B High Bay
ST P - AV5 4 BC/DL
B Control Room
B Office
C High Bay
T hemis - D2 GG/RF
C Control Room
P
P
F
C Office
Stereo
D High Bay
ASO Laminar Flow
D Control Room
GOES- N
D Office
D Conf Room Downstairs
Stereo - D2
GG/DL - VS
GOES- N
E Control Room
E Office
E Conf Room Upstairs
F Office Quad 1
F Office Quad 2
GOES- N (Opt 1)
ASO Mod
Astra-AV4
Stereo
F Office Quad 3
F Office Quad 4
S Encap Bay
S High Bay
H
P
F
Spin Bay
D2 & Stereo
D2
D2-T
S
D2 & Stereo
N Encap Bay
Th
T hemis & D2
N High Bay
5
12
19
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
THEMIS Badging & Training
Kathy Kerr / Analex KSC
KSC Badging & Training Status
John F. Kennedy Space Center
•
LAUNCH SERVICES PROGRAM
SLC-17 Badging & Training
– 41 THEMIS personnel identified for unescorted access to SLC-17
» 36 have good NAC/PRP; 5 are In Process
– 5 THEMIS personnel identified for SCAPE operations.
» 4 have completed SCAPE training; 1 person remaining
•
Open items:
– Required training: ELSA, CCAFS Safety and SLC-17 walk downs to be
scheduled post spacecraft arrival.
– Schedule SCAPE training for one remaining person
– AF Form 2856s have been completed and submitted to me. They will be
submitted to Pass & ID about 1 month prior to required pad access.
– Air Force Badging once prerequisites have been completed.
• Launch Site Planning Readiness Statement:
– Plans are in place to complete remaining open items.
– KSC Badging & Training is ready for THEMIS flight hardware arrival.
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
NASA / KSC Safety Readiness for THEMIS
Chuck Loftin
System Safety Engineer
KSC Safety & Mission Assurance
Launch Services Division
29 November 2006
Safety Documentation Status
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• MSPSP
- Final MSPSP approved 2 Nov 06
• S/C Processing
- Ground Processing Approval letter provided prior to
THEMIS Delta GOR
• Procedures
- Integrated and Contingency Procedures under
review
Readiness Statement
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• NASA/KSC Safety and Mission Assurance,
Launch Services Division has assessed the
readiness of the THEMIS spacecraft for NASA at
Astrotech, and has no constraints to the arrival of
the Spacecraft.
- Any open items or issues are being tracked via the
Verification Tracking Log (VTL).
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Telemetry and Communications Status / Readiness
Marty Lougheed / NASA KSC
TELEMETRY &
COMMUNICATIONS READINESS
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
NASA Communications has had no change in our
position since the THEMIS GOR ……………
we are "GO" for the THEMIS 11 Dec arrival.
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Status of Launch Site Procedures
Rick Sterling
Themis I & T Manager
Launch Site Procedures
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Following charts show status, where used and whether hazardous.
THEMIS I&T: LAUNCH SITE PLANS AND PROCEDURES
PLANS
thm-sys-002
thm-sys-046
thm-sys-047
thm-sys-052
PROCEDURES
thm-mint-proc-010
thm-mint-proc-011
thm-mint-proc-013
thm-mint-proc-014
thm-mint-proc-015
thm-mint-proc-019
thm-mint-proc-032
thm-mint-proc-034
thm-mint-proc-051
thm-mint-proc-053
thm-mint-proc-054
thm-mint-proc-055
thm-mint-proc-062
thm-mint-proc-063
thm-mint-proc-065
THEMIS
THEMIS
THEMIS
THEMIS
Magnetics Contamination Control Plan
Probe Shipping Plan
Launch Site Test Plan
Launch Site Contamination Control Plan
Status
Complete
Complete
Complete
Complete
Complete
THEMIS Probe Power On/Off Procedure
Complete
THEMIS Probe Umbilical Safe-to-Mate
Complete
THEMIS Probe LPT Procedure
Complete
THEMIS Probe AT Procedure
Complete
THEMIS Probe Handling Procedure
Complete
THEMIS Probe Solar Array Illumination Procedure
Complete
THEMIS Instrument LPT Procedure
Complete
THEMIS Instrument AT Procedure
Complete
\THEMIS Probe Fueling Procedure (KSC Proc)
Complete
THEMIS Probe Pre-Launch Closeout Procedure
Complete
THEMIS Probe Battery Ops Procedure
Complete
THEMIS Probe RCS Pressure Test and Leak Check
Complete
THEMIS PCA LV Mate Procedure
Complete
THEMIS PCA Electrical Test Procedure
House)
Complete
THEMIS PCA Launch Tower Electrical Test Procedure (at Block
ASO
YES
YES
YES
YES
PAD
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
YES
HAZ
HAZ
HAZ
HAZ
YES
HAZ
HAZ
YES
Launch Site Procedures
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
To download procedures or see more detailed listing including author, revision number, etc:
ftp://apollo.ssl.berkeley.edu/pub/THEMIS/2 Space Segment/2.2 Spacecraft/2.2.7 Launch Site Processing/2.2.7.1 Launch Vehicle Integration
thm-mint-proc-066
thm-mint-proc-067
thm-mint-proc-068
thm-mint-proc-069
thm-mint-proc-070
thm-mint-proc-071
thm-mint-proc-073
thm-mint-proc-077
thm-mint-proc-076
thm-mint-proc-077
thm-mint-proc-086
thm-mint-proc-105
thm-mint-proc-106
thm-mint-proc-107
thm-mint-proc-120
thm-mint-proc-122
thm-mint-proc-125
thm-mint-proc-126
thm-mint-proc-128
thm-mint-proc-132
thm-mint-proc-141
thm-sai-proc1668
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
THEMIS
PCA Pre Launch Closeout Proc
Complete
YES
PCA Spin Balance Procedure
Complete
YES
PCA Lifting and Handling Procedure
Complete
YES
PCA Assembly Procedure
Complete
YES
PCA Separation System Test Procedure
Complete
YES
PCA Purge Bag Installation and Removal
Complete
YES
PCA EGSE Safe-to-Mate
Complete
YES
Probe Simulator to Blockhouse EGSE Verification Check-Out
In Progress
Procedure
PCA to USPP Safe-to-Mate
In Progress YES
PCA Launch Countdown
Complete
YES
RF Chirp Test
In Progress YES
Simulated Pyro Test Procedure
Complete
YES
Battery Trending Test Procedure
Complete
YES
PPMU Safe-to-Mate Procedure
Complete
YES
Facility and MGSE Magnetic Test Procedures
Complete
YES
ESA/SST Purge Hookup Procedure
Complete
YES
Probe ESC Closeout Procedure
Complete
YES
Magnetic Screening and Degaussing Procedure
Complete
YES
Handling of Pyrotechnic Devices
Complete
YES
EGSE RACKS Moving Procedure
Complete
YES
Separation System Stow Procedure
Complete
YES
Side by Side Test
Complete
YES
YES
HAZ
HAZ
HAZ
HAZ
YES
YES
YES
YES
HAZ
YES
HAZ
YES
YES
HAZ
HAZ
HAZ
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
Launch Site Readiness Poll
William Van Dyke / NASA KSC
John F. Kennedy Space Center
LAUNCH SERVICES PROGRAM
• Launch Site Readiness Poll (Go/No Go)
– THEMIS Project
Peter Harvey
– NASA KSC Public Affairs
George Diller
– Boeing Delta Mission Integration
Vic Segall
– Astrotech Mission Management
Gerard Gleeson
– NASA LS Telemetry & Communicaitons
Marty Lougheed
– NASA KSC Safety
Chuck Loftin
– NASA MM
Garrett Skrobot
– NASA LS Launch Site Integration
William Van Dyke
– NASA LS Launch Site Integration Branch