ECE 333 Renewable Energy Systems Lecture 7: Power System Operations, Wind as a Resource Prof. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign overbye@illinois.edu Announcements • • Start reading Chapter 7; also read Prof. Sauer's article on course website explaining reactive power HW 3 is posted; it will be covered by an in-class quiz on Thursday Feb 13 – Material from Power Systems history and operations will be covered on exams (such as true/false) 1 Power Flow • A common power system analysis tool is the power flow – • Solves sets of non-linear equations enforcing "conservation of power" at each bus in the system (a consequence of KCL) – – • It shows how real and reactive power flows through a network, from generators to loads Loads are usually assumed to be constant power Used to determine if any transmission lines or transformers are overloaded and system voltages Educational version PowerWorld tool available at – http://www.powerworld.com/gloversarmaoverbye 2 PowerWorld Simulator Three Bus System Load with green arrows indicating amount of MW flow Bus 2 20 MW -4 MVR Bus 1 1.00 PU 204 MW 102 MVR 1.00 PU 106 MW 0 MVR 150 MW AGC ON 116 MVR AVR ON -14 MW -34 MW 10 MVR 4 MVR 34 MW -10 MVR Home Area Used to control output of generator -20 MW 4 MVR 14 MW -4 MVR Bus 3 1.00 PU 102 MW 51 MVR 100 MW Note the power balance at each bus 150 MW AGC ON 37 MVR AVR ON Direction of arrow is used to indicate direction of real power (MW) flow 3 Area Control Error (ACE) • The area control error is the difference between the actual flow out of an area, and the scheduled flow. • Ideally the ACE should always be zero. • Because the load is constantly changing, each utility must constantly change its generation to “chase” the ACE. MISO ACE| (in MW) from 9/19/12. At the time the MISO load was about 65GW https://www.misoenergy.org/MarketsOperations/RealTimeMarketData/Pages/ACEChart.aspx 4 Automatic Generation Control • • BAs use automatic generation control (AGC) to automatically change their generation to keep their ACE close to zero. Usually the BA control center calculates ACE based upon tie-line flows; then the AGC module sends control signals out to the generators every couple seconds. 5 Three Bus Case on AGC Bus 2 -40 MW 8 MVR 40 MW -8 MVR Bus 1 1.00 PU 266 MW 133 MVR 1.00 PU 101 MW 5 MVR 150 MW AGC ON 166 MVR AVR ON -39 MW -77 MW 25 MVR 12 MVR 78 MW -21 MVR Home Area 100 MW 39 MW -11 MVR Bus 3 1.00 PU 133 MW 67 MVR 250 MW AGC ON 34 MVR AVR ON 6 Generator Costs • • • • • There are many fixed and variable costs associated with power system operation. The major variable cost is associated with generation. Cost to generate a MWh can vary widely. For some types of units (such as hydro and nuclear) it is difficult to quantify. Many markets have moved from cost-based to pricebased generator costs 7 Economic Dispatch • • Economic dispatch (ED) determines the least cost dispatch of generation for an area. For a lossless system, the ED occurs when all the generators have equal marginal costs. IC1(PG,1) = IC2(PG,2) = … = ICm(PG,m) 8 Power Transactions • • • Power transactions are contracts between areas to do power transactions. Contracts can be for any amount of time at any price for any amount of power. Scheduled power transactions are implemented by modifying the area ACE: ACE = Pactual,tie-flow - Psched 9 100 MW Transaction Bus 2 8 MW -2 MVR -8 MW 2 MVR Bus 1 1.00 PU 225 MW 113 MVR 1.00 PU 0 MW 32 MVR 150 MW AGC ON 138 MVR AVR ON -92 MW -84 MW 27 MVR 30 MVR 85 MW -23 MVR Home Area 93 MW -25 MVR Bus 3 Scheduled Transactions 100.0 MW 100 MW 1.00 PU 113 MW 56 MVR 291 MW AGC ON 8 MVR AVR ON Scheduled 100 MW Transaction from Left to Right Net tie-line flow is now 100 MW 10 Security Constrained Economic Dispatch • Transmission constraints often limit system • • economics. Such limits required a constrained dispatch in order to maintain system security. In three bus case the generation at bus 3 must be constrained to avoid overloading the line from bus 2 to bus 3. 11 Security Constrained Dispatch Bus 2 -22 MW 4 MVR 22 MW -4 MVR Bus 1 1.00 PU 357 MW 179 MVR 1.00 PU 0 MW 37 MVR 100% 194 MW OFF AGC -142 MW 49 MVR 232 MVR AVR ON 145 MW 100% -37 MVR Home Area Bus 3 Scheduled Transactions 100.0 MW -122 MW 41 MVR 100 MW 124 MW -33 MVR 1.00 PU 179 MW 89 MVR 448 MW AGC ON 19 MVR AVR ON Dispatch is no longer optimal due to need to keep 12 Line from bus 2 to bus 3 from overloading Multiple Area Operation • • • If Areas have direct interconnections, then they may directly transact up to the capacity of their tie-lines. Actual power flows through the entire network according to the impedance of the transmission lines. Flow through other areas is known as “parallel path” or “loop flows.” 13 Seven Bus Case One-line Diagram 44 MW -42 MW -31 MW 0.99 PU 3 1.05 PU 1 System has three areas 106 MW -37 MW AGC ON 62 MW 79 MW 2 40 MW 20 MVR Top Area Cost 8029 $/MWH 1.00 PU -32 MW Case Hourly Cost 16933 $/MWH 32 MW 80 MW 30 MVR 4 110 MW 40 MVR 38 MW -61 MW 1.04 PU 31 MW -77 MW 5 40 MW -39 MW 94 MW AGC ON -14 MW Area top has five buses 1.01 PU 130 MW 40 MVR 168 MW AGC ON -40 MW 1.04 PU 6 Area left has one bus 20 MW -20 MW 40 MW 1.04 PU 20 MW 200 MW 0 MVR Left Area Cost 4189 $/MWH 200 MW AGC ON -20 MW 7 200 MW Right Area Cost 0 MVR 4715 $/MWH 201 MW AGC ON Area right has one bus 14 Seven Bus Case: Area View Top 40.1 MW 0.0 MW System has 40 MW of “Loop Flow” -40.1 MW 0.0 MW Left Area Losses 0.33 MW Area Losses 7.09 MW Actual flow between areas Scheduled Area Losses flow Right 40.1 MW 0.0 MW 0.65 MW Loop flow can result in higher losses 15 Seven Bus System – Loop Flow? Transaction has actually decreased the loop flow Top 4.8 MW 0.0 MW -4.8 MW 0.0 MW Left Area Losses -0.00 MW Area Losses 9.44 MW Right 104.8 MW 100.0 MW 100 MW Transaction between Left and Right Area Losses 4.34 MW Note that Top’s Losses have increased from 7.09MW to 9.44 MW 16 Pricing Electricity • • • • • Cost to supply electricity to bus is called the locational marginal price (LMP) Presently PJM and MISO post LMPs on the web In an ideal electricity market with no transmission limitations the LMPs are equal Transmission constraints can segment a market, resulting in differing LMP Determination of LMPs requires the solution on an Optimal Power Flow (OPF) 17 Three Bus Case LMPs: Line Limit NOT Enforced Gen 2’s cost is $12 per MWh Bus 2 60 MW 60 MW Bus 1 10.00 $/MWh 0 MW 10.00 $/MWh 120 MW 120% 180 MW 0 MW Gen 1’s cost is $10 per MWh 60 MW Total Cost 1800 $/hr 120% 120 MW 60 MW 10.00 $/MWh Bus 3 180 MW 0 MW Line from Bus 1 to Bus 3 is over-loaded; all buses have same marginal cost 18 Three Bus Case LMPS: Line Limits Enforced Bus 2 20 MW 20 MW Bus 1 10.00 $/MWh 60 MW 12.00 $/MWh 100 MW 80% 100% 120 MW 0 MW 80 MW Total Cost 1921 $/hr 80% 100% 100 MW 80 MW 14.01 $/MWh Bus 3 180 MW 0 MW Line from 1 to 3 is no longer overloaded, but now the marginal cost of electricity at 3 is $14 / MWh 19 Generation Supply Curve As the load goes up so does the price Price ($ / MWh) 80 Natural Gas Generation 60 Base Load Coal and Nuclear Generation 40 20 0 0 10000 20000 30000 40000 Generation (MW) Renewable Sources Such as Wind Have Low Marginal Cost, but they are Intermittent 20 MISO LMPs on Sept 19, 2012 (11:50am EST which is CDT) Available on-line at https://www.misoenergy.org/LMPContourMap/MISO_All.html 21 MISO LMPs on Feb 6, 2015, 1pm Central Available on-line at https://www.misoenergy.org/LMPContourMap/MISO_All.html 22 MISO Annual Load Duration Curves https://www.misoenergy.org/Library/Repository/Report/Annual%20Market%20Report/20 13%20Annual%20Market%20Assessment%20Report.pdf 23 MISO Average Prices and Wind Output https://www.misoenergy.org/Library/Repository/Report/Annual%20Market%20Report/20 13%20Annual%20Market%20Assessment%20Report.pdf 24 Wind Power Systems Photos taken Kate Davis near Moraine View State Park, IL 25 Historical Development of Wind Power • The first known wind turbine for producing electricity was by Charles F. Brush turbine, in Cleveland, Ohio in 1888 • • 12 kW Used electricity to charge batteries in the cellar of the owner’s mansion Note the person http://www.windpower.org/en/pictures/brush.htm 26 Historical Development of Wind Power • First wind turbine outside of the US to generate electricity was built by Poul la Cour in 1891 in Denmark • Used electricity from his wind turbines to electrolyze water to make hydrogen for the gas lights at the schoolhouse http://www.windpower.org/en/pictures/lacour.htm 27 Historical Development of Wind Power • In the US - first wind-electric systems built in • • • • the late 1890’s By 1930s and 1940s, large numbers in rural areas not served by the grid for pumping water and sometimes electricity generation Interest in wind power declined as the utility grid expanded and as reliable, inexpensive electricity could be purchased Oil crisis in 1970s created a renewed interest in wind until US government stopped giving tax Renewed interest again since the 1990s Photo: www.daviddarling.info/encyclopedia/W/AE_wind_energy.html 28 Global Installed Wind Capacity Total worldwide electric capacity is 4500GW, so wind, at almost 250GW, is 5.6% of total Source: Annual Market Update 2013, Global Wind Energy Council, 29 Wind Capacity Additions by Region Source: Annual Market Update 2013, Global Wind Energy Council, 30 Top 10 Countries - Installed Wind Capacity (as of the end of 2013) Source: Annual Market Update 2013, Global Wind Energy Council, 31 US Wind Resources http://www.windpoweringamerica.gov/pdfs/wind_maps/us_windmap.pdf http://www.windpower.org/en/pictures/lacour.htm 32 US Wind Capacity by State, 12/31/14 33 Wind Map for Illinois at 80m 34 Worldwide Wind Resource Map Source: www.ceoe.udel.edu/WindPower/ResourceMap/index-world.html 35 Types of Wind Turbines • • • • “Windmill”- used to grind grain into flour or pump water Many different names - “wind-driven generator”, “wind generator”, “wind turbine”, “wind-turbine generator (WTG)”, “wind energy conversion system (WECS)” Can have be horizontal axis wind turbines (HAWT) or vertical axis wind turbines (VAWT) Groups of wind turbines are located in what is called either a “wind farm” or a “wind park” 36 Vertical Axis Wind Turbines • • • • • Darrieus rotor - the only vertical axis machine with any commercial success Wind hitting the vertical blades, called aerofoils, generates lift to create rotation No yaw (rotation about vertical axis) control needed to keep them facing into the wind Heavy machinery in the nacelle is located on the ground Blades are closer to ground where windspeeds are lower http://www.absoluteastronomy.com/topics/Darrieus_wind_turbine 37 Horizontal Axis Wind Turbines • • • “Downwind” HAWT – a turbine with the blades behind (downwind from) the tower No yaw control needed- they naturally orient themselves in line with the wind Shadowing effect – when a blade swings behind the tower, the wind it encounters is briefly reduced and the blade flexes 38 Horizontal Axis Wind Turbines • • • • “Upwind” HAWT – blades are in front of (upwind of) the tower Most modern wind turbines are this type Blades are “upwind” of the tower Require somewhat complex yaw control to keep them facing into the wind – • • Need to search for the wind to start turning Operate more smoothly and deliver more power Largest turbines are on the order of 6 MW with 1.5 MW a quite common design 39 Number of Rotating Blades • Windmills have multiple blades – – – – • • need to provide high starting torque to overcome weight of the pumping rod must be able to operate at low wind speeds to provide nearly continuous water pumping a larger area of the rotor faces the wind Note, most seem to write “wind speed” as two words Turbines with many blades operate at much lower rotational speeds - as the speed increases, the turbulence caused by one blade impacts the other blades Most modern wind turbines have two or three blades 40 Worldwide Wind Energy Company Market Share, 2013 Installations Source:http://www.statista.com/statistics/272813/market-share-of-the-leading-wind-turbine-manufacturers-worldwide/ 41 Vestas Stock Price https://uk.finance.yahoo.com/echarts?s=VWS.CO#symbol=VWS.CO;range=my 42