project scheduling & progress report

advertisement

Project Scheduling

Progress Report

By: Ernawati Mustafa Kamal

School of Housing, Building & Planning

Universiti Sains Malaysia

What is project?

• A project is a collection of tasks that must be completed within certain time frame, with specific cost & quality.

We lead

What is Project

Planning

Process

Land

Input

• Money (capital)

• Labour

• Material

• Machine

What do we do to get it done?

How do we do it?

Output

• Design

• Product

• Buildings

• Infrastructure

What do we want?

We lead

Project Scheduling Objectives

• Estimating time of project by determining the earliest start and finish of each activity.

We lead

 Finding the minimum cost schedule needed to complete the project by a certain date.

 Investigating the results of possible delays in activity’s completion time.

 Progress control

 Smoothing out resource allocation over the duration of the project.

Project Scheduling

• Tasks are called “activities.”

- Estimated completion time (and sometimes costs) are associated with each activity.

We lead

- Activity completion time is related to the amount of resources committed to it.

- The degree of activity details depends on the application and how specific is the data.

Identifying the Activities of a Project

We lead

• To determine optimal schedules we need to

– Identify all the project’s activities.

– Determine the precedence relations among activities.

Identifying Activities

• Example:

- Company A is a contractor & they need to construct a house.

We lead

Identifying Activities

We lead

• Major task they need to perform & complete:

- Sub-structure

- Superstructure

- Internal Finishes

- Services and finishing

- External Works

Identifying Activities

We lead

• Company A needs to develop a precedence relations chart.

• The chart gives a concise set of tasks and their immediate predecessors.

Identifying Activities

Sub-Structure

Activity

A

B

Superstructure

C

J

I

G

H

D

E

F

Description

Piling

Pile caps and ground beams

Frame

Upper Floors

Roof

Stairs and Ramps

External Walls

Windows and External Doors

Internal Walls and Partitions

Internal Doors

Internal Finishes K

L

M

Wall finishes

Floor Finishes

Ceiling Finishes

We lead

Identifying Activities

Services & Finishing

External Works

Activity

N

O

P

Q

T

U

R

S

Description

Sanitary installation

Water installation

Electrical installation

Road, Paths, Pavings & Surfacing

Landscaping and Irrigation Systems

Fencing

External drainage

External services

From the activity description chart, we can determine immediate predecessors for each activity.

We lead

Scheduling Tools & Techniques

We lead

• Mathematical Analysis

- calculating theoretical early and late start and finish dates for all projects activities without regard for any resource limitations.

- The resulting dates are not schedule, but it indicate the time period within which activity should be schedule.

Mathematical Analysis

• Critical Path Method (CPM)

• Graphical Evaluation and Review Techniques

(GERT)

• Program Evaluation and Review Technique

(PERT)

We lead

Scheduling Tools & Techniques

• Bar Charts

- Milestone charts

- Gantt charts

• Horizontal time scale is used, often divided into weeks.

We lead

• Various operations comprising the project are listed vertically down the left-hand side.

Bar Charts

• The timing and duration of each operation indicated by a horizontal bar spanning the relevant period of weeks and shown on the same line as the operation it refers to.

We lead

Example of Bar Charts

We lead

Example of Bar Charts

We lead

Example of Bar Charts

We lead

Example of Bar Charts

We lead

Progress Report

We lead

• It is a document used for updating the progress of work.

• Can be in many forms i.e: report (short report, formal report), memo, letter, or presentation.

What is expected to be in progress report?

We lead

• Background of the project

• Discussion of achievement during that period of time (including the photos).

• Discussion of the problems arise

• Discussion on the work to be completed.

• Current cost/budget

• Assessment of whether you will meet the objectives in the proposed schedule and budget

Download