By: Ernawati Mustafa Kamal
School of Housing, Building & Planning
Universiti Sains Malaysia
What is project?
• A project is a collection of tasks that must be completed within certain time frame, with specific cost & quality.
We lead
What is Project
Planning
Process
•
Land
Input
• Money (capital)
• Labour
• Material
• Machine
What do we do to get it done?
How do we do it?
Output
• Design
• Product
• Buildings
• Infrastructure
What do we want?
We lead
Project Scheduling Objectives
• Estimating time of project by determining the earliest start and finish of each activity.
We lead
Finding the minimum cost schedule needed to complete the project by a certain date.
Investigating the results of possible delays in activity’s completion time.
Progress control
Smoothing out resource allocation over the duration of the project.
Project Scheduling
• Tasks are called “activities.”
- Estimated completion time (and sometimes costs) are associated with each activity.
We lead
- Activity completion time is related to the amount of resources committed to it.
- The degree of activity details depends on the application and how specific is the data.
Identifying the Activities of a Project
We lead
• To determine optimal schedules we need to
– Identify all the project’s activities.
– Determine the precedence relations among activities.
Identifying Activities
• Example:
- Company A is a contractor & they need to construct a house.
We lead
Identifying Activities
We lead
• Major task they need to perform & complete:
- Sub-structure
- Superstructure
- Internal Finishes
- Services and finishing
- External Works
Identifying Activities
We lead
• Company A needs to develop a precedence relations chart.
• The chart gives a concise set of tasks and their immediate predecessors.
Identifying Activities
Sub-Structure
Activity
A
B
Superstructure
C
J
I
G
H
D
E
F
Description
Piling
Pile caps and ground beams
Frame
Upper Floors
Roof
Stairs and Ramps
External Walls
Windows and External Doors
Internal Walls and Partitions
Internal Doors
Internal Finishes K
L
M
Wall finishes
Floor Finishes
Ceiling Finishes
We lead
Identifying Activities
Services & Finishing
External Works
Activity
N
O
P
Q
T
U
R
S
Description
Sanitary installation
Water installation
Electrical installation
Road, Paths, Pavings & Surfacing
Landscaping and Irrigation Systems
Fencing
External drainage
External services
From the activity description chart, we can determine immediate predecessors for each activity.
We lead
Scheduling Tools & Techniques
We lead
• Mathematical Analysis
- calculating theoretical early and late start and finish dates for all projects activities without regard for any resource limitations.
- The resulting dates are not schedule, but it indicate the time period within which activity should be schedule.
Mathematical Analysis
• Critical Path Method (CPM)
• Graphical Evaluation and Review Techniques
(GERT)
• Program Evaluation and Review Technique
(PERT)
We lead
Scheduling Tools & Techniques
• Bar Charts
- Milestone charts
- Gantt charts
• Horizontal time scale is used, often divided into weeks.
We lead
• Various operations comprising the project are listed vertically down the left-hand side.
Bar Charts
• The timing and duration of each operation indicated by a horizontal bar spanning the relevant period of weeks and shown on the same line as the operation it refers to.
We lead
Example of Bar Charts
We lead
Example of Bar Charts
We lead
Example of Bar Charts
We lead
Example of Bar Charts
We lead
Progress Report
We lead
• It is a document used for updating the progress of work.
• Can be in many forms i.e: report (short report, formal report), memo, letter, or presentation.
What is expected to be in progress report?
We lead
• Background of the project
• Discussion of achievement during that period of time (including the photos).
• Discussion of the problems arise
• Discussion on the work to be completed.
• Current cost/budget
• Assessment of whether you will meet the objectives in the proposed schedule and budget