CERTIFIED PROFFESSIONAL CONTRACTS MANAGER (CPCM) TEST THE AUDIENCE !! TEST YOUR KNOWLEDGE 1. What is the systematic practice of identifying & reducing the threats that exist in the project? A. B. C. D. Strategic Management Threat Management Cost, Schedule, & Performance Management Risk Management TEST YOUR KNOWLEDGE 2. The seller is responsible for risk of loss or damage occurring before delivery to the carrier in which of the following? A. Report of Shipment (RESHIP) B. Late notification to the Government Transportation System (GTS) C. Free on Board (F.O.B.) Destination D. Free on Board (F.O.B.) Origin TEST YOUR KNOWLEDGE 3. The maximum number of offerors normally selected to submit phase-two proposals in a two-phase Design & Build solicitation is? A. B. C. D. 5 10 3 Unlimited TEST YOUR KNOWLEDGE 4. In its simplest form, this is an inventory system in which a replenishment order is issued each time a withdrawal is made, and the quantity is equal to the amount of the withdrawal? A. B. C. D. Base-Inventory System Base-Leveling System Base-Stock System Base-Supply System TEST YOUR KNOWLEDGE 5. The courts and boards have recognized 4 methods for pricing equitable adjustment claims. Which of the following methods is NOT recognized? A. B. C. D. Actual Costs Actual Damages Jury Verdict Total Cost TEST YOUR KNOWLEDGE 6. Which of the following methods is NOT an example of a competitive acquisition method? A. B. C. D. Imprest Funds Purchase Agreements Purchase Cards Sealed Bidding TEST YOUR KNOWLEDGE 7. This is a temporary transfer possession of personal property without a change of ownership for the specific purpose & with the intent that possession will revert to the owner at a later date. A. B. C. D. Assignment Bailment Conveyance Temporary Transfer of Property TEST YOUR KNOWLEDGE 8. This clause permits non-performance for excusable conditions. A. B. C. D. Acts of God Differing Site Conditions Force Majeure Latent Site Conditions TEST YOUR KNOWLEDGE 9. Using one or more contracts to acquire information technology systems in successive, interoperable increments is called: A. B. C. D. Incremental Contracting Modular Contracting Blanket Purchase Agreement Successive System Contracting TEST YOUR KNOWLEDGE 10. Which of the following is an advantage to using a FFP contract? A. Fair & Reasonable price can be established at outset B. It places 100% of the financial risk on the seller C. Price is not subject to adjustment regardless of seller performance D. It’s the preferred contract type for the Agency, it reduces amount of resources required, & establishes a ceiling price on the onset. TEST YOUR KNOWLEDGE 11. Which of the following is an excusable delay in Government contracting: A. B. C. D. Hurricane Tornado Fire Power Outage TEST YOUR KNOWLEDGE 12. This document provides evidence of receipt of goods for shipment issued by a person engaged in the business of transporting goods? A. B. C. D. Bill of Goods Bill of Lading Bill of Materials Bill of Sale TEST YOUR KNOWLEDGE 13. This is an intentional failure of a party to enforce a contract requirement, usually done for an act of immediate or future consideration from the other party. It is sometimes referred to as a non-waiver or one-time waiver, but not as a relinquishment of rights: A. B. C. D. Estoppel Forbearance Fraud Rescission TEST YOUR KNOWLEDGE 14. The withdrawal of a requirement to purchase goods or services or both by the buyer: A. B. C. D. Discharge of Contract Termination for Convenience Cancellation Change in Requirements TEST YOUR KNOWLEDGE 15. A legal phrase used in connection with the construction of written documents to the effect that an ambiguous provision is construed most strongly against the person who selected the language: A. B. C. D. Caveat Emptor Estoppel Contra Proferntem Determination of Intent CERTIFIED PROFFESSIONAL CONTRACTS MANAGER (CPCM) REVIEW TEST YOUR KNOWLEDGE 1. What is the systematic practice of identifying & reducing the threats that exist in the project? A. B. C. D. Strategic Management Threat Management Cost, Schedule, & Performance Management Risk Management TEST YOUR KNOWLEDGE 1. What is the systematic practice of identifying & reducing the threats that exist in the project? A. B. C. D. Strategic Management Threat Management Cost, Schedule, & Performance Management Risk Management TEST YOUR KNOWLEDGE 2. The seller is responsible for risk of loss or damage occurring before delivery to the carrier in which of the following? A. Report of Shipment (RESHIP) B. Late notification to the Government Transportation System (GTS) C. Free on Board (F.O.B.) Destination D. Free on Board (F.O.B.) Origin TEST YOUR KNOWLEDGE 2. The seller is responsible for risk of loss or damage occurring before delivery to the carrier in which of the following? A. Report of Shipment (RESHIP) B. Late notification to the Government Transportation System (GTS) C. Free on Board (F.O.B.) Destination D. Free on Board (F.O.B.) Origin TEST YOUR KNOWLEDGE 3. The maximum number of offerors normally selected to submit phase-two proposals in a two-phase Design & Build solicitation is? A. B. C. D. 5 10 3 Unlimited TEST YOUR KNOWLEDGE 3. The maximum number of offerors normally selected to submit phase-two proposals in a two-phase Design & Build solicitation is? A. B. C. D. 5 10 3 Unlimited TEST YOUR KNOWLEDGE 4. In its simplest form, this is an inventory system in which a replenishment order is issued each time a withdrawal is made, and the quantity is equal to the amount of the withdrawal? A. B. C. D. Base-Inventory System Base-Leveling System Base-Stock System Base-Supply System TEST YOUR KNOWLEDGE 4. In its simplest form, this is an inventory system in which a replenishment order is issued each time a withdrawal is made, and the quantity is equal to the amount of the withdrawal? A. B. C. D. Base-Inventory System Base-Leveling System Base-Stock System Base-Supply System TEST YOUR KNOWLEDGE 5. The courts and boards have recognized 4 methods for pricing equitable adjustment claims. Which of the following methods is NOT recognized? A. B. C. D. Actual Costs Actual Damages Jury Verdict Total Cost TEST YOUR KNOWLEDGE 5. The courts and boards have recognized 4 methods for pricing equitable adjustment claims. Which of the following methods is NOT recognized? A. B. C. D. Actual Costs Actual Damages Jury Verdict Total Cost TEST YOUR KNOWLEDGE 6. Which of the following methods is NOT an example of a competitive acquisition method? A. B. C. D. Imprest Funds Purchase Agreements Purchase Cards Sealed Bidding TEST YOUR KNOWLEDGE 6. Which of the following methods is NOT an example of a competitive acquisition method? A. B. C. D. Imprest Funds Purchase Agreements Purchase Cards Sealed Bidding TEST YOUR KNOWLEDGE 7. This is a temporary transfer possession of personal property without a change of ownership for the specific purpose & with the intent that possession will revert to the owner at a later date. A. B. C. D. Assignment Bailment Conveyance Temporary Transfer of Property TEST YOUR KNOWLEDGE 7. This is a temporary transfer possession of personal property without a change of ownership for the specific purpose & with the intent that possession will revert to the owner at a later date. A. B. C. D. Assignment Bailment Conveyance Temporary Transfer of Property TEST YOUR KNOWLEDGE 8. This clause permits non-performance for excusable conditions. A. B. C. D. Acts of God Differing Site Conditions Force Majeure Latent Site Conditions TEST YOUR KNOWLEDGE 8. This clause permits non-performance for excusable conditions. A. B. C. D. Acts of God Differing Site Conditions Force Majeure Latent Site Conditions TEST YOUR KNOWLEDGE 9. Using one or more contracts to acquire information technology systems in successive, interoperable increments is called: A. B. C. D. Incremental Contracting Modular Contracting Blanket Purchase Agreement Successive System Contracting TEST YOUR KNOWLEDGE 9. Using one or more contracts to acquire information technology systems in successive, interoperable increments is called: A. B. C. D. Incremental Contracting Modular Contracting Blanket Purchase Agreement Successive System Contracting TEST YOUR KNOWLEDGE 10. Which of the following is an advantage to using a FFP contract? A. Fair & Reasonable price can be established at outset B. It places 100% of the financial risk on the seller C. Price is not subject to adjustment regardless of seller performance D. It’s the preferred contract type for the Agency, it reduces amount of resources required, & establishes a ceiling price on the onset. TEST YOUR KNOWLEDGE 10. Which of the following is an advantage to using a FFP contract? A. Fair & Reasonable price can be established at outset B. It places 100% of the financial risk on the seller C. Price is not subject to adjustment regardless of seller performance D. It’s the preferred contract type for the Agency, it reduces amount of resources required, & establishes a ceiling price on the onset. TEST YOUR KNOWLEDGE 11. Which of the following is an excusable delay in Government contracting: A. B. C. D. Hurricane Tornado Fire Power Outage TEST YOUR KNOWLEDGE 11. Which of the following is an excusable delay in Government contracting: A. B. C. D. Hurricane Tornado Fire Power Outage TEST YOUR KNOWLEDGE 12. This document provides evidence of receipt of goods for shipment issued by a person engaged in the business of transporting goods? A. B. C. D. Bill of Goods Bill of Lading Bill of Materials Bill of Sale TEST YOUR KNOWLEDGE 12. This document provides evidence of receipt of goods for shipment issued by a person engaged in the business of transporting goods? A. B. C. D. Bill of Goods Bill of Lading Bill of Materials Bill of Sale TEST YOUR KNOWLEDGE 13. This is an intentional failure of a party to enforce a contract requirement, usually done for an act of immediate or future consideration from the other party. It is sometimes referred to as a non-waiver or one-time waiver, but not as a relinquishment of rights: A. B. C. D. Estoppel Forbearance Fraud Rescission TEST YOUR KNOWLEDGE 13. This is an intentional failure of a party to enforce a contract requirement, usually done for an act of immediate or future consideration from the other party. It is sometimes referred to as a non-waiver or one-time waiver, but not as a relinquishment of rights: A. B. C. D. Estoppel Forbearance Fraud Rescission TEST YOUR KNOWLEDGE 14. The withdrawal of a requirement to purchase goods or services or both by the buyer: A. B. C. D. Discharge of Contract Termination for Convenience Cancellation Change in Requirements TEST YOUR KNOWLEDGE 14. The withdrawal of a requirement to purchase goods or services or both by the buyer: A. B. C. D. Discharge of Contract Termination for Convenience Cancellation Change in Requirements TEST YOUR KNOWLEDGE 15. A legal phrase used in connection with the construction of written documents to the effect that an ambiguous provision is construed most strongly against the person who selected the language: A. B. C. D. Caveat Emptor Estoppel Contra Proferntem Determination of Intent TEST YOUR KNOWLEDGE 15. A legal phrase used in connection with the construction of written documents to the effect that an ambiguous provision is construed most strongly against the person who selected the language: A. B. C. D. Caveat Emptor Estoppel Contra Proferntem Determination of Intent