July 2015 REQUEST FOR PROPOSAL FOR APPOINTMENT OF PROJECT ENGINEER (INDEPENDENT ENGINEER) FOR KOZHIKODU CITY ROADS IMPROVEMENT PROJECT (KCRIP) – PHASE -1 A July 2015 RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 1 July 2015 LETTER OF INVITATION Kerala Road Fund Board, a statutory body under Public Works Department, Government of Kerala intends to select agencies/consultant firms for Appointment as Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP), Phase – 1 A. Interested Agencies/consultant firms having experience in the services envisaged are hereby invited to submit their proposals. The document can be downloaded from the website www.krfb.org. Please note that Kerala Road Fund Board reserve the right to accept or reject all or any of the bids without assigning any reason whatsoever. Bid submissions must be received in the manner specified at the address given below not later than 4.00pm, 18th August 2015 Chief Executive Officer TC 4/1654, Mayooram, No: 7, Belhaven Gardens, Kowdiar P.O, Thiruvanathapuram 695 003 Tel: +91-471-2726080, Fax: +91-471-2726080, Web: www.krfb.org Important Dates Date of pre-bid meeting: 12.08.2015(10:30 hrs) Last date of receipt of queries at KRFB : 12.08.2015 Last date of submission of bids: 18.08.2015 (1700 hrs) RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 2 July 2015 REQUEST FOR PROPOSAL FOR APPOINTMENT AS PROJECT ENGINEER (INDEPENDENT ENGINEER) FOR KOZHIKODE CITY ROADS IMPROVEMENT PROJECT (KCRIP), PHASE-1, A 1. PROJECT BACKGROUND Kozhikode City Road Improvement Project (KCRIP), Phase-1A envisages development and up gradation of 22.25 Km of City roads under BOT Annuity basis. The scope of work will broadly include rehabilitation, up gradation and widening of the existing carriageway to two/four lane configuration with construction of new pavement, rehabilitation of existing pavement, junction development, drain etc. The following table summarizes the details of the proposed road stretches under Phase IA, SN. Corridor Description of Road Stretch No. 1 C1 Stadium – Puthiyara 2 C2 Karaparamba – Eranhipalam & Arayadathupalam- Kalluthankadavu (portion of mini bypass) 3 C3 Vellimadukunnu- Kovoor 4 C4 Gandhi Road - Mini Bypass and Kuniyilkavu Mavoor Road Junction 5 C6a Panathuthazham – CWRDM 6 C7 Pushpa Junction to Mankavu Junction Total Length (KM) 0.644 4.526 2.735 3.435 8.459 2.452 22.25 M/s Uralungal Labour Contract Co–operative Society Ltd, Vadakara have been selected as the Concessionaire of the project and LoA has already been issued to them for the above purpose. As per the Concession Agreement, the Concessionaire has to construct the project facilities in accordance with construction and design requirements and has to operate and maintain the project facilities for a Concession period of 17 years which includes construction period of two years and Annuity period of 15 years. Kerala Road Fund Board now intends to appoint a Project Engineer for the project in accordance with the provisions of the Concession Agreement for supervising and monitoring RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 3 July 2015 of compliance by the Concessionaire with the Project Requirements, more particularly to undertake, perform and carry out the duties, responsibilities and services set forth in the Concession Agreement. 2. ROLE OF PROJECT ENGINEER The Project Engineer shall be responsible for the activities and efficiency of his staff for the satisfactory execution of the work under his supervision. He has the responsibility to build and maintain an organization that can effectively provide the necessary staking, testing, and inspection to ensure that the project is constructed according to the plans and specifications and in compliance with the Concession Agreement. The Project Engineer should familiarize himself rapidly with the plans, specifications, and any Contract amendments to effectively administer the work. The Project Engineer is expected to play a positive and independent role in discharging its functions, thereby facilitating the smooth implementation of the project. Some of the principal responsibilities of the Project Engineer are: i) Independently review, monitor and where required by the Concession Agreement to approve activities associated with the Design, Construction, and Maintenance of the Project Facilities to ensure compliance by the Concessionaire with the DPR/Project requirements. ii) Ensure the Concessionaires compliance with the Concession Agreement and DPR iii) Inspect all workmanship and material iv) Make layout checks in line with approved lines and grades. v) Report to the parties of Concession Agreement on the various physical, technical and financial aspects of the project based on inspections, site visits and tests. vi) Assist the parties in arriving at an amicable settlement of disputes, should the need arise. vii) Review matters related to safety and traffic management measures adopted by the Concessionaire for the project. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 4 July 2015 viii) Assist and coordinate with other road users and stake holders in handling issues related to utility lines and other hindrances for the speedy implementation of the project. 3. SCOPE OF SERVICES 3.1 During Implementation i) Review of all working drawings submitted by the Concessionaire for its compliance to the project requirements including deviations from DPR, additions/ deletions of project facilities in accordance with Concession Agreement and submission of additional drawings required but not included in DPR. ii) Review and approval of As-built drawings prepared by the concessionaire iii) Review of implementation plan and O&M plan during implementation period iv) Suggest rehabilitation measures of the existing road, bridges and other structures. v) Monitor the progress in implementation of the project in accordance with Good Industry Practice and ensure compliance with the Construction Requirements. For this purpose the Project Engineer shall undertake, inter alia, the following activities and where appropriate make suitable suggestions: (a) Prepare a broad implementation plan with time schedule as per the requirement of the project and get a detailed implementation plan prepared by the Concessionaire. (b) Monitor the progress in implementation of the Project based on the Implementation Plan submitted by the Concessionaire. Review and approve the material testing and mix designs results and recommend special tests, where required, for materials and / or completed works, require removal / substitution of unsuitable materials and / or works and report deficiencies of the same. The Project Engineer is responsible for the final materials submittals and review, which shall be forwarded to KRFB with recommendation for final approval. (c) To attend all meetings, and prepare written minutes for distribution. (d) Monitor and report progress of scheduled utility relocation. (e) Coordination with the Contractor’s supervisory personnel regarding schedule, sequence, and method of work. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 5 July 2015 (f) Review and monitor the quality assurance and quality control procedures followed by the Concessionaire. (g) Review, monitor and report the detail of manpower and equipment’s deployed by the Concessionaire on daily basis. Review, update, monitor, and report on the Concessionaire’s work schedule and CPM-chart. VI) Coordination with the Concessionaire’s supervisory personnel regarding the schedule, sequence and method of work. (a) Monitor the Construction works for conformity with the DPR/ Project requirements (including rehabilitation of the existing road and bridge structures) (b) Review the safety and traffic management measures implemented. (c) Review and ascertain cost variation arising as a result of Change in Law and / or Change in Scope and determine the additional cost. (d) Monitor and review the results of tests to be carried out by the Concessionaire in accordance with the construction requirements and / or O & M requirements. (e) Suspension of whole or any part of construction works if in its reasonable opinion the same does not conform to the construction requirements. (f) Review and assist in finalization of the O & M Manual and first annual O & M Plan prepared by the Concessionaire. (g) The Project Engineer is responsible for Contract enforcement and is not to relieve the Concessionaire of his responsibilities without written authorization of KRFB. VII) Site Instructions Site Instruction involves a matter that cannot wait for a formal letter and an instruction in writing is imperative. Site Instructions must be given in writing by the Project Engineer to the Concessionaire in an approved format and copied to KRFB Representative. The Project Engineer will issue a formal letter confirming the directions stated in the Site Instruction as soon as possible. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 6 July 2015 3.2 Completion Certificate i) Upon completion of any of Project phases, the Project Engineer has to issue Provisional Certificate and / or Completion Certificate in accordance with the applicable provisions of the Concession Agreement certifying the completion of construction in accordance with the Construction Requirements. ii) Verify the ‘As Built’ drawings for each component of the works prepared by the Concessionaire and require removal of deficiencies found therein. iii) Carry out a technical audit of the Project Facilities constructed by the Concessionaire to ascertain the physical parameters as listed out in the Concession Agreement and DPR and to ascertain its compliance with the Construction and Design Requirements as stipulated in the Concession Agreement. 3.3 Meetings, Records and Reporting i) The Project Engineer would be required to participate in the Project review meetings held from time to time by the Parties and draft minutes of such meetings and communicate. ii) Project Engineer should maintain record of the activities undertaken by it in the discharge of its functions and responsibilities. This include records in respect of the following: (a) Manpower deployed and other organizational arrangement of the Project Engineer. (b) Review of documents submitted by the Concessionaire to meet Project Requirements such as manuals, drawings, As Built drawings, schedules, plans and reports. (c) Inspections undertaken and notices/ instructions issued to the Concessionaire. (d) Review of compliance with Project Requirements. (e) Tests and results (f) Land availability (including non- availability) (g) Annuity claims certified (h) Change of Scope and Change in Law RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 7 July 2015 (i) Emergency (including accidents) (j) Force Majeure Events (k) Breaches and defaults by the parties (l) Hand back requirements iii) The Project Engineer would be required to submit the following reports to the Parties of Concession Agreement during the Concession Period: a) Weekly Progress Report b) Monthly Progress Report Table of Statistics including date of Contract award, date of LoA, Concession period, approved time extensions if any, revised Contract period, days elapsed, percentage of time elapsed, percentage of anticipated completion (from progress schedule), percentage of actual completion (measured on the same basis as percentage of anticipated completion), Contract completion date, original Contract amount, approved Variation Orders, revised Contract amount, and value of completed work. Narrative description of Construction Activities. Narrative of the Engineer’s Activities. Pertinent Progress Photos. General Location Map. Narrative report of Progress Problems, their cause, and proposed solutions. Safety Issues including accident report Progress Chart with S curve showing scheduled progress and actual progress. Details submissions and status Details of manpower and equipment’s mobilized c) Surveillance Deficiency Report (SDR) In the event that procedural errors or deficient workmanship or defective materials are found. During surveillance by IE and after notifying and discussing matters with the Concessionaire, if satisfactory and timely resolution of a subject deficiency cannot be agreed, the IE staff will raise an SDR. The document, in duplicate, RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 8 July 2015 will be presented to the Concessionaires representative for signature for action within the noted time-period. The IE shall carry out a review of the action taken. Should the Concessionaire fail to achieve resolution to the satisfaction of the IE, a ‘Non-Conformity Report’ (NCR) will be raised. d) Non Conformity Procedure and corrective action. (NCR) Noncompliance report shall be raised for any work that is rejected for repair/rework. e) Report on Tests and report on notices issued i) Completion Certificate ii) Any supplemental or special report that may be considered necessary by the Project Engineer iii) Report on Tests and report on notices issued iv) Report on Handback Requirements v) Any other report as may be reasonably required by the client or as may be necessary to give effect to the provisions of the Agreement. 4 CONDITIONS OF APPOINTMENT Project Engineer shall be appointed for an initial term of 2 year and the period of appointment will be extended depending on the requirement of the project (and also based on performance of the Project Engineer). The Board may replace the Project Engineer in any of the following circumstances, with a notice period of one month. i) Upon expiry of the period/ term of his appointment including renewal / extension thereof. ii) If the Board decide not to renew/ extend the term of Project Engineer. iii) The Board has reason to believe that the Project Engineer has not discharged its duties in a fair, appropriate and diligent manner. iv) If, in accordance with the terms of his appointment, the Project Engineer resigns or notifies his intention not to continue as the Project Engineer, subject to a notice period of 1 month. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 9 July 2015 5. Eligibility Criteria i) Average annual Turnover of the Consultancy firm from its operations in India during the past 3 financial years ending 31.3.2015 shall be more than Rs.10 Crores. The concessionaire shall submit copies of the balance sheet and audited records duly certified by the Chartered Account. ii) Consultancy firm should have experience in the supervision/project management of state/NH/ Urban roads for 2 major infrastructure and road development projects for minimum of 200 km length at a cost of Rs.200 Crores in the last 8 years. Firms having experience as Project Engineer in PPP Projects will be given weightage. iii) The Project Engineer and his team must have the qualification and experience mentioned in Table-1. Firms having experience as Project Engineer in PPP projects in will be given preference. In case of JV, the lead partner must full fill the requirements as stated above. 6 QUALIFICATION AND SELECTION CRITERIA i) The selection of the Project Engineer shall be based on QCBS method. ii) The lead member/ firm shall have at least 10 years’ experience in working with Road Projects in similar capacity or in project managerial level either with a Concessionaire or with a Consultant. iii) The Project Engineer’s team shall have the following key personnel working full time, based in Kozhikode, for undertaking the assignment with appropriate qualification and experience in the following discipline: TEAM COMPOSITION TABLE-1 Sl. No. 1 Experience in Expertise Qualification Relevant Field (Years) Senior Highway Engineer i) Graduation in Civil Engineering with 20 cum Team Leader. 20 years’ experience out of which 10 years as Highway Engineer engaged in the supervision of state/NH/Urban RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 10 July 2015 2 Material Engineer 3 Lab Technician 4 Field Engineer (2 nos) 5 Land Surveyor roads with leading Consultants/contractors. ii) The Senior Highway Engineer should successfully complete 2 projects in the capacity of Team Leader/ Project Engineer/Project Manager/ Senior Highway Engineer. iii) Preference will be given for candidates having Knowledge of Auto cad/ and MS office. a) Graduation in Civil Engineering with 8 years’ experience as Material Engineer. Diploma in Civil Engineering with 5 years’ experience as Lab Technician in major road Projects. a) Graduation in Civil Engineering with 5 to 8 years’ experience in highway engineering/ quality control a) Diploma in Civil Engineering with 6 years’ experience or ITI with 10 years’ experience. 8 5 5to 8 6 to 10 In addition to the above, adequate office staff should be mobilized for the smooth and speedy discharge of responsibilities as detailed above. In case of necessity, other engineering and financial experts/ specialists are to be temporarily engaged to sort out specific issues. 6.1. a) Senior Highway Engineer cum Team Leader The senior Highway Engineer shall be a graduate Civil Engineer from a recognized University from India, with 20 years’ experience in the supervision and execution of major infrastructure and road projects with leading national/ international consultants/ contractors. He should have successfully completed at least 2 projects in the capacity of Team Leader/ Resident Engineer/Project Manager. Preference will be given to candidates having knowledge of Auto cad, M.S Office and Pert/Primavera. Some of the principal responsibilities of the Senior Highway Engineer are: Ensure the Concessionaire’s compliance with the Contract Documents. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 11 July 2015 Inspect all workmanship and materials. Coordinate the supply of vertical and horizontal controls for the Concessionaire. Make layout checks on lines and grades. Coordination with stake holders Maintain all file records on designated forms. These records include all reports on work force, equipment, progress, safety, etc. Review and approve the Concessionaire’s shop drawings. Locate, execute, and interpret all soils and materials testing according to the provisions in the Contract Documents and Standard Specifications. The Team Leader is responsible for Contract enforcement and is not to relieve the Concessionaire of his responsibilities without KRFB authorization. The Senior Highway Engineer/ Team Leader is responsible for the final materials submittals and review, which shall be forwarded to KRFB with recommendations for final approval. Check and certify payments for additional works. Check personnel, equipment, and material costs for all Variation Orders and Change Orders required under the terms of the Concession Agreement. Review requests for variation orders and time extensions. Preparation of the Monthly Report. Site Safety Monitoring wherein the monitoring activities, meetings, reviews, safety violations, rectification measures, and accident reports are included in the Monthly Progress Report. Inspect safeties conditions and inform the Concessionaire of construction safety violations and follow up action to be taken. Attend all meetings, and prepare written minutes for distribution. Review, update, monitor, and report on the Concessionaire’s work schedules, CPMchart. Monitor and report on progress of scheduled utility relocation work. Provide all photographs before, during, and after construction necessary to provide adequate documentation of changes in site and adjacent structures. Review and approve the concessionaire’s plans for protection of existing buildings and structures. b) Material Engineer The Material Engineer shall be a graduate Civil Engineer from a recognized university from India, with 8 years’ experience as a Material Engineer with reputed consultants/ contractors in major road projects. Some of the Principal responsibilities of the Materials Engineer are as follows: Field laboratory set-up, organization, maintenance, and operation. Performing sampling and testing of materials. Perform sampling, testing, record keeping, and reporting in accordance with Project Plans and Specifications and copy all test result to KRFB. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 12 July 2015 Report any failing or “borderline” test results immediately to the Team Leader and KRFB Coordinate with the Field Engineer in charge of the work to confirm approval of the work for testing and discuss areas of concern. Coordinate with the Concessionaire on work Priorities and schedules. Perform sampling and testing as quickly and efficiently as possible to avoid undue delay to the Concessionaire’s operations. Perform regular checks of material delivered to the project for conformance with the approved source or supplier. Maintain neat accurate records. Monitor the frequency and number of tests required for every operation. Review and approve mix design for all construction material. c) Lab Technician Lab Technician shall be Diploma in Civil Engineering, from a recognized institution by Government of India/ Kerala with at least 5 years’ experience in major road projects with reputed consultants and or contractors. The field laboratory technician is responsible for conducting field tests according to specified frequency as per approved inspection and test plan submitted by the Concessionaire, material selection, sampling, testing etc. as per relevant IRC/BS standards. d) Field Engineer Field Engineer shall be a graduate Civil Engineer from a recognized university from India, with 5 to 8 years’ experience in the supervision of major infrastructure and road projects with reputed consultant and or Contractors. He should have successfully completed at least two projects in the similar capacity of Field Engineer. Principal responsibilities of the Field Engineers are as follows: Ensure performance of the work in strict accordance with the plans and specifications. Maintain a detailed diary of the day’s work activities, issues, work approved or rejected, hours of operation, labour and equipment used, etc., and sign at the end of each day. Prepare daily progress report. Interface with the public, especially residents and business owners adjacent to the work, to mitigate the construction impacts. Coordinate with the Concessionaire’s field staff in charge of the work on a daily basis to check on the proper execution of the work. Coordinate with the Materials Engineer and arrange for sampling and testing of satisfactorily completed work, and quality assurance testing of suspect materials. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 13 July 2015 Coordinate with the Land surveyor to check the line and grade of completed work for conformance with the plans and specifications. Report questionable methods of operation by the Concessionaire the Team Leader and KRFB. Report any failure of the Concessionaires activities. Process the joint measurements forms and maintain records of where necessary Maintain detailed records of work performed by the concessionaire on a Day Works basis. Make special notes and document the Concessionaire’s activities that may lead to claims. Be fair and firm in dealings with the Concessionaire. Consider alternatives and consequences carefully before making decisions. d) Land Surveyor The Land Surveyor shall be Diploma in Civil Engineering (3 years Diploma) from a recognized university/ institution from India with at least 6 years of experience or ITI with at least 10 years’ experience as a land Surveyor in major road projects. The main responsibilities of the Land Surveyor are; Check the completed works for conformance to the line and grade required by the project plans in coordination with the Field Engineer assigned to the item of work. Perform regular checks of the Concessionaire’s setting out to verify proper execution and accuracy. Record all measurements, rod readings, and calculations neatly and accurately in field books as the work progresses. Coordinate with the Concessionaire’s surveyor on work priorities and schedules. The evaluation of the proposals shall be carried out in two stages: first the quality (70% Weightage), and then the cost (30% Weightage). Evaluators of technical proposals shall not have access to the financial proposals until the technical evaluation, including any Bank reviews and no objection, is concluded. Financial proposals shall be opened only thereafter. The evaluation shall be carried out in full conformity with the provisions of the ToR. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 14 July 2015 7. EVALUATION OF THE TECHNICAL PROPOSAL (QUALITY) The following Criteria shall be adopted by KRFB for the evaluation of the Technical Proposals submitted by Consultancy Firm. 1. Background / Reputation of the lead member/firm 2. Lead member/firm’s relevant Experience: 3. Construction stage project management plan and QC plan 4. Composition and Experience of Project Engineer team proposed Bidders meeting the eligibility criteria are required to submit details of the Background / Reputation of the lead member/firm, their experience in similar works, Details of team members / Professionals with durations proposed to be deployed for the assignment together with their qualification and experience, Approach, Methodology and Work Plan proposed to be followed for carrying out the said assignment etc. KRFB may invite the applicants to appear for a technical discussion to get more clarity on the application and the data presented before KRFB. The Selection Committee will carry out the technical evaluation applying the criteria and points rating as listed in the table below: TABLE-2 Sl. No. 1. 2. 3. 4. Parameter Maximum Total Technical Score Lead member/ firm’s background and profile in terms of the quantum and nature of consultancy assignment undertaken, overall experience and stature in the sector, presence in the country, team strength etc. Lead member/ firm’s experience as lead consultant in similar studies in the country in the past five years Proposed Approach, Methodology and Work Plan for undertaking the project. Composition and Experience of Project Engineer’s team (CVs). Total Technical Score RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 5 20 20 55 100 15 July 2015 The Maximum achievable Technical Score for any bidder would be 100. A minimum of 75 marks is necessary for qualifying in the Technical Proposal. The financial proposals of firms scoring less than 75 marks out of 100 marks for their Technical Proposal would be returned, unopened. 7.1 Firm’s relevant Experience Firms should indicate the number of completed projects, including the name of the Client for whom the assignment has been carried out. Firm’s experience in respect of this criterion should be supported by documentary evidence in the form of certificate from the clients, clearly stipulating the services rendered by the Project Engineer. Selection Committee would evaluate the experience of each firm in respect of eligible projects and assign score on its evaluation. Experience in the region will be given weightage. 7.2 Approaches and Methodology Bidders are required to furnish a detailed write-up on their Conceptual Clarity and Understanding of the project and its objectives. Bidders are also required to furnish the following: Proposed Approach; Proposed Methodology; and Construction stage project management and QC plan Work Plan to undertake the assignment. The Selection Committee would evaluate each item above and assign appropriate score to every bidder based on its evaluation as under. TABLE-3 Sl. No. 1. 2. 3. 4. 5. Finding of Evaluation Not submitted (Failure) Submission is below the requirement (Inadequate/poor) Submission meets the requirement (Adequate/Fair) Submission exceeds the requirement (Good) Submission far exceeds requirement (Excellent) RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A % of points 0% 30% 75% 90% 100% 16 July 2015 7.3 Team Composition and Experience of Key Personnel/Experts The firm shall submit the detailed biodata of all the key personnel (as specified in the RFP).The Consultancy Firm shall also submit an assurance that all the key personnel will be available during the term of the assignment. age limit of key staff should not be more than 65 years. Selection Committee would evaluate each member proposed to be deployed based on their qualifications, experience etc., and assign score for every bidder based on its evaluation as detailed below:TABLE-4 Sl. No. Expertise Marks 1 Senior Highway Engineer cum Team Leader 18 2 Material Engineer 11 3 Lab Technician 6 3 Field Engineer 6 4 Field Engineer 6 5 Land Surveyor 8 Total 55 The qualifications and experience of proposed key personnel in their curricula vitae must be accurate, complete, and signed by an authorized official of the Consultant and the individual proposed. The individuals shall be rated in the following three subcriteria, as relevant to the task: (a) Educational Qualification: General education and training, length of experience, positions held, time with the consulting firm as staff member, experience in developing countries, and so forth; (b) Overall Experience for the assignment: Training, and experience in the specific sector, field, subject, and so forth, relevant to the particular assignment; and (c) Experience in the region: Knowledge of the local language, culture, administrative system, government organization, and so forth. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 17 July 2015 7.4 Total Technical Score The total Technical Score of any bidder would be an arithmetic sum of scores obtained by the bidder for each of the parameter indicated above viz. experience, conceptual clarity and approach & methodology and team composition & experience. 7.5 Financial Proposal The Financial Proposal should be quoted in Indian Rupees as a lumpsum professional fee, on a monthly basis and should be inclusive of the total cost of the Study team, Supporting staff, camp office, operating cost of office and transport and all other expenses. 7.6 Evaluation of Financial Proposal (Cost) After the evaluation of Technical Proposal (quality) is completed, the KRFB shall notify those consultants whose proposals did not meet the minimum qualifying mark or were considered nonresponsive to the ToR, indicating that their financial proposals will be returned unopened after completing the selection process. The KRFB shall simultaneously notify the consultants that have secured the minimum qualifying mark, and indicate the date and time set for opening the financial proposals. The opening date shall not be sooner than one week after the notification date. The financial proposals shall be opened publicly in the presence of representatives of the consultant who choose to attend. The name of the consultant, the quality scores, and the proposed prices shall be read aloud and recorded when the financial proposals are opened. The KRFB shall prepare the minutes of the public opening. For the purpose of evaluation, ‘cost’ shall exclude local taxes, but shall include other reimbursable expenses, such as travel, translation, report printing, or secretarial expenses. The bidder, who quotes the lowest professional fee, will be awarded a financial score of 100 marks and other bidders will be given financial scores that are inversely proportional to their quoted professional fees. The formula for this will be, FX = 100 × L1 / Lx where L1 is the amount of professional fee quoted by the lowest bidder and Lx is the amount of professional fee quoted by the bidder under RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 18 July 2015 evaluation). KRFB will correct any arithmetical errors in Financial Proposals. While correcting ‘arithmetical errors,’ in case of discrepancy between amount mentioned in words and figures, the lower among the two shall prevail and only be considered. 7.7 Combined Quality and Cost Evaluation The total score shall be obtained by weighting the quality and cost scores and adding them. The proposed weightings for quality is 70 Points and cost shall be 30 Points. If ‘T’ is the total marks scored in Technical Proposal, and ‘F’ is the marks scored for the Financial Proposal. The final weighted score will be: 0.70*T + 0.30*F. The assignment shall be awarded to the bidder scoring the highest final weighted score. KRFB, however, reserves the right to reject any or all the bids received, without assigning any reasons and any liability to KRFB. 7.8 SUBMISSION OF APPLICATION Applications are to be submitted in sealed covers within the stipulated time with the following details. 1. Name of the lead member and associate firm with full contact address, e-mail id and phone number: 2. Locals address if any with details of contact person: 3. Profile of the firm: 4. CV’s of the key personnel with their undertaking regarding their availability for the Project for the entire appointment period: Experience certificate of the key personnel: An authorized representative of the firm or the lead member shall initial all pages of the Proposal. The Request for Proposal and submittals by the applicant will form part of the agreement. 8. OTHER CONDITIONS 8.1 Local Offices The Project Engineer should maintain an office at Kozhikode preferably close to the site office of the Concessionaire with infrastructure for routine office works and RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 19 July 2015 communication facilities. Key personnel as given in Table- 2 has to be posted in the local office during the entire appointment period and they shall not be moved out without the consent of the Kerala Road Fund Board. If any personnel have to be moved out a suitable replacement of meeting the prescribed qualification and experience shall be given immediately after formal approval from KRFB. The attendance sheet of the Project Engineer team shall be submitted to KRFB in daily/weekly basis. The payment will be made as per actual man month available. 8.2 Confidentiality The Project Engineer shall keep all the information pertaining to the assignment CONFIDENTIAL and shall not provide/disclose any information of the assignment to anybody except on specific instructions from KRFB. 8.3 Property Rights of Assignment Outputs The Project Engineer shall hand over soft copies of all the deliverables, drawings and all related workings & outputs of the assignment generated for executing the assignment as & when requested by KRFB during the course of the assignment and on successful completion of the assignment. Such deliverables, drawings and related outputs are the Sole Property of KRFB and the Project Engineer shall treat all these information Confidential and shall not share with anybody else except on specific written instructions by KRFB. 8.4 Award of Contract The contract will be awarded following negotiations. After negotiations are successfully completed, an agreement will be executed with the authorized signatory of the lead consultant in the standard form of contract 8.5 KRFB will have the authority to cancel this invitation for bid without any reason. The Proposals must reach Chief Executive Officer, Kerala Road Fund Board, TC 4/1654, Mayooram, No. 7, Belhaven Gardens, Kowdiar P O, Thiruvananthapuram 695 003, on or before 17.00 hrs 18th August 2015 (IST) delivered in person or by Registered Post or by Courier. Any proposal received by KRFB after the deadline for submission shall be returned unopened. KRFB shall not be responsible for any postal or courier delays. RFP for Appointment of Project Engineer (Independent Engineer) for Kozhikode City Roads Improvement Project (KCRIP) Phase-1, A 20